options for the electrification of rural villages in the...

118
i Options for the Electrification of Rural Villages in the Province of Riau, Indonesia A dissertation submitted to Murdoch University for the degree of Master of Science Kunaifi Sarjana/BE (STTNAS, Indonesia) Supervisor: Dr Trevor Pryor School of Engineering and Energy School of Engineering and Energy Murdoch University Perth Australia 2009

Upload: dangxuyen

Post on 03-Mar-2019

218 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

i

Options for the Electrification of Rural

Villages in the Province of Riau, Indonesia

A dissertation submitted to Murdoch University for the degree of

Master of Science

Kunaifi Sarjana/BE (STTNAS, Indonesia)

Supervisor: Dr Trevor Pryor School of Engineering and Energy

School of Engineering and Energy Murdoch University

Perth Australia 2009  

Page 2: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

ii

Declaration of Authorship 

I declare that this dissertation is my own account of my research and contains as

its main content work which has not previously been submitted for a degree at any

university.

Signed:

Kunaifi

Date: 26 June 2009

 

Page 3: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

iii

Abstract  

Currently over one million households in the Province of Riau in Indonesia,

mainly in rural villages, do not have access to electricity. This dissertation was

aimed to fill the gap of the lack of studies in exploiting local renewable energy

resources to extend the reliable, affordable and sustainable electricity supplies for

Riau’s rural villages. It identifies, designs, and analyses the feasible options that

harness solar energy, hydrokinetic power from rivers and palm-biodiesel fuel for

diesel generators.

Along with a literature study, the HOMER simulation program was used as a

technical design tool, and the I3A framework proposed by Retnanestri (2007) was

adopted as a general design tool to enhance the sustainability of rural

electrification programs (REPs) in Riau.

Two options have been recommended to meet the future electrical load in a

typical Riau rural village. The first option is a hybrid power system comprised of

a photovoltaic array, Darrieus hydrokinetic turbines (DHTs), a back-up diesel

generator, a battery bank, and an inverter. The second option consists of a diesel

generator with biodiesel fuel.

The first option met 100% of the load but the second option had around 20%

capacity shortage. In the first option, the DHTs contributed 55% of the power

output, indicating the viability of exploiting the river power in Riau. The first

option had low O&M costs but its capital cost was high, while the second option

had the opposite cost structure. The costs of energy (COEs) of both options were

higher than the current electricity tariff in Riau, but would be lower than the COE

of a diesel-only system. To enhance the sustainability of the REP implementations

in Riau, it would be necessary to consider the Institutional issues related to

Accessibility, Availability and Acceptability aspects, which simultaneously look

at all features of the REP’s “hardware-software-orgware.”

Page 4: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

iv

Acknowledgements 

After an eleven month struggle, finally this dissertation is done! It initially went slowly due to my difficulties coping with the Perth’s winter, but tremendous help and support from many people and institutions have allowed me to finish it. This dissertation would not have been possible without the profound thoughts, support and guidance from my supervisor, Dr Trevor Pryor of the School of Engineering and Energy Murdoch University, to whom I would like to express my deep gratitude and respect. Similar appreciation to all academics at Murdoch University from whom I have learnt so much within last two years; Professor Philip Jennings, Dr Jonathan Whale, Dr August Schalpfer, Dr Katrina Lyon, Mr Adam McHugh, Mr Peter Devereux, among others. Epis and Iyon, I sincerely thank both of you for your valuable time, skills and courage, that made the vital data from the field available to me, although you had to put yourselves at great risk by wading in the Batang Kuantan just a day after the villagers saw a crocodile crawling on the riverbank. I would never have allowed that if you had let me know beforehand. I am also grateful to the Chiefs of Saik, Pulau Panjang Hulu and Pulau Panjang Hilir Villages for their warm reception and help in seeking canoes and rowers for my field team fellows. A hopeful question from the villagers, “will the villages be electrified soon?” has made me sad and gave me deeper insight that they really need help. My gratitude also goes out to a number of institutions that kindly provided a broad range of support (financially, intellectually, and logistically), among others; AusAID (my Master’s study sponsor institution), School of Engineering and Energy Murdoch University, Murdoch International, PLN Teluk Kuantan, Department of Electrical Engineering and Faculty of Science and Technology UIN Suska Riau, Alternative Hydro Solutions Ltd. Canada, and CV Generindo Jakarta. I would also like to gratefully acknowledge the assistance I have received from Tom Lambert of Mistaya Engineering (the NREL’s HOMER simulation program developer) for his kindly respond to my questions about HOMER, Dr Maria Retnanestri (of UNSW, for allowing me to use her I3A framework), Poppy D. Lestari and Zulfatri Aini (of Faculty of Science and Technology UIN Suska Riau, who managed to get field work approval from the Faculty Dean for me), Iswadi HR. and Teddy Purnamirza (for providing Riau energy data for me), Dr Sally Knowles (of Murdoch University, for editing my dissertation), and Tania Urmee (of Murdoch University) for her valuable advice about electrical load assessment method. I really appreciated Benny L. Maluegha, Luky Djani and Pak Suharsono, my great housemates, for their valuable time, intelligence, humour, and patience in discussing about lecture materials of my other units that allow me to concentrate to my dissertation, for their excellent comments about my dissertation seminar presentation practice, and for their great friendship. I dedicate my dissertation to my late beloved parents; Bapak Ali Soe’id and Omak Mina Asiah, and to my wife and son; Murparsaulian and Zia Al Khair Nailian, my sources of inspiration and strength, who have dedicated their years supporting my study, that make me feel loved, proud and fortunate. My greater family, based in Indonesia, Edison Asmisor, Nelfizon Asmi, Sacra, Rinda Sutri, Herdian Asmi, Meliani, Rita Eliza, Fitri Zalianis, and their families, Ayah M. Simanjuntak, Ibu Damsiah, Herman, Samson Rambah Pasir, Umi Khoiri, Dumasari, Tiurlan, Bengki Gultom, and Pitria Mayasari, who have always been great sources of encouragement. Finally, I am thankful to Allah SWT., the Greater source of my life for spiritual guidance.

Page 5: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

v

“The narrow and incorrect view about Renewable Energies is the prejudice that they would be an economic burden. The most urgent need is to overcome these mental barriers, including the psychological fear of the consequences of changes for the individuals and society on the whole” (Dr. Hermann Scheer, General Chairman of World Council for Renewable Energy, President of EUROSOLAR). From: Bassam, N. E. and P. Maegaard. 2004. Integrated Renewable Energy for Rural Communities: Planning Guidelines, Technologies and Applications. Amsterdam: Elsevier.

 

Page 6: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

vi

Acronyms, Glossary and Terms 

APBD Anggaran Pendapatan dan Belanja Daerah (Provincial Annual Budget)

BPS Biro Pusat Statistik (Bureau of Statistics)

CHP Combined Heat-Power or Cogeneration System

COE Cost of Energy

DESDM Departemen Energi dan Sumber Daya Mineral (Department of Energy and Mineral Resources)

Distamben Dinas Pertambangan dan Energi (Mining and Energy Board)

GDP Gross Domestic Product

GHG Greenhouse gases

Kepri Propinsi Kepulauan Riau (The Province of Riau Island)

NASA SMSE NASA’s Surface Meteorology and Solar Energy database

NGO Non-Governmental Organization

NPC Net Present Cost

O&M Operation and Maintenance

PLN Riau-Kepri PLN Riau and Kepulauan Riau

PLN PT. Perusahaan Listrik Negara (National Utility Company)

PV Photovoltaic

RAPS Remote Area Power Supply

RE Renewable Energy

REP Rural Electrification Program

RIS Riau Interconnected System

RUKD Riau Rencana Umum Ketenagalistrikan Riau (Riau Electric Power General Plan)

Page 7: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

vii

Table of Contents 

Declaration of Authorship .................................................................................. ii Abstract .................. .................................................................................... iii Acknowledgements ........................................................................................... iv Acronyms, Glossary and Terms ........................................................................ vi Table of Contents ............................................................................................. vii List of Figures .................................................................................................... x List of Tables.................................................................................................... xii Chapter 1 Introduction ...................................................................................... 1

1.1 Problem Definition ................................................................................1

1.2 Objectives and Potential Contribution ...................................................2

1.3 Previous Research..................................................................................3

1.4 Structure of Dissertation ........................................................................4

Chapter 2 Methodology ..................................................................................... 7 2.1 Problem Identification ...........................................................................7

2.2 Site Candidates Selection ......................................................................7

2.3 Renewable Energy Resources Assessment ............................................7

2.4 Definitive Reference Village Selection .................................................8

2.5 Options Identification ............................................................................8

2.6 System Design and Analysis .................................................................8

2.7 Sustainable Rural Electrification Programs Design ............................10

Chapter 3 the Province of Riau ........................................................................ 12 3.1 Introduction .........................................................................................12

3.2 Overview of Riau.................................................................................12

3.2.1 Geography and Climate ............................................................ 12

3.2.2 Population Distribution ............................................................ 14

3.2.3 Economic Status ....................................................................... 14

3.3 Electricity Industry ..............................................................................15

3.3.1 Introduction .............................................................................. 15

3.3.2 Current Scenario of electricity production ............................... 15

3.3.3 Electricity Supply Crisis ........................................................... 17

3.3.4 Future demand for electricity ................................................... 18

3.3.5 Cost of Energy .......................................................................... 19

Page 8: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

viii

3.4 Energy Related Social Issues ...............................................................20

3.4.1 Introduction .............................................................................. 20

3.4.2 Poverty ...................................................................................... 21

3.4.3 Key Health Problems ................................................................ 22

3.4.4 Education .................................................................................. 24

3.4.5 Women’s Liberty ...................................................................... 25

3.5 Renewable Energy Potential ................................................................26

3.5.1 Biodiesel ................................................................................... 26

3.5.2 Hydropower .............................................................................. 28

3.5.3 Solar .......................................................................................... 29

3.6 Concluding Remarks ...........................................................................29

Chapter 4 Evaluation of Hybrid RAPS for Riau .............................................. 31 4.1 Introduction .........................................................................................31

4.2 Selecting a Reference Village ..............................................................31

4.2.1 Selecting Three Site Candidates ............................................... 31

4.2.2 Energy Resources Assessments ................................................ 33

4.2.3 Selecting a Reference Village .................................................. 39

4.2.4 Overview of the Reference Village .......................................... 39

4.3 System Design .....................................................................................41

4.3.1 General criteria of the system ................................................... 41

4.3.2 Electrical load ........................................................................... 41

4.3.3 System design ........................................................................... 46

4.4 Results and discussion .........................................................................57

4.4.1 Economic analysis .................................................................... 58

4.4.2 Electrical output analysis .......................................................... 59

4.4.3 Emissions analysis .................................................................... 61

4.4.4 Sensitivity analysis ................................................................... 61

4.4.5 Strategies to improve the system’s performance ...................... 61

4.5 System Configuration and Component Performances.........................62

4.5.1 System configuration ................................................................ 62

4.5.2 Component specifications ........................................................ 63

4.5.3 Component performance .......................................................... 65

4.5.4 Control ...................................................................................... 68

4.5.5 Integrated system power output ............................................... 69

4.6 Concluding Remarks ...........................................................................70

Page 9: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

ix

Chapter 5 Evaluation of Biodiesel Power Systems for Riau ............................. 72 5.1 Introduction .........................................................................................72

5.2 Method of Biodiesel Power Systems Design ......................................73

5.3 System Design .....................................................................................73

5.3.1 Fuel Input ................................................................................. 74

5.3.2 Emissions .................................................................................. 74

5.3.3 Schedule ................................................................................... 75

5.4 Simulation Results and Discussion .....................................................76

5.5 Concluding Remarks ...........................................................................79

Chapter 6 Sustainable Rural Electrification Programs .................................... 81 6.1 Introduction .........................................................................................81

6.2 The I3A Framework in Brief ...............................................................81

6.3 Recommendations to Enhance RE Projects’ Sustainability ................83

6.3.1 Recommendations to Enhance Institutional Sustainability ...... 83

6.3.2 Recommendations to Enhance Financial Sustainability .......... 84

6.3.3 Recommendations to Enhance Technological Sustainability .. 84

6.3.4 Recommendations to Enhance Social Sustainability ............... 85

6.3.5 Recommendations to Enhance Ecological Sustainability ........ 85

6.4 Concluding Remarks ...........................................................................86

Chapter 7 Conclusions and Recommendations ................................................ 87 7.1 Conclusions .........................................................................................87

7.2 Recommendations ...............................................................................89

7.3 Final Words .........................................................................................90

References ..................................................................................................... 91 Appendix A Solar radiation data .............................................................................. 98

Appendix B HOMER Input Summary .................................................................... 99 Appendix C Estimating monthly average flow speed using rainfall variation.104 Appendix D Specification of the components of the hybrid RAPS system . 105 Appendix E Simulation results of a diesel only system with zero capacity

shortage ...................................................................................... 106

 

Page 10: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

x

List of Figures 

Figure 2.1 -  Research methodology .................................................................... 131 

Figure 3.1 -  Riau’s geographical position in Indonesia. ....................................... 13 

Figure 3.2 -  The map of Riau showing major town and four main rivers. ............ 13 

Figure 3.3 -  Riau’s population distribution, cities and villages. ........................... 14 

Figure 3.4 -  Electrical Power Supply Systems in Riau. ........................................ 16 

Figure 3.5 - Koto Panjang Hydro-Power Plant. .................................................... 18 

Figure 3.6 -  Electricity consumption projection, 1997 – 2020. ............................ 19 

Figure 3.7 -  Per capita electrcity consumption in some SEA countries ................ 21 

Figure 3.8 -  A woman in a village in Riau. ........................................................... 22 

Figure 3.9 -  Energy sources for lighting in Riau. .................................................. 23 

Figure 3.10 -  Typical traditional stove used by households in Riau. ...................... 23 

Figure 3.11 -  Typical school in a Riau rural village. .............................................. 24 

Figure 3.12 -  A women in a village in Riau. ........................................................... 25 

Figure 3.13 -  Typical Riau palm plantation ............................................................ 27 

Figure 3.14 -  Siak River .......................................................................................... 28 

Figure 3.15 -  Solar resources in main cities of Riau ............................................... 29

Figure 4.1 -  The schematic of the river flow velocity measurement. ................... 33 

Figure 4.2 -  Actual measurement of river flow velocity. ...................................... 34 

Figure 4.3 -  Schematic of the river depth measurement. ...................................... 35 

Figure 4.4 -  Actual river depth measurement. ....................................................... 35 

Figure 4.5 -  Schematic of the river width measurement. ...................................... 36 

Figure 4.6 -  The depths of the river near three villages. ....................................... 37 

Figure 4.7 -  Monthly averaged horizontal solar radiation at Saik. ........................ 39 

Figure 4.8 -  Typical middle income household at Saik. ....................................... 40 

Figure 4.9 -  Monthly electricity consumption of selected households in Muaro Tombang ............................................................................................ 42 

Figure 4.10 -  The estimated electrical load profile in Saik. .................................... 45 

Figure 4.11 -  Revised estimated electrical load profile in Saik. ............................. 46 

Figure 4.12 -  Architecture of HOMER simulation and optimisation. ..................... 47 

Figure 4.13 -  HOMER’s component selection input window. ................................ 48 

Figure 4.14 -  HOMER’s load input window. .......................................................... 49 

Figure 4.15 -  Hydrokinetic turbine power curve. .................................................... 51 

Figure 4.16 -  Trojan T-105 batteries. ...................................................................... 53 

Page 11: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

xi

Figure 4.17 -  Rainfall in western part of Riau ........................................................ 55 

Figure 4.18 -  The HOMER’s hydrokinetic resource input window ........................ 55 

Figure 4.19 -  Hybrid RAPS system configuration for Saik. ................................... 57 

Figure 4.20 -  Hybrid RAPS system optimization results. ....................................... 58 

Figure 4.21 -  Lifecycle costs of hybrid RAPS system by components. .................. 59 

Figure 4.22 -  Monthly electricity production of each component of the hybrid RAPS system. .................................................................................... 60 

Figure 4.23 -  Parallel hybrid configuration of the system. ..................................... 63 

Figure 4.24 -  Darrieus hydrokinetic turbine and its boat mounting method ........... 64 

Figure 4.25 -  DHTs power output. .......................................................................... 67 

Figure 4.26 -  PV array power output. ..................................................................... 67 

Figure 4.27 -  Battery bank frequency of SOC. ....................................................... 67 

Figure 4.28 -  Inverter output. .................................................................................. 67 

Figure 4.29 -  Rectifier output. ................................................................................. 68 

Figure 4.30 -  Diesel generator output. .................................................................... 68 

Figure 4.31 -  Charge controller, blocking diodes and bypass diodes circuit. ......... 69 

Figure 4.32 -  Integrated system power output. ....................................................... 70

Figure 5.1 -  Biodiesel daily operation schedule. ................................................... 75 

Figure 5.2 -  Optimisation results of the Biodiesel power system simulation. ...... 77 

Figure 5.3 -  Costs of biodiesel power system. ...................................................... 77

Figure 6.1 -  The I3A Model: Sustainable RE Delivery Framework ..................... 82 

Page 12: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

xii

List of Tables 

Table 3.1 -  Electricity tariff in Riau ..................................................................... 19 

Table 3.2 -  Riau’s Plantation status, 2007. .......................................................... 26 

Table 3.3 -  Biodiesel manufacturers in Riau. ...................................................... 27 

Table 3.4 -  Hydro-power potential from large rivers. .......................................... 28

Table 4.1 -  Three site candidates for hybrid RAPS system. ................................ 32 

Table 4.2 -  The river current velocity near three villages. ................................... 37 

Table 4.3 -  Summary of river characteristics in three villages. ........................... 38 

Table 4.4 -  Information summary of Siak. ........................................................... 40 

Table 4.5 -  Estimated load devices of all consumer groups in Saik. ................... 43 

Table 4.6 -  Electrical devices’ operational of all consumer groups in Saik. ....... 44 

Table 4.7 -  Summary of other information was entered into HOMER. .............. 56 

Table 4.8 -  Optimisation and sensitivity variables of the inputs. ........................ 57 

Table 4.9 -  Economic performance of the hybrid RAPS system. ........................ 58 

Table 4.10 -  Electrical performance of the hybrid RAPS system. ......................... 60 

Table 4.11 -  Electrical performance of each component. ...................................... 65

Table 5.1 -  Properties of palm biodiesel. ............................................................. 74 

Table 5.2 -  Average biodiesel emission compared to conventional diesel. ......... 75 

Table 5.3 -  Design information for biodiesel power system. ............................... 76 

Table 5.4 -  Generator performance for B100 and B20 systems. ......................... 78 

Table 5.5 -  Emission of B100 and B20 systems. ................................................. 79

Table 6.1 -  Summary of the I3A framework for practical use. ............................ 83 

Page 13: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

1

Chapter 1 Introduction 

The role of electricity is critical for modern society to live a better quality of life

and has been used for an enormous, and proliferating, number of applications [1].

We consider modern living to be defined by the availability of electric lamps, air

conditioners, communication, industrial electric motors, electric trains, and even

extraterrestrial human-made objects. All are dependent on the power of electricity.

Thus, it is obvious that major difficulties would be experienced by human

civilisations today when access to electricity is restricted or limited.

Unfortunately, services provided by electricity are not equally delivered to all

global inhabitants. More than 1.6 billion people in the world – most are in the

developing countries - have never felt the delight of the electricity services [2]. In

Indonesia, over 70 million people in 2005 did not have any electricity

connections, of which more than 80% live in remote areas, and 50% were outside

the economic centre of Java and Bali islands [3].

In order to promote the expansion of distributed power generation, to balance the

concentrated ones, Remote Area Power Supply (RAPS) Systems, by means of

maturely available technologies, are the fashionable options for addressing the

challenge of low electrification rates in Indonesia.

1.1 Problem Definition  

In the Province of Riau in Indonesia, access to electricity seems to be a ‘never

ending’ problem. Urban communities of Riau have yet to achieve reliable

Page 14: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

2

electricity services, while people in rural areas are still dreaming of connecting to

an electricity supply. In 2009, over one million dwellings in Riau are still not

electrified, mostly in rural villages located on four large riverbanks [4].

Despite its strong economy, the lack of electricity supply has contributed to social

issues such as poverty, poor health services, low education, and gender inequity.

Furthermore, the environmental challenges with regard to greenhouse gas (GHG)

emissions from fossil fuel burning in diesel power stations, as the main power

generators in Riau, are obvious [5]. Finally, the lack of studies, expertise and

experiences in dealing with rural electrification programs, are some of the

impediments among Government agencies, to optimize REP implementations in

Riau. With only 4,000 dwellings targeted per year [4], it would take 250 years to

extend electricity to all Riau people.

On the other hand, Riau has potential to build a mixed-power system strategy by

introducing renewable energy (RE) to the existing power generation systems. This

dissertation explores the ways of harnessing the promising sources of renewable

energy in Riau including biodiesel, solar photovoltaic (PV) and river hydro-

kinetic energies as a contribution to understanding how to address the electricity

supply issues in Riau, particularly in rural areas.

1.2 Objectives and Potential Contribution 

The main objectives of this study are:

1. To identify the electricity supply issues in Riau and their effects on the social

life overall, with particular emphasis on the rural areas.

Page 15: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

3

2. To identify the feasible options, from a technical perspective, to provide

electricity for rural communities in Riau, based on the available technologies

and local energy potential, with particular attention to RE.

3. To perform the design and analysis of power systems for the identified

feasible options.

4. To propose recommendations to enhance the sustainability of REPs in Riau.

This dissertation is among the first holistic studies, if not the first, to fill the gap

with respect to the lack of local expertise and experience related to electricity

delivery for rural communities in Riau. The target audience includes Government

agencies (national, provincial and district levels), policy makers, energy planners,

Non-Governmental Organizations (NGOs) and other interested parties.

1.3 Previous Research 

The only identified academic study which addresses Riau electricity supply is the

Riau Electric Power General Plan (RUKD Riau) of the Riau Mining and Energy

Board [6]. RUKD Riau identifies issues around Riau electricity supply, primary

sources of energy, and the future electrical power supply strategic plans (with a

focus on the energy policy perspective). With respect to rural electrification,

RUKD Riau identifies three obstacles for implementing REPs in Riau: (1) most of

the villages have small populations that are very remote and scattered, (2) lack of

road access for fuel transport, and (3) insufficient local energy potential [7]. The

latter, unfortunately, was not supported by any evidence. Additionally, the

recommendations proposed were focused on extending the grids or installing

Page 16: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

4

diesel generators, which contradict the above points 1 and 2, respectively [8]. In

general, RUKD Riau does not reflect the electricity needs of rural communities,

which are the majority of Riau’s population.

1.4 Structure of Dissertation 

This dissertation consists of seven chapters, which are organised as follows:

Chapter 1: Introduction overviews the rationale for this study. It includes the

problem definition, objectives of the study, potential contribution, previous related

research, and the structure of the dissertation.

Chapter 2: Methodology comprises methods implemented covering seven

stages. These are formulating the problem definition, selecting site candidates for

the study, assessing local renewable energy resources, selecting a definitive

reference village, indentifying options to generate electricity for rural villages in

Riau, designing and analysing the identified options, and designing a

comprehensive sustainable REPs.

Chapter 3: The Province of Riau introduces general information about the

Province of Riau, the location of this study. It consists of an overview about Riau

(geography, climate, population, and economic status). Then, the current electricity

industry in Riau is introduced by considering the current scenario of electricity

production, electricity supply crisis, future demand for electricity, and the electricity

tariff. Following this technical overview, the social issues related to the absence or

the lack of electricity supply, are outlined. They include poverty, health, education,

and gender equity issues. Finally, three RE potentials applicable to this dissertation

Page 17: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

5

are presented. They include biodiesel, hydrokinetic power from rivers, and solar

energies.

Chapter 4: Evaluation of Hybrid RAPS for Riau deals with the first option

considered in this dissertation. It evaluates a detailed process of designing

hybrid renewable RAPS for Riau, in four parts. The first part deals with the

process of selecting a reference village. It covers selecting three site candidates

based on a number of criteria. These comprise assessing RE resource in three

site candidates, and selecting a definitive reference village by comparing

parameters from three site candidates. In the second part, the process of

designing a hybrid RAPS system in the reference village is explained in great

detail. The key elements for design are: specifying general criteria of the system,

assessing electrical load, selecting the simulation software, inputting

information to the software, and running the simulation. The simulation results

(economics, electrical and emission) are presented and discussed in the third

part. Strategies to improve the system’s performance are also proposed in this

part. The last part covers system configuration, components’ performances,

control, and integrated power output of the system.

Chapter 5: Evaluation of Biodiesel Power Systems for Riau deals with the

second option considered in this dissertation. It contains the methodology used in

designing a biodiesel power system using the HOMER simulation program, issues

pertaining to running the simulation and the results and discussion.

Chapter 6: Sustainable Rural Electrification Program identifies issues that are

intrinsic to the implementation of REPs in Riau. It consists of two parts. The first

Page 18: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

6

part outlines information about the I3A framework suggested by Retnanestri as

the design tool for a sustainable REP in Riau [7]. In the second part, a list of

recommendations to enhance the sustainability of the REPs is presented. They

include recommendations in institutional, financial, technological, social, and

ecological aspects of REPs.

Chapter 7: Conclusion and Recommendation presents conclusions that have

been derived from this study, followed by recommendations for further study and

for practical implementation of both proposed options. This chapter concludes

with a few brief final words.

Page 19: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

7

Chapter 2 Methodology 

Different methodologies have been applied to address each objective of this study.

Each methodology was selected to suit the seven phases used to undertake this

research. The detail methodology is presented in Figure 2.1.

2.1 Problem Identification  

The problem identification involved a literature survey in collecting general

information about Riau such as geography, climate, population, economic status,

current electricity industry and future demand, and cost of energy (COE) was

collected. The main focus of the survey was on the renewable energy sources

available, electricity supply crisis in areas where the grids exist, as well as social

issues related to the absence of electricity in areas in the absence of electricity.

2.2 Site Candidates Selection  

Three villages were selected as site candidates for the power systems. Each

village met the following criteria: accessible for undertaking field work, has no

access to the grid and was unlikely to have the grid extended in the near future,

has both micro-hydro and solar energy resources, is close to the river body, and

has a relatively small population.

2.3 Renewable Energy Resources Assessment  

The potential for river power, solar resource and biodiesel resource in the three

site candidates were assessed. In the selected river, the flow velocity, depth, and

Page 20: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

8

width were measured using a float method, long-scaled stick, and stretching metal

string, respectively. The solar insolation and clearness index for a year long period

was obtained from the NASA Surface Meteorology and Solar Energy database

(SMSE). Information about biodiesel resources in Riau was obtained through a

literature survey.

2.4 Definitive Reference Village Selection  

Based on the criteria in Section 2.2 and comparing parameters from three site

candidates, one village was selected as the definitive reference village on which

the system design was based.

2.5 Options Identification  

Feasible options of generating electricity in rural villages were proposed based on

available power generating technologies and local energy resource potentials. The

paramount feature of this task was power extraction from renewable resources.

The available technologies were identified through a literature survey based on

best practices in off-grid power systems applications.

2.6 System Design and Analysis  

Notwithstanding the types of power systems selected in Section 2.5, the following

is the sequence of system design used in this dissertation.

Page 21: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

9

Step 1: Establishing general criteria of the systems

The approved systems followed these criteria: they consisted of a photovoltaic

component – at least in one option (refer to Section 4.3.1), they have lowest Net

Present Cost (NPC), and would deliver the lowest environmental impact.

Step 2: Electrical load assessment

Electrical load assessment comprises identification of consumer groups, listing

load devices (after the village is electrified), and plotting the load profile of the

village. Information about the consumer groups came from the village statistic

board in the reference village. Information about load devices and load profile

was obtained from two sources including: the local utility office (electricity

consumption in several households at a nearby grid-connected village), and the

author’s understandings of the electricity consumption pattern in another grid-

connected village near the reference village.

Step 3: System design and analysis

The power supply systems were designed using the HOMER(R) simulation

software developed by the National Renewable Energy Laboratory (NREL) of the

United States of America. Special attention was given to the following

considerations:

- Since HOMER is not equipped with a free-flow river module as used in this

study, the wind power modules have been used instead. Information about

hydro turbine was inputted to HOMER’s wind turbine module, and

Page 22: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

10

information about river flow speed was provided to the HOMER’s wind

resource module.

- To simulate the biodiesel power system, the fuel properties and emission

factors of biodiesel fuel were specified.

The analysis of the simulation results was based on simulation output information

and its logical relation with inputs and underlying power system theories. The

currency used was US Dollars (US$1 = 9,000 Indonesian Rupiah (Rp.).

2.7 Sustainable Rural Electrification Programs Design 

Implementing REPs for rural villages in developing countries like Indonesia must

take account of technical and non-technical aspects. All underlying aspects were

addressed by adopting the I3A (Implementation, 3A) framework proposed and

tested by Retnanestri as a general project design tool that the REP planners need

to consider to ensure the projects will be sustainable [9].

Page 23: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

11

Figure 2.1 - Research methodology.

Page 24: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

12

Chapter 3 The Province of Riau 

3.1 Introduction 

The Province of Riau – also known as Central Sumatra – is among Indonesia’s

richest regional areas. However, despite its strong economic structure and the

large potential of the energy resources it possesses, the province is still

encountering problems due to poverty, poor health services, low levels of

education, gender inequity, and insufficient electricity supply.

This chapter, based on a review of the literature, introduces general

information about Riau in relation to energy-related issues. The first part of

the chapter overviews Riau’s geography and climate, population, and

economy. It is followed by Riau’s electricity industry status and a discussion

of the current electricity supply scenario, electricity crisis, future demand,

and the COE. The social impacts of the electricity crisis are briefly outlined.

This chapter concludes with a review of three available renewable energy

resources which are relevant to this dissertation.

3.2 Overview of Riau 

3.2.1 Geography and Climate

Riau is located in the middle of Sumatra Island, in the western part of Indonesia,

and it lies precisely on the equator (Figure 3.1). It is spread between Latitude

02o25'00’’North and 01o05'00’’South, and between Longitude 100o00'00’’ to

105o05'00’’East [10].

Page 25: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

Figure

Riau’s

rainy se

average

Figure

Hundre

The riv

other d

e 3.1 - Ria

climate is

easons are a

e temperatu

e 3.2 - The

eds of river

vers are imp

domestic us

au’s geograp

wet and tro

almost equa

ure in Pekan

e map of Ri

rs flow thro

portant for t

se such as

1

phical posit

opical with

al, with app

nbaru, the ca

iau showing

ough Riau,

transportatio

for laundr

13

ion in Indon

two season

proximately

apital city, i

g major tow

with four o

on, agricultu

ry and bath

nesia [11].

ns. The leng

160 days o

is 27.2°C. [8

n and four m

of them bei

ure, drinkin

hing. This p

gths of the

of rain per y

8].

main rivers

ing the maj

ng water sup

project atte

dry and

year. The

[12].

jor ones.

pply and

empts to

Page 26: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

14

harness power from those rivers – together with other local energy resources – in

generating power for the nearby communities. The map of Riau in Figure 3.2

shows the four large rivers: Kuantan, Rokan, Kampar and Siak Rivers.

3.2.2 Population Distribution

The population of Riau in 2006 was 4.8 million with an annual growth of 3.8 %

per annum (from 1998 to 2002) [13], which is higher than the average national

population growth at 1.4% per annum for the same period [14]. As shown in

Figure 3.3, around 45 % of the inhabitants live in the cities and 55 % are villagers

living in rural areas [15].

Figure 3.3 - Riau’s population distribution, cities and villages [13].

Due to cultural background, most of the population, both in cities and villages, live by

four large riverbanks [16] - [17]. Unfortunately, information about the exact

percentage of population living in the riverbank villages is unavailable.

3.2.3 Economic Status

As the largest oil producer in Indonesia, some 61.5% of Riau’s total revenue in

2006 came from natural resources ‘sharing’ [18]. The contribution from oil

Page 27: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

15

revenue has made Riau one of the Provinces with the largest annual budget

(APBD) in Indonesia. Accordingly, the per capita Gross Domestic Product (GDP)

is high; for example, it was US$3,200 in 2006, or twice the average national per

capita GDP at US$1,663 [19]. However, if oil revenue is excluded, the GDP per

capita falls to US$1,600 [20].

The majority of the Riau population are farmers (53%), and the rest work for trade

and hospitality (14%) and service sectors (10%) [11]. The average inflation rate in

Pekanbaru during January to November 2008 was 0.1% [21]. The unemployment

rate in 2007 was 10.39% [22].

3.3 Electricity Industry 

3.3.1 Introduction

Riau is still facing electricity supply challenges. By 2005, the electrification ratio

was only 40% so that the majority of rural villages do not have access to

electricity [23], [24]. According to the IEA [25], the root of the problem causing

the electricity crisis throughout the country is the inadequate capacity of the

Indonesian Government to raise and administer the capital required to increase its

electricity infrastructure. The latter is the case in Riau.

3.3.2 Current Scenario of electricity production

Electricity supply generation in Indonesia is dominated by the national utility

company, PT. Perusahaan Listrik Negara (PLN), which is wholly owned by the

Central Government. Riau and its neighbour, the Province of Riau Islands (Kepri),

Page 28: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

16

share a regional PLN office named PT. PLN Riau and Kepulauan Riau (PLN

Riau-Kepri).

There are three power systems currently in existence in Riau (Figure 3.4).

According to the PLN Riau-Kepri [5], the largest public system consists of a

number of isolated microgrids from diesel generators (mainly situated in the

District’s capital cities), small capacity off-grid renewable power systems, and a 4

MW private cogeneration system. The second system is the Riau Interconnected

System (RIS) coupled to the 150 kVA South and Central Sumatra

(SumBagSelTeng) System. The maximum operating capacity of the RIS is 230

MW. The third system is the isolated captive generators owned and operated by

industries operating in Riau for self uses with the total capacity in 2005 of 950

MW [24].

Figure 3.4 - Electrical Power Supply Systems in Riau [5].

Page 29: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

17

3.3.3 Electricity Supply Crisis

Apart from the unelectrified areas, in the areas to where the grids are extended,

both through the RIS and isolated microgrids, the power supply is insufficient.

The society is increasingly encountering electrical power service tribulations such

as power quality issues (frequency and voltage fluctuations), power restrictions,

and even blackouts [26]. To provide one example, in Rokan Hulu District which

is around 200 km from Pekanbaru, where a microgrid powered by a diesel

generator exists, people cannot properly operate home appliances like televisions,

electric pumps, refrigerators, air-conditioners, lamps, etc., due to frequency and

voltage fluctuations.

According to the PLN Riau-Kepri [5], the peak load of the RIS is around 270

MW, whilst the supply is only 230 MW. Thus, in normal situations, areas

connected to the RIS experience a power deficit of around 40 MW. The shortfall

could swell anytime if one or more plants in the SumBagSelTeng network

encounter problems, because its share of the RIS is significant; around 35% [5].

For example, the output depletion of the Ombilin Hydro Power Plant in the

neighbouring province which is connected to the SumBangSelTeng network in

2004 has aggravated the ongoing electricity crisis in Riau [26].

Pekanbaru, where the power supply is most secure, is not exempt from blackouts.

During the dry season, when the output of hydro plants decreases, the normal

daily blackout in Pekanbaru is around 6 hours, and in a worst case situation could

reach 24 hours a day [27].

Page 30: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

Figure

In the f

water-c

isolated

remain

power

of 54%

DESDM

generat

the life

electric

3.3.4 F

Accord

electric

e 3.5 - Kothttpar-1

future, the c

catchment a

d diesel gen

ing protecte

source in R

%, while th

M and Rah

tors in Riau

etime of a d

city supply i

Future dem

ding to Dist

city demand

to Panjang Hp://img.phot1.jpg).

crisis is like

area and th

nerators. Re

ed forest ar

RIS, is only

he deforesta

hardjo and

u have been

diesel gener

in the area b

and for ele

tamben Riau

d in the peri

1

Hydro-Powtobucket.co

ely to contin

he decreasi

ecent data c

round Koto

y 33%, lowe

ation is ong

d Fitriana

n in operati

rator is 30 y

beyond the

ectricity

u [6], as sh

iod of 2004

18

wer Plant (Soom/albums/v

nue, or even

ing perform

confirm that

o Panjang H

er than the

going [28],

[25], [30],

on for over

years, in 5

RIS must b

hown in Figu

4 – 2013 in

ource: v687/ranids

n worsen, du

mance of th

t, due to th

Hydro-powe

prescribed

[29]. Also

most of

r 15 to 25 y

years’ time

e addressed

ure 3.6, the

Riau is aro

s/bendungko

ue to the de

he majority

he deforesta

er Plant, the

land-use re

o, according

the isolated

years. By a

e new challe

d by PLN.

e average gr

ound 8.6% p

otokamp

ecreasing

y of the

ation, the

e largest

egulation

g to the

d diesel

assuming

enges of

rowth of

per year,

Page 31: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

and the

time, in

current

Figure

3.3.5 C

A unifo

electric

governm

Indone

Table 3

Ta

Social

e peak load

n the low

t demand.

e 3.6 - Ele

Cost of Ener

orm electric

city tariff

ment office

sia Decree N

3.1 - Electrioffices

ariff group

Services

is expected

growth sce

ectricity con

rgy

city tariff is

for residen

es (e.g. he

No. 104/200

icity tariff fs.

PowMax. (

450

1

d to grow b

enario, the

nsumption p

s applied th

ntial, socia

ealth clinics

03.

for residenti

er (VA)

Ins(US$

0

19

y 7.63% pe

demand co

projection, 1

hroughout In

al services

s), based o

ial, social se

stalment fee$/kVA/mont

1.11

er year. As

ould be mo

1997 – 2020

ndonesia. T

(e.g. wor

on the Pres

ervices and

e th)

Price (U

shown, in t

ore than do

0 [6].

Table 3.1 sh

rship centr

sident of R

governmen

per unit conUS$ cent/kW

00-30 kWh:31-60 kWh:

> 60 kWh:

ten years

ouble to

hows the

res) and

Republic

nt

nsumed Wh)

:

1.4

: 2.9: 4.0

Page 32: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

20

Table 3.1 – (cont.)

Source: Office of President of Republic Indonesia [31].

3.4 Energy Related Social Issues 

3.4.1 Introduction

Riau’s electrification is among the lowest for comparable regions in Indonesia.

According to PEUI [24], in 2005, the annual per capita electricity consumption in

Riau was only 264 kWh. This is equivalent to around 0.7 kWh a day, or the

equivalent of running two 25 watts lamps and an 80 watts television for 5 hours a

day, not more. The Riau per capita electricity consumption was far below the

Tariff group Power Max. (VA)

Instalment fee (US$/kVA/month)

Price per unit consumed (US$ cent/kWh)

Social Services 900 1.67 00-20 kWh: 2.221-60 kWh: 3.3

> 60 kWh: 4.01,300 2.78 00-20 kWh: 2.8

21-60 kWh: 3.7> 60 kWh: 4.5

Residential

450

1.22

00-30 kWh:

1.9

31-60 kWh: 4.0> 60 kWh: 5.5

900 2.22 00-20 kWh: 3.121-60 kWh: 4.9

> 60 kWh: 5.51,300 3.34 00-20 kWh: 4.3

21-60 kWh: 4.9> 60 kWh 5.5

Government offices

450

2.22

6.4

900 2.73 6.71,300 2.73 6.7

Page 33: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

21

national average at 484 kWh per year in 2005 [24], and is almost negligible if

compared to some nations in South East Asia (SEA) (Figure 3.7).

* The 2002 data source for Riau is from the Distamben Riau [6], and the 2004 data is from PEUI [25]

Figure 3.7 - Per capita electrcity consumption in some SEA countries, 2002 & 2004 [32].

Mapako and Prasad argue that the level of access to electricity, in many

developing countries, is commonly seen as one of the essential indicators of

development [33]. Noticeably, the low level of electricity access influences the

social and economic welfare of the Riau people.

This section looks at the correlation between energy consumption, particularly

electrical energy, and social issues in Riau, i.e. poverty, health, education, and

gender equity.

3.4.2 Poverty

Despite its strong financial structure (refer to Section 3.2.3), poverty is the major

issue in Riau which is yet to be resolved. The BPS Riau defines the poor as those

with less than US$ 24 income per month or below US$ 0.8 per day [23]. Using

Page 34: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

this def

2007, w

poverty

in Riau

villager

their po

Figure

3.4.3 K

Lack o

and cr

kerosen

used by

Rokan

of the

househ

finition, aro

where 9.5%

y line was u

u would b

rs to engag

overty is per

e 3.8 - A w

Key Health

of electricity

eates a he

ne lamps. F

y around 40

Hulu Distri

households

holds in 200

ound 22.43

% lived in ci

used, which

e greater.

ge in incom

rpetuated.

woman in a

Problems

y in Riau v

avily relian

Figure 3.9 sh

0% - 55% h

icts. A wor

s are still u

6 were usin

2

% of Riau p

ties and 13

is US$ 1.25

Without ac

me-generatin

village in R

villages cau

nce on trad

hows, in 20

households

se situation

using these

ng kerosene

22

population l

% in villag

5 per day [3

ccess to el

ng activities

Riau (Photo

uses difficul

ditional bio

006, kerosen

in Kuantan

n takes place

e traditional

and wick la

lived below

es. If the W

34], the num

lectricity, th

s is restricte

: Harlepis a

lties for obt

omass (esp

ne and wick

n Singingi,

e in Indragi

l lamps. O

amps for co

w the povert

World Bank’

mber of poo

he opportu

ed, and acc

and Iyon, 20

taining clea

pecially wo

k lamps we

Indragiri H

iri Hilir wh

verall, 33%

ooking and l

ty line in

’s global

or people

unity for

ordingly

008).

an water

ood) and

ere being

Hulu and

here 60%

% of the

lighting.

Page 35: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

Figure

The op

the Ria

particu

monox

Figure

e 3.9 - Ene

pen fire meth

au commun

larly wome

ide pollutio

e 3.10 - Typhttpm).

20

40

60

80

100

120

140

160

180

Num

ber o

f hou

seho

lds

ergy source

hod for coo

nity. Since t

en and child

on.

pical traditiop://malaysia

0

0,000

0,000

0,000

0,000

0,000

0,000

0,000

0,000

0,000

Kuantan Singingi

IndragiriHulu

Electri

2

s for lightin

oking and li

they are usu

dren – are e

onal stove uana.pnm.my

Indragiri Hulu

Indragiri Hilir

Pelalawan

city (PLN & Non PLN)

23

ng in Riau [3

ighting carri

ually used i

exposed to ‘

used by houy/Alat%20Tr

Siak

Kampar

Rokan Hulu

District

Kerosene &

35].

ies a seriou

indoors, the

‘particulate

useholds in Rradisonal/da

Bengkalis

Rokan Hilir

& wick lamps

us health pro

e house me

matter’ and

Riau (Sourcapur_dapurk

Pekanb

aru

Dum

ai

oblem to

embers –

d carbon

ce: kayu.ht

Page 36: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

There i

of Riau

million

countri

every 2

3.4.4 E

Accord

54.76%

23.35%

educati

2006,

increas

Figure

is no data ab

u people. Ho

n premature

ies caused b

20 seconds [

Education

ding to the

% of the po

% Senior H

ion qualific

graduation

se in 4 year

e 3.11 - Typelec

bout the im

owever, as

e deaths an

by indoor b

[36].

e Riau Go

opulation is

High Schoo

cations [37]

s from Ele

rs [38].

pical schoolctrified (Pho

2

mpact of the

a compariso

nnually amo

biomass bu

overnment,

s Elementar

ol, and on

]. This situ

ementary S

l in a Riau roto: Harlep

24

open fire m

on, WHO s

ong women

urning, whi

by 2002,

ry School,

nly 3.44%

ation has n

School wer

rural villageis and Iyon,

method on th

shows that t

n and child

ch is equiv

the highes

18.45% Ju

of populat

not improve

re 55 % o

e: beautiful , 2008).

he health co

there are aro

dren in dev

valent to on

st qualifica

unior High

tion obtain

ed significa

or showed

building bu

onditions

ound 1.6

veloping

ne death

ation of

School,

n higher

ntly. By

0.24 %

ut is not

Page 37: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

A low

electric

School

of educ

electric

gaining

3.4.5 W

The no

the maj

kilomet

clothes

lessen

product

Figure

level of e

city is a pa

s in unelect

cation due to

city supply

g access to i

Women’s Li

otion “pover

ajority of w

tres to get f

in the river

their oppo

tive activiti

e 3.12 - A w

education i

articular con

trified villa

o their inab

is also af

information

iberty

rty has a wo

women in Ri

firewood fo

r and carryi

ortunity to

ies.

woman in a

2

s likely to

nstraint for

ages (Figure

ility to oper

ffecting info

n.

oman’s face

iau’s unelec

or cooking.

ng drinking

get a bet

village in R

25

continue

r the achiev

e 3.11) cann

rate some le

formal educ

e” takes pla

ctrified vill

Women als

g water from

tter educati

Riau (Photo

the poverty

vement of

not provide

earning equ

cation amon

ace in Riau

lages have

so spend a l

m the rivers.

ion and to

: Harlepis a

y, and the

a better ed

e an optima

uipment. The

ng the vill

[39]. For e

to walk for

lot of time

. All these a

o do econo

and Iyon, 20

lack of

ducation.

l quality

e lack of

agers in

example,

r several

washing

activities

omically

008).

Page 38: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

26

3.5 Renewable Energy Potential  

Riau has a number of renewable energy possibilities including peat land,

processed-wood, biodiesel, coconut oil and coconut by-products, micro-hydro

power, solar energy, and geothermal energy. In this section, the potential of three

of them; biodiesel, micro-hydro, and solar energy are assessed.

3.5.1 Biodiesel

As shown in Table 3.2, Riau has a large potential for biomass energies. Palm

plantations cover an area of almost 1.5 million hectares, offering a large potential

for biodiesel fuel production. By 2001, there were 44 Crude Palm Oil (CPO)

plants operating in Riau [40].

Table 3.2 - Riau’s Plantation status, 2007.

Commodity Area (hectares) Production (Tons) Palm 1,428,814.21 3,142,440.02 Coconut 546,938.13 528,926.14 Rubber tree 528,746.48 396,290.70 Areca palm 9,325.56 6,742.42 Cacao 4,903.87 4,152.71 Uncaria gambir 5,109.00 1,758.00

Source: Riau Government [41].

The opportunity for using palm biodiesel in transportation and power generation

has been initiated by the Government. As shown in Table 3.3, there are five

biodiesel factories operating in Riau with the total capacity of 535 thousand

tonnes per year. More factories are to be built in the near future following the

Government program to increase biodiesel production from currently 1 million

tonnes per year to 6 million tonnes in 2010 [9].

Page 39: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

Figure

Table 3

No. C1 P

2 P

3 RpAT

4 Rp

5 P(S

Source

e 3.13 - Typhttp

3.3 - Biodie

Company PT Sari Dum

PT Indo Biof

Riau Provincpartnership wAssessment Technology Riau Provincpartnership w

PT Wilmar B(Subsidiary oSingapore)

: Business W

pical Riau pp://farm1.sta

esel manufa

mai Sejati

fuels

cial Governmwith The Ageand Applicat(BPPT)) cial Governmwith BPPT)

Bioenergi Indof Wilmar H

Watch Indo

2

palm plantatatic.flickr.c

acturers in R

ment (in ency For thetion

ment (in

donesia Holdings -

onesia [42].

27

tion (Sourceom/29/5677

Riau.

Products- Product:- Location- Capacity- Operatio- Product:- Location- Capacity- Operatio

e - Product:- Location- Capacity- Operatio- Product:- Location- Capacity- Operatio- Product:- Location- Capacity- Operatio- Investme- The complantationKalimant

e: 79725_4f91

, production: biodiesel n: Bengkalis y: 100,000 toon commenc: biodiesel n: Dumai (Riy: 150,000 toon commenc: biodiesel n: Riau y: 3,000 tonson commenc: biodiesel n: Riau y: 30,000 tonon commenc: biodiesel n: Dumai (Riy: 252,000 toon commencent: US$ 100

mpany owns an in Riau andtan

1c6565a.jpg

n capacity, e

(Riau) ons / year ement: 2009

iau) ons / year ement: 2009

s / year ement: 2006

ns / year ement: 2009

iau) ons / year ement: 20090 million a 150,000-hed East

g?v=0).

etc.

9

9

6

9

9

ectare

Page 40: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

3.5.2 H

The est

summa

in Riau

extract

or smal

Table 3

Na

IndragKampa

Rokan

Rokan

Source

Figure

Hydropowe

timated tota

arises severa

u. Unfortun

specified p

ller hydro-p

3.4 - Hydro

me of River

giri River ar River

n River

n River

: Distamben

e 3.14 - Siakinhttp

r

al potential

al studies th

nately, the d

power outpu

power gener

o-power pote

r

LubukTanjun

Lubuk

Siboda

n Riau [6].

k River: onetic energy

p://farm4.stat

2

for hydro-p

hat were un

data does n

ut; whether

rations from

ential from

Location

k Ambacang ng Balit Vill

k Bendahara

ak Village

ne of four lar(Source:

atic.flickr.com

28

power in Ri

ndertaken to

not indicate

r from dam

m river kinet

large rivers

P

Village age

Village

rge rivers in

m/3049/2444

iau is 949 M

o assess hyd

the techno

mmed-large h

tic energy.

s.

Potential (MW)

350 JI178 B

n132 B

n56 B

n

n Riau with

4824227_7b

MW [25]. T

dro-power p

ology to be

hydro-powe

Data sour

ICA, 1979 Bappeda Riaun.d. Bappeda Riaun.d. Bappeda Riaun.d.

potential fo

b589d4f10.jp

Table 3.4

potential

used to

er plants

rce

u,

u,

u,

or hydro

pg?v=0).

Page 41: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

29

3.5.3 Solar

Due to its equatorial location, Riau is endowed with good solar resource. In areas

close to the equator, the monthly variation of the day length is very small, and the

sun elevation at noon is reasonably high across the year [43]. Figure 3.15 below

summarises the average daily solar radiation in the main cities of Riau. Overall,

the average solar radiation on a horizontal surface in Riau is 4.7 kWh/m2/day and

the average clearness index is 0.46.

Figure 3.15 - Solar resources in main cities of Riau [44].

To compare, the solar radiation in Singapore, based on five years hourly data

recorded by the Meteorological Service Singapore, is 14.5 MJ/m2/day [45], which

is equivalent to 4.03 kWh/m2/day. Singapore is situated just across the Malaka

Strait to the east of Riau.

3.6 Concluding Remarks 

In this chapter, general information about Riau was reviewed, and special

attention was given to the current electricity supply provision. It has been shown

0.42

0.43

0.44

0.45

0.46

0.47

0.48

0.49

4.2

4.3

4.4

4.5

4.6

4.7

4.8

4.9

Bengkalis

Dum

ai 

Tembilahan

Rengat

Bangkinang

Teluk Ku

antan

Pekanb

aru 

Pangkalan Ke

rinci

Bagan Siapiapi

Pasir P

engaraian

Siak Sri Indrapura

Riau

 (average)

Kwh/m2/day

Solar radiation on horizontal surface Clearness index (0‐1)

Page 42: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

30

that the Riau power security under the current electricity strategy is weak. The

low ratio of electrification and low quality of supply are among the reasons that

perpetuate the ongoing electricity supply crisis which is likely to continue in the

future.

The lack of electricity supply affects mainly the villagers – the majority of the

Riau population. The poverty rate among the villagers is high, the health risk of

burning biomass is clear, many people are less-educated, and women’s rights need

to be improved. To provide better access to electricity for villages, a number of

renewable energy resources are available to be exploited. Three of them include

biodiesel, solar, and micro-hydro energies.

Page 43: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

31

Chapter 4 Evaluation of Hybrid RAPS for Riau 

4.1 Introduction 

In this chapter a detailed evaluation of hybrid renewable RAPS systems for Riau

is presented. The chapter begins with the selection of a reference village on which

the system designed will be based. A load analysis of the reference village will

then be undertaken. Then a computer simulation program will be used as a design

tool. The technologies considered include solar PV, river hydrokinetic power, and

diesel generator. The simulation output will be applied to specify the system

configuration and components used. This process is intended to be applicable in

other unelectrified villages near the four large rivers in Riau.

4.2 Selecting a Reference Village 

4.2.1 Selecting Three Site Candidates

It has been shown in Chapter 3 that the majority of the unelectrified villages in

Riau are situated by four large riverbanks. Among those, three have been chosen

as the potential sites for hybrid RAPS systems, and one of the three subsequently,

will be chosen to become the definitive reference village for this dissertation. The

need for a reference village is solely for the system design purposes. In reality, all

unelectrified villages are demanding electricity.

Indeed, no two rivers are identical because of a number of physical characteristics

they possess [46]. Therefore, it has been assumed that the river near the reference

Page 44: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

32

village shares common physical characteristics e.g. roughness of river beds and

sides, the depth, and the width, etc. with other rivers in Riau.

Three villages (Saik, Pulau Panjang Hulu, and Pulau Panjang Hilir) on the

Kuantan riverbank in Kuantan Singingi District were nominated based on the

following criteria: accessible for undertaking field work, have no access to the

grid and unlikely to have the grid extended in near future, have both micro-hydro

and solar energy resources, are close to the river body (to minimize distribution

losses), and have relatively small populations. In practice, there were trade-offs in

following the above criteria. Some villages are very remote with small

populations, which were suitable for RAPS system, but were not selected because

undertaking field work in those villages would require considerable effort and

costs. Table 4.1 summarises basic information about the three candidate villages

based on the villages’ statistic boards.

Table 4.1 - Three site candidates for hybrid RAPS system.

Pulau Panjang Hulu

Pulau Panjang Hilir

Saik

Location1 0.27 S, 101.47 E

0.30 S, 101.49 E

0.37 S, 101.24 E

Number of households 353 460 221 Number of worship centres 9 15 6 Health clinic 1 1 1 Village office 1 1 1 School 1 0 0 Small shop 9 36 9 Distance of the proposed microhydro’s site: - to the population centre (m) - to the farthest house (m)

200 2,500

100 4,000

200 2,500

Length of the village (m) 4,000 7,000 4,000 1) Source: Google Earth(R)

Page 45: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

33

4.2.2 Energy Resources Assessments

4.2.2.1 River hydrokinetic power

A series of field work visits has been performed to measure key parameters

required in designing a hydrokinetic power system which uses the Kuantan River.

Unlike most hydro-power systems that require a head1, the power output from a

free-flow river power system is mainly influenced by its flow velocity and flow

rate. Also, to determine the point of the system installation, information about the

river’s depth is needed.

Figure 4.1 - The schematic of the river flow velocity measurement.

Some traditional methods have been applied to measure the above three physical

characteristics at three villages. The current velocity was measured using the

float method suggested by Fraenkel et al. [47]. As shown in Figure 4.1, two

strings (S1 and S2) were stretched from the riverbank to the river body,

1 The “head” is defined as “the vertical height, in metres, from the turbine up to the point where the water enters the intake pipe of penstock” (Source: N. E. Bassam and P. Maegaard, Integrated Renewable Energy for Rural Communities: Planning Guidelines, Technologies and Applications. Amsterdam: Elsevier, 2004).

flow direction

S1

S2 20 m

Page 46: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

34

perpendicular to the water flow direction. Then, a soft-drink tin-can which filled

by water was released before String 1, flowed downstream to String 2. The

current velocity is calculated by dividing the strings’ distance (i.e. 20 metres)

over the time spent by the tin-can to travel from S1 to S2. For each site, ten

measurements were undertaken. A picture of the actual flow velocity

measurements is shown in Figure 4.2 (the tin-can was emptied from water, so it

could be captured by the camera).

Figure 4.2 - Actual measurement of river flow velocity (Photo: Harlepis and

Iyon, 2008).

The depth of the river was measured using a long-scaled stick which was

submerged to the level of the river bed and the scales of the stick on the surface

were recorded. The measurement was performed at 5 metres intervals using a

canoe. Figure 4.3.b shows the depth measurement schematic and Figure 4.4 shows

the actual measurement.

Page 47: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

35

Figure 4.3 - Schematic of the river depth measurement.

Figure 4.4 - Actual river depth measurement (Photo: Harlepis and Iyon, 2008).

The depth information can also be used to estimate the cross-sectional area of the

river. Based on Figure 4.3.a and an equation from Twidell and Weir [48], the

cross sectional area A, in square metres is:

A ≈

Also, using the values of velocity and cross-sectional area, the flow rate of the

river can be calculated using the following formula [49].

  ,              

(b)

y4

y3

y2

(a)

y1 z1

z2

z3

Page 48: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

36

Figure 4.5 - Schematic of the river width measurement.

The width of the river was measured by simply stretching a thin metal string from

one side of the river to another (Figure 4.5). The dotted line was the imaginary

straight string crossing the river. A number of sticks were erected in the river to

avoid the current pulling the string downstream. There is no correction factor used

to compensate for the effect of water pulling on the string, because the river width

is not a critical parameter in the design process.

Figure 4.6 shows the depth of the river and Table 4.2 is the flow velocity at

three locations. Among three villages, Pulau Panjang Hulu is not preferred as

the system location, because the deep part of the river is not on the village

side.

The summary of the physical characteristics of the river is shown in Table 4.3.

A correction factor of 0.8 has been applied to the measured values to

accommodate friction effects along the bottom and sides of the river on the

current velocity [49].

Page 49: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

37

Figure 4.6 - The depths of the river near the three candidate villages.

Table 4.2 - The river current velocity near three villages.

Measurement #

Velocity (m/s) P. Panjang Hulu P. Panjang Hilir Saik

1 1.04 1.09 1.81 2 1.01 1.06 1.77 3 1.04 1.06 1.77 4 1.02 1.07 1.69 5 1.03 1.05 1.8 6 1.04 1.06 1.74 7 1.04 1.05 1.71 8 1.03 1.06 1.75 9 1.04 1.06 1.7

10 1.04 1.05 1.72 Average 1.03 1.06 1.75

Average x 0.8 0.82 0.85 1.40

Village 1.5 2.2 2.2 2.5 3 3 3 3.2 3.1 3.4 4 4 3.4 4.1 4.1 4.2 3.4 2.7

Pulau Panjang Hulu

Pulau Panjang Hilir

Village 5 5.2 5 4.4 4.2 3.8 3.5 3.5 3.3 3.1 2.8 2.2 1.9 1.8 1.4 1.3 1 0.8 4.7

Saik

Village 3.8 4.3 4.4 3.9 3.7 3.7 3.6 3.6 3.4 3.2 2.4 2.2 2.1 1

metre

metre

metre

Page 50: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

38

Table 4.3 - Summary of river characteristics in three villages.

Pulau Panjang Hulu

Pulau Panjang Hilir

Saik

Average current velocity (m/s) 0.82 0.85 1.4

Viable average depth (m) 3.6 5 4.1 Cross sectional area (m2) 285 288 227 Flow rate (m3/s) 234 245 318 Width (m) 92 98 72

4.2.2.2 Solar radiation

Solar radiation data was obtained from the NASA SMSE satellite

measurements. The NASA SMSE database was derived from the meteorology

and solar energy parameters that have been recorded for 22 years by over 200

satellites. The accuracy of the data ranges from 6 to 12% [45]. Among the

twelve parameters available in the database, for this dissertation only solar

insolation on horizontal surface and insolation clearness index were used.

Detailed solar resource data for the three villages is available in Appendix A and

it is shown in Figure 4.7. The three villages have the same solar resource

information, because of their close proximity to each other. As shown in Figure

4.7, the annual average solar radiation is 4.69 kWh/m2/day, and ranges from 4.05

kWh/m2/day to 5.01 kWh/m2/day in January and April, respectively. Due to its

equatorial position, the likeliness of the cloud-cover over Riau is relatively high

throughout the year [44]. The annual average clearness index is 0.46 and varies

from 0.39 to 0.51 in January and June/July, respectively. The lowest clearness

index of 0.39 represents a fair value.

Page 51: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

39

Figure 4.7 - Monthly averaged horizontal solar radiation at Saik, which is same

as those in the other two villages.

To conclude, three villages have a good solar radiation level although slightly less

than the ideal solar radiation of 5 to 6 kWh/m2/day [51], and has fair clearness

index. The main positive feature is the small annual variation for both parameters.

This would allow a PV system to operate optimally across the year without any

requirement for a solar tracking system.

4.2.3 Selecting a Reference Village

A reference village was selected based on criteria in Section 4.2.1 which is

summarized in Table 4.1 and Table 4.3. Solar radiation was excluded because its

values are the same for all candidates.

Referring to Section 4.2.2.1.2, Pulau Panjang Hulu is no longer considered.

Between two other villages, Saik has several attributes that distinguish it from

Pulau Panjang Hilir. It has a smaller number of households and smaller size, and

has a faster river flow velocity. Accordingly, Saik has been chosen as the

reference village for this dissertation.

4.2.4 Overview of the Reference Village

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov DecAnnual Ave.

Solar radiation 4.05 4.66 4.84 5.01 4.87 4.8 4.79 4.76 4.8 4.94 4.63 4.23 4.69

Clearness index 0.39 0.44 0.46 0.49 0.5 0.51 0.51 0.48 0.46 0.47 0.45 0.42 0.46

0

0.1

0.2

0.3

0.4

0.5

0.6

0

1

2

3

4

5

6

Clearness inde

x

SOlar radiation (kWh/m2/day)

Page 52: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

40

Table 4.4 summarises information about Saik. A typical middle income household

is shown in Figure 4.8.

Table 4.4 - Information summary of Siak.

Buildings: - Households - Worship centres - Health clinic

221

6 1

Length of the village (m) 4,000Transportation available River (by canoes or a small wooden boat) Distance from river field measurements location: - To the population centre (m) - To the farthest house (m)

200

2,500River information: - Average current velocity (m/s) - Average depth (m) - Cross sectional area (m2) - Flow rate (m3/s) - Width (m)

1.4 4.1

227 396

72Solar resource information: - Annual average insolation incident on a Horizontal Surface

(kWh/m2/day) - Annual averaged Insolation Clearness Index

4.69 0.46

Economy: - Average income (US$/day per household) 5 - Main occupations of the population Farmer, merchants, house builders

Figure 4.8 - Typical middle income household at Saik (Photo: Harlepis and

Iyon, 2008).

Page 53: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

41

4.3 System Design 

4.3.1 General criteria of the system

The system to be designed followed the following criteria:

It contains a PV component

It has the lowest NPC

It has the lowest environmental impact.

Choosing PV components matched the Indonesian Government’s enthusiasm for

exploiting renewable resources for REPs, particularly solar energy, either for

unelectrified locations or to support existing diesel stand alone systems [50], [51].

4.3.2 Electrical load

4.3.2.1 Consumer Groups

As shown in Table 4.4 above, based on the village’s statistic board, the future

electricity consumer groups in Saik include 221 residential, 6 worship centres and

a health clinic, as well as street lighting.

4.3.2.2 Load Devices

To date there have not been any studies of the electrical load in Saik. Information

about load devices and load profiles were obtained from two sources: local utility

office (electricity consumption of several households in the nearest village which

Page 54: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

42

is connected to the grid), and the author’s understanding about the electricity

consumption pattern in another grid-connected village near Saik.

Figure 4.9 below shows the actual meter reading of five selected households in the

closest grid-connected village to Saik named Muaro Tombang, provided by PLN

Riau-Kepri Rengat Branch (Teluk Kuantan Office). The high-income households

consume around 250 kWh per month or 8.3 kWh per day. The middle-income

consumption ranges from 1.6 kWh to 3.6 kWh per day. The low-income

households in Muaro Tombang usually do not have electricity. The annual

variation of the load is small.

Figure 4.9 - Monthly electricity consumption of selected households in Muaro

Tombang (Source: PLN Riau-Kepri, Rengat Branch, Teluk Kuantan Office, unpublished).

Based on information from Figure 4.9, a list of load devices was created for Saik

(Table 4.5). To determine the operating hours of the appliances and to plot the

load profile, the author’s understanding of the lifestyle of villagers in Riau was

used.

0

50

100

150

200

250

300

1 2 3 4 5 6 7 8 9 10 11 12

Mon

thly electricity con

sumption (kWh)

Month of year

High income

Middle income 1

Middle income 2

Middle income 3

Middle income 4

Page 55: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

43

Table 4.5 - Estimated load devices of the typical consumer groups in Saik.

No. Electrical device Description Rated power (watt)

Quantity Total power (watt)

Typical household 1 Radio and tape player A simple radio with tape

player 10 1 10

2 Television and parabola receiver

21 inch colour TV 82 1 82

3 Mobile phone and charger

Nokia mobile charger 4 1 4

4 Iron Dry Iron 300 1 3005 Lamp 1 Fluorescent lamp in

bedrooms8 2 16

6 Lamp 2 Fluorescent lamp in living room

11 1 11

7 Lamp 3 Fluorescent lamp in kitchen

11 1 11

8 Lamp 4 Fluorescent lamp in bathroom

8 1 8

9 Lamp 5 Fluorescent lamp in toilets 5 1 5

Typical worship centre 10 Radio and tape player A simple radio with tape

player10 1 10

11 Fan 1 Ceiling fan with 40 2 8012 Lamp 1 Fluorescent lamp near

front door5 1 5

13 Lamp 2 Fluorescent lamp inside 11 4 4414 Sound system Sound system for outdoor 100 1 100The health clinic 15 Vaccine refrigerator/

freezer Refrigerator with freezing compartment

54 1 54

16 Lamps Fluorescent lamp near front door

5 1 5

Street lightings 17 Lamps Fluorescent lamps (200 m

intervals)11 20 220

4.3.2.3 Load Profiles

Table 4.6 below shows the list of electric devices and their daily operational

pattern for all consumer groups.

Page 56: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

44

Table 4.6 - Electrical devices’ operational details for all consumer groups in Saik.

No. Electrical device Total power (watt)

Time of operation

Num. of operation

hours Daily Wh

Typical household 1 Radio and tape

player 10 10 0.5 5

2 Television and parabola receiver

82 9, 10, 11, 20, 21, 22

6 492

3 Mobile phone and charger

4 20, 21 1.5 6

4 Iron 300 14 1 3005 Lamp 1 16 21, 22 2 32 6 Lamp 2 11 18-22 5 55 7 Lamp 3 11 19 1 11 8 Lamp 4 8 19, 20 2 16 9 Lamp 5 5 19 0.5 2.5

Total per household 919.5Total household in the village: 919.5 x 221 203 kWh

Typical worship centre 10 Radio and tape

player 10 4, 12, 15, 17 2 20

11 Fan 1 80 12, 15, 18-20 4 32012 Lamp 1 5 18-04 11 55 13 Lamp 2 44 4, 18-20 3.5 15414 Sound system 100 4, 12, 15, 17 2 200Total per worship centre 749Total worship centre in the village: 749 x 6 4.5 kWhThe health clinic 15 Vaccine

refrigerator/ freezer

54 00-24 24 1296

16 Lamps 5 18-05 12 60 Total 1.36 kWhStreet lightings 17 Lamps 220 18-06 12 2.6 kWhGRAND TOTAL FOR THE WHOLE VILLAGE 212 kWh

Around 96% of electricity is consumed by the residential sector. The typical daily

electricity consumption rates of a household, a worship centre, the health clinic and

street lighting are 1 kWh, 0.75 kWh, 1.36 kWh, and 2.6 kWh respectively. The total

daily electricity consumption for all Saik’s consumer groups is estimated at 212 kWh.

Page 57: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

45

Figure 4.10 below shows the estimated load profile for Saik. A large peak demand

of 66 kW occurs at 2 PM due to ironing at all households. There are also two

smaller peak demands of around 22 kW before midday and before midnight. In

practice, however, such a load profile is not suitable for renewable RAPS system

applications, especially if the system reliability is demanded. This is because a

large capacity of the system, and thus also a large capital cost, would be needed to

meet the peak load, which unfortunately, occurs for one hour only.

Figure 4.10 - The estimated electrical load profile in Saik.

Therefore, this load profile has been modified by applying an ironing-scheduling

as follows: each household is given three hours per week, on a specified day, for

ironing. By dividing the number of households (221) over 6 working days of a

week, 37 households would do their ironing per day; half from 12:00 PM to 3:00

PM and the other half from 3:00 PM to 6:00 PM. Figure 4.11 below is the revised

daily load profile for the proposed schedule. One major change is the reduction of

the 2 PM surge and a reduction of peak load from 66 kW to 25 kW. Similarly, the

daily energy consumption falls from 212 kWh to 180 kWh.

0

10000

20000

30000

40000

50000

60000

70000

00 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23

Electrical ene

rgy use (W

att)

Hour of day

Residential Worship centres Helath clinic Street lights

Page 58: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

46

The majority of load occurs between 8 to 10 PM. The load fluctuations take place

throughout the day. The lowest demand of 54 W to 770 W occurs from 11 PM to 8 AM

and increases to around 6 kW from 12 to 5 PM. Two peak load times occur in the

morning (9 to 11 AM) and in the evening (8 to 10 PM), both start and end abruptly.

Figure 4.11 - Revised estimated electrical load profile in Saik.

4.3.3 System design

This section presents a detailed description of the process used in designing the

power system for the given revised load. It started with selection of a computer

simulation program and was followed by the application of design steps.

4.3.3.1 Simulation Software Selection

The NREL HOMER(R) simulation program has been chosen as a tool for system

design. HOMER was selected due to its capability to evaluate the best option by

harnessing energy from a single or combination of various energy resources [52].

Its sound economic model provides rational selection of the most cost effective

option [54]. Furthermore, its hourly energy flow approach offers a comprehensive

analysis of the system performance throughout a year [54]. In addition, its

0

5000

10000

15000

20000

25000

30000

00 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23

Electrical ene

rgy use (W

att)

Hour of day

Residential Worship centres Health clinic Street Lights

Page 59: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

47

greenhouse gas emission analysis is important to examine the ecological

performance of the proposed system.

4.3.3.2 Simulation Inputs

Figure 4.12 shows the architecture of HOMER, which was taken from Fung et al.

with a small modification [53]. There are three main parts of HOMER; inputs,

HOMER simulation and outputs.

Figure 4.12 - Architecture of HOMER simulation and optimisation.

Unfortunately, HOMER is not equipped with a hydrokinetic power module

considered in this dissertation, while its run-of-river (hydro) module is not

suitable for this study. Therefore, instead of using its hydro module, its wind

Load Resources Components Optimisation

INPUT

HOMER Simulation

Optimal System Category

Net Present Cost

Cost of Energy US$/kWh

Excess Energy Fraction (%)

OUTPUT

Total Capital Cost

Fuel Consumption

Renewable Fraction (%)

CO2 emission (kg/yr)

Page 60: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

48

turbine module has been used with hydrokinetic input rather than wind-related

information. This approach was considered because wind turbines share some

similarities with hydrokinetic turbines which are commonly referred to as

‘underwater wind turbines.’ Thus, the wind turbine power-curve has been

replaced with the power curve of the selected hydrokinetic turbine by altering the

wind speed information with the river current velocity. Tom Lambert, who

developed HOMER at NREL in an email message to the author on 6 April 2009

affirmed that this idea “will work.”

In the next section, some examples of the process of providing input to HOMER

are presented.

4.3.3.3 Component selection

A range of typical RAPS system components has been selected which included a

Primary Load, a Photovoltaic, a Wind Turbine, a Converter, a Generator, and a

Battery bank (Figure 4.13).

Figure 4.13 - HOMER’s component selection input window.

Page 61: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

49

4.3.3.4 Load input

The load information provided for HOMER (Figure 4.14) was taken from Figure

4.11 above. Small random variability of 5% has been applied for both day-to-day

and time-step-to-time-step (refer to Section 4.3.2.2). All loads are alternating

current (AC) equipment and appliances. HOMER calculated the scaled annual

average of the load of 180 kWh/day, peak load at 30 kW and a 0.253 load factor.

A summary of the load input is provided in Appendix B page 89.

Figure 4.14 - HOMER’s load input window.

4.3.3.5 PV input

According to DESDM [54], the installed cost of a complete PV system in

Indonesia is around US$10/Wp2. However, DESDM does not mention whether

other enabling components such as inverters, battery chargers, cables and array

structures are included in the above cost guideline. Due to the high price of 2 To compare, the price of PV module only (Kyocera Solar Panel KC130GT) offered by the

Aviotech International based in Jakarta is US$5.7/Wp (Source: Aviotech International. n.d. Katalog Produk: Panel Surya / Solar Panel. http://aviotech.indonetwork.co.id/969761/panel-surya-solar-panel.htm (accessed 3 February 2009)

Page 62: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

50

inverters and relatively low cost of battery chargers and cables, it was assumed

that the cost of inverters is not included in the above cost guideline. Also, since

the report does not mention the area covered by the specified costing estimation,

it has been assumed that this cost is applicable for Saik. Replacement cost is

estimated at about US$8/Wp. To allow the natural module cleaning by the rain,

a slope of 70 was used rather than using the latitude angle of 0.40. A summary of

the PV input is provided in Appendix B page 89.

4.3.3.6 Hydro Turbine input

As mentioned in Section 4.3.3.2, the hydrokinetic turbine information was

inserted into the Wind Turbine Input window. The Darrieus Hydrokinetic

Turbines (DHT) developed by Alternative Hydro Solutions in Canada has been

chosen because of its simple structure and its ability to generate a relatively high

power output from low to medium flow velocities. Figure 4.15 is the power curve

of the turbine based on information from the turbine’s manufacturer. The turbine’s

rated power is 3 kW at 1.4 m/s current velocity. Since the information about the

power outputs at the flow speed above 1.5 m/s flow was not available, it has been

assumed that above 1.5 m/s, there are no increases in power output.

Page 63: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

51

Figure 4.15 - Hydrokinetic turbine power curve.

To calculate the turbine capital cost, the following formula was used.

     ,    

 

To calculate the Net Purchase FOB and the import duty cost, the formulas

suggested by Putra (2008) were used:

  ,  

                

where: Import duty tariff : 12.5%3

Freight cost : US$22,3404

3 There is no specific import duty tariff for hydrokinetic turbines. This tariff is an approximation

by assuming the import duty tariff for hydrokinetic turbines is same as the import duty tariff for electrical transformers which is 12.5% (Indonesian Custom, 2008).

4 Freight cost was calculated using the DHL Canada online rate calculator (http://www.dhl.ca/ca/wfRateCalculator.aspx). Based on information from the turbine manufacturer, each turbine is packed in two boxes. The size of the first box is 0.5m x 0.5m x 1m. The size of the second box is 2m x 2m x 1m. The weights of the first and second box are 150kg and 250kg, respectively. The destination city is Pekanbaru (post code 28281).

Page 64: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

52

Insurance : 0%

Gross Purchase : US$27,5005

Discount : 5% = US$1,3756

Value-added Tax, VAT : 5% = US$1,3757

Installation costs : US$500 (using local materials and labour).

Note: most of the above costs and prices were in Canadian Dollars which were converted into US Dollars using http:www.xe.com website.

Based on the above formulas and by allowing a fixed local delivery cost of

US$125, the total capital cost for each turbine is US$56,700 and the replacement

cost is US$56,200. A summary of the hydro turbine is available in Appendix B

page 90.

4.3.3.7 Generator input

Hybrid energy systems use synchronous alternators which are directly connected

to a diesel-engine [55]. It must be equipped with an electric starter system to

allow automatic start and stop. The generator was not permitted to work at less

than 40% of its rated power to avoid ‘glazing’ on the cylinder walls and prevent

a low load efficiency operation [57]. Based on information from CV Generindo,

a diesel generator distributor in Jakarta, the capital and replacement costs per

kW were US$450. The costs included unit price, electric starter, shipment, and

installation costs. Operational and maintenance costs were estimated at US$0.5

per hour. A summary of the generator input is available in Appendix B page 91.

5 The gross purchase (unit price) is based on information from the turbine manufacturer. 6 It was assumed 5% discount applied. 7 VAT in Canada: 7% (Source: http://www.economywatch.com/business-and-

economy/canada.html)

Page 65: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

53

4.3.3.8 Batteries input

Trojan T-105 batteries have been selected because of their popularity and

relatively low cost [54]. Trojan T-105 is a 6V deep-cycle battery with 185Ah and

225Ah capacity at 5 hour and 20 hour rate, respectively [56]. Figure 4.16 shows

detailed information about Trojan T-105. The capital and replacement costs of a

Trojan T-105 is US$215 including an estimation of the shipping and installation

costs [57]. The O&M cost is US$5 per year. A 48 volts system voltage was

specified by placing 8 batteries per string. A summary of the batteries input is

available in Appendix B page 92.

Figure 4.16 - Trojan T-105 batteries.

4.3.3.9 Hydro resource input

The river flow velocity has been entered into the Wind Resource module. The

monthly averaged flow velocity cannot be input into the Wind Resource Input

window, because, as shown in Figure 4.18, HOMER will synthesize the data

following four wind-related parameters i.e. “Weibull distribution value,

Page 66: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

54

autocorrelation factor, diurnal pattern strength, and hour of peak wind speed”

(source: HOMER’s Help facility). The river flow velocity, of course, does not

fluctuate like the wind speed following the Weibull distribution. Instead, an

hourly flow velocity over a period of one year has been supplied to ‘force’

HOMER to work without considering its Weibull-influenced characteristic.

Unfortunately, the river flow velocity data for the whole year was not available

and the field measurements were performed on just one day. In order to estimate

the flow velocity over the year, the seasonal variation of the rainfall measurement

was used. As shown in the flow rate equation in Section 4.2.2.1.1, the flow

velocity is proportional to the flow rate, and the flow rate is proportional to the

amount of rainfall. Figure 4.17 is the average rainfall (from 1971 to 2000) in the

western part of Riau (Zone 10) where Saik is located. Each month is divided into

three time groups; I, II, and III which represent the first, middle and last ten days

of a month, respectively. The field measurement in Saik was taken in the time

group of September I (Figure 4.17).

In September I, which was the base month, the rainfall is 52 mm and the flow

speed was 1.4 m/s. In the other time groups, for instance May III, the rainfall is 60

mm or 15% higher than September I’s rainfall. Accordingly, the flow speed in

May III was assumed also 15% higher than September I’s flow speed. A detailed

account of the process in generating the hourly flow speed is available in

Appendix C. Figure 4.18 shows HOMER’s Hydro Resource Input window.

Page 67: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

55

Figure 4.17 - Rainfall in western part of Riau (Zone 10): The field measurement

in Saik was taken in the time group of September I [58].

Figure 4.18 - The HOMER’s hydrokinetic resource input window (using Wind

Resource module).

4.3.3.10 Other inputs

There was a lot of information provided to HOMER other than some examples

overviewed above. The summary of other information is shown in Table 4.7 and a

detailed version can be seen in Appendix B.

Page 68: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

56

Table 4.7 - Summary of other information was entered into HOMER.

Input Notes Solar resources Similar to information in Figure 4.7 above.

Converter Inverter efficiency: 90%

Rectifier efficiency: 85% Inverter and diesel generator were allowed to operate

in parallel. Capital cost: US$2000/kW (based on information from the SolarPowerIndo, an inverter distributor in Jakarta)

Diesel Diesel price: US$0.6 [61]. Sensitivity value of US$ 1/litre was specified

Economic Project lifetime: 25 years.

Annual interest rate: of 8% [62].

System control Both dispatched strategies were applied (i.e. cycle charging and load following) to allow HOMER to choose the optimal dispatch strategy.

Setpoin state of charge: 30%, to maximize the lifetime of the battery.

The generator was allowed to operate simultaneously. Generator with a capacity less than the peak load was

allowed to operate.

Reliability constraint Maximum annual capacity shortage constraint: 10% and 30% (to reduce the capital cost).

4.3.3.11 Optimisation variables

Table 4.8 summarises the components and their sizes as well as sensitivity

variables which have been entered into HOMER. As discussed in Section 4.3.1,

there is no option for a zero PV array. In Figure 4.19 the schematic of the system

is shown. This is a system where a diesel generator meets the load directly and

charges the batteries through an inverter, and other technologies i.e. PV array,

hydrokinetic turbines and battery bank feed to the load via an inverter.

Page 69: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

57

Table 4.8 - Optimisation and sensitivity variables of the inputs.

No.

Optimization variables Sensitivity Variables

PV Array (kW

Hydro turbine

(quantity)

Generator (kW)

Storage T-105

(strings)

Converter (kW) Diesel US$/L Capacity

shortage (%)

1 5 0 0 0 0 0.6 0.02 10 1 18 6 20 1.0 103 35 2 8 30 304 40 3 10 35 5 4 12 40 6 5 14 7 10 16

Figure 4.19 - Hybrid RAPS system configuration for Saik.

4.4 Results and discussion 

HOMER has simulated nearly 4 thousand possible system configurations and 6

sensitivities. Figure 4.20 shows, in tabular form, the optimisation results of the

base case in which sensitivities were not considered. Three cases of hybrid

systems have been considered. The results were ranked based on the Net Present

Cost (NPC). The lowest NPC system, the ‘winner,’ is in the first row. The

winning system comprises a 5 kW PV array, 2 DHTs (3kW each), an 18 kW

diesel generator, 64 x 225 Ah batteries, and a 20 kW inverter.

Page 70: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

58

Figure 4.20 - Hybrid RAPS system optimization results.

4.4.1 Economic analysis

Table 4.9 and Figure 4.21 summarise the economic performance of the winning

system. The capital cost constituted the largest portion of the total NPC at 72%,

followed by fuel cost (15%), replacement cost (10%) and O&M costs (4%).

The component incurring the largest cost is the DHTs (36%) followed by the

diesel generator (24%), inverter and PV modules (16%) and battery bank (7%).

The turbine costs are high because all components must be directly imported and

therefore modest costs of shipping, import duty and manufacturer’s profit were

included. The other components, though also overseas products, are available in

Indonesia.

Table 4.9 - Economic performance of the hybrid RAPS system.

Component Capital ($)

Replacement (US$)

O&M (US$)

Fuel (US$)

Salvage (US$)

Total (US$)

PV 50,000 0 0 0 0 50,000 DHTs 113,400 0 1,067 0 0 114,467 Generator 8,100 9,303 11,737 48,030 -396 76,774 Batteries 13,760 9,326 53 0 -1,005 22,134 Converter 40,000 12,610 0 0 -1,947 50,663 System 225,260 31,239 12,858 48,030 -3,348 314,039 Levelized COE US$0.448/kWh

Page 71: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

59

The COE for the optimum system is US$0.448/kWh. If compared to the current

electricity tariff of small residences in Indonesia which is US$0.019 /kWh

(Section 3.3.5) which is heavily subsidised, the COE of the RAPS system is 23.6

times higher. However, if compared to the COE of a diesel generator only system

at US$0.595/kWh8, which is a popular option for rural electrification in Riau

today, the RAPS system offers a competitive COE which is lower by 25%.

Unfortunately, the capital cost of the hybrid system is far above the generator only

option at around 17 fold9. Therefore, special financial concessions are needed to

implement such a system in Riau.

Figure 4.21 - Lifecycle costs of hybrid RAPS system by components.

4.4.2 Electrical output analysis

Table 4.10 shows the electrical performance of the RAPS system for the base case

optimum system. The total electricity production is 88,471 kWh/year, mostly

from renewable elements of the system. The system is capable of meeting 100%

8 The COE for the diesel generator only system was obtained by undertaking another separate

HOMER simulation. 9 The capital cost of the diesel generator only system was US$13,500.

Page 72: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

60

of the load throughout the year and has space for future demand growth with

around 21% excess power.

Table 4.10 - Electrical performance of the hybrid RAPS system.

Parameter kWh/year % Production

PV array 7,694 9 Hydro turbines 48,391 55 Diesel generator 32,387 37

Consumption AC primarily load 65,697 100

Quantity Excess electricity 18,303 21 Capacity shortage 0 0

Renewable fraction 64

Figure 4.22 shows the power production of each generator by month. The PV

array produces almost the same amount of power throughout the year. The output

of the diesel generator is dictated by the output of the DHTs; when the DHTs

produce less power, the role of the diesel generator is increasing, and vice versa.

Figure 4.22 - Monthly electricity production of each component of the hybrid

RAPS system.

Page 73: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

61

4.4.3 Emissions analysis

The hybrid RAPS system emits 19.7 tonnes of carbon dioxide (CO2) per year. This

is a particular advantage of implementing such a system because if compared to the

diesel only system, the CO2 emission would be 114 tonnes per annum or 580%

higher.

4.4.4 Sensitivity analysis

Sensitivity analysis includes changes in diesel price and maximum load to be

unmet. If the diesel price rose from US$0.6/litre to US$1/litre, the system size is

changed and the role of the diesel generator is slightly reduced. The number of

batteries is increased from 64 to 96, and the diesel generator’s share of the output

is reduced by 2%. In consequence, the COE is increased by 10%.

If 10% of the capacity shortage is allowed, one DHT can be removed from the

system and the number of batteries becomes 48. The COE is decreased by 10%,

but the diesel generator’s contribution becomes dominant (i.e. 54%).

4.4.5 Strategies to improve the system’s performance

There are two potential strategies to increase the performance of the hybrid RAPS

system, both economically and technically. The first strategy is by using the

locally produced DHTs. This would decrease the cost of the DHTs significantly

because the costs of shipping and import duty can be removed and the price of the

turbines will be lower. In turn, the NPC of the system would fall thereby

contributing to a significant reduction in the COE.

Page 74: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

62

The second strategy is by using the higher capacity of the DHTs. It has been

assumed that at flow velocity above 1.5 m/s, there is no increase in the turbine’s

power output (refer to Section 4.3.3.6). Conversely, it has been shown in Section

4.3.3.9 and Appendix C that 70% of the time of over a year, the flow velocity is

greater than 1.5 m/s. If higher rated power turbines were used, the number of the

DHTs can be reduced to only one (but producing the same output), the role of the

diesel generator will be minimised, and the sizes of other components can be

lessened. These strategies, if combined together, have the potential to improve the

economical and technical performance of the hybrid RAPS system significantly.

4.5 System Configuration and Component Performances 

In this section, the physical configuration of the base case system is proposed. The

components were selected based on the market availability to provide a ‘ready to

use’ information for REPs’ planners and executors in Riau. Specifications and

operation performance of each component are presented. At the end, relations

among components in the system are analysed.

4.5.1 System configuration

In this project, a parallel hybrid configuration (Figure 4.23) has been chosen due

to its ability in meeting the load optimally, to promote high diesel generator

efficiency and therefore minimise the diesel generator maintenance, and reduce

the rated capacity of both diesel and renewable generators [59]. Another reason

was because the system configuration simulated by HOMER, as shown in Figure

4.19, is a parallel hybrid configuration.

Page 75: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

63

Parallel hybrid configuration allows the system to decide which component(s) to

operate under a specific load. During a low load period, the inverter takes power

from the battery, converts it to alternating current (AC) then supplies the load. As

load exceeds the actual capacity of the battery bank, a synchronised control

system in the inverter activates the diesel generator, which takes over the load,

and exports excess power to the battery bank. In this instance, the inverter

changes its function to become a battery charger. As the load increases

continually and exceeds the diesel capacity, the diesel remains active, and the

inverter returns to its genuine function to draw power from the battery bank to

‘help’ the diesel generator to meet the load.

Figure 4.23 - Parallel hybrid configuration of the system.

4.5.2 Component specifications

The specifications of components are available in Appendix D. In general, the

components specifications should be consistent. For example, the input

requirement of the battery charger must match the output of the PV array or the

DHTs. Similarly, the output of the battery bank must be able to activate the

Page 76: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

64

inverter, and the inverter output has to match the load requirements. The size of

each component is also critical. Fortunately, HOMER output provides the

recommended sizes of the components.

The DHTs are the unique components of the system, while the other components are

commonly found in many hybrid RAPS systems. Stephen Gregory of the Alternative

Hydro Solutions Ltd., the turbine manufacturer, in an email message to the author on

15 April 2009 explained this unit involves a gearbox to provide a faster rotation to the

generator and a permanent magnet alternator to allow operation in a wide range of

water flow speeds. The alternator is mounted on the turbine shaft and positioned

above the waterline for system longevity and ease of maintenance. Figure 4.24, which

is taken from the Newenergycorp, which produces a similar type of turbine, shows

the picture of the unit and the mounting method considered for this project. A boat

was used for simplicity and in order to allow the unit to follow the variation of the

river depth.

This picture intentionally left blank due to the absence of written permission from the author

Figure 4.24 - Darrieus hydrokinetic turbine and its boat mounting method (Source: http://www.newenergycorp.ca/index.htm).

The original outputs of the alternators are a variable voltage AC electricity

ranging from 0 to 165 volts which is converted by an integrated rectifier to

Page 77: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

65

DC. Unfortunately, information about the input and output voltages of the

rectifier is not available. Therefore, in this dissertation, a battery charger was

added to make sure that the turbine outputs can charge the batteries. This,

unfortunately, reduced the overall efficiency of the DHT system due to power

losses in rectifier and battery charger. The detailed specifications of components

are available in Appendix D page 95.

4.5.3 Component performance

Table 4.11 shows the electrical performance of each component, as estimated by

HOMER. The DHTs and diesel generator have a relatively high capacity factor;

92% and 44%, respectively. This indicates that both generators, especially the

DHT, work optimally, and in turn, provide the majority of power output. The

other components i.e. PV array and converter (inverter and rectifier) have lower

capacity factors.

Table 4.11 - Electrical performance of each component.

Component Simulation output PV array output

Mean output (kW) 0.88 Mean output (kWh/day) 21.1 Capacity factor (%) 17.6

DHTs Mean output (kW) 5.52 Capacity factor (%) 92.1

Generator output Hours of operation (hrs/yr.) 2,199 Operational life (yrs.) 6.82 Capacity factor 20.5 Mean electrical out. (kW) 14.7 Mean electrical efficiency (%) 43.9

Page 78: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

66

Table 4.11 – (cont.)

Component Simulation output Battery output

String size 8 Strings in parallel 8 Bus voltage (V) 48 Usable nominal capacity (kWh) 60.5 Autonomy (hrs.) 8.06 Expected life (yrs.) 10.0

Inverter output Mean output (kW) 3.8 Capacity factor (%) 19.0 Hours of operation (hrs./yr.) 8,749

Rectifier output Mean output (kW) 0.0 Maximum output (kW) 1.3 Capacity factor (%) 19.0 Hours of operation (hrs./yr.) 11

The monthly outputs of components are shown at Figure 4.25 to 4.30. The DHTs

produce continuous power throughout the year, with less production during June

to August, following the seasonal flow speed variation. To compensate for this,

the diesel generator output is increased during this period. The inverter operates

almost throughout the year, except for 11 hours in June when the outputs of

renewable generators are low and cause the diesel generator to operate at high

load producing excess power to charge the battery through the rectifier. The diesel

generator starts and stops two times per day at almost the same time, to serve two

peak demands well before midday and before midnight.

Page 79: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

67

Figure 4.25 - DHTs power output.

Figure 4.26 - PV array power output.

Figure 4.27 - Battery bank frequency of SOC.

Figure 4.28 - Inverter output.

Page 80: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

68

Figure 4.29 - Rectifier output.

Figure 4.30 - Diesel generator output.

4.5.4 Control

Controls for hybrid power systems carry out a number of tasks. Two of them are

subsystem management and battery regulation [60]. Subsystem management

determines when to start/stop the diesel generator, and when to

connect/disconnect the loads or some portions of the renewable generators e.g. PV

array and hydro turbines. This job is carried out by a synchronised control

integrated in the inverter. The battery regulation is performed by the charge

controller to avoid the battery bank from being overcharged, and it commonly in

switched series configuration [44].

In addition, for a system that includes PV arrays, blocking (or string) diodes are

used to avert the batteries from being discharged through the PV cells at night and

to protect the battery from short circuiting. Also, bypass diodes are used to

prevent the PV cells from being overheated due to shading on the cells [44]. The

Page 81: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

69

blocking diodes are connected in series with each PV string and the bypass diodes

are connected in parallel with every PV module. Figure 4.31 shows the circuit of a

charge controller, the blocking diodes and bypass diodes used in this dissertation.

Figure 4.31 - Charge controller, blocking diodes and bypass diodes circuit,

modified from Markvart and Castaner [44].

Specification of the charge controller (solar and hydro) is shown in Appendix D

page 96. The charge controllers will disconnect renewable generators when the

battery bank is fully charged. This feature allows the DHTs to work without a

dump load to avoid overcharging.

4.5.5 Integrated system power output

Figure 4.32 shows a sample of combined hourly simulation results of components

for June 16. This day was chosen because output of the DHTs on this day is

among the lowest. As shown below, the majority of the load is supplied by the

battery which is charged by the PV array and the DHTs. The main role of the

diesel generator is to serve peak loads.

Page 82: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

70

Figure 4.32 - Integrated system power output.

4.6 Concluding Remarks 

A detailed design process to evaluate a feasible power generating system to

provide electricity for remote villages near four large rivers of Riau has been

performed.

From the HOMER simulation, it was found that the best technology to provide

electricity for Saik, the reference village, is a PV/Hydrokinetic/Diesel/Battery/

Inverter hybrid system. The system is capable of meeting 100% of the load with

21% space for the load growth. Renewables served 63% of the load and the

largest contribution of 55% was provided by the DHTs. The initial cost of the

system was US$ 225,260, which was the largest component of the costs (72%). If

the hydro turbines were produced locally and a larger DHT was used, a significant

reduction of cost could be achieved to compete with a popular option for rural

electrification i.e. diesel only system. The COE was US$0.448 or around 24 times

Page 83: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

71

of current electricity tariff in Riau, but 25% lower than the COE of a diesel only

system.

The Indonesian Governments (national, provincial and district levels) have the

REPs mainly using the PV systems. However, the lack of local expertise and

experience has been impeding the introduction of hybrid RAPS systems from

renewable energy sources in Riau. This study, therefore, proposes a feasible

option which is reliable, has low O&M costs, lower COE, and is cleaner.

Page 84: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

72

Chapter 5 Evaluation of Biodiesel Power Systems for Riau 

5.1 Introduction 

It has been shown in Section 3.5.1 that Riau is the largest palm biodiesel producer

in Indonesia. This production capacity provides the opportunity to develop

biodiesel-fuelled power generating systems to address the power supply shortage

in Riau.

Biodiesel is now the most commonly accepted fuel to substitute petroleum diesel

fuel for diesel engines for the following advantages as suggested by Demirbas: (1)

Portable; (2) Readily available; (3) Renewable; (4) Higher combustion efficiency;

(5) Lower sulphur and aromatic content; (6) Higher cetane number; (7) Inherent

lubricant in the neat form; (8) High flash point and (9) Biodegradable. Furthermore,

since biodiesel is available locally, it could help a country to lessen its reliance on

imported petroleum [61].

The major drawbacks of biodiesel, referring to Demirbas include: (1) Higher

viscosity; (2) Lower energy content; (3) Higher cloud point and pour point; (4)

Higher nitrogen oxide (NOx) emission rates; (5) Lower engine speed and power;

(6) Injector coking; (7) Engine compatibility; (8) Higher price and (9) Higher

engine wear [65].

This chapter evaluates the feasibility of generating electricity for villages in Riau,

both in rural and urban areas, using diesel generators with palm biodiesel fuel.

Page 85: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

73

5.2 Method of Biodiesel Power Systems Design  

Theoretically, palm biodiesel can be used as fuel in power generating plants in

blends with conventional diesel. The most popular blends, which were considered

in this dissertation, are B5 and B2010. B20 was chosen because its performance

has been widely tested and it is applicable in any diesel engine [62], while the

B100 was selected to represent an ideal condition that might well be widely

adopted in the near future. Three assumptions have been made in using B100,

they include: (1) No impact of B100 on equipment and fuel systems; (2) No

additional precautions, handling, maintenance, and engine modification

considerations; (3) Instead of using a biodiesel-specialised generator, a general

diesel generator has been used.

Again, HOMER was used as a tool for system design. It was assumed that load

was the same as the load for Saik (refer to Section 4.3.2).

5.3 System Design  

The design process of the biodiesel systems was the same as one used when

designing the hybrid RAPS system in Chapter 4. The considerations for design

include; determining the general criteria, determining the load, inputting

information to HOMER, and running the simulation.

10 B20 refers to the ratio of biodiesel and diesel is 20:80, while B100 is just “biodiesel.”

Page 86: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

74

5.3.1 Fuel Input

When biodiesel is used in blends with conventional diesel, differences in the basic

chemical properties of both types of fuels affect the engine performance and

pollutant emissions [63]. Thus, to use palm biodiesel fuel in the HOMER

simulation, it is necessary to specify its properties as shown in Table 5.1.

The value of carbon content of B20 fuel was interpolated from the values of

conventional diesel and B100 fuels. The carbon content of the conventional diesel

fuel is 86.337% and carbon content of B100 is 30% [64], [65]. Therefore, the carbon

content of B20 is 75%. Similarly, the sulphur content of conventional diesel fuel and

biodiesel are 0.3% and 0.2%, respectively, resulting in a sulphur content of B20 at

0.28% [70].

Table 5.1 - Properties of palm biodiesel.

B100 B20 Lower heating value, LHV (MJ/kg) 36.65 (1 45.40 (2 Density (kg/m3) 920 (1 848 (2 Carbon content (%) 30 (3 75 Sulphur content (%) 0.2 (4 0.28

1. Beer et al. [71] 2. Pandey [66] 3. Wilson and Burgh [69] 4. Loo and Koppejan [67]

5.3.2 Emissions

Table 5.2 shows the average biodiesel emission properties compared to

conventional diesel based on the information from the United States

Environmental Protection Agency [68].

Page 87: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

75

Table 5.2 - Average biodiesel emission compared to conventional diesel.

Emission type Conventional Diesel*

B100 B20

Carbon monoxide (g/L of fuel) 6.5 3.38 5.72Unburned hydrocarbons (g/L of fuel) 0.72 0.24 0.58Particulate matter (g/L of fuel) 0.49 0.26 0.43Proportion of fuel sulphur converted to PM (%)**

2.2 2.2 2.2

Nitrogen oxide (g/L of fuel) 58 63.8 59.16

* Source: HOMER’s Help facility ** Data not available, assume similar as of

diesel

5.3.3 Schedule

The generator was not intended to run for 24 hours a day in order to avoid long

periods of low load operation11. Instead, a scheduling mechanism has been applied

to the generator and has allowed the system to meet 81.5% of the load. As shown in

Figure 5.1, regardless of the seasonal condition, the generator was forced to run

from 9:00 AM to 1:00 PM to serve the daytime peak load (refer to Figure 4.1 in

Section 4.3.2). Similarly, it also runs from 7:00 PM to 22:00 PM to supply the night

time peak load. Beyond these periods of time, the generator was forced off.

Figure 5.1 - Biodiesel daily operation schedule. 11 A separate HOMER simulation with zero capacity shortage was made for comparison purposes.

The results can be seen in Appendix E.

Page 88: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

76

A specification of the fuel properties, emission properties and the operational

schedule of the generator above, were among the major changes made in

preparing the simulation of the biodiesel power system in HOMER. Table 5.3

summarises other inputs which are same as those outlined in Chapter 4.

Table 5.3 - Design information for biodiesel power system.

Design parameter Notes General criteria of the system To use B20 and B100 in a conventional

diesel generator Electrical load (refer to Section 4.3.2) Average energy consumption Peak load

180 kWh/day 29.6 kW

Component selected Primarily Load, Diesel generator Generator input Capital cost Sizes to consider Lifetime

US$450/kW 0, 20, 25, 30, 35, 40 kW 15,000 hours

Biodiesel input Diesel price

US$0.6/litre (Sambodo 2009, 8)

Economic input Project lifetime Annual interest rate

25 years. 8% (Bank of Indonesia, 2009).

System control input Dispatch strategy

Load following.

Constraints Input Maximum annual capacity shortage

0% and 30%.

5.4 Simulation Results and Discussion 

Figure 5.2 shows the optimisation results of the simulation for both B20 and

B100, which were identical. HOMER recommended a 30 kW biodiesel generator

to serve the load. The capital cost was US$13,500 and the operating cost was

US$16,123. With total NPC of US$185,610, the COE is US$0.318.

Page 89: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

77

Figure 5.2 - Optimisation results of the Biodiesel power system simulation.

Figure 5.3 shows the costs breakdown of the system. The highest cost is for fuel

(68%), while the smallest cost is incurred by the capital cost of the system (7.3%).

Replacement and O&M costs were 14.3% and 11.3%, respectively.

Figure 5.3 - Costs of biodiesel power system.

Table 5.4 is the performance of diesel generator for both systems (B100 and B20).

It is shown that both generators have the same performance in almost all

parameters, except for specific fuel consumption (SFC), annual fuel energy input

and generator efficiency. The main drawback of the system is because not all load

can be met (capacity shortage is 18.5%).

It has been found that both systems consume the same amounts of fuel which is

19,606 litres/year. This result has revealed a weakness in HOMER for simulating a

Page 90: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

78

diesel power system with different fuel properties. As shown in Table 5.1, B100 has

smaller LHV than B20 and therefore the fuel energy input of B100 is smaller than

B20, which is confirmed in Table 5.4. Consequently, to produce the same power

output, the B100 system should have consumed more fuel than the B20 system

rather than the same. Also, by multiplying SFC and annual electrical production,

both systems should have resulted in different annual fuel consumption instead of

the same.

This issue arises because when the fuel for a generator is changed, HOMER does

not automatically change the fuel curve inputs. It would be necessary to adjust the

fuel curve slope and intercept, or else the required fuel consumption will not

change. If the fuel was changed to a less-energetic fuel, one should increase the

fuel curve slope and intercept accordingly. However, this method was not used

because information about the values required for adjusting the fuel curve slope

and intercept is unavailable.

Table 5.4 - Generator performance for B100 and B20 systems.

Units B100 B20 Hours of operation hr/yr 3,285 3,285 Operational life yr 4.57 4.57 Capacity factor % 22.9 22.9 Electrical production kWh/yr 60,264 60,264 Mean electrical output kW 18.3 18.3 Fuel consumption L/yr 19,606 19,606 Specific fuel consumption L/kWh 0.325 0.328 Fuel energy input kWh/yr 183,636 209,676 Mean electrical efficiency % 32.8 28.7 Capacity shortage % 18.5 18.5 Excess electricity % 9.2 9.2

Page 91: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

79

The prime advantage of using biodiesel power system is its lower emission

characteristic compared to a conventional diesel power system. Table 5.5 shows

the emissions of both systems. B100 system has reduced more than 57% of CO2

compared to the B20 system. Emissions of the other pollutants in the B100 system

are always less than B20 system, except for Nitrogen oxide (NOx). This is

because the concentration of NOx in biodiesel is greater than in diesel fuel.

Table 5.5 - Emission of B100 and B20 systems.

Pollutant Emissions (kg/yr)

B100 B20 Carbon dioxide 21,294 49,116 Carbon monoxide 71.5 121 Unburned hydrocarbons 5.08 12.3 Particulate matter 5.5 9.1 Sulphur dioxide 76.1 98.2 Nitrogen oxides 1,350 1,252

5.5 Concluding Remarks 

The role of palm biodiesel fuel for power generation in Riau is large. Despite its

drawbacks compared to petroleum diesel fuel, biodiesel is being produced and

entering the fuel markets, driven by some major advantages such as its

renewability, and the fact that it is locally available, is ready to use to operate

general diesel engine, and is more environmental friendly. The latter, however,

does not include the ecological effects of replacing native forests with palm

plantations. In this chapter, the HOMER simulation program has been used to

evaluate options for generating electricity for both rural and urban areas in Riau

from B100 and B20 fuels. HOMER recommended a 30 kW biodiesel power

system to meet the load. However, the diesel was scheduled to operate during day

Page 92: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

80

and night times peak demand only, resulting in a nearly 20% capacity shortage.

The major expenses were for fuel. With a low capital cost and cheap COE, such a

system is a viable option (technically and economically) for power generation in

Riau.

Page 93: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

81

Chapter 6 Sustainable Rural Electrification Programs 

6.1 Introduction 

In Chapters 4 and 5, two options for providing electricity to rural villages in Riau

have been evaluated. It has been found that both hybrid renewable and biodiesel-

fuelled power systems are among the feasible options to be considered. However,

implementing REPs in villages in developing countries like Indonesia is not solely

a matter of dealing with the technical aspects of the programs. Also, there are

corresponding non-technical issues that the REPs’ planners need to take into

account to ensure the projects are sustainable.

This chapter identifies the main issues that accompany REPs in Riau. The I3A

framework proposed and successfully tested by Retnanestri is adopted in this

thesis [7]. Despite its original context, which was focused on the PV energy

system applications in Indonesia, this framework can also be applied to general

rural electrification projects [7]. The I3A framework is used in this dissertation as

a design tool, although it can also be implemented as an analytical tool to assess

the sustainability and identify barriers for RE projects.

6.2 The I3A Framework in Brief 

The I3A framework is generally aimed at acknowledging all stakeholder interests,

maximising equity, assuring the continuity of RE and institutionalising RE in

order to develop the capacity of the host communities in meeting their growing

Page 94: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

82

needs, and in turn, to contribute to sustainable development in rural areas. In

practical terms, the design of RE projects should integrate a partnership with

target communities as an empowerment process to allow the host communities to

gain required capacity to independently manage the O&M, financing and redesign

of RE systems in meeting their growing needs [69].

Figure 6.1 shows the sustainable RE delivery framework following the I3A

Model. The main finding of the I3A (Implementation, 3A) framework is that “to

be sustainable and equitable, RE projects should be implemented in an

institutional framework that addresses RE Accessibility (financial, institutional

and technological), Availability (technical quality and continuity) and

Acceptability (social and ecological),” which simultaneously looks at all facets of

the RE’s “hardware-software-orgware” [75].

Figure 6.1 - The I3A Model: Sustainable RE Delivery Framework [75].

Page 95: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

83

To put the I3A framework into practice, it is necessary to assess the components

as summarised in Table 6.1.

Table 6.1 - Summary of the I3A framework for practical use.

I3A element Corresponding aspect Description

Implementation Institutional Deal with the social system of RE projects which covers: “the stakeholders and their objectives, skills, interrelationships and roles in RE delivery”. In addition, “the enabling environment describes external factors that may affect RE delivery.”

Accessibility Financial, institutional and technological

Tackle the equity issues of RE projects which cover: “financial, institutional and technological perspectives (RE affordability, profitability, financing, skills and networks).”

Availability technical quality and continuity

Deal with the issues of the “quality and continuity of energy supply in order to maintain user trust and confidence in RE systems and their providers.”

Acceptability social and ecological

Address the “social and ecological viewpoints, identifying the extent to which RE can acculturate into local life, enhancing rural socioeconomic culture and promoting ecological care” to facilitate sustainable rural development.

Source: Retnanestri et al. [75]

6.3 Recommendations to Enhance RE Projects’ Sustainability 

The following is a list of recommendations to consider by any party in designing

rural RE program delivery in Riau. All recommendations are based on the I3A

framework suggested by Retnanesti [7]. Recommendations may appear in more-

than-one aspect and this understanding is important for looking at the interrelation

among those aspects.

6.3.1 Recommendations to Enhance Institutional Sustainability

1. Design projects as simply as possible which are well-matched with pre-

existing situations (institutions, energy supplies and end-uses).

Page 96: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

84

2. Understand and encourage participation of pre-existing institutions e.g. health,

education, governance, NGOs, commerce, religious, social, women, youth, etc.

3. Provide skill-transfer activities to build the capacity of the above institutions

including project management skills, project design, operation, evaluation and

decommissioning.

4. Use competitive tendering to minimise costs of the project, and aim to

emphasise the importance of project budget on software and orgware.

5. Evaluate and improve project design and delivery strategies, involving the

local communities at all times.

6.3.2 Recommendations to Enhance Financial Sustainability

1. Use competitive tendering to minimize cost of project, and aim to emphasise

the project budget on software and orgware.

2. Ensure financial intervention matches the market segment of target

community.

3. Assist the target community to do income generating activities.

4. Design projects as simply as possible, to reduce overall project costs.

5. Attempt “modularity and trialability” of system hardware to promote

affordability.

6. Evaluate and improve project design and delivery strategies, involving the

local communities at all times.

6.3.3 Recommendations to Enhance Technological Sustainability

1. Design projects as simply as possible following the principles of “simplicity,

modularity, trialability and upgradability.”

Page 97: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

85

2. Build local capacity (including non-energy specialists) for design, operation

and maintenance, and decommissioning of RE system.

3. Monitor and evaluate field performance to improve designs and enhance

project performance.

4. Design the project to be well-matched with the current “absorptive capacity”

of the target community.

6.3.4 Recommendations to Enhance Social Sustainability

1. Assist the target community to maximise the electricity services to enhance

health, education, economy and quality of life in general.

2. Provide end users with knowledge and skill and then engage them to

participate in local RE institutions, and in RE design, operation, refurbishment

and decommissioning.

3. Attempt to prioritise the need of the less-advantaged members of rural

communities.

4. Design projects as simply as possible, to enhance opportunities for community

participation.

6.3.5 Recommendations to Enhance Ecological Sustainability

1. Design RE hardware to make possible use of “recycling, reuse and

ecologically sound disposal.”

2. Provide end users with knowledge and skill to be able to apply ecological

sustainability concepts in operating and decommissioning of RE hardware.

3. Encourage the end users to apply the system to promote fossil fuels

displacement.

Page 98: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

86

6.4 Concluding Remarks 

Five aspects integrated in a rural RE program have been introduced. They are

institutional, financial, technological, social and ecological aspects. To assure the

sustainability of a rural RE program overall, each of above aspects has to be

sustainable. The I3A framework proposed by Retnanestri has been used as the

design tool for the REP programs delivery for rural villages in Riau [7]. The I3A

framework was developed to assure the Institutional sustainability and enhance

Accessibility, Availability and Acceptability of REPs in target communities. The

framework is also adaptable to be used as an analytical instrument in evaluating

the sustainability and identifying and overcoming barriers to the implementation

of REPs in Riau. A list of recommendation for each aspect has also been

provided.

Page 99: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

87

Chapter 7 Conclusions and Recommendations 

7.1 Conclusions  

This study aimed to identify options and to design feasible systems to provide

electricity for communities in rural villages in the Province of Riau, Indonesia by

harnessing power from renewable energy resources. It has also set out to identify

and recommend factors to enhance the sustainability of REP in Riau.

Two power generating system options have been identified. The first option was a

hybrid RAPS system for rural villages near four large rivers of Riau, and the

second option was the use of biodiesel as a fuel for a diesel generator. The

HOMER simulation program developed by the NREL has been used as the design

tool for both options.

The design of a hybrid RAPS system took place in the context of a village named

Saik. It incorporates a 5 kW PV array, two 3 kW DHTs, an 18 kW diesel

generator, 64 x 225 Ah batteries, and a 20 kW inverter constructed in a parallel

configuration. Over the project lifetime of 25 years, the total NPC is US$314,039,

of which the capital cost constituted the largest portion (72%). The component

incurring the largest cost is the DHTs (36%) followed by the diesel generator

(24%), inverter and PV modules (16%) and battery bank (7%). The COE is

US$0.448/kWh, which is 24 times the current electricity tariff, but 25% lower

than a diesel only system’s COE.

With 63% renewable contribution, the system is capable of meeting 100% of the

load (households, worship centre, health clinic, and street lighting) throughout the

Page 100: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

88

year and has spare capacity to meet future demand growth with around 21%

excess power. Interestingly, with a relatively slow river flow velocity (1.4 m/s),

the DHTs contributes to 55% of the power output, where the diesel generator and

PV array contributions are 37% and 9%, respectively. From the environmental

perspective, the hybrid RAPS system emits 19.7 tonnes of CO2 per year, far below

a diesel only system that would emit 580% higher CO2 to the atmosphere.

The second option looked at the potential for using palm B20 and B100 as fuels

in general diesel engines to take advantage of the large biodiesel production in

Riau. With the same load as in Saik, a 30 kW diesel generator system was

proposed. The capital cost was low (US$13,500), but the fuel cost was high

(US$146,617). With a total NPC of US$185,610, the COE is US$0.318, which

is 29% lower than the hybrid RAPS system’s COE. However, with 18.5%

capacity shortage, the biodiesel power system cannot meet all loads as the

hybrid RAPS system does.

If both systems are implemented in rural villages of Riau in the future, it is critical

to consider factors that influence the sustainability of the REPs. The I3A

(Implementation, 3A) framework proposed by Retnanestri was used as the design

tool [7]. It recommends the REP Implementation strategy as the “institutional

framework that addresses RE Accessibility (financial, institutional and

technological), Availability (technical quality and continuity) and Acceptability

(social and ecological),” which simultaneously incorporates all aspects of the

REP’s “hardware-software-orgware”.

Page 101: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

89

7.2 Recommendations 

The results of this study have led to the following recommendations. For further

study, it is recommended to:

1. Investigate the diesel generator performance when operating with palm

biodiesel fuel.

2. Perform a validation study with respects to the use of HOMER’s wind

modules with hydrokinetic hydro power inputs.

3. Evaluate a hybrid RAPS system which combines biodiesel power system

with other components such as PV, battery bank, etc.

4. Identify other options for generating electricity by harnessing other potential

energy resources possessed by Riau such as coconut fuel, coconut by-

products, biogas from waste treatment facilities in palm oil fabrics, etc.

5. Assess the effectiveness of the I3A framework for Riau’s situation, in

particular.

In order to implement the first option i.e. the hybrid RAPS system, the following

points are recommended:

1. Use locally produced DHTs to reduce the capital cost. This would remove the

shipping and import duty costs. Also, the locally manufactured turbine’s

price will be cheaper. In turn, the NPC and the COE would fall significantly.

2. Use the DHTs with higher rated power to harness the flow velocity above 1.5

m/s and decrease the capital cost by reducing the number of DHTs.

3. Perform the actual load assessment for the target village.

4. Assess the river flow velocity for at least one full year period.

Page 102: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

90

7.3 Final Words 

This dissertation is among the first holistic studies, if not the first, that tackles

issues related to electricity delivery for rural communities in Riau, by considering

both technical and non-technical aspects of REPs. This, hopefully, will contribute

to fill the gaps of the lack of studies of introducing renewable energy technologies

in Riau.

The Government agencies (national, provincial and district levels), policy makers,

energy planners, Non-Governmental Organisations (NGOs) and other parties are

welcome to consider these options, not only because they offer reliable and

cleaner power generation strategies, but also because they include interesting

economic features i.e. low O&M. Consequently, these options will entail lower

COE to the villagers. Above all, this initiative is expected to contribute to

combating poverty, inadequate health services, low-level of education, gender

inequity, and environmental issues in Riau.

Page 103: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

6

References 

[1] H. Khatib, “Electricity in the global energy scene,” IEE Proceedings A (Science, Measurement and Technology), vol. 140, no. 1, p. 25, January 1993. Available: IEEExplore, http://0-ieeexplore.ieee.org.prospero.murdoch.edu.au. [Accessed 12 October 2008].

[2] International Energy Agency, “The developing world and the electricity challenge: Investment needs, barriers and prospects,” International Energy Agency, 2005. [Online]. Available: http://www.iea.org/Textbase/work/2005/poverty/blurb.pdf. [Accessed 26 November 2008].

[3] The World Bank, “Electricity for All: Options for Increasing Access for Indonesia,” The World Bank, 2005. [Online]. Available: http://siteresources.worldbank.org/INTINDONESIA/Resources/Publication/280016-1106130305439/Electricity-for-All-Options-for-Increasing-Access-in-Indonesia.pdf. [Accessed 2 January 2008].

[4] Riau Mining and Energy Board, “Lebih Satu Juta KK di Riau Tak Berlistrik,” Riau Mining and Energy Board, 2009. [Online]. Available: http://www.riaupos.com/main/index.php?mib=berita.detail&id=517. [accessed 17 February 2009].

[5] PLN Riau-Kepri, “Kondisi Sistem Kelistrikan Riau dan Kepulauan Riau: Status 30 Desember 2008,” PLN Riau-Kepri, 2008. [Online]. Available: http://www.pln-riau.co.id/yonery/kondisimingguan30des/kondisimingguan30des.htm. [Accessed: 6 January 2009].

[6] Riau Mining and Energy Board, Riau Electric Power General Plan, Pekanbaru: Riau Mining and Energy Board, 2003.

[7] M. Retnanestri, M. “The I3A Framework: Enhancing the Sustainability of Off-Grid Photovoltaic Energy Service Delivery in Indonesia,” Ph.D. Thesis, School of Electrical Engineering and Telecommunications, the University of New South Wales, 2007. [Online]. Available: http://unsworks.unsw.edu.au/vital/access/manager/Repository/unsworks:1598. [Accessed: 26 May 2009].

[8] Riau Statistic Board, “Riau dalam Angka 2007: Keadaan Geografis,” BPS Riau, 2008. [Online]. Available: http://riau.bps.go.id/publikasi-online/riau-dalam-angka/bab-1-keadaan-geografis.html. [Accessed: 16 October 2008].

[9] M. T. Sambodo, “Sustainable Biofuel Development in Indonesia: Hoping the Dream Come True,” Institute for Global and Environmental Strategies, 2009. [Online]. Available: http://www.iges.or.jp/en/bf/pdf/activity20090204/session5/Sambodo.pdf. [Accessed: 5 May 2009].

Page 104: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

92

[10] Riau Government, “Profil Pemerintahan / Peta Wilayah Administratif,” Riau Government, 2007. [Online]. Available: http://www.riau.go.id/images/petriau_1.jpg. [Accessed: 16 October 2008].

[11] Riau Statistic Board, “Riau dalam Angka 2007: Penduduk dan Ketenagakerjaan,” BPS Riau, 2008. [Online]. Available: http://riau.bps.go.id/publikasi-online/riau-dalam-angka/bab-4-penduduk-ketenagakerjaan.html. [Accessed: 16 October 2008].

[12] Riau Government, “Kependudukan,” Riau Government, 2007. [Online]. Available: http://www.riau.go.id/index.php?module=articles&func=display&aid=115. [Accessed 16 October 2008].

[13] Riau Environmental Impact Management Agency, Agenda 21 Riau. Pekanbaru: Badan Pengendalian Dampak Lingkungan Propinsi Riau, 2005.

[14] O. Basuki, “Tak Mudah Merelokasi Pecinta Sungai,” Kompas, 9 December 2003. Available: http://www2.kompas.com/kompas-cetak/0312/09/daerah/727677.htm. [Accessed: 11 December 2008].

[15] Chaidir, “Malaria Kemiskinan,” 2004. [Online]. Available: http://www.chaidir.com/?m=bc&id=259. [Accessed: 11 December 2008].

[16] Riau Archipelago Government, “Masa Prasejarah dan Kerajaan Melayu,” Wisaya Melayu. [Online] Available: http://www.wisatamelayu.com/id/profile.php?geo=10. [Accessed: 11 December 2008].

[17] Riau Mandiri, “Tiga Anggota DPRD Siak Gugat DPD PDS Riau ke PN,” Riau Mandiri, 2005. [Online]. Available: http://riaumandiri.net/indexben.php?id=4359. [Accessed: 11 December 2008].

[18] B. Utomo, “Notion of Melayu and Kemelayuan,” Melayu Online. [Online]. Available: http://melayuonline.com/researcher/?a=SlIvaUpTL0lMeTRVYzY%3D=&l=bambang-budi-utomo. [Accessed: 11 December 2008].

[19] Indonesian Finance Department. “Realisasi APBD Tahun 2006: Total Se-Provinsi Riau,” Departemen Keuangan RI, 2007. [Online]. Available: http://www.djpk.depkeu.go.id/apbd2006_konsolidasi.php?jenis=Realisasi&kode=04-Prop.+Riau&satuan=3-Jutaan. [Accessed: 16 October 2008].

[20] Central Bank of Indonesia, “Growth Domestic Product 2006,” Bank Indonesia, 2007. [Online]. Available: http://www.bi.go.id/web/en/Publikasi/Investor+Relation+Unit/Email+Archive/GDP+2006.htm. [Accessed: 11 December 2008}.

[21] Riau Statistic Board, “Riau dalam Angka 2007: Pendapatan Regional Per Kapita,” BPS Riau, 2008. [Online] Available: http://riau.bps.go.id/publikasi-online/riau-dalam-angka/pendapatan-regional-kapita.html. [Accessed: 16 October 2008].

Page 105: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

93

[22] Riau Statistic Board, “Press Release Inflasi,” BPS Riau, 2008. [Online]. Available: http://riau.bps.go.id/kategori/press-releases/ihk. [Accessed: 16 October 2008].

[23] Riau Statistic Board, “Tingkat Kemiskinan Riau Tahun 2007,” BPS Riau, 2008. [Online] Available: http://riau.bps.go.id/attachments/BRS-01082007-kemiskinan.pdf. [Accessed: 16 October 2008].

[24] Energy Centre University of Indonesia, Indonesia Energy Outlook and Statistics, Jakarta: Energy Centre University of Indonesia, 2002. [Online]. Available: http://peui.eng.ui.ac.id/files/publikasi2007/EXECUTIVE%20SUMMARY%20IEOS%202006.pdf. [Accessed: 20 October 2008].

[25] Department of Energy and Mineral Resources, “National Electric Power General Plan,” Department of Energy and Mineral Resources, 2004. [Online]. Available: http://www.esdm.go.id/regulasi/kepmen/doc_download/594-keputusan-menteri-esdm-no0954-k30mem-2004.html. [Accessed: 15 October 2008].

[26] International Energy Agency, Energy Policy Review of Indonesia, Paris: OECD/IEA, 2008. [E-book]. Available: http://0-new.sourceoecd.org.prospero.murdoch.edu.au. [Accessed: 26 December 2008).

[27] Kompas, “Krisis Listrik Landa Sumbar, Riau, dan Jambi,” Kompas, 2004. [Online] Available: http://www2.kompas.com/kompas-cetak/0406/16/utama/1088590.htm. [Accessed: 17 October 2008].

[28] Kompas, “Krisis Listrik Ancam Sumatra,” Kompas, 2004. [Online]. Available: http://bolaeropa.kompas.com/kompas-cetak/0407/14/utama/1148581.htm. [Accessed: 17 October 2008].

[29] PLTA Koto Panjang Masih Berpolemik, 2007. [Online]. Available: http://www.bangrusli.net/index.php?option=com_content&task=view&id=471&Itemid=38. [Accessed: 2 November 2008].

[30] Eyes on the Forests, “Status of Riau’s Forests,” Eyes on the Forests, 2009. [Online]. Available: http://eyesontheforest.or.id/index.php?option=com_content&task=view&id=8&Itemid=17&lang=english. [Accessed: 5 November 2008].

[31] I. Rahardjo and I. Fitriana, “Analisis Potensi Pembangkit Energi Surya di Indonesia,” BPPT. [Online]. Available: http://www.geocities.com/markal_bppt/publish/pltkcl/plrahard.pdf. [Accessed: 15 October 2008].

[32] President of Republic Indonesia, “Keputusan Presiden Republik Indonesia Nomor 104 Tahun 2003 tentang Harga Jual Tenaga Listrik Tahun 2004 yang Disediakan oleh Perusahaan Perseroan (Persero) PT Perusahaan Listrik Negara,” President of Republic Indonesia, 2003. [Online]. Available: http://www.jdih.bpk.go.id/index.php?option=com_remository&Itemid=40&func=download&id=974&chk=067bce8f6a5fc86983b9a9a4655fe58b. [Accessed: 6 April 2009].

Page 106: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

94

[33] The European Institute of Japanese Studies, “Electricity consumption per capita: ASIA ranking,” EIJS, 2005. [Online]. Available: http://dataranking.com/table.cgi?TP=ee02-3&LG=e&FL=&RG=4. [Accessed: 18 October 2008].

[34] M. Mapako and G. Prasad, “Rural Electrification in Zimbabwe Reduces Poverty by Targeting Income-Generating Activities,” Energy Research Centre University of Cape Town. [Online]. Available: http://www.erc.uct.ac.za/Research/publications/07Mapako-Prasad%20Rural%20electrfication%20Zimbabwe.pdf. [Accessed: 29 April 2009].

[35] The World Bank, “New global poverty estimates confirm China’s leading role in meeting MDGs,” The World Bank, 2008. [Online]. Available: http://eapblog.worldbank.org/content/new-global-poverty-estimates-confirm-china%E2%80%99s-leading-role-in-meeting-mdgs. [Accessed: 11 December 2008].

[36] Riau Research and Development Board, “Sub Sektor Kelistrikan,” Balitbangda Riau, 2007. [Online] Available: http://www.balitbang.riau.go.id/index.php?litbang=subhal&sublink=kelistrikan. [Accessed: 16 October 2008].

[37] World Health Organization, “Indoor air pollution and health,” WHO, 2005. [Online] Available: http://www.who.int/mediacentre/factsheets/fs292/en/index.html. [Accessed: 17 November 2007].

[38] Riau Government, “Daya Dukung dan Persoalan Utama Riau,” Riau Government, 2006. [Online] Available: http://www.riau.go.id/index.php?module=articles&func=display&aid=150. [Accessed: 16 October 2008].

[39] Riauterkini, “Sebanyak 55 Persen Penduduk Riau Tamat SD,” Riau Terkini, 2006. [Online]. Available: http://www.riauterkini.com/politik.php?arr=8308. [Accessed: 16 October 2008].

[40] The World Bank, “Conference finds that poverty has a woman’s face,” The World Bank Newsletter, vol. 1, no. 5, 2003. [Newsletter]. Available: http://siteresources.worldbank.org/INTCAMBODIA/newsletters/20193951/oct03newsletter.pdf. [Accessed: 12 April 2009].

[41] W. R. Susila, “Contribution of Oil Palm Industry to Economic Growth and Poverty Alleviation in Indonesia,” Jurnal Litbang Pertanian, vol. 23, no. 3, pp. 107-114, 2004. [Online]. Available: http://www.pustaka-deptan.go.id/publikasi/p3233045.pdf. [Accessed: 9 January 2008].

[42] Riau Government, “Data dan Informasi Pembangunan di Propinsi Riau,” Riau Government, 2007. [Online] Available: http://www.riau.go.id/download/Riau_2007.pdf. [Accessed: 8 September 2008].

[43] The Business Watch Indonesia, “Biofuel Industry in Indonesia: Some Critical Issues,” The Business Watch Indonesia. [Online]. Available: http://www.fair-

Page 107: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

95

biz.org/admin-bwi/file/publikasi/20070828100425.pdf. [Accessed: 6 May 2009].

[44] T. Markvart and L. Castaner, Practical Handbook of Photovoltaics Fundamentals and Applications. Oxford: Elsevier Ltd., 2003.

[45] National Aeronautics and Space Administration (NASA), “Surface meteorology and Solar Energy,” NASA. [Online]. Available: http://eosweb.larc.nasa.gov/sse/. [Accessed: 17 October 2008].

[46] G. L. Morrison and Sudjito, “Solar Radiation Data for Indonesia,” Solar Energy vol. 49, no. 1, pp.65-76, 1992. [Online]. Available: http://www.sciencedirect.com.dbgw.lis.curtin.edu.au. [Accessed: 11 December 2008].

[47] T. Whitten, S. J. Damanik, J. Anwar and N. Hisyam, The Ecology of Sumatra. Tuttle Publishing, 2000.

[48] P. Fraenkel, O. Paish, V. Bokalders, A. Harvey, A. Brown and R. Edwards, Micro-Hydro Power: A Guide for Development Workers. London: Intermediate Technology Publications Ltd., 1991.

[49] J. Twidell and T. Weir, Renewable Energy Resources 2nd edition. New York: Taylor & Francis, 2006.

[50] W. D. Weight and J. L. Sonderegger, Manual of Applied Field Hydrogeology. New York : McGraw-Hill, 2001.

[51] T. Pryor, Lecture material of the Unit PEC622 Renewable Energy Resources. Perth: Murdoch University, 2009.

[52] Perusahaan Listrik Negara (PLN), “Rencana dan Strategi PLN dalam Pemanfaatan PV,” CEEM UNSW, 2008. [Online]. Available: http://www.ceem.unsw.edu.au/content/userDocs/7AryoSenoajiPLNPVandPLN.pdf. [Accessed: 22 March 2009].

[53] Department of Energy and Mineral Resources, “Kebijakan & RPP di Bidang Energi Baru Terbarukan,” CEEM UNSW, 2008. [Online] Available: http://www.ceem.unsw.edu.au/content/userDocs/2RatnaAriatiDJLPE_DGEEUREPolicies.pdf. [Accessed: 22 March 2009].

[54] T. Givler and P. Lilienthal, “Using HOMER software, NREL micropower optimization model, to explore the role of Gen-sets in small solar power system: Case study Srilanka,” 2005. [Online] Available: http://www.scribd.com/doc/6610003/Homer-Case-Study-Sri-Lanka?autodown=pdf. [Accessed: 12 April 2009].

[55] C.C. Fung, W. Rattanongphisat and C. Nayar, “A simulation study on the economic aspects of hybrid energy systems for remote islands in Thailand,” Proceedings of 2002 IEEE Region 10 Conference on Computers, Communications, Control and Power Engineering, vol. 3, no. 3, pp. 1966-1969, 2002. [Online]. Available: http://0-ieeexplore.ieee.org.prospero.murdoch.edu.au. [Accessed: 27 November 2008].

Page 108: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

96

[56] Department of Energy and Mineral Resources, ”Analisa Ekonomi dan Kapasitas Pembangkit Listrik Skala Menengan (PSM) Energi Terbarukan,” DESMD. [Online] Available: http://www.djlpe.esdm.go.id/modules/_website/images/content/5563178811.pdf. [Accessed: 20 October 2008].

[57] T. Markvart, Solar Electricity. West Sussex: John Wiley & Sons Ltd., 2004.

[58] TrojanBattery, “T-105 6V Deep Cycle Battery,” Torjan Battery, 2007. [Online] Available: http://www.trojanbattery.com/Products/T-1056V.aspx. [Accessed: 12 April 2009).

[59] Sentradaya, “Battery Trojan type T105 dan type T875 for golf car,” Sentra Daya. [Online] Available: http://sclsby.itrademarket.com/584314/battery-trojan-type-t105-dan-type-t-875-for-golf-car.htm. [Accessed: 12 April 2009].

[60] Bureau of Meteorology and Geophysics, “Prakiraan Musim Hujan 2008/2009 di Indonesia,” BMG, 2008. [Online] Available: http://iklim.bmg.go.id/PMH0809.pdf. [Accessed: 22 March 2009].

[61] Department of Energy and Mineral Resources, “Peraturan Menteri ESDM No.16 Tahun 2008 tentang Harga Jual Eceran Bahan bakar Minyak Jenis Minyak Tanah (Kerosenen), Bensin Premium dan Minyak Solar (Gas Oil) Untuk Keperluan Rumah Tangga, Usaha Kecil, Usaha Perikanan, Transportasi dan Pelayanan Umum,” 2009. [Online] Available: http://www.esdm.go.id/regulasi/permen/doc_download/710-peraturan-menteri-esdm-no16-tahun-2008.html. [Accessed: 21 April 2009].

[62] Bank of Indonesia, “BI Rate,” 2009. [Online] Available: http://www.bi.go.id/web. [Accessed: 12 April 2009].

[63] C. V. Nayar, S. J. Phillips, W. L. James, T. L. Pryor and D. Remmer, “Novel Wind/Diesel/Battery Hybrid Energy System,” Solar Energy vol. 51, no, 1, pp. 65-78, 1993. [Online]. Available: http://www.sciencedirect.com.dbgw.lis.curtin.edu.au. [Accessed: 20 April 2009].

[64] Sandia National Laboratory, “Hybrid Power Systems,” Sandia National Laboratory. [Online] Available: http://photovoltaics.sandia.gov/docs/HybridDescript.html. [Accessed: 26 April 2009].

[65] A. Demirbas, Biodiesel : a realistic fuel alternative for diesel engines. London: Springer, 2008.

[66] A. N. Shah, G. N. Shan and T. J. Wei, “Carbonyls Emission Comparison of a Turbocharged Diesel Engine Fuelled with Diesel, Biodiesel, and Biodiesel-Diesel Blend,” Jordan Journal of Mechanical and Industrial Engineering, vol. 3, no. 2, pp. 111 – 118, 2009. [Online]. Available: http://jjmie.hu.edu.jo/files/v3n2/4.pdf. [Accessed: 5 May 2009].

[67] P. Benjumea, J. Agudelo and A. Agudelo, “Basic Properties of Palm Oil Biodiesel-Diesel Blends,” Fuel, vol. 87, pp. 2069-2075, 2008.

Page 109: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

97

[68] Energy Information Administration, “Emissions of Greenhouse Gases in the United States,” EIA. [Online]. Available: http://www.eia.doe.gov/oiaf/1605/archive/87-92rpt/appa.html. [Accessed: 2 May 2009].

[69] J. R. Wilson and G. Burgh, Energizing Our Future: Rational Choices for the 21st Century. New Jersey: Wiley-Interscience, 2008.

[70] T. Lidderdale, “Demand, Supply, and Price Outlook for Low-Sulfur Diesel Fuel,” EIA, 1993. [Online]. Available: http://www.eia.doe.gov/pub/pdf/feature/lidder2.pdf. [Accessed: 2 May 2009].

[71] T. Beer, T. Grant and P. K. Campbell, “The greenhouse and air quality emissions of biodiesel blends in Australia,” CSIRO, 2007. [Online]. Available: http://www.csiro.au/files/files/phm1.pdf. [Accessed: 19 March 2009].

[72] A. Pandey, Handbook of Plant-based Biofuel, Parkway NW: CRC Press, 2009.

[73] S. V. Loo and J. Koppejan. eds., The Handbook of Biomass Combustion and Co-firing. London: Earthscan, 2008.

[74] National biodiesel Board, “Biodiesel - Guidance on Blends Above B20,” National Biodiesel Board. [Online]. Available: http://www.biodiesel.org/pdf_files/Biodiesel_Blends_Above%20_20_Final.pdf. [Accessed: 5 May 2009].

[75] M. Retnanestri, H. Outhred, Tugino, B. Astuti, A. Rezavidi and A. Prastawa, “An ADRA Research Project to Overcome Barriers to Renewable Energy in Rural Indonesia by Community Capacity Building Using the I3A Framework,” Paper on the ISES-AP - 3rd International Solar Energy Society Conference – Asia Pacific Region (ISES-AP-08), 2008. [Online] Available: http://www.ceem.unsw.edu.au/content/userDocs/Retnanestri_ADRApaper.pdf. [Accessed: 26 May 2009].

Page 110: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

6

Appendix A 

Solar radiation data 

Source: NASA Surface meteorology and Solar Energy

Pulau Panjang Hulu (0.27 S, 101.47 E)

Pulau Panjang Hilir (0.30 S, 101.49 E)

Saik (0.37 S, 101.24 E)

Note: Since three sites are closely situated, they have identical solar radiation values. The data of one of sited i.e Saik is presented here.

Monthly Averaged Insolation Incident on a Horizontal Surface (kWh/m2/day)

Lat -0.37 Lon 101.24

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Annual Average

22-year Average

4.05 4.66 4.84 5.01 4.87 4.80 4.79 4.76 4.80 4.94 4.63 4.23 4.69

Minimum and Maximum Difference from Monthly Averaged Insolation

(%) Lat -0.37Lon 101.24

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

Minimum -8 -16 -10 -7 -11 -14 -8 -10 -10 -7 -12 -18 Maximum 13 12 13 11 9 7 7 13 7 12 11 18

Monthly Averaged Insolation Clearness Index

(0 to 1.0) Lat -0.37 Lon 101.24

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Annual Average

22-year Average K

0.39 0.44 0.46 0.49 0.50 0.51 0.51 0.48 0.46 0.47 0.45 0.42 0.46

Minimum K

0.36 0.37 0.41 0.45 0.45 0.44 0.47 0.43 0.41 0.44 0.40 0.34 0.41

Maximum K

0.44 0.49 0.52 0.54 0.55 0.55 0.54 0.54 0.49 0.53 0.50 0.49 0.52

Page 111: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

99

Appendix B 

HOMER Input Summary 

AC Load: Load

Data source: Synthetic Daily noise: 5% Hourly noise: 5% Scaled annual average:

180 kWh/d

Scaled peak load: 29.6 kW Load factor: 0.253

PV

Size (kW) Capital ($) Replacement ($) O&M ($/yr) 1.000 10,000 8,000 0

Sizes to consider: 5, 10, 35, 40 kW

Lifetime: 25 yr

Derating factor: 90%

Tracking system: No Tracking

Slope: 7 deg

Azimuth: 180 deg

Ground reflectance: 20%

Solar Resource

Latitude: 0 degrees 37 minutes South Longitude: 101 degrees 24 minutes East Time zone: GMT +7:00

Data source: Synthetic

Page 112: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

100

Month Clearness Index

Average Radiation

(kWh/m2/day)

Jan 0.400 4.050 Feb 0.447 4.660 Mar 0.460 4.840 Apr 0.492 5.010 May 0.507 4.870 Jun 0.520 4.800 Jul 0.511 4.790 Aug 0.482 4.760 Sep 0.465 4.800 Oct 0.476 4.940 Nov 0.456 4.630 Dec 0.424 4.230

Scaled annual average: 4.7 kWh/m²/d

DC Wind Turbine (i.e. Darrieus Hydrokinetic Turbine)

Quantity Capital ($) Replacement ($) O&M ($/yr)1 56,700 56,200 50

Quantities to consider: 0, 1, 2, 3, 4, 5, 10 Lifetime: 25 yr Hub height: 20 m

Page 113: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

101

Wind Resource (i.e. river flow velocity)

Data source: FlowVelocity2.xls

Month River Flow Speed

(m/s) Jan 1.93 Feb 1.67 Mar 2.18 Apr 2.41 May 1.95 Jun 1.09 Jul 1.28

Aug 1.30 Sep 1.86 Oct 2.34 Nov 2.92 Dec 2.30

Weibull k: 3.71 Autocorrelation factor: 0.999 Diurnal pattern strength: 0.0000000307 Hour of peak river flow speed: 13 Scaled annual average: 1.94 m/s Anemometer height: 20 m Altitude: 10 m Wind shear profile: Logarithmic Surface roughness length: 0.01 m

AC Generator: Gen18

Size (kW) Capital ($) Replacement ($) O&M ($/hr) 18.000 8,100 8,100 0.500

Sizes to consider: 0, 18 kW Lifetime: 15,000 hrs Min. load ratio: 40% Heat recovery ratio: 0% Fuel used: Diesel Fuel curve intercept:

0.0101 L/hr/kW

Fuel curve slope: 0.219 L/hr/kW

Page 114: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

102

Fuel: Diesel

Price: $ 0.6, 1.0/L Lower heating value: 43.2 MJ/kg Density: 820 kg/m3 Carbon content: 88.0% Sulfur content: 0.330%

Battery: Trojan T-105

Quantity Capital ($) Replacement ($) O&M ($/yr) 1 215 215 5.00 2 430 430 5.00

Quantities to consider: 0, 6, 8, 10, 12, 14, 16 Voltage: 6 V Nominal capacity: 225 Ah Lifetime throughput: 845 kWh Min battery life: 5 yr

Converter

Size (kW) Capital ($) Replacement ($) O&M ($/yr) 1.000 2,000 2,000 0

Sizes to consider: 0, 20, 30, 35, 40 kW Lifetime: 15 yr Inverter efficiency: 90% Inverter can parallel with AC generator:

Yes

Rectifier relative capacity: 100% Rectifier efficiency: 85%

Economics

Annual real interest rate: 8% Project lifetime: 25 yr Capacity shortage penalty: $ 0/kWh System fixed capital cost: $ 0 System fixed O&M cost: $ 0/yr

Page 115: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

103

Generator control

Check load following: Yes Check cycle charging: Yes Setpoint state of charge: 30%

Allow systems with multiple generators: Yes Allow multiple generators to operate simultaneously: Yes Allow systems with generator capacity less than peak load: Yes

Emissions

Carbon dioxide penalty: $ 0/t Carbon monoxide penalty: $ 0/t Unburned hydrocarbons penalty: $ 0/t Particulate matter penalty: $ 0/t Sulfur dioxide penalty: $ 0/t Nitrogen oxides penalty: $ 0/t

Constraints

Maximum annual capacity shortage: 0, 10, 30% Minimum renewable fraction: 0%

Operating reserve as percentage of hourly load: 10% Operating reserve as percentage of peak load: 0% Operating reserve as percentage of solar power output: 25% Operating reserve as percentage of wind power output: 50%

Page 116: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

104

Appendix C 

Estimating monthly average flow speed using rainfall variation. 

Month of Year

Time Group

Rainfall (mm)

Fraction compared to base i.e Sept. group I

Flow Speed (m/s)

Monthly averaged flow speed with correction

factor of 0.8 (m/s) Jan I 74 1.42 2.56 2.05

II 84 1.62 2.91 2.33 III 53 1.02 1.83 1.47

Feb I 70 1.35 2.42 1.94 II 64 1.23 2.22 1.77 III 44 0.85 1.52 1.22

Mar I 70 1.35 2.42 1.94 II 68 1.31 2.35 1.88 III 96 1.85 3.32 2.66

Apr I 84 1.62 2.91 2.33 II 84 1.62 2.91 2.33 III 93 1.79 3.22 2.58

May I 86 1.65 2.98 2.38 II 66 1.27 2.28 1.83 III 60 1.15 2.08 1.66

Jun I 44 0.85 1.52 1.22 II 36 0.69 1.25 1.00 III 38 0.73 1.32 1.05

Jul I 42 0.81 1.45 1.16 II 47 0.90 1.63 1.30 III 50 0.96 1.73 1.38

Aug I 50 0.96 1.73 1.38 II 43 0.83 1.49 1.19 III 48 0.92 1.66 1.33

Sep I 52 1.00 1.80 1.44 II 66 1.27 2.28 1.83 III 83 1.60 2.87 2.30

Oct I 84 1.62 2.91 2.33 II 76 1.46 2.63 2.10 III 93 1.79 3.22 2.58

Nov I 119 2.29 4.12 3.30 II 98 1.88 3.39 2.71 III 99 1.90 3.43 2.74

Dec I 79 1.52 2.73 2.19 II 77 1.48 2.67 2.13 III 92 1.77 3.18 2.55

Page 117: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

105

Appendix D 

Specification of the components of the hybrid RAPS system 

This Appendix D intentionally left blank due to the absence of written permission

from the authors.

 

Page 118: Options for the Electrification of Rural Villages in the ...researchrepository.murdoch.edu.au/2070/1/Kunaifi_2009.pdf · Options for the Electrification of Rural Villages in the Province

106

Appendix E 

Simulation  results  of  a  diesel  only  system with  zero  capacity 

shortage 

Parameter Result/Note System configuration A 30 kW diesel generatorCapital cost (US$) 13,500 Replacement costs (US$) 80,694 O&M costs (US$) 46,756 Fuel cost (US$) 276,829 Total NPC (US$) 416,990 Levelized COE (US$/kWh) 0.595Electricity production (kWh/yr.) 125,964 Electrical load (kWh/yr.) 65,700 Excess electricity (%) 47.8Capacity shortage (%) 0.1Generator lifetime (yr.) 1.71Generator capacity factor (%) 47.9Generator mean output (kW) 14.4Generator fuel consumption (litre/yr.) 43,222 Generator Specific fuel consumption (litra/kWh) 0.343Mean electricity efficiency (%) 29.6Carbon dioxide emission (kg/yr) 113,817