Page 1: Our Addition Process

Good Homes & Additions

adds a family room

and master bathroom

to our homeDecember 3, 2010 –

January 28, 2011

Page 2: Our Addition Process

BEFORE

Page 3: Our Addition Process

Day 1

Officially underway!

Page 4: Our Addition Process

Taking off the deck

Page 5: Our Addition Process

Digging the hole

Page 6: Our Addition Process

Our dirt piles

Page 7: Our Addition Process

The foundation

Page 8: Our Addition Process
Page 9: Our Addition Process

Day 2

Special delivery

Page 10: Our Addition Process

The cinder block arrives

Page 11: Our Addition Process
Page 12: Our Addition Process
Page 13: Our Addition Process

More piles in the yard

Page 14: Our Addition Process

Day 3

The mason gets to work on the crawl space

Page 15: Our Addition Process
Page 16: Our Addition Process
Page 17: Our Addition Process

Day 4

The foundation/crawl space walls are complete.

Page 18: Our Addition Process
Page 19: Our Addition Process
Page 20: Our Addition Process

Day 5

One less pile of dirt in our yard

Page 21: Our Addition Process
Page 22: Our Addition Process

The cement mixer arrives.

Page 23: Our Addition Process

A floor for the crawl space…

Page 24: Our Addition Process

and basement access

Page 25: Our Addition Process

Stone for under the eventual patio

Page 26: Our Addition Process

Day 6

Our steel beam

Page 27: Our Addition Process

Lumber for framing is delivered

Page 28: Our Addition Process

Ruts in our yard

Page 29: Our Addition Process

Day 7

We have a floor!

Page 30: Our Addition Process

Getting the back wall ready

Page 31: Our Addition Process

Setting the wall in place

Page 32: Our Addition Process
Page 33: Our Addition Process
Page 34: Our Addition Process

Day 8

The shower arrives

Page 35: Our Addition Process

The view from the front

Page 36: Our Addition Process

All the walls are up!

Page 37: Our Addition Process

The bathroom-to-be

Page 38: Our Addition Process

Day 9

Roof trusses arrive

Page 39: Our Addition Process

The house is wrapped and the roof is started.

Page 40: Our Addition Process
Page 41: Our Addition Process

Interior view

Page 42: Our Addition Process

Day 10

The windows arrive...

Page 43: Our Addition Process

and are installed.

Page 44: Our Addition Process
Page 45: Our Addition Process
Page 46: Our Addition Process

Turning a window into a door

Page 47: Our Addition Process

Day 11

Pipes and wires

Page 48: Our Addition Process
Page 49: Our Addition Process
Page 50: Our Addition Process
Page 51: Our Addition Process

Day 12

Shingles on the roof

Page 52: Our Addition Process
Page 53: Our Addition Process

Roughing in the HVAC

Page 54: Our Addition Process
Page 55: Our Addition Process

Day 13

The fireplace is in place.

Page 56: Our Addition Process

The “dog house” and vent

Page 57: Our Addition Process

Day 14

Getting the future doorway ready

Page 58: Our Addition Process

Day 15

Insulation installation

Page 59: Our Addition Process
Page 60: Our Addition Process
Page 61: Our Addition Process
Page 62: Our Addition Process

Day 16

Running wires for the speakers

Page 63: Our Addition Process
Page 64: Our Addition Process

Siding delivery

Page 65: Our Addition Process

Day 17

The drywall arrives

Page 66: Our Addition Process
Page 67: Our Addition Process
Page 68: Our Addition Process

A tight fit!

Page 69: Our Addition Process

The siding gets started

Page 70: Our Addition Process
Page 71: Our Addition Process
Page 72: Our Addition Process

Day 18

Here comes the door

Page 73: Our Addition Process
Page 74: Our Addition Process

Day 19

More siding going up

Page 75: Our Addition Process
Page 76: Our Addition Process
Page 77: Our Addition Process

Drywall being hung

Page 78: Our Addition Process

Day 20

Page 79: Our Addition Process
Page 80: Our Addition Process

Day 21

Blowing insulation into the ceilings

Page 81: Our Addition Process

More siding

Page 82: Our Addition Process
Page 83: Our Addition Process

The beginning of the drywall finishing

Page 84: Our Addition Process
Page 85: Our Addition Process

Day 22

More work on the drywall

Page 86: Our Addition Process
Page 87: Our Addition Process

Finishing the siding

Page 88: Our Addition Process

More HVAC installation

Page 89: Our Addition Process

Day 23

And still more drywall finishing

Page 90: Our Addition Process

The new furnace

Page 91: Our Addition Process

and air conditioner

Page 92: Our Addition Process

Shutters on the front

Page 93: Our Addition Process

Day 24

Even more drywall work

Page 94: Our Addition Process
Page 95: Our Addition Process

Day 25

Finished and ready for paint!

Page 96: Our Addition Process
Page 97: Our Addition Process

Day 26

Before the French doors

Page 98: Our Addition Process

How they kept the house clean!

Page 99: Our Addition Process

New French doors

Page 100: Our Addition Process

Window sills

Page 101: Our Addition Process

Bathroom - clean and ready for paint

Page 102: Our Addition Process

Day 27

Insulating the crawl space ceiling

Page 103: Our Addition Process

Working on the trim

Page 104: Our Addition Process

Trim for the doors

Page 105: Our Addition Process

Trim for the windows

Page 106: Our Addition Process

Day 28

Doors in place

Page 107: Our Addition Process

All trimmed and ready for paint

Page 108: Our Addition Process

Day 29

Plastic over the windows…

Page 109: Our Addition Process

and doorway

Page 110: Our Addition Process

A coat of primer and painted doors

Page 111: Our Addition Process

Gutters going up

Page 112: Our Addition Process

Day 30

“Thyme” in the bathroom

Page 113: Our Addition Process
Page 114: Our Addition Process

The hardwood gets acclimated

Page 115: Our Addition Process

Downspout

Page 116: Our Addition Process

Day 31

“Mild Wind” in the family roomand stained boards for the step

Page 117: Our Addition Process

Granite fireplace surround is installed

Page 118: Our Addition Process

Ready to install the vinyl

Page 119: Our Addition Process

The new bathroom floor

Page 120: Our Addition Process

Day 32

Getting started on the hardwood

Page 121: Our Addition Process
Page 122: Our Addition Process

Day 33

Family room floor is almost done

Page 123: Our Addition Process
Page 124: Our Addition Process

Day 34

Steps are built

Page 125: Our Addition Process

Baseboard is up

Page 126: Our Addition Process

Plumbing is working

Page 127: Our Addition Process

Exterior light installed

Page 128: Our Addition Process

Day 35

Carpet is patched

Page 129: Our Addition Process

The little things

Page 130: Our Addition Process

Mantel in a box

Page 131: Our Addition Process

Day 36

Laying out the mantel

Page 132: Our Addition Process

More little details

Page 133: Our Addition Process

Final HVAC

Page 134: Our Addition Process

Day 37

“Mocha” on the mantel

Page 135: Our Addition Process

Final coat of paint andglass doors uncovered

Page 136: Our Addition Process

Clean shower

Page 137: Our Addition Process

Freshly painted walls and baseboard

Page 138: Our Addition Process

Day 38

Finishing touches

Page 139: Our Addition Process
Page 140: Our Addition Process

The closet shelving

Page 141: Our Addition Process

Mantel up and fireplace working

Page 142: Our Addition Process

Day 39

The TV is hung

Page 143: Our Addition Process

Final plumbing

Page 144: Our Addition Process

Day 40

Insulating the walls of the crawl space

Page 145: Our Addition Process

Inspection completeTime to decorate!

Page 146: Our Addition Process

Furniture in place

Page 147: Our Addition Process

Epilogue

Curtains!

Page 148: Our Addition Process

The perfect chair

Page 149: Our Addition Process

Our music corner