“X” Platform Migrations -Challenges and Time Reduction Techniques

Raju KanumuryVice President

Database Administration Services

I n n o v a t e I n t e g r a t e O p e r a t eI n n o v a t e I n t e g r a t e O p e r a t e

Page 2: oracle platform migration

AGENDA Requirements

Complexities

Oracle Migration Path

Customized Migration Path

Time Consuming Operations

Time Reduction Methods

Iterations

Testing Methods

Page 3: oracle platform migration

Two SUN Solaris Machines to Four Linux Machines

Single node DB to Two Node RAC

Separation of single node admin/CM tier to Two Parallel Concurrent Processing nodes

Single Forms/Web node to TwoForm/Web nodes with Load Balancer

Requirements Complexities Oracle Migration PathCustomized Migration

Path

Seven HP Unix Machines to Eighteen Linux Machines

Single node DB to Six Node RAC

Separation of single node admin/CM tier to Two Parallel Concurrent Processing nodes

Four Forms/Web tiers to TenForms/Web Tiers with Shared Application Top

Integration and failover capability for third party/external software

Scenario I Scenario II

Page 4: oracle platform migration

OS - Solaris 8 to OEL 5.3

DB - 8.1.7.4 to 10.2.0.4 (RAC)

App - 11.5.4 to 11.5.10 CU2

App - Latest Financial Family Pack

1.8 TB data migration to Linux

Downtime Allocated – 48 hrs

Requirements Complexities Oracle Migration PathCustomized Migration

Path

Scenario I Scenario II

OS – HP UX 11.11 to OEL 5.3

DB – Non RAC to RAC

4.0 TB data migration to Linux

JDBC driver updates for RAC compatibility of third party software

Resource Management of DB byusing services

Downtime Allocated – 40 hrs

Page 5: oracle platform migration

Single Node DB to RAC DB with ASM

Parallel Concurrent Processing (PCP) configuration

Fixed and tight downtime because of their operational requirements

Anticipated increase in user load since they were planning to add more countries as a part of global rollout

Migration and functioning of customizations

Performance of critical functionalities & processes

Commonalities between Scenario I and II

Requirements Complexities Oracle Migration PathCustomized Migration

Path

Page 6: oracle platform migration

Multiple DB Upgrades

8.1.7.4 to 9.2.0.6

9.2.0.6 to 10.2.0.4

Application Upgrade

11.5.4 to 11.5.10 CU2

Export and Import

1.8 TB of Data

Scenario I Scenario II

Export and Import of huge amount of data

4.0 TB of Data

Shared Application Tier Configuration

Adding numerous nodes

10 nodes and 2 CM nodes

Third Party integration that is crucial to most of business functionalities

Requirements Complexities Oracle Migration PathCustomized Migration

Path

Page 7: oracle platform migration

Scenario - I

Tar

get

So

urc

e

Export

Data

Create

Shell

DB

Tech Stack

Install/Copy

Import

Data

Add Nodes

Configuration

Parallel

Concurrent

Processing

Configuration

Aplly Financial

Family Pack

DB

Backup

DB

Upgrade

9.2.0.6

APPS Upgrade

11.5.4 to 11.5.10 .2

DB

Upgrade

10.2.0.4

Scenario - II

Ta

rge

tS

ou

rce

Clone POC2

DB/APPS

from PROD

Use prepared

documentPrepare

DB for

migration

Export

Data

Create

Shell

DB

Tech Stack

Install/Copy

Import

Data

Shared Apps Tier

configuration

Add Nodes

Configuration

Parallel

Concurrent

Processing

Configuration

Third Party

Integration

Requirements Complexities Oracle Migration PathCustomized Migration

Path

Page 8: oracle platform migration

Scenario I Scenario II

Pre-

Downtime

Downtime

Source DB Backup 4

Source DB Upgrade (9.2.0.6) 6

Source APP Upgrade 18

Source DB Upgrade (10.2.0.4) 6

Source Export 8

Target DB Shell 8

Target Import 15

Target TechStack 4

Target AutoConfig 2

Target Add Nodes 4

Target Apply Patches 6

Verification & Validation 4

Total Time 12 73

Major Activity

Pre-

Downtime

Downtime

Source DB Backup 4

Prepare Source DB for Export 2

Source Export 15

Target DB Shell 8

Target Import 32

Target TechStack 4

Shared Appl Top & Auto Config 2

PCP Config 2

Add Nodes – Total 10 forms/web nodes 6

Third party configuration 8

Verification & Validation 4

Total Time 12 75

Major Activity Time in Hrs

Requirements Complexities Oracle Migration PathCustomized Migration

Path

Page 9: oracle platform migration

Scenario - I

Tar

get

So

urc

e

Export

Data

Create

Shell

DB

Fresh Install of

11.5.10.2

Import

Data

Add Nodes

Configuration

Parallel

Concurrent

Processing

Configuration

Aplly Financial

Family Pack

Build

Standby

DB

DB

Upgrade

9.2.0.6

APPS Upgrade

11.5.4 to 11.5.10 .2

DB

Upgrade

10.2.0.4X XMigrated Partial

Activity

(Source -> Target)

APPS Upgrade

11.5.4 to 11.5.10 .2

(“D” Driver)

Scenario - II

Ta

rge

tS

ou

rce

Use prepared

documentPrepare

DB for

migration

Create

Shell

DB

Tech Stack

Install/Copy

Shared Apps Tier

configuration

Add Nodes

Configuration

Parallel

Concurrent

Processing

Configuration

Third Party

Integration

Export

Metadata

Export

BigTables

&

FNDLOBS

Import

Users

Import Big

&

FNDLOBS

Build

Indexes

Export

AllTables

Export

Metadata

Import

AllTables

Import

Procs etc

Import

Procs etc

Apply Archive

Logs

Build

Stand

by DB

Requirements Complexities Oracle Migration PathCustomized Migration

Path

Page 10: oracle platform migration

Scenario I – Run Times Scenario II – Run Times

Pre-

Downtime

Downtime

Source Standby DB 6

Source App Prep 2

Source DB Upgrade 6

Source Export 3

Target Fresh Install 5

Target DB Shell 8

Target Import 8

Target App Upgrade 8

Target AutoConfig 2

Target Add Nodes 4

Target Apply Patches 6

Verification & Validation 4

Total Time 19 43

Major Activity

Pre-

Downtime

Downtime

Source Standby DB 8

Source Export Big Tables/Metadata 12

Prepare Source DB for Export 2

Source Export All Tables/Metadata 6

Target DB Shell 8

Target Import - Users/Big Tables & Indexes 8

Target Import – AllTables/Sync Big Tables 6

Target Import – Procs Etc 3

Target Import - Const & Build Indexes 7

Shared Appl Top & Auto Config 2

PCP Config 2

Add Nodes – Total 10 forms/web nodes 2

Third party configuration 2

Verification & Validation 4

Total Time 36 36

Major Activity

Requirements Complexities Oracle Migration PathCustomized Migration

Path

Page 11: oracle platform migration

Application Upgrade

“d” driver

DB Upgrade

Scenario I Scenario II

Size of the DB

Shared Application Tier

Number of nodes to be configured

Third Party integrations

Time Consuming Operations

Time Reduction Methods

Iterations Testing Methods

Backup Operation

Export/Import Operations

PCP Configuration

Application Configuration

Page 12: oracle platform migration

Analyze whether work can be performed ahead of downtime. Push as much as activities to pre downtime

Build Standby DB

Sync tables by exporting ahead of downtime

Look whether there are any performance attributes or improvements that can be performed on an individual process

Number parallel workers (adpatch & datapump)

Datapump Performance Patches

Purge obsolete data

Based on DB size break the process into logical elements so that same process can be submitted in multiple threads

Break Export and Import into logical groups

Customize index creation process

Areas to focus

Time Consuming Operations

Time Reduction Methods

Iterations Testing Methods

Page 13: oracle platform migration

Problem

Time taken for backup – depending on the size of DB they may take considerable time

In case of upgrades or conversions restoration time need to be considered as part of roll back

Solution

Create Physical Standby ahead of conversion and start applying logs. Except applying few logs after start of downtime majority of the work for this operation can be pushed in to pre downtime category

Restoration time need not be considered since original PROD system is intact

Backup Operation

Time Consuming Operations

Time Reduction Methods

Iterations Testing Methods

Page 14: oracle platform migration

Problem

Oracle given parameter files have commands for full export with some user exclusions

In proof of concept exports it is observed that few big tables and FND_LOBS are taking considerable time in export

Upon analysis it is observed that top 10% of tables occupy 50 to 60% of total DB size

Solution

Identify and list top 10 to 15 non transactional tables related to history and TL

Create MVIEW logs on above tables to keep track of changes

Export Operation

Time Consuming Operations

Time Reduction Methods

Iterations Testing Methods

Page 15: oracle platform migration

Solution

Split full export into multiple parts so that few tables can be exported ahead of downtime

Create Shell DB along with required tablespaces before downtime

Export Big tables, FND_LOBS and Metadata by using multiple parameter file instead of one

Exclude statistics from all the parameter files

Use enough parallel threads for faster export. Limit parallel threads not to exceed the number of dump files that are being generated by export

Export Operation

Time Consuming Operations

Time Reduction Methods

Iterations Testing Methods

Page 16: oracle platform migration

Export Operation – Time Lines

Time Consuming Operations

Time Reduction Methods

Iterations Testing Methods

Page 17: oracle platform migration

Problem

Oracle given parameter files have commands for full import

In proof of concept imports it is observed that majority of the time is being spent on building indexes and primary key constraints

Datapump serializes activities like index creation and procedures etc. which can consume lot of time

Solution

Split full import into multiple parts so that exported tables can be imported ahead of downtime

Develop custom process to synch the imported tables between source an target based on the changes logged in MVIEW logs

Import Operation

Time Consuming Operations

Time Reduction Methods

Iterations Testing Methods

Page 18: oracle platform migration

Solution

As first pass import users, table structures and data only. This way you can assure sync process will not effect any other data

Except constraints other DB elements like views, triggers, procedures etc. should be imported as soon as data imports are completed

Exclude indexes in all import parameter files

Customize index creation by creating indexes externally. Come up with automated procedure to load indexes from dump file into a table. Write code so that multiple indexes can be created in parallel

Run import constraints in parallel with index creation which is performed external to datapump

Use enough parallel threads for faster import. Limit parallel threads not to exceed the number of dump files that are being generated by export

Import Operation

Time Consuming Operations

Time Reduction Methods

Iterations Testing Methods

Page 19: oracle platform migration

Import Operation – Time Lines

Time Consuming Operations

Time Reduction Methods

Iterations Testing Methods

03:00

Start of Import

11:00

End of Import03:25 - 11:00

Full Import – 32Hours

Oracle Suggested

Import

03:00 - 03:25

Import Users

Custom Pre Downtime

Import Activities

13:00 - 16:00

Build Indexes - Big Tables

08:00 - 08:25

Import Users

4/4/2010 8:01 AM

Start of Import

4/4/2010 3:59 PM

End of Import

08:25 - 13:00

Import BigTables

8:25 AM - 11:55 AM

Import FND_LOBS

03:00

Start of Import

11:00

End of Import03:25 - 11:00

Full Import – 32Hours

08:00 - 08:25

Import Users

08:00

Start of Import

16:00

End of Import

08:25 - 13:00

Import BigTables

08:25 - 11:55

Import FND_LOBS

03:00

Start of Import 09:00 - 11:59

Import Procs

03:00 - 09:00

Import AllTables

19:00

End of Import

Custom Pre Downtime

Import Activities

Oracle Suggested

Import

19:00 - 11:00

Downtime Savings

Custom Downtime

Import Activities

03:00 - 03:25

Import Users

12:00 - 16:00

Import Constraints

12:00 - 19:00

Build Indexes

13:00 - 16:00

Build Indexes - Big Tables

Page 20: oracle platform migration

Problem

Code tree needs to be copied from source

New tech stack needs to installed using rapidwiz. Also developer patch sets need to be applied

Environment files and context files need to be modified to reflect correct configuration and instance

PCP settings need to be enabled. Profile options need to set correctly for PCP and managers need to be updated with right primary and secondary nodes

Solution

Implement code and patch freeze - one week before go live date is preferred

Conduct dry run on the future production infrastructure during that week simulating whole go live activities

Application/PCP Configuration

Time Consuming Operations

Time Reduction Methods

Iterations Testing Methods

Page 21: oracle platform migration

Solution

Use the same naming conventions, ports, directories etc that will be used as part of future production

After configuration is complete on dry run, test all important components and functionalities

Upon successful testing download the manager data using FNDLOAD

Create scripts to update database components that are needed as part of PCP configuration like some profile values etc.

Preserve all components except the database. Drop the database and recreate shell database to be ready for go live activity

During go live activities execute database updates, loads and autoconfig only

Time Consuming Operations

Time Reduction Methods

Iterations Testing Methods

Application/PCP Configuration

Page 22: oracle platform migration

Problem

Usually upgrades are performed applying relevant maintenance packs which are big in size. Extraction and verification takes time and it increases this effort if a customer has MLS

Out of three drivers depending on the products used by customer, “d” driver can take long time to complete its activity

It is also observed that some conversion programs are the main culprits

Lot of time is spent on compilation of objects by DB upgrades

Solution

Try to understand the products used by customer and critical functions in these processes

Application/DB Upgrade

Time Consuming Operations

Time Reduction Methods

Iterations Testing Methods

Page 23: oracle platform migration

Solution

Suggest customer to purge any unused historical data related to these products

In proof of concept run identify the workers which took significant time and try to tune the sql or code

Create custom indexes based on the logic and drop them after processes is completed

Make sure archiving is turned off on DB during application of maintenance packs

Make sure that statistics related to objects being used are up to date

Use parallel compile options to speed up DB upgrade

Time Consuming Operations

Time Reduction Methods

Iterations Testing Methods

Application/DB Upgrade

Page 24: oracle platform migration

Time Consuming Operations

Time Reduction Methods

Iterations Testing Methods

Iteration - I

Iteration 1 (Proof of Concept) – Hours Taken 71 DB Nodes: 1 App Nodes: 1

Ta

rg

et

So

urc

e

Clone POC

DB/APPS

from PROD

Read

Oracle

migration

notes

Prepare

Document with

Detailed Steps

needed for

migration

Prepare

DB for

migration

Export

Data

Create

Shell

DB

Tech Stack

Install/Copy

Import

Data

Shared Apps Tier

configuration

Thitrd Party

Integration

Page 25: oracle platform migration

Time Consuming Operations

Time Reduction Methods

Iterations Testing Methods

Iteration - II

Iteration 2 (Verify Steps & Fine Tune Processes) Hours Taken 54 DB Nodes: 2 App Nodes: 4

Ta

rg

et

So

urc

e

Clone POC2

DB/APPS

from PROD

Use prepared

documentPrepare

DB for

migration

Export

Data

Create

Shell

DB

Tech Stack

Install/Copy

Import

Data

Shared Apps Tier

configuration

Add Nodes

Configuration

Fine Tune

DB & Export

Parameters

Parallel

Concurrent

Processing

Configuration

Third Party

Integration

Page 26: oracle platform migration

Time Consuming Operations

Time Reduction Methods

Iterations Testing Methods

Iteration - III

Iteration 3 (CustomizeTime Consuming Processes) Hours Taken 42 DB Nodes: 3 App Nodes: 4

Ta

rg

et

So

urc

e

Clone POC 3

DB/APPS

from PROD

Use prepared

documentPrepare

DB for

migration

Export

Data

Create

Shell

DB

Tech Stack

Install/Copy

Import

Data

Shared Apps Tier

configuration

Add Nodes

Configuration

Parallel

Concurrent

Processing

Configuration

Third Party

Integration

Export

Metadata

Export

BigTables

&

FNDLOBS

Import

Users

Import Big

&

FNDLOBS

Build

Indexes

Page 27: oracle platform migration

Time Consuming Operations

Time Reduction Methods

Iterations Testing Methods

Iteration - IV

Iteration 4 (Parallelize Operations within Processes) Hours Taken 36 DB Nodes: 3 App Nodes: 4

Ta

rg

et

So

urc

e

Clone POC4

DB/APPS

from PROD

Use prepared

documentPrepare

DB for

migration

Create

Shell

DB

Tech Stack

Install/Copy

Shared Apps Tier

configuration

Add Nodes

Configuration

Parallel

Concurrent

Processing

Configuration

Third Party

Integration

Export

Metadata

Export

BigTables

&

FNDLOBS

Import

Users

Import Big

&

FNDLOBS

Build

Indexes

Export

AllTables

Export

Metadata

Import

AllTables

Import

Procs etc

Import

Procs etc

Page 28: oracle platform migration

Time Consuming Operations

Time Reduction Methods

Iterations Testing Methods

Iteration - V

Iteration 5 (Parallelize Operations within Processes) Hours Taken 32 DB Nodes: 6 App Nodes: 12

Dow

ntim

e

Targ

et

Dow

ntim

e

Sou

rce

Get

Tar

get R

eady

for

Dow

ntim

e

Pre

Dow

ntim

e

Targ

et

Pre

Dow

ntim

e

Sou

rce

Preserve

Teck Stack &

Code Trees

Build

Indexe

s

Add Nodes

Configuration

Prepare

DB for

migration

Import

Procs etc

Export

Metadata

Import Statistics

into New PROD

DB

Build

Indexes on

Imported

Tables

Import

Users

Import

Procs etc

Import Big

& FNDLOB

Tables

DB Updates

related to PCP

Import

Procs etc

Parallel

Concurrent

Processing

Configuration

Create

Shell

PROD DB

Third Party

Integration

Export

Metadata

Create

Shell

PROD

DB

Import

Procs etc

Tech Stack

Install/Copy

Third Party

Integration

Drop

PROD DB

on Target

Create

Materialized

Views on

Tables

Expported

Export Statistics

from Source

Use prepared

document

Shared Apps Tier

configuration

Export

BigTables

&

FNDLOBS

Import

Users

Import

BigTables

&

FNDLOBS

Run Auto Config

to configure

nodes

Build

Indexes

Import

AllTables

Use prepared

document

Export

AllTables

Import

AllTables

Page 29: oracle platform migration

Time Consuming Operations

Time Reduction Methods

Iterations Testing Methods

Methods Used Functionality Testing

Can be performed by automated tools like Load Runner or Oracle Applications Testing Suite using prewritten test scripts

Can also be performed by super users to assure that main functionality is working

Should be part of iteration 1 and 3

Performance Testing

If the customer has any tools like Load Runner to simulate business functionalities it will be more scientific. In case of customers who do not have tools manual effort is required and testing will be limited to critical business functionalities

Online Transactions and Batch jobs/processes can be tracked for actual times in existing PROD system and then can be evaluated with migrated system

Page 30: oracle platform migration

Time Consuming Operations

Time Reduction Methods

Iterations Testing Methods

Methods Used Performance Testing

Any processes that differ in elapsed time between existing PROD and migrated system have to be traced

Tracing for online transactions can be done with help of forms trace where as for batch programs it needs to be turned on at program level

All the trace files can be analyzed either by TKPROF or TRACE Analyzer for identifying the issues

This test needs to be performed in iteration 3 and 4

Failover Testing

This test mainly applies to systems which have multiple nodes and failover capabilities. Ex RAC Databases, Parallel Concurrent Processing (PCP) etc

Page 31: oracle platform migration

Time Consuming Operations

Time Reduction Methods

Iterations Testing Methods

Methods Used

Failover Testing

RAC Database Failover

SQLPLUS Session Failover (Only Selects)

Application Functionality with Node down

PCP Failover

Couple of DB nodes down

CM node down

CM Managers Failover from primary to secondary

Load Balancer Failover

Shutdown of one or multiple nodes of APPS tier

Page 32: oracle platform migration

Time Consuming Operations

Time Reduction Methods

Iterations Testing Methods

Methods Used

Load/Capacity Testing

This testing requires automated tools to simulate the load. Manual effort to replicate is very hard

This is usually done in batches with different set of users covering all business functionalities to produce real time scenario

Batch size of concurrent users 200, 400. 600, 1200 and 2000

Active Application Nodes 1, 2, 4, 6 and 8

Active DB Nodes 1, 2, 4, and 6

The following statistics are collected on both application and database tiers

CPU/Memory/Disk Utilization

Load Average

Functionality or Screen Timings

Page 33: oracle platform migration

Thank You

Q&A

“X” Platform Migrations