overview of wave energy technology...(typically 100 kw to 2 mw) short-term (days to months) tests in...

28
Overview of Wave Energy Technology Mirko Previsic Technology Lead – EPRI Ocean Energy Programs

Upload: others

Post on 05-Dec-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Overview of Wave Energy Technology...(typically 100 kW to 2 MW) Short-term (days to months) tests in natural waters (typically 10 kW to 100 kW) Rigorous laboratory tow- or wave-tank

Overview of Wave Energy Technology

Mirko PrevisicTechnology Lead – EPRI Ocean Energy Programs

Page 2: Overview of Wave Energy Technology...(typically 100 kW to 2 MW) Short-term (days to months) tests in natural waters (typically 10 kW to 100 kW) Rigorous laboratory tow- or wave-tank

2

Agenda

• The Resource in perspective

• Siting Considerations

• Technology Examples

Page 3: Overview of Wave Energy Technology...(typically 100 kW to 2 MW) Short-term (days to months) tests in natural waters (typically 10 kW to 100 kW) Rigorous laboratory tow- or wave-tank

3

The source of the issue is you and me …increasing energy demand

Source: U.S. Department of Energy, Energy Information Administration, Annual Energy Review 2005 andAnnual Energy Outlook 2007 Early Release

0

1,000

2,000

3,000

4,000

5,000

6,000

1970

1975

1980

1985

1990

1995

2000

2005

2010

2015

2020

2025

2030

billi

on k

ilow

atth

ours

Historical Projected

Page 4: Overview of Wave Energy Technology...(typically 100 kW to 2 MW) Short-term (days to months) tests in natural waters (typically 10 kW to 100 kW) Rigorous laboratory tow- or wave-tank

4

Renewable Energy Benefits

• Electricity is the leading source of US carbon emissions• Fossil fuel-based generation produces other emissions as well• Avoided emissions at an installed capacity of 4000 MW (California has a

technical potential of > 15,000MW) of wave plants at 40% capacity factorusing a proxy coal plant with emissions at NSPS limit (actual plants may beless)

Pollutant Emissions Rate (tons/year) SOx 1.4 lbs/MWhr 10,000 NOx 1.0 lbs/MWhr 7,000 CO2 0.8 tons/MWhr 11,000,000 Mercury 2.1 X 10-6 lbs/MWhr 0.014 Particulates 0.2 lbs/MWhr 1,400

Page 5: Overview of Wave Energy Technology...(typically 100 kW to 2 MW) Short-term (days to months) tests in natural waters (typically 10 kW to 100 kW) Rigorous laboratory tow- or wave-tank

5

Wave Power Densities - Globally

Page 6: Overview of Wave Energy Technology...(typically 100 kW to 2 MW) Short-term (days to months) tests in natural waters (typically 10 kW to 100 kW) Rigorous laboratory tow- or wave-tank

6

U.S. Offshore Wave Energy Resources

New Englandand Mid-Atlantic

110 TWh/yr

WA, OR, CA440 TWh/yr

Southern AK1,250 TWh/yr

Northern HI300 TWh/yr

Total flux into all regions with mean wavepower density >10 kW/m is 2,100 TWh/yr

Extracting 15% of total fluxand converting to electricity at80% efficiency would yield252 TWh/yr

Page 7: Overview of Wave Energy Technology...(typically 100 kW to 2 MW) Short-term (days to months) tests in natural waters (typically 10 kW to 100 kW) Rigorous laboratory tow- or wave-tank

7

U.S. Wave and Current Energy Potential

U.S. conventional hydro-electricgeneration in 2004 was ~260 TWh/yr

Wave and current generation potential

– Offshore wave 250-260 TWh/yr(15% of primary energy)

– Tidal, river, and ocean currentsTBD but maybe half of wave

Potential to meet nearly 10%of national demand

Page 8: Overview of Wave Energy Technology...(typically 100 kW to 2 MW) Short-term (days to months) tests in natural waters (typically 10 kW to 100 kW) Rigorous laboratory tow- or wave-tank

8

California Wave Energy Resource

Coast Length: 1200 km

Average Power: 37,000 MW

Technical Potential: 7,460 MW

⇒65 TWh/yr =>

⇒23% of California Electricity Needs

California has a significant Wave Energy Potential, justifying moving forward with ademonstration plant in a controlled and closely monitored environment

Page 9: Overview of Wave Energy Technology...(typically 100 kW to 2 MW) Short-term (days to months) tests in natural waters (typically 10 kW to 100 kW) Rigorous laboratory tow- or wave-tank

9

Agenda

• The Resource in perspective

• Siting Considerations

• Technology Examples

Page 10: Overview of Wave Energy Technology...(typically 100 kW to 2 MW) Short-term (days to months) tests in natural waters (typically 10 kW to 100 kW) Rigorous laboratory tow- or wave-tank

10

What makes a good Wave Power Site?

• High Wave Power Density• Nearby Port Infrastructure for Operational Considerations• Nearby Grid Interconnection• Water depth of about 50m

Page 11: Overview of Wave Energy Technology...(typically 100 kW to 2 MW) Short-term (days to months) tests in natural waters (typically 10 kW to 100 kW) Rigorous laboratory tow- or wave-tank

11

State Overview – Port Facilitites

Humboldt Bay

Noyo Harbor

Bodega Bay

SF Bay Area

Half Moon Bay

Monterrey Bay

Morro Bay

Santa Barbara

Los Angeles

San Diego

Deepwater Ports in California

- Humboldt Bay

- SF Bay Area

- Los Angeles

- San Diego

Other ports would likely need some

Modifications to carry out O&M such

as dredging and building docks etc.

Page 12: Overview of Wave Energy Technology...(typically 100 kW to 2 MW) Short-term (days to months) tests in natural waters (typically 10 kW to 100 kW) Rigorous laboratory tow- or wave-tank

12

Deployment Locations – SF Area

21kW/m

35kW/m

31kW/m

11kW/m

Principal Wave Direction

Substation

Substation

Substation

Page 13: Overview of Wave Energy Technology...(typically 100 kW to 2 MW) Short-term (days to months) tests in natural waters (typically 10 kW to 100 kW) Rigorous laboratory tow- or wave-tank

13

Technology Development Status

Long-term (>1 yr duration)prototypes in natural waters

(typically 100 kW to 2 MW)

Short-term (days to months)tests in natural waters

(typically 10 kW to 100 kW)

Rigorous laboratorytow- or wave-tank

physical model tests(1/50- to 1/5-scale)

a fewdozen

hundreds

a few

Thousand of concepts and patents on oceanenergy conversion technology

It typically takes 5 to 10 years for a technologyto progress from concept-only to deployment

of a long-term prototype

Page 14: Overview of Wave Energy Technology...(typically 100 kW to 2 MW) Short-term (days to months) tests in natural waters (typically 10 kW to 100 kW) Rigorous laboratory tow- or wave-tank

14

Components of a Wave Farm

Unit 1

G G

Unit 2

SubstationSub-sea Junction

Box

Riser Cable

Jumper Cable

Landfall

1km

...Unit 82

G

7690m

18

00m

Cluster 1: 154 Devices

Cluster 2-4

26kV

/ 4

0M

VA

Existing Grid

Wave

Direction

Page 15: Overview of Wave Energy Technology...(typically 100 kW to 2 MW) Short-term (days to months) tests in natural waters (typically 10 kW to 100 kW) Rigorous laboratory tow- or wave-tank

15

Agenda

• The Resource in perspective

• Siting Considerations

• Technology Examples

Page 16: Overview of Wave Energy Technology...(typically 100 kW to 2 MW) Short-term (days to months) tests in natural waters (typically 10 kW to 100 kW) Rigorous laboratory tow- or wave-tank

16

Wave Power Conversion Principles

16

Page 17: Overview of Wave Energy Technology...(typically 100 kW to 2 MW) Short-term (days to months) tests in natural waters (typically 10 kW to 100 kW) Rigorous laboratory tow- or wave-tank

17

UK Based Ocean Power Delivery Pelamis

Power module at front of eachtube section contains twohydraulic cylinders that arestroked by relative pitch andyaw between adjacent sections

relativePITCH

relativeYAW

TOP VIEW

SIDE VIEW

3.5 m dia x150 m long

Pelamis 750 kW prototype installed in Augustof 2004 in 50 m water depth, 2 km offshore theEuropean Marine Energy Centre, Orkney, UK

Pelamis 1st commercial sale occurred2005 – OPD Pelamis in Portugal –contains an early 3 unit qualification

Page 18: Overview of Wave Energy Technology...(typically 100 kW to 2 MW) Short-term (days to months) tests in natural waters (typically 10 kW to 100 kW) Rigorous laboratory tow- or wave-tank

18

UK Based Ocean Power Delivery Pelamis

Total Device Length: 150mDevice Diameter: 4.63mStructural Steel Weight: 380tonsAverage Power (24kW/m): 152kWWater Depth: >50m

Page 19: Overview of Wave Energy Technology...(typically 100 kW to 2 MW) Short-term (days to months) tests in natural waters (typically 10 kW to 100 kW) Rigorous laboratory tow- or wave-tank

19

Mooring (Pelamis Example)

Page 20: Overview of Wave Energy Technology...(typically 100 kW to 2 MW) Short-term (days to months) tests in natural waters (typically 10 kW to 100 kW) Rigorous laboratory tow- or wave-tank

20

Mooring Components (Pelamis Example)

Page 21: Overview of Wave Energy Technology...(typically 100 kW to 2 MW) Short-term (days to months) tests in natural waters (typically 10 kW to 100 kW) Rigorous laboratory tow- or wave-tank

21

Operation

Page 22: Overview of Wave Energy Technology...(typically 100 kW to 2 MW) Short-term (days to months) tests in natural waters (typically 10 kW to 100 kW) Rigorous laboratory tow- or wave-tank

22

North America Wave Energy ProjectsKaneohe HI – OPT PowerBuoy

Page 23: Overview of Wave Energy Technology...(typically 100 kW to 2 MW) Short-term (days to months) tests in natural waters (typically 10 kW to 100 kW) Rigorous laboratory tow- or wave-tank

23

OPT PowerBuoy - Specs

Reference: PAD filed with FERC in July

Page 24: Overview of Wave Energy Technology...(typically 100 kW to 2 MW) Short-term (days to months) tests in natural waters (typically 10 kW to 100 kW) Rigorous laboratory tow- or wave-tank

24

OPT PowerBuoy – Mooring Configuration

Anchor Blocks:

-Concrete block measuring 6x6x3m

-165 metric tons

Page 25: Overview of Wave Energy Technology...(typically 100 kW to 2 MW) Short-term (days to months) tests in natural waters (typically 10 kW to 100 kW) Rigorous laboratory tow- or wave-tank

25

Finavera - AquaBuOY

Page 26: Overview of Wave Energy Technology...(typically 100 kW to 2 MW) Short-term (days to months) tests in natural waters (typically 10 kW to 100 kW) Rigorous laboratory tow- or wave-tank

26

Path Forward In California

Page 27: Overview of Wave Energy Technology...(typically 100 kW to 2 MW) Short-term (days to months) tests in natural waters (typically 10 kW to 100 kW) Rigorous laboratory tow- or wave-tank

27

End

Any questions?

Email: [email protected]

Need more data? EPRI has published 20 reports onwave energy conversion. Available at:

www.epri.com/oceanenergy

Page 28: Overview of Wave Energy Technology...(typically 100 kW to 2 MW) Short-term (days to months) tests in natural waters (typically 10 kW to 100 kW) Rigorous laboratory tow- or wave-tank

28

Wave Power – PG&E Wave Plug

PG&ESubstatio

nWav

e P

lug

Wave FarmDevice A

Wave FarmDevice B

Demo Device A

Demo Device BDemo Device C

PG&E Permit Area

Shared O&M Facilities

Dis

tribu

ted

Per

mitt

ing

Cos

tsWave Direction