p09451 detailed design review bryan mccormick (me) project manager andy freedman (me) heat...
Post on 15-Jan-2016
217 views
TRANSCRIPT
P09451 Detailed Design Review
Bryan McCormick (ME) Project ManagerAndy Freedman (ME) Heat Transfer/Fluids Analysis & Design
John Kreuder (ME) Thermal ModelerKen McLoud (ME) Structural Designer
Jon Holdsworth (EE) Electrical System DesignerGabriela Santa Cruz (IE) Engineering Economics
Closer Look at the Solution
T=465K T=459K T=458K T=457KT=438K
Current System
Current System
Piping
Control System
0 5 10 15 20 25 300
0.5
1
1.5
2
2.5
3
3.5
4Power
Rload
pow
er
Control System – Plant Model
In1 Out1
plant
In1 Out1
mosfet
dpdr
To Workspace1
time
To Workspace
In1 Out1
PID controller
0
Constant
Clock
1
Out11s
Integrator
Kd
Gain2
Ki
Gain1
Kp
Gain
du/dt
Derivative
1
In1
Mosfet Compensation
Response - optimized
Response – non-optimal
Automated Peak Power
Impedance Matching Circuit for Peak Power
VariabletGSD
DS RVVkI
V
)(
1
ShuntVariableLoad RRR
Sensors
Total Sensors (Inputs to DAQ)
Thermocouples On Modules 48
Before/Inbetween/After Zones 5
Inlet/Outlet of Cold Exhaust 4
Heater Inlet 1
Mass Flows Air 1
Water 1
Compression Force Flexi-Force Sensors 8
Change in Air Pressure Pressure Transducers 3
Voltages Load Voltages 4
Shunt Voltages 4
79 Total
Block Diagram
Layout
Data Collection
• Goal: Collect enough data to test for reliability and reproducibility of current measurements.
• Performed 4 tests under the same conditions (200 C and 100cfm)
• Assembled the unit twice by two different operators, tested two times for each assembly
Data Collection Process: Assembly and Set-up
Test 1 Test 2 ImprovementCleaning Cleaning 1:02 1:50
Bottom Assembly
Applying Thermal Paste to Modules: Three Modules, 1 side 4:12 3:46 Considered thermal pads, not feasibleThree Modules, 2nd side 3:38 3:16 Considered thermal pads, not feasible
Placing Insulation 1:04 1:02 Marked Places for Modules for easy placementSetting on Bottom Plate 1:22 0:52 Bolts attached to bottom plateSub Total 10:16 8:56
Top Assembly
Applying Thermal Paste to Modules: Three Modules, 1 side 3:51 3:04 Considered thermal pads, not feasibleThree Modules, 2nd side 2:47 2:21 Considered thermal pads, not feasible
Placing Insulation 0:38 0:44 Marked Places for Modules for easy placementSetting Top Plate 0:28 0:59 Sub Total 8:44 7:08
Final Assembly
Placing Washers and Nuts 1:30 1:15 Tightening 3:01 4:21 Better Tool ClearanceOutside Insulation 1:26 1:59 More space to insert, less piecesThermocouples 6:50 5:54 Embeded in Power UnitSub Total 12:47 13:29
Set-up in Stand
Set on Jacks and Lift 1:47 2:51 Block with Appropriate Height in Test StandAttaching to Stand 10:29 7:14 Better Tool ClearancePlugging into DAQ 6:54 6:01 Color CodingSub Total 18:10 16:06
Total 49.57 45.39
Issues/Solutions on Data Processing
Issue Solution
Long, tedious clean-up Record output with headers
Set up different output formats depending on the application.
Inconsistent data, uncertainty in the origin
Data constraints with LED indicator when out of range in front panel
Statistical Analysis
Hypothesis Testing: Difference Between Means
# of standard deviations away from the hypothesized zero difference
0:0:21210aHH
Reject Ho for |T|>2.093
2/t
21
21
11
)(
nnS
xxT
p
0:
0:
21
210
aH
H
2
)1()1(
21
222
2112
nn
SnSnS pWhere
Project Charter
Project Name Thermoelectric Module for Large Scale Systems Project Lead Bryan McCormickDate, Revision # Project Sponsor Dresser-Rand: Paul Chilcott
Start Date 12/1/08 SDT Leader Completion Date 5/22/09
Idea Submitter Dr. Robert StevensCurrent Phase Detailed Design
Element Description Team Charter
Process DefinitionThe business process in which opportunity exists. This project is aimed at acquiring an improved understanding of the workings of thermoelectric
(TE) devices as a means to recovering wasted energy from Dresser-Rand turbo machinery exhausts in the form of usable power.
Strategic Goal/ Business Case
Describe the opportunity as it relates to strategic business goals. A clear understanding of the workings, benefits and fallbacks of thermoelectric devices is important when deciding whether it is feasible to implement this technology in industry, and whether it is the best choice among alternative technologies.
ProblemStatement
State the significant issue(s) that needs to be addressed or opportunities to pursue. To better understand thermoelectrics and their potential applications in industry for energy recovery, it is important to have a reliable, flexible and efficient test stand to validate models. The current test stand requires long set-up times, does not provide readily available data and has too many variables that compromise the reliability of the acquired data. There are also different configurations that could be tested if the stand allowed for more flexibility, which would produce a wider range of data to draw conclusions from.
Benefits Impact ($)
What are the anticipated business results and when would the results be realized?
• Upgraded thermoelectric test rig utilizing interchangeable air-cooling on the cold side and capabilities for different configurations.• Upgraded data acquisition system.• Improved Power Unit.•Documented data on module performance for verification of theoretical results.(All these deliverables are expected to be ready by 05/22/09)
What is the preliminary budget estimate for the project cost?This project counts with a budget of $7500
Scope/Boundaries Describe the project's scope and boundaries. Describe what is in and outside the scope.
Activities within scope include:1. Implement air-cooling on cold side of thermo-electric array in addition to the water-cooling system.2. Be able to experimentally validate thermoelectric system models and enable more parameters to be explored.4. Improve set-up and shut-down procedures to reduce assembly times. 3. Improve user interface and data acquisition to allow greater ease of use of the test stand.The scope excludes:- Any study or design of the system that would eventually be implemented in industry.
Schedule/Milestones What are the start and completion dates of the project?
Starting Date: 12/01/08 System Level Design:01/02/09 Detailed Design:01/30/09 Project Completion:5/22/09
Benefit to CustomersWho are the Customers, what benefit will they see and what are their most critical
requirements?
Dresser-Rand: The results of experimentally testing valuable aspects of thermoelectric modules will provide insights on the feasibility of implementing this technology to provide energy recovery capabilities to Dresser-Rand's customers, which would further increase the value of the products, specially in applications in remote locations.RIT: This knowledge will help bring RIT to the forefront of this emerging technology.
Support Required (if any) Will you need any special capabilities, hardware, etc.?
Key Stakeholders Who has been identified as a Key Stakeholder(s) for this project?Primary Stakeholder: Dresser-Rand Secondary Stakeholder: RIT
BOMPart # Description Approximate Unit Price Quantity Cost Supplier Estimated Lead Time
Electrical SystemIRF640NPbF Power MOSFET $1.34 8 $10.72 Avnet <1 weekAavid Thermalloy: 6396BG MOSFET Heat Sinks $1.46 4 $5.84 Future Electronics <1 weekOhmite: TCH35P1R00JE Shunt Resistors $6.98 8 $55.84 Digikey <1 weekAavid Thermalloy: 593002B03400G Shunt Resistor Heat Sinks $0.68 4 $2.72 Future Electronics <1 week
Power Supply $300.00 1 $300.00PB-400 Breadboards $4.00 0 $0.00 All Electronics <1 week
DAQ expansion (32 channels) $480.00 0 $0.00Piping
4561T613 2" pipe 72" length $65.12 2 $130.24 McMaster-Carr4672T16 90 deg elbow $31.15 6 $186.90 McMaster-Carr4657T35 45 deg elbow $33.63 12 $403.56 McMaster-Carr4657T55 tees $58.19 4 $232.76 McMaster-Carr1JRL6 valves $47.70 3 $143.10 Grainger
Custom Headers 1 $0.00Power UnitHeatsink (linear ft) $387.72 1 $387.72 Aavid Thermalloy 2-3 daysPlate Aluminum $0.00Angle Aluminum $0.00 McMaster-CarrEndcap/Manifolds $0.00Cold plates $500.00 2 $1,000.00 Solid State Cooling
5591S Thermal gel pads (sheet) $15.52 0 $0.00 3MSensors and ModulesMelcor TE modules $26.50 40 $1,060.00 Melcor 2-3 weeksTaihauxing TE modules $30.00 40 $1,200.00 Taihauxing 2-3 weeksK type Thermocouples (1/16") $22.00 72 $1,584.00K type Thermocouples $22.00 3 $66.00K type Thermocouples $22.00 4 $88.00Thermocouple extension wire $138.00 1 $138.00 OmegaPressure Transducers $8.55 2 $17.10 Freescale SemiconductorFlexiforce sensors (sheet, 8 per sheet) $110.00 1 $110.00Op-Amps $0.34 16 $5.44 MicrochipManufacturingMachining $0.00Welding $0.00 Mahany