OSHPD’s Electronic Services Portal
SNovember 17, 2011 — Web Seminar
Mary Barker
Welcome & Program Overview
Mary BarkerRoger RichterCalifornia Hospital Association
2
Presenter: John Gillengerten
John Gillengerten is a licensed structural engineer with 30 years of experience in seismic design of buildings and nonstructural systems and components. He is a district structural engineer for the California Office of Statewide Health Planning and Development, Facilities Development Division and is active in building code development.
3
Introduction to the Electronic Services Portal (e-SP)
John GillengertenJohn Gillengerten Office of Statewide Health Planningand Development
3
Agenda
O i Overview
e-SP Implementation
Navigating the revised application forms
e-SP Citizen Access
5
Overview
Thi ti di th f ll i t iThis section discusses the following topics:
Why replace logbook?
What is e-SP
Changes in OSHPD procedures, staff roles and responsibilities
6
and responsibilities
4
Why Replace Logbook?
Logbook was difficult to support
Developed by OSHPD staff two decades ago
Custom implementation based on Paradox–no company supports it
Original developers are no longer with OSHPD
7
OSHPD
Hard to incorporate changes to our business processes into logbook
What is e-SP?
e-SP is a customized implementation of the off-the-shelf Accela Automation software system
Used by thousands of agencies across the world at the local, state, and federal levels
Web and Cloud-based application
8
pp
5
What will e-SP do for OSHPD?
Help OSHPD manage workload tasks
Allow OSHPD to better understand the construction history of facilities and buildings
Tracks initial construction, modifications over time, and earthquake damage on a
9
over time, and earthquake damage on a building by building basis
Tracks project histories for IORs and individual licensed professionals
Changes in OSHPD procedures, staff roles and responsibilities
e-SP promotes structure in OSHPD processes through a variety of means
Business Process Controls
Structured Workflow
Task Assignments
10
6
Business Process Controls
Workflow Controls
Certain tasks cannot proceed out of sequence
Select individuals will have the ability to override parts of the workflow sequence
Required data fields
If required information is not provided, workflow
11
cannot proceed
Accountability
e-SP maintains a record of all user activities
Business Processes in e-SP
Ability to perform certain tasks is restricted
Users are assigned to groups that have certain rights
Ability to add/edit certain data is restricted
Facility numbers
12
Building name/numbers
Design professional/IOR data
Field Visit Reports
7
e-SP Implementation
Thi ti di th f ll i t iThis section discusses the following topics:
Project structure in e-SP
Building information
Plan review processes
Management of post-approval documents
13
Management of post-approval documents
Field observations and reviews
Alternate methods of compliance
Incremental and phased projects
Project Structure in e-SP
LogbookAll j t l t d t
e-SPAll j t d f All projects are related to a
facility
All plan and field review records are identified by an OSHPD Project Number
Separate data bases for SB 1953 and building data
All projects are made up of a group of related records
FDD building projects will be related to an “Application for New Project”
Applications for New Project are related to a facility
14
related to a facility and to buildings
Other records cover information currently in various logbook modules
8
e-SP Application for New Project
Project Number System
e-SP supports two project numbering systems
e-SP system
Legacy System (H, S, I, E, and G projects)
Records submitted prior to “go Live” used the old numbering system
16
the old numbering system
Projects and records submitted after “go Live” use the e-SP system
9
e-SP Project Number System
Every record in e-SP has a unique record number R d b i ll i d b h Record numbers are automatically assigned by the system based on when the record is created
Examples Buildings = BLD-##### Application for New Project = P-year- ##### Annual Building Permit = ABP-year- #####
Post Appro al Doc ment PAD ear #####
17
Post Approval Document = PAD-year- ##### EOC event/incident = EOE-year- ##### IOR = Type (A/B/C/R)- ##### Seismic Compliance Review = Type (SES/SCR)-
year- #####
Project Numbers
Project numbers are assigned automatically
Structural and nonstructural projects cannot be identified by the project number In lieu of identifying projects that include
structural work as “H” or “I” projects, the PT uses a checkbox to indicate the project i l d i it d/ l t l l d
18
includes primary gravity and/or lateral load elements/systems
This checkbox is included in the new application form
10
Legacy Numbering System
Records retain original project number
Record for PADs in the system were automatically assigned by the system using the project number plus the PAD number
Examples
Parent Application for New Project:
19
Parent Application for New Project: HS052947-0
PAD: HS052947-0-CO0003
Increment or ABP ID Number
Related Records
Every record in e-SP has a unique record number
Most OSHPD plan and field activities will be related to an Application for New Project
Records of activities such as Building Permits PADs Field Obser ation Visits
20
Permits, PADs, Field Observation Visits, etc. are related to the application for review, but do not share a common record number
11
Related Records
Building Information
All projects must be associated with one or more buildings One or more buildings must be related to the
project prior to plan approval
The building and facilities database is maintained by the Structural Services Unit
22
yand cannot be edited by most staff
Tracking projects by building allows a more accurate assessment of the condition of the building
12
Buildings Completed after 2002
Buildings completed after 2002 may not be in the e-SP data base, since they were not included in the SB 1953 compliance plans
A new building record must be created prior to approval of projects involving these buildings
23
buildings
Information needed to create a building record
Facility number
Facility needs to be created first for new facilities
Building name
Building status
Proposed, under construction, completed
Use of building
24
Acute Psych only
Skilled Nursing only
Acute Psych and Skilled Nursing only
All other uses
13
Information needed to create a building record (cont.)
Building Lateral Force Resisting System
OSHPD project number The “original” project number the building
was constructed under
Number of stories
Height
25
g
Number of basement levels
Penthouses (Yes or No)
Design code
Plan Review Processes
Application for new project is the portal for initiating review activities
Covers the following submittal types
Preliminary Review
Final Review
26
Geotech Review
Collaborative Review
Phased Review
14
Workflow Process
Intake
First Review
Triage
Review
Back Check Reviews
27
Triage
Review
Plan Approval
TIO and Local Approvals
Status of TIO and local approvals tracked for each discipline
Project cannot be approved until:
TIO has been approved by all disciplines
Local authority approval granted for all disciplines
Engineering Geologic Review and Supplemental G d R R i
28
Ground Response Review
CGS is considered a “local approval” authority
These review tasks are set to “Remarks” until approval is granted
15
Building Permits
The building permit record can be entered into e-SP at any time but it cannot be approved until theat any time but it cannot be approved until the parent project has plan approval For incremental projects, the increment must have
plan approval
Building permits cannot be approved until an IOR has been approved and added to the BP record and a contract cost is provided
29
The building permit record number will not be the same as the parent record number
It is best to hold the building permit application until the plans are nearing approval, so that the IOR and contractor data are accurate
Construction Start
Notice of Start of Construction must be received prior to the start of work
Once the Building Permit has been issued and the Notice of Start of Construction is received, all construction processes are tracked under the parent record
30
tracked under the parent record
No field operation tasks occur under the building permit record
16
Post-Approval Documents (PADS)
All changes to approved plans and specifications are considered PADs
Two types of PADs Amended Construction Documents (ACD)
Changes made after plan approval
Deferred Items (DI)
31
Instruction Bulletins (IB), Change Orders (CO) and Addendum (AD) only exist as legacy records No new records of these types
Amended Construction Documents (ACDs)
ACDs cannot be created until parent project has plan approval
On incremental projects, ACDs cannot be created until at least one increment has plan approval
32
17
Tracking PADs
In order to simplify searching for PADs, tracking numbers are used for each PADnumbers are used for each PAD The PAD record number and the parent record
number are different
PADs received prior to “go Live” have the tracking number in the record ID number HS052947-0-CO0003
PADs received after to “go Live” have two tracking
33
g gnumbers Applicant Tracking Number OSHPD Tracking Number
Two numbers are needed since only PADs that materially alter the work will be entered in e-SP
Legacy Tracking Numbers
PAD tracking number is part of the Record Number
HS052947-0-CO0003 = Change Order 0003
HS052947-0-FL0003 = AMC 0003
HS052947-0-DA0003 = Deferred Item 0003
34
0003
HS052947-0-IB0003 = Instruction Bulletin 0003
HS052947-0-AD0003 = Addendum 0003
18
e-SP Tracking Numbers
Applicant tracking number can be in any format desired
OSHPD tracking numbers for PAD records use a standard format
Amended Construction Document = ACD ####
Deferred Items = DI ####
Uses a space and 4 digits (add leading eros)
35
Uses a space and 4 digits (add leading zeros)
Staff will verify that duplicate OSHPD tracking numbers are not assigned to PADs on the same Application for New Project Record or Incremental Master
PADs – Field Review Intake
Most Amended Construction Documents are present to the Field Staff at the job site The Field Staff person is responsible for
completing the intake of the ACD
The Field Staff who initiated the ACD intake reviews the documents and determines which disciplines need to triage
36
determines which disciplines need to triage the ACD
ACDs that are referred to the Office for review are returned to the client for processing
19
Field Observations and Reviews
All field activities are recorded in e-SP
Site observations
Triage/review of PADs
Triage/review of applications for new FREER projects
Field visit and field review reports are
37
Field visit and field review reports are generated by e-SP and can be delivered by email
Outstanding Items Lists
All significant code violations and non-compliance items are tracked in e-SP
Field Issues: Outstanding Items List (OIL) table
Plan Review Issues: Review Outstanding Items List (ROIL) table
Each OIL and ROIL item is assigned a status
Cleared
38
Cleared
Escalate
Recheck
A report of the OIL and ROIL lists can be generated by the staff
20
Annual Building Permit
Facilities may apply for an Annual Building Permit (ABP)(ABP) The ABP no longer functions as the actual building
permit for projects
Once an ABP is issued, projects are submitted as an Application for New Project Client indicates that the project will be under the
ABP h li i
39
ABP on the application
A separate building permit is issued for each project under the ABP
e-SP automatically relates the Application for New Project to the ABP
Alternate Methods of Compliance
Types of Alternate Methods of Compliance (AMCs)
Alternate Method of Compliance
Alternate Method of Protection
Design Criteria
Program Flex
40
Program Flex
Unreasonable Hardship
21
Alternate Methods of Compliance
AMC Workflow
Project intake
Supervisor/RCO review
Staff recommendations
Supervisor/RCO decision
Supervisor/RCO may approve or deny an AMC d i th i i iti l i if th t bilit f th
41
during their initial review, if the acceptability of the proposal is clear
Supervisor/RCO may take in the AMC for review and recommendation by technical staff
Supervisor/RCO Decision
Two options are available – approve or deny If the staff have made an “approve with comment
recommendation”, the applicant will be contacted to discuss the comments prior to final decision
Client may accept comments (approve) or decline to accept comments (deny)
If Client accepts the comments, they should provide the RCO with a revised written proposal to be
42
the RCO with a revised written proposal to be attached to the record
There are no back check iterations on AMCs, so comments will be made in a manner that permits a ready response
22
Incremental Projects
Client submits an application for Incremental Master
Application describes the number and scope of each increment
Estimated submittal dates are provided for each increment
All project costs and fees are tracked on the Incremental Master
43
Incremental Master
All Increments are “children” of the Incremental Master
All PADs and AMCs are “children” of the Incremental Master, not the Increments
Increments
Each increment covers a defined scope of work
Client submits an Plan Review Application Under Incremental Project (Increment) for each increment
Field operations (field visits) are conducted
44
Field operations (field visits) are conducted under the increment record
23
Phased Review Projects
OSHPD pre-submittal reviews are divided into up to 4 phasesto 4 phases Phase 1 Conceptual/Criteria Phase 2 Detailed Design Phase 3 Pre - Implementation Phase 4 Implementation (Final Review)
Phases 1, 2 and 3 may be further divided into a maximum of 3 segments (1a, 1b, 1c, 2a, 2b, etc.)
45
maximum of 3 segments (1a, 1b, 1c, 2a, 2b, etc.) Phased reviews must include at least two phases
Phase 4 Implementation (Final Review) At least one other Phase (selected at the discretion
of the applicant)
Phase Scope and Schedule
The scope of the review for each phase segment must be clearly defined
Estimated submittal dates for each phase segment must be provided
Actual submittal dates are logged when the segment is received
46
segment is received
Applicant may request OSHPD complete review of phase segments by specified dates
24
Phase Segment Review
Phase segments are assigned to disciplines for review
Review results are:
Acceptance letter sent
Acceptance with comment letter sent
Th b k h k it ti h
47
There are no back check iterations on phase segments. Client responds to comments in the next segment or at final review
Thank You
John Gillengerten District Structural EngineerOffice of Statewide Health Planning
and Development(916) 440 8369(916) [email protected]