owto seminar 03022014

Upload: laszlo-arany

Post on 02-Jun-2018

223 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/10/2019 OWTO Seminar 03022014

    1/31

    Foundation Capabilities and LimitationsOffshore Wind Turbine Optimisation Seminar

    3rd

    - 4th

    February 2014 Dexter House, London

    Dr. C. R. Golightly GO-ELS Ltd. - Offshore Wind Turbine Optimisation Seminar 3 rd - 4th February 2014

    Dr. Chris Golightly GO-ELS Ltd.Geotechnical & Engineering Geology Consultant

    Source: Univ. Mass. 1974

    Source: WINDFLOAT Website

    Sources from top leftclockwise: Arup, BIFAB,COWI, RAVE Alpha Ventus

    Source: BELWIND Website

  • 8/10/2019 OWTO Seminar 03022014

    2/31

    Summary - Offshore Wind Turbine Foundations

    Introduction Global Offshore Wind Energy

    Differences; Oil & Gas Platforms Wind Turbines

    Types of Foundation for Offshore Wind Turbines [OWT]

    Codes and Standards; DNV, GL IEC, US

    Environmental, Geophysical & Geotechnical Site Investigations

    Monopiles Design & Installation

    4 Leg Piled Jackets OWEC, BIFAB, Truss Towers, Twisted Jacket

    Tripods Weserwind Alpha Ventus & OGN-Aquind

    BARD Tripile

    Gravity Base Structures [GBS] Gravitas, Vici Ventus, Gifford-Vinci, SeatowerSuction Caisson UF Monopod, Tripods, Quadrapods

    Others: Guyed Tower - A-Framed Monopile - TITAN Jack Up

    Foundation Costs - Comparisons

    Foundation Issues & Problems (1); Early Refusals & Piling Noise

    Pile Foundation Issues & Problems (2); Vibro Installation & Scour

    Pile Foundation Issues & Problems (3); Grouted Connections

    Pile Foundation Issues & Problems (4); Monopile Resonance, Cyclic Friction Degradation & Long Term Tilt in Sands

    Offshore Floating Solutions Huge Potential Offshore Wind ResourceFabrication Costs (Early 2010)

    Maps: UK Round 3 & German North Sea Sites

    Offshore Wind Cost Trends Need for Reduction

    Seabed A nchored Foundation Templates [SAFT]

    Conclusions, References, Contact Details

    Dr. C. R. Golightly GO-ELS Ltd. - Offshore Wind Turbine Optimisation Seminar 3rd

    - 4th February 2014

  • 8/10/2019 OWTO Seminar 03022014

    3/31

    Introduction Global OffshoreWind Energy

    Clean & abundant energy on global scale should accelerateas fossil fuel costs rise & renewables gain economies ofscale and innovation occurs The Crossover

    First offshore windfarm Denmark 1991. Proportion of RE inseveral European countries is increasing.

    But: as OW industry goes large scale, developers & lendersare conservative and risk averse. Stated liking for Creativeinnovation but also proven technnology .

    European focus is on Germany, Denmark, Sweden, Belgium& UK. France, USA, China, Japan developing rapidly Meditteranean, India, Brazil, S. Africa & others in future.

    Bigger, higher larger conventional 3 blade Siemens/VestasHAWT turbines dominant. Several 8 MW versions could betwin blade and VAWT in future (Sandia Labs. Studies).

    Move offshore from monopiles [15 - 30 m WD] jackets(UK)& tripods (Germany) [30-45 m WD] eventually to spar andTLP floaters [40-60 m +WD]

    In UK, offshore wind developers registered interest indeploying 46 GW of capacity & 10 GW has been progressedto consent determination, construction and operation.

    UK governments Renewables Roadmap aims to cut cost ofwind power to 100 per megawatt hour (MWh), with 18GW capacity off UK coast by 2020.

    Dr. C. R. Golightly GO-ELS Ltd. - Offshore Wind Turbine Optimisation Seminar 3 rd - 4th February 2014

    Source: Moustafaeipour, 2009

  • 8/10/2019 OWTO Seminar 03022014

    4/31

    LCOE Ranges and Averages [IRENA, 2013]

    Dr. C. R. Golightly GO-ELS Ltd. - Offshore Wind Turbine Optimisation Seminar 3 rd - 4th February 2014

  • 8/10/2019 OWTO Seminar 03022014

    5/31

    Differences; Oil & Gas Platforms Wind Turbines

    Oil & Gas Platforms

    Relatively stiff structures, usuallyfounded on long driven piles andmudmats

    Axial loads dominate due to highstructure weights

    Structural dynamics are not critical withweight >>> bending moments

    Wave loads tend to dominate design inhigh energy areas such as North Sea

    Straightforward Force Responserelationship

    Each design is one- off Prototype at asingle location

    Offshore Wind Turbines

    Relatively flexible towers on variety offoundation types, monopiles 4 to 9 mdiameter, tripods/4 leg jackets, GBS.

    Structural dynamics always critical. 3PEigenvalue resonance

    Bending moment and lateral responsemore important than axial load

    Wind and wave loads both veryimportant

    Complex uncorrelated/uncoupledloading

    Large Nos. of OWT in arrays (80 [German AVTripods] to 2000 [FOREWIND Statoil UK])

    Dr. C. R. Golightly GO-ELS Ltd. - Offshore Wind Turbine Optimisation Seminar 3 rd - 4th February 2014

  • 8/10/2019 OWTO Seminar 03022014

    6/31

    Types of Foundation for Offshore Wind Turbines [OWT]

    Choice of foundation solution influenced by: Water depth and seabed conditions,

    especially depth to rockhead Environmental loading (wind, wave, tidal) Onshore fabrication, storage and

    transportation requirements. Offshore vessel & equipment spread costs

    & availability Installation & Construction methodology

    available. Developer CAPEX investment appetite and

    OPEX (Repair & Maintenance) predictions Smarter solutions available (suctioncaissons, GBS, lighter jackets/trusses,hybrids, seabed anchored templates)Foundations 30 to 40% of overall CAPEX &rising. Cost reductions essential

    Smarter lighter hybrid foundations needed& move away from riskier costly conventionaldriven tubular steel piling.

    Dr. C. R. Golightly GO-ELS Ltd. - Offshore Wind Turbine Optimisation Seminar 3 rd - 4th February 2014

    Source: UPWIND Project Final Report 2011

    Source: NREL

  • 8/10/2019 OWTO Seminar 03022014

    7/31

    Codes and Standards; DNV, GL IEC, US

    Codes and Standards Hierarchy Offshore German Windfarms

    A. Bundesamt fur Seeschifffahrt undHydrographie [BSH, Federal Regulator]

    B1. Germanischer Lloyd [GL]

    B2. Det Norsk Veritas [DNV]

    B3. IEC

    B4. DIN (German National Standards)

    C1. API-RP2A (Oil & Gas OffshoreStructures)

    C2. DIBt

    C3. Norsok (Norwegian Offshore)

    C4. DASt Richtlinie

    D. Other Specific Standardswhere above do not covertechnical design in sufficientdetail

    Most Relevant Codes and Standards Det Norske Veritas DNV Offshore Standard DNV-OS-J101,Design for Offshore Wind Turbine Structures, Norway, 2004.Germanischer Lloyd Rules and Guidelines, IV IndustrialServices, Part 2 Guideline for the certification of offshorewind turbines, Germanischer Lloyd Windenergie GmbHHamburg, 2005.BSH Standard: 2007-06, Design of Offshore Wind Turbines

    API RP 2A Recommended Practice for Planning, Designingand Constructing Fixed Offshore Platforms

    LRFD Load and Resistance Factor Design, First Edition, July1993.- WSD Working stress design, 21 st edition, December2000. EN 1997-1:2009-09: Eurocode 7: Geotechnical Deisgn;Parts 1, 2 and 3.RECOFF Recommendations for Design of Offshore windturbines (RECOFF), European Energy, Environment andSustainable Development ProgrammeNorsok Standard N-003 Marine Actions, 2007.

    Dr. C. R. Golightly GO-ELS Ltd. - Offshore Wind Turbine Optimisation Seminar 3 rd - 4th February 2014

  • 8/10/2019 OWTO Seminar 03022014

    8/31

    Foundation Concepts 2012 2020 [Roland Berger Study 2013]

    Dr. C. R. Golightly GO-ELS Ltd. - Offshore Wind Turbine Optimisation Seminar 3 rd - 4th February 2014

  • 8/10/2019 OWTO Seminar 03022014

    9/31

    Environmental, Geophysical & Geotechnical Site Investigations Environmental Surveys

    Biogenic reefs & Benthic communitiesMarine archaeology, wrecks and seabed obstructionsGrab and gravity core sampling of Seabed surface sediments, for scour, plumes and cable burialSeabed mobility, sand waves and shoals

    Geophysical and Geotechnical Surveys

    Swath bathymetry, side scan sonar imagerySeismic reflection profiling for geological shallow stratigraphy and shallow gas presenceMagnetometer for pipelines, cables, metal objects and seabed junk & unexploded ordnance [UXO] Boreholes, vibrocores and cone penetration testing for geotechnical engineering parameters and soillayering

    Guidance Notes

    Society for Underwater Technology (SUT)/ Offshore Site Investigation and Geotechnics (OSIG) Committee(2005). Guidance Notes on Site Investigation for Offshore Renewable Projects, Rev. 02, March 2005.

    Bundesamt fur Seeschifffahrt und Hydrographie [BSH], (2008). Ground Investigations for OffshoreWindfarms. BSH Standard No. 7004, p. 40.

    Dr. C. R. Golightly GO-ELS Ltd. - Offshore Wind Turbine Optimisation Seminar 3 rd - 4th February 2014

  • 8/10/2019 OWTO Seminar 03022014

    10/31

    Monopiles Design &Installation

    Not a Pile but Driven Tubular SteelThin Walled Shell.

    Typically 4.5 - 9 m diameter,sometimes tapered

    Wall thicknesses 30 - 80 mm. D/t ratiovery high ~ 80 120.

    WD cut-off 20 to 35 m > pile lateral &seabed soil stiffnesses & layering.

    Weights up to 900 tonnes, limited byfloat out & crane capacities

    Driven or drive-drill-drive (UK) or evendrilled and grouted (France)

    Transition piece glued onto monopile

    with brittle high strength cement ~very strong granite > problems Simple, quick, suited to shallow water:

    problems - driving refusals & weight. Structure frequency limitations &

    fabrication, handling and installationconstraints.

    Dr. C. R. Golightly GO-ELS Ltd. - Offshore Wind Turbine Optimisation Seminar 3 rd - 4th February 2014

  • 8/10/2019 OWTO Seminar 03022014

    11/31

  • 8/10/2019 OWTO Seminar 03022014

    12/31

    Tripods Alpha Ventus & OGN-Aquind

    Weserwind - ALPHA VENTUS German federal funding 2001 2007 6 OWEC jackets/6 OWT tripods EPCI Contract value EUR 32m Client consortium: Vattenfall, Eon & EWE

    (DOTI) 1st offshore us of seabed template pre-

    piling (IHC) Adopted by Borkum West 2, Globaltech 1

    OGN-Aquind Newcastle based Oil & Gas fabricator TRITON 3 leg truss jacket for use in WD

    over 30 m & up to 80 m Major UK Govt. funding in 2012 for

    development and design of prototype jacket

    Steel savings, planning to be able tofabricate 150 jackets per year atHadrians Yard in Wallsend

    Dr. C. R. Golightly GO-ELS Ltd. - Offshore Wind Turbine Optimisation Seminar 3 rd - 4th February 2014

  • 8/10/2019 OWTO Seminar 03022014

    13/31

    BARD Tripile

    Dr. C. R. Golightly GO-ELS Ltd. - Offshore Wind Turbine Optimisation Seminar 3rd

    - 4th February 2014

  • 8/10/2019 OWTO Seminar 03022014

    14/31

    Gravity Base Structures [GBS] Gravitas, Vici Ventus, Gifford-Vinci, Seatower

    Simplicity: Certainty of delivery, increasedprogramme opportunities with fewer constraintsMinimal Seabed Preparation: Installed directlyonto seabed whenever possible avoiding needto remove or disturb surface sedimentsSelf-Floating: No heavy lift or specialist towingor installation vessels required. Reduced supplychain & weather constraints. Improved costcertainty, increased supplier base & lower costs

    Flexibility: Can be relocated, repowered andremoved at end of operational life. RC non-piled ballasted GBS with skirt option

    best solution in WD up to 60 m Large OWT up to 8 MW & standardised

    design Collar designs can accommodate ~ 2 deg

    vertical alignment tolerance Loading situation different to piled

    foundations & substantial vertical loadingrequired to ensure stability

    But: Generally impractical for OWT inrelatively shallow (< 15 m) water

    Bad publicity: German Strabag BSH rejection& over-designed Thornton Bank GBS.

    Dr. C. R. Golightly GO-ELS Ltd. - Offshore Wind Turbine Optimisation Seminar 3 rd - 4th February 2014

  • 8/10/2019 OWTO Seminar 03022014

    15/31

    Suction Caisson UF Monopod, Tripods, Quadrapods

    Suitable for all sand densities andintermediate strength clay Installation relatively simple &

    extensive oil & gas experiencefrom GoM, North Sea, W.Africa

    Installation/capacity predictionanalyses well developed. Scour

    protection design essential Highest quality geotechnical data

    and analyses necessary forstability assessment. Cyclicloading assessment critical

    Monopods installed successfullyfor Horns Rev Met Masts in 2009& adopted in 2012 for UKForewind/Firth of Forth Met Masts(Universal Foundation Monopod).

    SPT in NL developing tripod SCsolution funded by Carbon Trust.Dudgeon full field SC jacketsplanned for 2016.

    Dr. C. R. Golightly GO-ELS Ltd. - Offshore Wind Turbine Optimisation Seminar 3 rd - 4th February 2014

    Source: Oxford University Civil Engineering

    Source: SLP Engineering

    Source: DONG

    Source: DONG

  • 8/10/2019 OWTO Seminar 03022014

    16/31

    Guyed Tower and A-Framed Monopile

    Dr. C. R. Golightly GO-ELS Ltd. - Offshore Wind Turbine Optimisation Seminar 3 rd - 4th February 2014

    Source: WA Design Ltd.Source: Bunce and Carey EWEA 2001

  • 8/10/2019 OWTO Seminar 03022014

    17/31

    TITAN 200 FWSS Jack Up Concept

    Dr. C. R. Golightly GO-ELS Ltd. - Offshore Wind Turbine Optimisation Seminar 3 rd - 4th February 2014

    Source: http://offshorewindpowersystemsoftexas.com/titan_200_deep_offshore_platform

  • 8/10/2019 OWTO Seminar 03022014

    18/31

    Pile Foundation Issues & Problems (1); Early Refusals & Piling Noise

    Piling Refusals

    Heavy long large diameter monopilesand jacket piles increasingly being over-driven and drilled out in glacial depositsand bedrocks: Expensive and risky.

    Pile Tip Buckling

    (cf. Valhall Norwegian Aker/BP problems

    in 2004, Oil & Gas platform expensiverepair and claim). Over driving in verydense and /or cemented glacialmaterials in S. North Sea may lead tobuckling failures if the industry continuesto adopt conservatively long piles

    Piling Noise

    2011 rules in Germany 160 Dba @ 750

    m. restricted working periods &expensive mitigation measures. In UK soft start up piling and observationsrequired. Helical piles considered inScotland. Germany Air BubbleCurtains [ABC] & Hydro Sound Dampers[HSD] London Array, Baltic Sea tests.

    Dr. C. R. Golightly GO-ELS Ltd. - Offshore Wind Turbine Optimisation Seminar 3 rd - 4th February 2014

  • 8/10/2019 OWTO Seminar 03022014

    19/31

    Pile Foundation Issues & Problems (2); Vibro Installation & Scour

    Vibro-InstallationTripods levelled using seabed vibro-installation to ~8 15 m using vibrohammers to reduce conventional hammernoise, allowing sequential levelling. Newishtechnique used on several large projects.

    Accepted commercially viable offshoreGermany for partial pile installations

    through pile sleeves or pre-installed groupsor monopiles.

    Scour Prediction & Mitigation

    Scour prediction according to DNV; S=1.3-1.6 * D. depends upon WD, soil type andgrading and seabed current.

    May be allowed to develop (longer piles) orgravel and rock dump protection required (~500 -700 k Euros per monopile)

    Alternatives include frond mats (plasticseaweed), rock mats, pile eddy breakingfins or diversion berms and fences

    Accurate and cheap acoustic direct scourmonitoring now possible (e.g. Alpha Ventus).

    Available commercially.

    Dr. C. R. Golightly GO-ELS Ltd. - Offshore Wind Turbine Optimisation Seminar 3 rd - 4th February 2014

    Source: Thyssen-Krupp.Source: SLP Engineering

    Source: CEFAS Travelling Sand Waves @ Monopiles

  • 8/10/2019 OWTO Seminar 03022014

    20/31

    Pile Foundation Issues & Problems (3); Grouted Connections

    For OWT monopiles, the transition piece [TP] transmits highbending moments. Brittle rock-like grouted connections wereadopted for most European projects for speed & cost savings.Most excluded reinforcing shear keys due to design codeomission. These have settled, cracked and failed on 70% UKmonopiles. Systemic design fault. Variety of extensive andcostly repairs have been required on many European projects.Oil & gas platform jackets used API designed grouted

    connections for decades, but grout connection in jackets holda large mass so are always in compression. OWTs are light &subjected to long term cyclic bending, so complex vertical +bending force coupling & tensile stresses.

    Ability to transfer large moment is not fully understood &design theories have limitations & shortfalls. The use ofconical TP sections as a solution [controlled failure] isuncertain in the long term.Industry best practice and code guidelines review on reliabilityof grouted connections. DNV guidelines were revised in 2011(new Code 2014), but still anomalies in predicting behaviour.Research ongoing to understand size and fatigue effects.Many developers reverting to bolted flange connections(Scroby Sands, North Hoyle and Blyth 12 years ago), withsome considering pile swaging or even slip joints as a morereliable long term solution. Requires verticality, careful driving.

    Dr. C. R. Golightly GO-ELS Ltd. - Offshore Wind Turbine Optimisation Seminar 3 rd - 4th February 2014

    Source: Harding et al 2012

    Source: Lotsberg 2012

  • 8/10/2019 OWTO Seminar 03022014

    21/31

    Pile Foundation Issues & Problems (4); Monopile Resonance, CyclicFriction Degradation & Long Term Tilt in Sands

    Monopile Resonance

    Selection of dynamic properties essential for costeffective/reliable design. Affects rotor and supportstructure interaction & soil-foundation dynamic response.

    Design solutions depend upon ratio between fundamentalstructure eigenfrequency f o, rotor frequency f R and bladepassing frequency f b = N b* f R choice between soft -soft [f o < f R ], soft -stiff [f R < f o < f b] and stiff -stiff [f B < f o].Cyclic Friction Degradation

    Substantial reductions in axial pile friction and lateral P-Yresponse may occur due to the cyclic long term loadingexperienced by monopiles supporting large heavy 3-bladed5 MW + HAWT turbines

    Long Term OWT Tower Tilt in Sands

    Settling of towers/monopiles embedded in sands but notkeyed into bedrock may be large, leading to excessive tiltand shutdown & resetting for gearbox turbines.

    Tilt of 0.5 deg is usual for OWT. Permanent tilt due toConstruction tolerance permanent tilt is subtracted, withtypical values 0.20 to 0.25 deg. Allowable operationalrotational stiffness is typically 25 to 30 GNm/radians.

    Dr. C. R. Golightly GO-ELS Ltd. - Offshore Wind Turbine Optimisation Seminar 3 rd - 4th February 2014

    CyclicDisplacement

    Accumulation in

    Sands. Source: Achmus, Abdel-Rahman & Kuo(2007)

  • 8/10/2019 OWTO Seminar 03022014

    22/31

    Foundation Costs Comparisons

    Dr. C. R. Golightly GO-ELS Ltd. - Offshore Wind Turbine Optimisation Seminar 3 rd - 4th February 2014

    Source: UPWIND Project Final report

  • 8/10/2019 OWTO Seminar 03022014

    23/31

    Offshore Floating Solutions Huge Potential Offshore Wind Resource

    Dr. C. R. Golightly GO-ELS Ltd. - Offshore Wind Turbine Optimisation Seminar 3 rd - 4th February 2014

    Source: The Offshore Valuation, 2010.

  • 8/10/2019 OWTO Seminar 03022014

    24/31

    Future Offshore Wind Tethered Floating Structures 2 Examples

    Dr. C. R. Golightly GO-ELS Ltd. - Offshore Wind Turbine Optimisation Seminar 3rd

    - 4th February 2014

    Source: Maine Int. Consulting, 2013.

  • 8/10/2019 OWTO Seminar 03022014

    25/31

    Fabrication Costs (early 2010)

    Dr. C. R. Golightly GO-ELS Ltd. - Offshore Wind Turbine Optimisation Seminar 3 rd - 4th February 2014

    Source: Ballast Nedam, 2010.

  • 8/10/2019 OWTO Seminar 03022014

    26/31

    Maps: UK Round 3 & German North Sea Sites

    Dr. C. R. Golightly GO-ELS Ltd. - Offshore Wind Turbine Optimisation Seminar 3 rd - 4th February 2014

  • 8/10/2019 OWTO Seminar 03022014

    27/31

    Offshore Wind Cost Trends Need for Reductions

    Cost increases since 2005 due tocommodity price rises (mainlysteel) and installation

    Monopile costs per kW flat-lining1991 2008

    Deeper waters:- heavier and longer over-designed monopiles- more extensive and expensiveequipment and vessel spreads- higher downtime and weatherstandby costs

    Insistence on known technologyleading to lack of innovation,conservatism, risk aversion on thepart of developers and lenders.

    Lack of experience in developerorganisations; general skillsshortage.

    Dr. C. R. Golightly GO-ELS Ltd. - Offshore Wind Turbine Optimisation Seminar 3 rd - 4th February 2014

    Source: van der Zwaan et al, 2011

    Source: The Offshore Valuation, 2010

  • 8/10/2019 OWTO Seminar 03022014

    28/31

    Main Conclusions (1)

    1. Initially this new offshore industry has understandably used conservative

    monopile and piled tripod (Germany) & 4-leg jacket (UK) solutions. CAPEXand investment still limited compared to other energy industries.

    2. European Offshore Wind Industry has developed several foundationsolutions, steel /concrete, monopiles, AV piled tripods, BARD tripiles, triple& 4-leg jackets, truss towers, twisted jacket, guyed & A-frame monopiles,monopod suction caisson, triple/quad suction caissons.

    3. Main Foundation Risks: Grouted connections, piling noise mitigation, over-conservative long, stiff, heavy pile design, pile tip buckling, unplanneddrilling/re-driving, tilt and settlement.

    4. As more difficult rocky, irregular sites are encountered in deeper water,innovative and creative thinking necessary at an earlier stage (c.f. Atlanticand Argyll Array cancellations due to challenging seabed conditions)

    5. Grouted connections fiasco -70% UK MPs failed. To be avoided if possible.Use bolted flanges or other direct connections. If unavoidable use shearkeys & robust grout seals. Are non shear keyed conical [1 o-3o] sectionsand/or elastomeric spring bearings valid for fatigue design life?

    Dr. C. R. Golightly GO-ELS Ltd. - Offshore Wind Turbine Optimisation Seminar 3 rd - 4th February 2014

  • 8/10/2019 OWTO Seminar 03022014

    29/31

    Main Conclusions (2)

    6. Industry as a whole needs more realistic offshore turbine tilt criteria, based

    upon sound engineering analysis. Big impact on structure costs, influencingbusiness cases. Development of tilt-tolerant DD turbines can reduce costs.

    7. New foundation solutions [e.g. Carbon Trust] slowly & patchily embraced(Met. Masts) in UK/Germany. Concrete GBS, twisted jackets & suctioncaissons more suited to some sites. Solutions extensive in offshore oil & gas.

    8. For foundation costs to reduce [halved acc. US DoE], innovative solutionsneeded, selected/tailored to specific site conditions. Conservative risk averseattitudes in a relatively new industry should change as experience is gained.

    9. The current plans to move to ~10 m dia., 1200 Tonne, 60 m + lengthmonopiles in ~40 m WD may be questionable & should be challenged.

    10. Globally, early development of floating alternatives increasing, HYWIND

    [Statoil], Principle Power [WINDFLOAT], Wave Hub [Glosten], Blue H,Offshore Japan [Various], France [IDEOL, WINFLO, VERTIWIND].

    11. Gyro-stabilised floaters, fully submerged concrete/composites, tensiontethered damped synthetic mooring line, FPSO template, vertical axisturbines [VAWT] in WD > 50 m hold out most promise. Hybrid wind/tidal?

    Dr. C. R. Golightly GO-ELS Ltd. - Offshore Wind Turbine Optimisation Seminar 3 rd - 4th February 2014

  • 8/10/2019 OWTO Seminar 03022014

    30/31

    References & Links

    References Douglas- Westwood (2013), World Offshore Wind Market Forecast 2013 -2022, 5 th Edition.Golightly, C.R. (2014), Tilting of Monopiles ; Long, Heavy and Stiff; Pushed Beyond Their Limits, GroundEngineering; 2014, vol 47, No. 1, pp 20-23.van der Zwaan, R., Rivera-Tinoco, R., Lensink, S. & van den Oosterkamp , P., (2010) Evolving Economics of OffshoreWind Power: Cost Reductions from Scaling and Learning , Amsterdam 2010, p. 9. The Offshore Evaluation Group (2010), The Offshore Valuation Report; A Valuation of the UKs Offshore RenewableEnergy Resource, Public Interest Research Centre, p. 108. Maine International Consulting (2013), Floating Offshore Wind Foundations; Industry Consortia and Projects in theUnited States, Europe and Japan; An Overview, May 2013, p. 45Roland Berger (2013), Offshore Wind Toward 2020; On The Pathway to Cost Competitiveness, April 2013, p. 25.

    LinksEWEA Offshore Statistics 2013 ewea.org/fileadmin/files/library/publications/statistics/EWEA_OffshoreStats_July2013.pdfEC Marine Knowledge 2020 Databaseec.europa.eu/maritimeaffairs/policy/marine_knowledge_2020Global Wind Energy Council Country & Global Reportswww.gwec.net/publications/country-reportsIRENA Costs Database; irena.org/costsUK Govt. Offshore Wind Industrial Strategyhttps://www.gov.uk/government/uploads/system/uploadsUSA Offshore Wind Database: offshorewind.net4C Offshore Wind Database: 4coffshore.comUPWIND EWEA Project Final Report: upwind.eu

    Dr. C. R. Golightly GO-ELS Ltd. - Offshore Wind Turbine Optimisation Seminar 3 rd - 4th February 2014

  • 8/10/2019 OWTO Seminar 03022014

    31/31

    Contact Details

    Dr. C.R. Golightly, BSc, MSc, PhD, MICE, FGS . Geotechnical and Engineering Geology ConsultantRue Marc Brison 10G, 1300 Limal, BelgiumTel. +32 10 41 95 25Mobile: +44 755 4612888Email: [email protected]: chrisgolightly;

    Linked In: www.linkedin.com/pub/5/4b5/469

    You Pay for a Site Investigation -Whether You do One or Not Coleet al, 1991.

    Ignore The Geology at Your Peril Prof. John Burland, Imperial College.

    d

    http://www.linkedin.com/pub/5/4b5/469http://www.linkedin.com/pub/5/4b5/469