overview of ceos actions in support of geo 2009-2011 work plan ivan petiteville ceo esa 1 23 rd ceos...

18
Overview of CEOS Actions in Support of GEO 2009- 2011 Work Plan Ivan Petiteville CEO ESA 1 23 rd CEOS Plenary I Phuket, Thailand I 3-5 November2009

Upload: cody-whitehead

Post on 05-Jan-2016

213 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Overview of CEOS Actions in Support of GEO 2009-2011 Work Plan Ivan Petiteville CEO ESA 1 23 rd CEOS Plenary I Phuket, Thailand I 3-5 November2009

Overview of CEOS Actions in Support of GEO 2009-2011

Work PlanIvan Petiteville

CEOESA

123rd CEOS Plenary I Phuket, Thailand I 3-5 November2009

Page 2: Overview of CEOS Actions in Support of GEO 2009-2011 Work Plan Ivan Petiteville CEO ESA 1 23 rd CEOS Plenary I Phuket, Thailand I 3-5 November2009

Plan

• Overview

• Overall Status

• Lessons Learned

The 23rd CEOS Plenary I Phuket, Thailand I 3-5 November 2009 2

Page 3: Overview of CEOS Actions in Support of GEO 2009-2011 Work Plan Ivan Petiteville CEO ESA 1 23 rd CEOS Plenary I Phuket, Thailand I 3-5 November2009

Overview

The 23rd CEOS Plenary I Phuket, Thailand I 3-5 November 2009 3

Page 4: Overview of CEOS Actions in Support of GEO 2009-2011 Work Plan Ivan Petiteville CEO ESA 1 23 rd CEOS Plenary I Phuket, Thailand I 3-5 November2009

CEOS Support to GEOMultifold support:• Coordination role

– CEOS is Point of Contact for 11 GEO Tasks (out of 16 co-led by CEOS)

• Support to GEO groups: – GEO Committees, adhoc GEO groups (e.g. Target Team), GEO Task

Teams

• Strong involvement of CEOS Support Groups:– 3 Working Groups, 6 Virtual Constellation teams, 8 CEOS SBA teams

of experts, SEO– Many resources from CEOS Agencies

The 23rd CEOS Plenary I Phuket, Thailand I 3-5 November 2009 4

Page 5: Overview of CEOS Actions in Support of GEO 2009-2011 Work Plan Ivan Petiteville CEO ESA 1 23 rd CEOS Plenary I Phuket, Thailand I 3-5 November2009

CEOS Groups

The 23rd CEOS Plenary I Phuket, Thailand I 3-5 November 2009 5

Page 6: Overview of CEOS Actions in Support of GEO 2009-2011 Work Plan Ivan Petiteville CEO ESA 1 23 rd CEOS Plenary I Phuket, Thailand I 3-5 November2009

GEO Tasks/Sub-Tasks Co-Led by CEOS

The 23rd CEOS Plenary I Phuket, Thailand I 3-5 November 2009 6

only CEOS POC

both CEOS & GEO POC

Page 7: Overview of CEOS Actions in Support of GEO 2009-2011 Work Plan Ivan Petiteville CEO ESA 1 23 rd CEOS Plenary I Phuket, Thailand I 3-5 November2009

CEOS-GEO Actions Figures (March 09)

• In 2009, CEOS activities are related to 36 GEO 2009-2011 Tasks (out of 115)

• 93 GEO Actions (related to 36 GEO Tasks) + + 59 “GCOS” Actions (related to CL-06-01c “Key Climate Data from Satellite Systems” )– From 2008 to 2009, number of Actions roughly divided by 2 – 47 in Cat. 1 (top priority; significant outcomes or to be completed

before Nov. 09)– 26 in Cat. 2 (other top priority)– 38 GCOS top priority Actions (21 from 2008 + 17 started in 2009

The 23rd CEOS Plenary I Phuket, Thailand I 3-5 November 2009 7

Page 8: Overview of CEOS Actions in Support of GEO 2009-2011 Work Plan Ivan Petiteville CEO ESA 1 23 rd CEOS Plenary I Phuket, Thailand I 3-5 November2009

CEOS Activities in Support to GEO

SIT Chair has sought CEOS Agencies commitment to allocate the necessary resources to support all the actions•Tag-up telecons with CEOS Principals in preparation for both SIT-23 and SIT-24•SIT-23 Tour de Table

The 23rd CEOS Plenary I Phuket, Thailand I 3-5 November 2009 8

Page 9: Overview of CEOS Actions in Support of GEO 2009-2011 Work Plan Ivan Petiteville CEO ESA 1 23 rd CEOS Plenary I Phuket, Thailand I 3-5 November2009

Overall Status

The 23rd CEOS Plenary I Phuket, Thailand I 3-5 November 2009 9

Page 10: Overview of CEOS Actions in Support of GEO 2009-2011 Work Plan Ivan Petiteville CEO ESA 1 23 rd CEOS Plenary I Phuket, Thailand I 3-5 November2009

CEOS Cat 1 Actions Overall Status (Oct. 7, 09)

• 14 Cat 1 Actions are “CLOSED” and 5 are about to be “CLOSED”– 8 Cat 2-to-4 Actions also “CLOSED”

• 21 Cat 1 Actions are on-schedule ( or with delays < 3 months).

• 6 Cat 1 Actions are significantly delayed (> 3 months)

• No status information received for at least the last 3 months for 2 actions

The 23rd CEOS Plenary I Phuket, Thailand I 3-5 November 2009 10

Page 11: Overview of CEOS Actions in Support of GEO 2009-2011 Work Plan Ivan Petiteville CEO ESA 1 23 rd CEOS Plenary I Phuket, Thailand I 3-5 November2009

Status (Oct. 7, 2009)

CEOS GEO Cat 1 Actions Overall Status

Status (Oct. 7, 2009)Predicted Status (Dec. 31, 2009)

Page 12: Overview of CEOS Actions in Support of GEO 2009-2011 Work Plan Ivan Petiteville CEO ESA 1 23 rd CEOS Plenary I Phuket, Thailand I 3-5 November2009

Overall Cat Actions Status (Oct. 7, 2009)

Page 13: Overview of CEOS Actions in Support of GEO 2009-2011 Work Plan Ivan Petiteville CEO ESA 1 23 rd CEOS Plenary I Phuket, Thailand I 3-5 November2009

Some Figures on Achievements (1/2)

• Major documents produced (at least 16 actions):

– e.g. Ocean Surface Topography Constellation User Requirements;

– e.g. Atmospheric Composition Constellation (ACC) Air Quality Workshop report and Gap Analysis Study report

• More than 30 new public datasets generated (at least 15 actions)– e.g. Optical and Radar data acquired for GEO FCT; – e.g. Real time malaria risk map, …– As in 2008, these datasets will be registered in GEOSS

Registry

Page 14: Overview of CEOS Actions in Support of GEO 2009-2011 Work Plan Ivan Petiteville CEO ESA 1 23 rd CEOS Plenary I Phuket, Thailand I 3-5 November2009

Some Figures on Achievements (2/2)

• About 13 Workshops and Training Courses organized (8 actions)

– e.g. 2-weeks training course ‘Methods and Application of Ocean Color Remote Sensing in African Coastal and regional Seas’ (Ocean Colour Radiometry Constellation) ,…

• About 8 Web Portals set up or significantly upgraded (8 actions)

– e.g. Solar Shield project ; – e.g. CEOS Earth Observation Handbook, …

Page 15: Overview of CEOS Actions in Support of GEO 2009-2011 Work Plan Ivan Petiteville CEO ESA 1 23 rd CEOS Plenary I Phuket, Thailand I 3-5 November2009

Lessons Learned

Page 16: Overview of CEOS Actions in Support of GEO 2009-2011 Work Plan Ivan Petiteville CEO ESA 1 23 rd CEOS Plenary I Phuket, Thailand I 3-5 November2009

Lessons Learned (1/3)

1. Overall Actions progress status similar to last year

2. Majority of Actions refer to activities planned independently of GEO WP but still their outcomes and deliverables are of interest to the User Community. Currently outcomes detailed only in CEOS IP v3.1 (not user-friendly !!) Publication and advertising even of “minor” achievements to be

improved (e.g. on CEOS Web Site, or a potential CEOS Annual Report )

3. Difficulties as CEO to manage some of those Actions because of lack / infrequent reporting More regular reporting expected from CEOS SBA Coordinators and

actionees . Plan to go to on-line and more user-friendly version (still requires

efforts from actionees). See proposal from SEO.

Page 17: Overview of CEOS Actions in Support of GEO 2009-2011 Work Plan Ivan Petiteville CEO ESA 1 23 rd CEOS Plenary I Phuket, Thailand I 3-5 November2009

Lessons Learned (2/3)

4. Number of CEOS-GEO Actions could be reduced: Some actions run by a single Agency:

Should involve more than one single Agency Should demonstrate that their accomplishment requires

involvement of other agencies Actions that can be done by a single Agency should not be

considered.

Some current CEOS-GEO Actions do not deserve to be in that list e.g. Action leading to the publication of an article for a

conference. Instead the article could be referenced on the CEOS Web Site ("news" page and "articles" page) or published in a CEOS Annual Report (more of an outreach orientation than CEOS IP)

Page 18: Overview of CEOS Actions in Support of GEO 2009-2011 Work Plan Ivan Petiteville CEO ESA 1 23 rd CEOS Plenary I Phuket, Thailand I 3-5 November2009

Lessons Learned (3/3)

5. Management of some GEO Tasks co-led by CEOS to be improved: Improved coordination with other GEO Task co-Leads

and Contributors More regular reporting (GEO Secretariat expects three

reports a year)