ENGINEERING ORDER N° TC-108-7 Completion date DD/MM/AAAA Original Review Date: April 13, 2016. Page 1 of 78 TITLE: Accomplishment with Airworthiness Directive 2012-24-08 in N800KS Aircraft Quality Control Certification: Aircraft: N 800 KS F.H.: 60000 F.C. 24000 Place: Inspector: Sign: Lic. N°: AFECTED PART: Aircraft Engine Component A. Reason: This service bulletin provides the instructions and the kits to change the anti-icing system for the angle of attack sensor, the total air temperature, and the pitot probes. The changes to the system will let the anti-icing system automatically supply power to heat the probes. The anti-icing system will automatically come on (AUTO) after engine start if the crew does not activate the system. If this service bulletin is not accomplished, the air data sensors could be unheated which could let ice form on the sensors, and cause erroneous air data. Unreliable air data can lead to loss of crew situational awareness which could cause failure to maintain safe flight and landing of the airplane. B. Effectivity: The present Order of Engineering is applicable to the following aircraft: Boeing 737-700C N 800 KS Operated by United Airlines. C. Compliance time: Boeing recommends that the change given in the service bulletin be done within 24 months after the Revision 1 date of this service bulletin. D. Manpower: The table 1 and 2 shows an estimate of the task hours necessary to do this configuration changes for each airplane. This estimate is for PREPARED BY: Ing. Jose Luis Cedano Nova. APPROVED BY: Ing. Andrés Eduardo Parra Catama. REFERENCES: AD 2012-24-08. Boeing Service N800KS Inspección

Upload: jose-luis-cedano-nova

Post on 12-Jul-2016

64 views

Category:

Documents


23 download

DESCRIPTION

Orden de Ingeniería AD 2012-24-08737-700C

TRANSCRIPT

Page 1: Orden de Ingeniería AD 2012-24-08

ENGINEERING ORDERN° TC-108-7

Completion date DD/MM/AAAAOriginal Review

Date: April 13, 2016. Page 1 of 68

TITLE: Accomplishment with Airworthiness Directive 2012-24-08 in N800KS Aircraft

Quality Control Certification:

Aircraft: N 800 KS F.H.: 60000 F.C. 24000 Place:

Inspector: Sign: Lic. N°:

AFECTED PART:

Aircraft

Engine

Component

A. Reason: This service bulletin provides the instructions and the kits to change the anti-icing system for the angle of attack sensor, the total air temperature, and the pitot probes. The changes to the system will let the anti-icing system automatically supply power to heat the probes. The anti-icing system will automatically come on (AUTO) after engine start if the crew does not activate the system. If this service bulletin is not accomplished, the air data sensors could be unheated which could let ice form on the sensors, and cause erroneous air data. Unreliable air data can lead to loss of crew situational awareness which could cause failure to maintain safe flight and landing of the airplane.

B. Effectivity: The present Order of Engineering is applicable to the following aircraft:

Boeing 737-700C N 800 KS Operated by United Airlines.

C. Compliance time: Boeing recommends that the change given in the service bulletin be done within 24 months after the Revision 1 date of this service bulletin.

D. Manpower: The table 1 and 2 shows an estimate of the task hours necessary to do this configuration changes for each airplane. This estimate is for direct labor only, done by an experienced crew. Adjust the estimate with operator task hour data if necessary. The estimate does not include lost time. These are some examples of lost time:

Time to adjust to the workplace Time to schedule the work Time to inspect the work Time to cure the materials Time to find the tools

A. Material-Price availability:

For Group 10: Kit number 002A0006-101

PREPARED BY:

Ing. Jose Luis Cedano Nova.

APPROVED BY:

Ing. Andrés Eduardo Parra Catama.

REFERENCES:

AD 2012-24-08.

Boeing Service Bulletin 737-30A1063

CATEGORY:

Inspection

Alteration

N800KS

Inspección

Page 2: Orden de Ingeniería AD 2012-24-08

ENGINEERING ORDERN° TC-108-7

Completion date DD/MM/AAAAOriginal Review

Date: April 13, 2016. Page 2 of 68

TITLE: Accomplishment with Airworthiness Directive 2012-24-08 in N800KS Aircraft

Inspección Repair Name: Top Kit – Tube Automation - ReplacementUnit price: $7,781.00For Group 14:Kit number 002A0006-105Name: Top Kit – Tube Automation - ReplacementUnit price: $7,292.00

B. Special tools:

None

C. Weight and Balance Changes:

Not changed.

D. Electrical Load Data:

Not changed.

E. Material information:

1. Part necessary

Kit number 002A0006-101 (Group 10) or 002A0006-105 (Group 14)Name: Top Kit – Tube Automation - Replacement Detailed kit for the work is shown in tables 3, 4,5,6,7.

2. Parts and material supplied by the operator

Detailed Parts and material supplied is shown in tables 8, 9, 10.

F. Special Tooling Necessary to do this Order: No special tools or equipment are necessary to do the change in this service bulletin. But, maintenance and overhaul tools in the manuals given in Paragraph 1.J., References, can be necessary. Examine operator tool supply to make sure all necessary tools are available.

ACCOMPLISHMENT:

Inmediatly

Repetitive

Once

N800KS

Page 3: Orden de Ingeniería AD 2012-24-08

ENGINEERING ORDERN° TC-108-7

Completion date DD/MM/AAAAOriginal Review

Date: April 13, 2016. Page 3 of 68

TITLE: Accomplishment with Airworthiness Directive 2012-24-08 in N800KS Aircraft

Table 1.

N800KS

Page 4: Orden de Ingeniería AD 2012-24-08

ENGINEERING ORDERN° TC-108-7

Completion date DD/MM/AAAAOriginal Review

Date: April 13, 2016. Page 4 of 68

TITLE: Accomplishment with Airworthiness Directive 2012-24-08 in N800KS Aircraft

Table 2

N800KS

Page 5: Orden de Ingeniería AD 2012-24-08

ENGINEERING ORDERN° TC-108-7

Completion date DD/MM/AAAAOriginal Review

Date: April 13, 2016. Page 5 of 68

TITLE: Accomplishment with Airworthiness Directive 2012-24-08 in N800KS Aircraft

Table 3

Table 4

N800KS

Page 6: Orden de Ingeniería AD 2012-24-08

ENGINEERING ORDERN° TC-108-7

Completion date DD/MM/AAAAOriginal Review

Date: April 13, 2016. Page 6 of 68

TITLE: Accomplishment with Airworthiness Directive 2012-24-08 in N800KS Aircraft

Table 5

Table 6

N800KS

Page 7: Orden de Ingeniería AD 2012-24-08

ENGINEERING ORDERN° TC-108-7

Completion date DD/MM/AAAAOriginal Review

Date: April 13, 2016. Page 7 of 68

TITLE: Accomplishment with Airworthiness Directive 2012-24-08 in N800KS Aircraft

Table 7

Table 8 (Parts and Materials Supplied by the Operator)

N800KS

Page 8: Orden de Ingeniería AD 2012-24-08

ENGINEERING ORDERN° TC-108-7

Completion date DD/MM/AAAAOriginal Review

Date: April 13, 2016. Page 8 of 68

TITLE: Accomplishment with Airworthiness Directive 2012-24-08 in N800KS Aircraft

Table 9 (Parts Modified and Reidentified)

Table 10 (Parts Necessary to Change Spares)

GENERAL INFORMATION

N800KS

Page 9: Orden de Ingeniería AD 2012-24-08

ENGINEERING ORDERN° TC-108-7

Completion date DD/MM/AAAAOriginal Review

Date: April 13, 2016. Page 9 of 68

TITLE: Accomplishment with Airworthiness Directive 2012-24-08 in N800KS Aircraft

CAUTION: KEEP THE WORK AREA, WIRES AND ELECTRICAL BUNDLES CLEAN OF METAL PARTICLES OR CONTAMINATION WHEN YOU USE TOOLS. UNWANTED MATERIAL, METAL PARTICLES OR CONTAMINATION CAUGHT IN WIRE BUNDLES CAN CAUSE DAMAGE TO THE BUNDLES. DAMAGED WIRE BUNDLES CAN CAUSE SPARKS OR OTHER ELECTRICAL DAMAGE.

NOTE:

1. Manual titles are referred to by acronyms. Refer to Paragraph 1.J., References, for definition of the acronyms.

2. Obey all of the warnings and cautions given in the specified manual sections.

3. Unless shown differently, these dimensions and tolerances are used:

Linear dimensions are in inches Tolerance on linear dimensions, other than rivet and bolt edge margins, is

plus or minus 0.03 inch Tolerance on rivet and bolt edge margin is plus or minus 0.05 inch Angular tolerance is plus or minus 2 degrees Whole dimensions for standard solid rivets are given in 737-700 SRM

Chapter 51. Torque limits to tighten nuts and bolts are given in 737-700 SRM Chapter

51.

4. For approved fastener and process material substitutions, refer to 737-700 SRM Chapter 51. Alternate fasteners are given in 737-700 SRM Chapter 51 and Boeing Drawing 65-88700.

5. Refer to the SWPM 20-10-11 and SWPM 20-10-12 for the wire installation procedures, and SWPM 20-10-19 for the wire separation requirements, as accepted procedures.

6. The necessary conditions for selection of clamp type and size are included in SWPM 20-10-12. If any wire bundle support clamp specified in this service bulletin does not make a correct fit on the wire bundle, refer to SWPM 20-10-12 as an accepted procedure to select a clamp that fits correctly.

7. If the length of any fastener specified in this service bulletin does not meet the installation standards given in 737-700 SRM Chapter 51, then a fastener of the same specification, or an approved substitute, with a length which meets the installation standards given in 737-700 SRM Chapter 51 may be used.

8. These work instructions refer to procedures included in other Boeing documents. When the words "refer to" are used and the operator has an accepted alternative procedure, the accepted alternative procedure can be used. When the words "as

N800KS

Page 10: Orden de Ingeniería AD 2012-24-08

ENGINEERING ORDERN° TC-108-7

Completion date DD/MM/AAAAOriginal Review

Date: April 13, 2016. Page 10 of 68

TITLE: Accomplishment with Airworthiness Directive 2012-24-08 in N800KS Aircraft

given in" are included in the instruction, the procedure in the Boeing document must be used.

9. Work Instructions and the figures can include operation of tools or test equipment. Boeing Engineering Tool Drawings, the Illustrated Tool and Equipment Manual, and the Special Tool and Ground Handling Drawing Index contain data on versions of the tools or test equipment that you can use. It is permitted to use replaced tools. It is not permitted to use superseded tools.

10. If it is necessary to remove more parts for access, you can remove those parts. If you can get access without removing identified parts, it is not necessary to remove all of the identified parts. Jacking and shoring limitations must be observed.

11. Where the work instructions include installation of a kept part, a new or serviceable part with the same part number can be installed as an alternative to the kept part. The removed part can be discarded if a new or serviceable part is installed.

12. This service bulletin includes functional test procedures for the systems changed by this service bulletin. More functional tests can possibly be necessary in accordance with standard maintenance practices because of interruption to other airplane systems.

13. Some Boeing parts are supplied in a temporary configuration. Those parts are identified with a 'U', 'W', or 'Y' in place of the '-' (dash) in the part number. It is permitted to install parts identified with a 'U', 'W', or 'Y' as an alternative to the '-' (dash) part number. Boeing Drawing 005W0900 contains more data.

N800KS

Page 11: Orden de Ingeniería AD 2012-24-08

ENGINEERING ORDERN° TC-108-7

Completion date DD/MM/AAAAOriginal Review

Date: April 13, 2016. Page 11 of 68

TITLE: Accomplishment with Airworthiness Directive 2012-24-08 in N800KS Aircraft

Work Instructions of the Service Bulletin 737-30-1063, Revision 1, dated July 10, 2012

Technician InspectorL/H R/H L/H RH

Part 1 – Work Instructions

a. Remove electrical power from the airplane. Refer to 737-600/700/800/900 AMM 24-22-00 as an accepted procedure.

b. Replace the P5-9 window/pitot heat module, in accordance with FIGURE 1.

c. Install the circuit breakers at the P18-3 circuit breaker panel, in accordance with FIGURE 2.

d. Group 1-2, 9-10, 12: Install the inserts and relays on the P18 side wall, in accordance with FIGURE 3 and FIGURE 4.

e. Group 3-8, 11, 13-14: Install the relay bracket and relays inside the P18, in accordance with FIGURE 7.

f. Group 10: Change the wire bundles, W0018 and W0020, in accordance with FIGURE 14 and FIGURE 39.

g. Group 14: Change the wire bundles, W0018 and W0020, in accordance with FIGURE 14 and FIGURE 15.

h. Change the wire bundle, W0220, in accordance with FIGURE 16 and FIGURE 17.

i. Change the wire bundles, W0311 and W0313, in accordance with FIGURE 18 and FIGURE 19.

j. Group 10, 14: Change the wire bundle, W2112, in accordance with FIGURE 20 and FIGURE 25.

k. Group 10, 14: Change the wire bundle, W2114, in accordance with FIGURE 21 and FIGURE 25.

l. Group 10, 14: Change the wire bundle, W5158, in accordance with FIGURE 22 and FIGURE 25.

m. Group 10, 14: Change the wire bundle, W5510, in accordance with FIGURE 23 and FIGURE 25.

n. Group 10, 14: Change the wire bundle, W2212, in accordance with FIGURE 24 and FIGURE 25.

o. Group 2, 4, 7-8, 10, 14: Change the wire bundle, W2218, in accordance with FIGURE 29 and FIGURE 30.

p. Change the wire bundle, W5310, in accordance with FIGURE 31 and FIGURE 32.

q. Change the wire bundle, W2237, in accordance with FIGURE 33 and FIGURE 34.

r. Group 1-4, 6-7, 10, 14: Change the wire bundle, W3381, in accordance with FIGURE 35 and FIGURE 36.

s. Restore the electrical power to the airplane. Refer to 737-600/700/800/900 AMM 24-22-00 as an accepted procedure.

t. Do an operational test of the Lavatory-Occupied Sign test. Refer to 737-600/700/800/900 AMM 33-26-03 as an accepted

N800KS

Page 12: Orden de Ingeniería AD 2012-24-08

ENGINEERING ORDERN° TC-108-7

Completion date DD/MM/AAAAOriginal Review

Date: April 13, 2016. Page 12 of 68

TITLE: Accomplishment with Airworthiness Directive 2012-24-08 in N800KS Aircraft

N800KS

Page 13: Orden de Ingeniería AD 2012-24-08

ENGINEERING ORDERN° TC-108-7

Completion date DD/MM/AAAAOriginal Review

Date: April 13, 2016. Page 13 of 68

TITLE: Accomplishment with Airworthiness Directive 2012-24-08 in N800KS Aircraft

FIGURE 1: REPLACEMENT OF THE P5-9 WINDOW/PITOT HEAT MODULE(SHEET 1 OF 2)

N800KS

Page 14: Orden de Ingeniería AD 2012-24-08

ENGINEERING ORDERN° TC-108-7

Completion date DD/MM/AAAAOriginal Review

Date: April 13, 2016. Page 14 of 68

TITLE: Accomplishment with Airworthiness Directive 2012-24-08 in N800KS Aircraft

FIGURE 1: REPLACEMENT OF THE P5-9 WINDOW/PITOT HEAT MODULE(SHEET 2 OF 2)

N800KS

Page 15: Orden de Ingeniería AD 2012-24-08

ENGINEERING ORDERN° TC-108-7

Completion date DD/MM/AAAAOriginal Review

Date: April 13, 2016. Page 15 of 68

TITLE: Accomplishment with Airworthiness Directive 2012-24-08 in N800KS Aircraft

FIGURE 2: INSTALLATION OF THE CIRCUIT BREAKERS INSIDE P18 PANEL(SHEET 1 OF 2)

N800KS

Page 16: Orden de Ingeniería AD 2012-24-08

ENGINEERING ORDERN° TC-108-7

Completion date DD/MM/AAAAOriginal Review

Date: April 13, 2016. Page 16 of 68

TITLE: Accomplishment with Airworthiness Directive 2012-24-08 in N800KS Aircraft

FIGURE 2: INSTALLATION OF THE CIRCUIT BREAKERS INSIDE P18 PANEL(SHEET 2 OF 2)

N800KS

Page 17: Orden de Ingeniería AD 2012-24-08

ENGINEERING ORDERN° TC-108-7

Completion date DD/MM/AAAAOriginal Review

Date: April 13, 2016. Page 17 of 68

TITLE: Accomplishment with Airworthiness Directive 2012-24-08 in N800KS Aircraft

This Figure applies only to: Group 1-2, 9-10, 12.

FIGURE 3: INSTALLATION OF THE INSERTS ON THE P18 PANEL(SHEET 1 OF 2)

N800KS

Page 18: Orden de Ingeniería AD 2012-24-08

ENGINEERING ORDERN° TC-108-7

Completion date DD/MM/AAAAOriginal Review

Date: April 13, 2016. Page 18 of 68

TITLE: Accomplishment with Airworthiness Directive 2012-24-08 in N800KS Aircraft

FIGURE 3: INSTALLATION OF THE INSERTS ON THE P18 PANEL(SHEET 2 OF 2)

This Figure applies only to: Group 1-2, 9-10, 12.

FIGURE 4: INSTALLATION OF THE BRACKET, RELAYS ON THE P18 PANEL(SHEET 1 OF 4)

N800KS

Page 19: Orden de Ingeniería AD 2012-24-08

ENGINEERING ORDERN° TC-108-7

Completion date DD/MM/AAAAOriginal Review

Date: April 13, 2016. Page 19 of 68

TITLE: Accomplishment with Airworthiness Directive 2012-24-08 in N800KS Aircraft

FIGURE 4: INSTALLATION OF THE BRACKET, RELAYS ON THE P18 PANEL(SHEET 2 OF 4)

N800KS

Page 20: Orden de Ingeniería AD 2012-24-08

ENGINEERING ORDERN° TC-108-7

Completion date DD/MM/AAAAOriginal Review

Date: April 13, 2016. Page 20 of 68

TITLE: Accomplishment with Airworthiness Directive 2012-24-08 in N800KS Aircraft

FIGURE 4: INSTALLATION OF THE BRACKET, RELAYS ON THE P18 PANEL(SHEET 3 OF 4)

N800KS

Page 21: Orden de Ingeniería AD 2012-24-08

ENGINEERING ORDERN° TC-108-7

Completion date DD/MM/AAAAOriginal Review

Date: April 13, 2016. Page 21 of 68

TITLE: Accomplishment with Airworthiness Directive 2012-24-08 in N800KS Aircraft

FIGURE 4: INSTALLATION OF THE BRACKET, RELAYS ON THE P18 PANEL(SHEET 4 OF 4)

This Figure applies only to: Group 3-8, 11, 13-14.

N800KS

Page 22: Orden de Ingeniería AD 2012-24-08

ENGINEERING ORDERN° TC-108-7

Completion date DD/MM/AAAAOriginal Review

Date: April 13, 2016. Page 22 of 68

TITLE: Accomplishment with Airworthiness Directive 2012-24-08 in N800KS Aircraft

FIGURE 7: INSTALLATION OF THE BRACKET, RELAYS IN THE P18 PANEL(SHEET 1 OF 4)

N800KS

Page 23: Orden de Ingeniería AD 2012-24-08

ENGINEERING ORDERN° TC-108-7

Completion date DD/MM/AAAAOriginal Review

Date: April 13, 2016. Page 23 of 68

TITLE: Accomplishment with Airworthiness Directive 2012-24-08 in N800KS Aircraft

FIGURE 7: INSTALLATION OF THE BRACKET, RELAYS IN THE P18 PANEL(SHEET 2 OF 4)

N800KS

Page 24: Orden de Ingeniería AD 2012-24-08

ENGINEERING ORDERN° TC-108-7

Completion date DD/MM/AAAAOriginal Review

Date: April 13, 2016. Page 24 of 68

TITLE: Accomplishment with Airworthiness Directive 2012-24-08 in N800KS Aircraft

FIGURE 7: INSTALLATION OF THE BRACKET, RELAYS IN THE P18 PANEL(SHEET 3 OF 4)

N800KS

Page 25: Orden de Ingeniería AD 2012-24-08

ENGINEERING ORDERN° TC-108-7

Completion date DD/MM/AAAAOriginal Review

Date: April 13, 2016. Page 25 of 68

TITLE: Accomplishment with Airworthiness Directive 2012-24-08 in N800KS Aircraft

FIGURE 7: INSTALLATION OF THE BRACKET, RELAYS IN THE P18 PANEL(SHEET 4 OF 4)

This Figure applies only to: Group 10, 14.

N800KS

Page 26: Orden de Ingeniería AD 2012-24-08

ENGINEERING ORDERN° TC-108-7

Completion date DD/MM/AAAAOriginal Review

Date: April 13, 2016. Page 26 of 68

TITLE: Accomplishment with Airworthiness Directive 2012-24-08 in N800KS Aircraft

FIGURE 14: CHANGE THE WIRE BUNDLES, W0018 AND W0020(SHEET 1 OF 4)

Reference: 737-600/700/800/900 WDM 30-31-11, 737-600/700/800/900 WDM 30-31-12

N800KS

Page 27: Orden de Ingeniería AD 2012-24-08

ENGINEERING ORDERN° TC-108-7

Completion date DD/MM/AAAAOriginal Review

Date: April 13, 2016. Page 27 of 68

TITLE: Accomplishment with Airworthiness Directive 2012-24-08 in N800KS Aircraft

FIGURE 14: CHANGE THE WIRE BUNDLES, W0018 AND W0020(SHEET 2 OF 4)

Reference: 737-600/700/800/900 WDM 24-61-21, 737-600/700/800/900 WDM 24-61-23

N800KS

Page 28: Orden de Ingeniería AD 2012-24-08

ENGINEERING ORDERN° TC-108-7

Completion date DD/MM/AAAAOriginal Review

Date: April 13, 2016. Page 28 of 68

TITLE: Accomplishment with Airworthiness Directive 2012-24-08 in N800KS Aircraft

The flag note numbers shown below agree with the numbers shown in the flag symbols in the figure.

FIGURE 14: CHANGE THE WIRE BUNDLES, W0018 AND W0020(SHEET 3 OF 4)

N800KS

Page 29: Orden de Ingeniería AD 2012-24-08

ENGINEERING ORDERN° TC-108-7

Completion date DD/MM/AAAAOriginal Review

Date: April 13, 2016. Page 29 of 68

TITLE: Accomplishment with Airworthiness Directive 2012-24-08 in N800KS Aircraft

FIGURE 14: CHANGE THE WIRE BUNDLES, W0018 AND W0020(SHEET 4 OF 4)

N800KS

Page 30: Orden de Ingeniería AD 2012-24-08

ENGINEERING ORDERN° TC-108-7

Completion date DD/MM/AAAAOriginal Review

Date: April 13, 2016. Page 30 of 68

TITLE: Accomplishment with Airworthiness Directive 2012-24-08 in N800KS Aircraft

This Figure applies only to: Group 14.

FIGURE 15: ROUTE THE WIRE BUNDLES, W0018 AND W0020(SHEET 1 OF 2)

N800KS

Page 31: Orden de Ingeniería AD 2012-24-08

ENGINEERING ORDERN° TC-108-7

Completion date DD/MM/AAAAOriginal Review

Date: April 13, 2016. Page 31 of 68

TITLE: Accomplishment with Airworthiness Directive 2012-24-08 in N800KS Aircraft

FIGURE 15: ROUTE THE WIRE BUNDLES, W0018 AND W0020(SHEET 2 OF 2)

N800KS

Page 32: Orden de Ingeniería AD 2012-24-08

ENGINEERING ORDERN° TC-108-7

Completion date DD/MM/AAAAOriginal Review

Date: April 13, 2016. Page 32 of 68

TITLE: Accomplishment with Airworthiness Directive 2012-24-08 in N800KS Aircraft

FIGURE 16: CHANGE THE WIRE BUNDLE, W0220, INSIDE E2-2(SHEET 1 OF 1)

N800KS

Page 33: Orden de Ingeniería AD 2012-24-08

ENGINEERING ORDERN° TC-108-7

Completion date DD/MM/AAAAOriginal Review

Date: April 13, 2016. Page 33 of 68

TITLE: Accomplishment with Airworthiness Directive 2012-24-08 in N800KS Aircraft

FIGURE 17: ROUTE THE WIRE BUNDLE, W0220, INSIDE E2-2(SHEET 1 OF 1)

N800KS

Page 34: Orden de Ingeniería AD 2012-24-08

ENGINEERING ORDERN° TC-108-7

Completion date DD/MM/AAAAOriginal Review

Date: April 13, 2016. Page 34 of 68

TITLE: Accomplishment with Airworthiness Directive 2012-24-08 in N800KS Aircraft

FIGURE 18: CHANGE THE WIRE BUNDLES, W0311 AND W0313, INSIDE E3-1(SHEET 1 OF 2)

N800KS

Page 35: Orden de Ingeniería AD 2012-24-08

ENGINEERING ORDERN° TC-108-7

Completion date DD/MM/AAAAOriginal Review

Date: April 13, 2016. Page 35 of 68

TITLE: Accomplishment with Airworthiness Directive 2012-24-08 in N800KS Aircraft

FIGURE 18: CHANGE THE WIRE BUNDLES, W0311 AND W0313, INSIDE E3-1(SHEET 2 OF 2)

N800KS

Page 36: Orden de Ingeniería AD 2012-24-08

ENGINEERING ORDERN° TC-108-7

Completion date DD/MM/AAAAOriginal Review

Date: April 13, 2016. Page 36 of 68

TITLE: Accomplishment with Airworthiness Directive 2012-24-08 in N800KS Aircraft

FIGURE 19: ROUTE THE WIRE BUNDLES, W0311 AND W0313, INSIDE E3-1(SHEET 1 OF 1)

N800KS

Page 37: Orden de Ingeniería AD 2012-24-08

ENGINEERING ORDERN° TC-108-7

Completion date DD/MM/AAAAOriginal Review

Date: April 13, 2016. Page 37 of 68

TITLE: Accomplishment with Airworthiness Directive 2012-24-08 in N800KS Aircraft

This Figure applies only to: Group 10, 14.

FIGURE 20: CHANGE THE WIRE BUNDLE, W2112(SHEET 1 OF 1)

N800KS

Page 38: Orden de Ingeniería AD 2012-24-08

ENGINEERING ORDERN° TC-108-7

Completion date DD/MM/AAAAOriginal Review

Date: April 13, 2016. Page 38 of 68

TITLE: Accomplishment with Airworthiness Directive 2012-24-08 in N800KS Aircraft

This Figure applies only to: Group 10, 14.

FIGURE 21: CHANGE THE WIRE BUNDLE, W2114(SHEET 1 OF 2)

N800KS

Page 39: Orden de Ingeniería AD 2012-24-08

ENGINEERING ORDERN° TC-108-7

Completion date DD/MM/AAAAOriginal Review

Date: April 13, 2016. Page 39 of 68

TITLE: Accomplishment with Airworthiness Directive 2012-24-08 in N800KS Aircraft

FIGURE 21: CHANGE THE WIRE BUNDLE, W2114(SHEET 2 OF 2)

This Figure applies only to: Group 10, 14.

N800KS

Page 40: Orden de Ingeniería AD 2012-24-08

ENGINEERING ORDERN° TC-108-7

Completion date DD/MM/AAAAOriginal Review

Date: April 13, 2016. Page 40 of 68

TITLE: Accomplishment with Airworthiness Directive 2012-24-08 in N800KS Aircraft

This Figure applies only to: Group 10, 14.

N800KS

Page 41: Orden de Ingeniería AD 2012-24-08

ENGINEERING ORDERN° TC-108-7

Completion date DD/MM/AAAAOriginal Review

Date: April 13, 2016. Page 41 of 68

TITLE: Accomplishment with Airworthiness Directive 2012-24-08 in N800KS Aircraft

FIGURE 23: CHANGE THE WIRE BUNDLE, W5510(SHEET 1 OF 1)

This Figure applies only to: Group 10, 14.

N800KS

Page 42: Orden de Ingeniería AD 2012-24-08

ENGINEERING ORDERN° TC-108-7

Completion date DD/MM/AAAAOriginal Review

Date: April 13, 2016. Page 42 of 68

TITLE: Accomplishment with Airworthiness Directive 2012-24-08 in N800KS Aircraft

FIGURE 24: CHANGE THE WIRE BUNDLE, W2212(SHEET 1 OF 2)

N800KS

Page 43: Orden de Ingeniería AD 2012-24-08

ENGINEERING ORDERN° TC-108-7

Completion date DD/MM/AAAAOriginal Review

Date: April 13, 2016. Page 43 of 68

TITLE: Accomplishment with Airworthiness Directive 2012-24-08 in N800KS Aircraft

FIGURE 24: CHANGE THE WIRE BUNDLE, W2212(SHEET 2 OF 2)

This Figure applies only to: Group 10, 14.

N800KS

Page 44: Orden de Ingeniería AD 2012-24-08

ENGINEERING ORDERN° TC-108-7

Completion date DD/MM/AAAAOriginal Review

Date: April 13, 2016. Page 44 of 68

TITLE: Accomplishment with Airworthiness Directive 2012-24-08 in N800KS Aircraft

FIGURE 25: ROUTE THE WIRE BUNDLES, W2112, W2114, W2212, W5158, W5510(SHEET 1 OF 5)

N800KS

Page 45: Orden de Ingeniería AD 2012-24-08

ENGINEERING ORDERN° TC-108-7

Completion date DD/MM/AAAAOriginal Review

Date: April 13, 2016. Page 45 of 68

TITLE: Accomplishment with Airworthiness Directive 2012-24-08 in N800KS Aircraft

FIGURE 25: ROUTE THE WIRE BUNDLES, W2112, W2114, W2212, W5158, W5510(SHEET 2 OF 5)

N800KS

Page 46: Orden de Ingeniería AD 2012-24-08

ENGINEERING ORDERN° TC-108-7

Completion date DD/MM/AAAAOriginal Review

Date: April 13, 2016. Page 46 of 68

TITLE: Accomplishment with Airworthiness Directive 2012-24-08 in N800KS Aircraft

FIGURE 25: ROUTE THE WIRE BUNDLES, W2112, W2114, W2212, W5158, W5510(SHEET 3 OF 5)

N800KS

Page 47: Orden de Ingeniería AD 2012-24-08

ENGINEERING ORDERN° TC-108-7

Completion date DD/MM/AAAAOriginal Review

Date: April 13, 2016. Page 47 of 68

TITLE: Accomplishment with Airworthiness Directive 2012-24-08 in N800KS Aircraft

FIGURE 25: ROUTE THE WIRE BUNDLES, W2112, W2114, W2212, W5158, W5510(SHEET 4 OF 5)

FIGURE 25: ROUTE THE WIRE BUNDLES, W2112, W2114, W2212, W5158, W5510(SHEET 5 OF 5)

N800KS

Page 48: Orden de Ingeniería AD 2012-24-08

ENGINEERING ORDERN° TC-108-7

Completion date DD/MM/AAAAOriginal Review

Date: April 13, 2016. Page 48 of 68

TITLE: Accomplishment with Airworthiness Directive 2012-24-08 in N800KS Aircraft

This Figure applies only to: Group 2, 4-5, 7, 9-11, 14.

FIGURE 29: CHANGE THE WIRE BUNDLE, W2218(SHEET 1 OF 2)

N800KS

Page 49: Orden de Ingeniería AD 2012-24-08

ENGINEERING ORDERN° TC-108-7

Completion date DD/MM/AAAAOriginal Review

Date: April 13, 2016. Page 49 of 68

TITLE: Accomplishment with Airworthiness Directive 2012-24-08 in N800KS Aircraft

FIGURE 29: CHANGE THE WIRE BUNDLE, W2218(SHEET 2 OF 2)

N800KS

Page 50: Orden de Ingeniería AD 2012-24-08

ENGINEERING ORDERN° TC-108-7

Completion date DD/MM/AAAAOriginal Review

Date: April 13, 2016. Page 50 of 68

TITLE: Accomplishment with Airworthiness Directive 2012-24-08 in N800KS Aircraft

FIGURE 30: ROUTE THE WIRE BUNDLE, W2218(SHEET 1 OF 4)

N800KS

Page 51: Orden de Ingeniería AD 2012-24-08

ENGINEERING ORDERN° TC-108-7

Completion date DD/MM/AAAAOriginal Review

Date: April 13, 2016. Page 51 of 68

TITLE: Accomplishment with Airworthiness Directive 2012-24-08 in N800KS Aircraft

FIGURE 30: ROUTE THE WIRE BUNDLE, W2218(SHEET 2 OF 4)

N800KS

Page 52: Orden de Ingeniería AD 2012-24-08

ENGINEERING ORDERN° TC-108-7

Completion date DD/MM/AAAAOriginal Review

Date: April 13, 2016. Page 52 of 68

TITLE: Accomplishment with Airworthiness Directive 2012-24-08 in N800KS Aircraft

FIGURE 30: ROUTE THE WIRE BUNDLE, W2218(SHEET 3 OF 4)

N800KS

Page 53: Orden de Ingeniería AD 2012-24-08

ENGINEERING ORDERN° TC-108-7

Completion date DD/MM/AAAAOriginal Review

Date: April 13, 2016. Page 53 of 68

TITLE: Accomplishment with Airworthiness Directive 2012-24-08 in N800KS Aircraft

FIGURE 30: ROUTE THE WIRE BUNDLE, W2218(SHEET 4 OF 4)

N800KS

Page 54: Orden de Ingeniería AD 2012-24-08

ENGINEERING ORDERN° TC-108-7

Completion date DD/MM/AAAAOriginal Review

Date: April 13, 2016. Page 54 of 68

TITLE: Accomplishment with Airworthiness Directive 2012-24-08 in N800KS Aircraft

FIGURE 31: CHANGE THE WIRE BUNDLE, W5310(SHEET 1 OF 1)

N800KS

Page 55: Orden de Ingeniería AD 2012-24-08

ENGINEERING ORDERN° TC-108-7

Completion date DD/MM/AAAAOriginal Review

Date: April 13, 2016. Page 55 of 68

TITLE: Accomplishment with Airworthiness Directive 2012-24-08 in N800KS Aircraft

FIGURE 32: ROUTE THE WIRE BUNDLE, W5310, FROM E2-2 TO E3-1(SHEET 1 OF 1)

N800KS

Page 56: Orden de Ingeniería AD 2012-24-08

ENGINEERING ORDERN° TC-108-7

Completion date DD/MM/AAAAOriginal Review

Date: April 13, 2016. Page 56 of 68

TITLE: Accomplishment with Airworthiness Directive 2012-24-08 in N800KS Aircraft

FIGURE 33: CHANGE THE WIRE BUNDLE, W2237(SHEET 1 OF 1)

N800KS

Page 57: Orden de Ingeniería AD 2012-24-08

ENGINEERING ORDERN° TC-108-7

Completion date DD/MM/AAAAOriginal Review

Date: April 13, 2016. Page 57 of 68

TITLE: Accomplishment with Airworthiness Directive 2012-24-08 in N800KS Aircraft

FIGURE 34: ROUTE THE WIRE BUNDLE, W2237(SHEET 1 OF 2)

N800KS

Page 58: Orden de Ingeniería AD 2012-24-08

ENGINEERING ORDERN° TC-108-7

Completion date DD/MM/AAAAOriginal Review

Date: April 13, 2016. Page 58 of 68

TITLE: Accomplishment with Airworthiness Directive 2012-24-08 in N800KS Aircraft

FIGURE 34: ROUTE THE WIRE BUNDLE, W2237(SHEET 2 OF 2)

N800KS

Page 59: Orden de Ingeniería AD 2012-24-08

ENGINEERING ORDERN° TC-108-7

Completion date DD/MM/AAAAOriginal Review

Date: April 13, 2016. Page 59 of 68

TITLE: Accomplishment with Airworthiness Directive 2012-24-08 in N800KS Aircraft

This Figure applies only to: Group 1-4, 6-7, 10, 14.

FIGURE 35: CHANGE THE WIRE BUNDLE, W3381(SHEET 1 OF 1)

This Figure applies only to: Group 1-4, 6-7, 10, 14.

N800KS

Page 60: Orden de Ingeniería AD 2012-24-08

ENGINEERING ORDERN° TC-108-7

Completion date DD/MM/AAAAOriginal Review

Date: April 13, 2016. Page 60 of 68

TITLE: Accomplishment with Airworthiness Directive 2012-24-08 in N800KS Aircraft

FIGURE 36: ROUTE THE WIRE BUNDLE, W3381(SHEET 1 OF 5)

N800KS

Page 61: Orden de Ingeniería AD 2012-24-08

ENGINEERING ORDERN° TC-108-7

Completion date DD/MM/AAAAOriginal Review

Date: April 13, 2016. Page 61 of 68

TITLE: Accomplishment with Airworthiness Directive 2012-24-08 in N800KS Aircraft

FIGURE 36: ROUTE THE WIRE BUNDLE, W3381(SHEET 2 OF 5)

N800KS

Page 62: Orden de Ingeniería AD 2012-24-08

ENGINEERING ORDERN° TC-108-7

Completion date DD/MM/AAAAOriginal Review

Date: April 13, 2016. Page 62 of 68

TITLE: Accomplishment with Airworthiness Directive 2012-24-08 in N800KS Aircraft

FIGURE 36: ROUTE THE WIRE BUNDLE, W3381(SHEET 3 OF 5)

N800KS

Page 63: Orden de Ingeniería AD 2012-24-08

ENGINEERING ORDERN° TC-108-7

Completion date DD/MM/AAAAOriginal Review

Date: April 13, 2016. Page 63 of 68

TITLE: Accomplishment with Airworthiness Directive 2012-24-08 in N800KS Aircraft

FIGURE 36: ROUTE THE WIRE BUNDLE, W3381(SHEET 4 OF 5)

N800KS

Page 64: Orden de Ingeniería AD 2012-24-08

ENGINEERING ORDERN° TC-108-7

Completion date DD/MM/AAAAOriginal Review

Date: April 13, 2016. Page 64 of 68

TITLE: Accomplishment with Airworthiness Directive 2012-24-08 in N800KS Aircraft

FIGURE 36: ROUTE THE WIRE BUNDLE, W3381(SHEET 5 OF 5)

N800KS

Page 65: Orden de Ingeniería AD 2012-24-08

ENGINEERING ORDERN° TC-108-7

Completion date DD/MM/AAAAOriginal Review

Date: April 13, 2016. Page 65 of 68

TITLE: Accomplishment with Airworthiness Directive 2012-24-08 in N800KS Aircraft

This Figure applies only to: Group 10.

FIGURE 39: ROUTE THE WIRE BUNDLES, W0018 AND W0020(SHEET 1 OF 3)

N800KS

Page 66: Orden de Ingeniería AD 2012-24-08

ENGINEERING ORDERN° TC-108-7

Completion date DD/MM/AAAAOriginal Review

Date: April 13, 2016. Page 66 of 68

TITLE: Accomplishment with Airworthiness Directive 2012-24-08 in N800KS Aircraft

FIGURE 39: ROUTE THE WIRE BUNDLES, W0018 AND W0020(SHEET 2 OF 3)

N800KS

Page 67: Orden de Ingeniería AD 2012-24-08

ENGINEERING ORDERN° TC-108-7

Completion date DD/MM/AAAAOriginal Review

Date: April 13, 2016. Page 67 of 68

TITLE: Accomplishment with Airworthiness Directive 2012-24-08 in N800KS Aircraft

FIGURE 39: ROUTE THE WIRE BUNDLES, W0018 AND W0020(SHEET 3 OF 3)

Put an " X" Inspection Method Applied:

Visual Inspection ( )

Current EDDY: HFEC ( ), MFEC ( ), LFEC ( ).

Dye penetrant: ( ).

X-ray: ( ).

Boroscope: ( ).

Other ( )

Wich: _______________________________________________

Aircraft observations:______________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

N800KS

Page 68: Orden de Ingeniería AD 2012-24-08

ENGINEERING ORDERN° TC-108-7

Completion date DD/MM/AAAAOriginal Review

Date: April 13, 2016. Page 68 of 68

TITLE: Accomplishment with Airworthiness Directive 2012-24-08 in N800KS Aircraft

Stock Observations:______________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

______________________________Technical sign

_______________________Inspector sign

N800KS