optimisation of point life cycle costs through load-dependent maintenance
DESCRIPTION
OPTIMISATION OF POINT LIFE CYCLE COSTS THROUGH LOAD-DEPENDENT MAINTENANCE German Aerospace Center – Institute of Transportation Systems. Katja Beck, Bärbel Jäger, Karsten Lemmer. Motivation. Demand for more economic efficiency in the railway sector. - PowerPoint PPT PresentationTRANSCRIPT
OPTIMISATION OF POINT LIFE CYCLE COSTS THROUGH LOAD-DEPENDENT MAINTENANCE > Slide 1Institute of Transportation Systems >
OPTIMISATION OF POINT LIFE CYCLE COSTS THROUGH
LOAD-DEPENDENT MAINTENANCE
German Aerospace Center – Institute of Transportation Systems
Katja Beck, Bärbel Jäger, Karsten Lemmer
OPTIMISATION OF POINT LIFE CYCLE COSTS THROUGH LOAD-DEPENDENT MAINTENANCE > Slide 2Institute of Transportation Systems
Motivation
1. Demand for more economic efficiency in the railway sector
3. Maintenance costs of infrastructure elements are cost drivers
2. More economic efficiency through a decrease in life cycle costs
OPTIMISATION OF POINT LIFE CYCLE COSTS THROUGH LOAD-DEPENDENT MAINTENANCE > Slide 3Institute of Transportation Systems
Life Cycle Costs – Maintenance Strategy
LCC – sum over all costs generated in the life phases of a product (DIN EN 60300-3-3)
Maintenance cost determined mainly by
Number of CM and PM cases
Duration
Manpower needed
Formation cycle Market cycle
1.Concept & Definition
2.Design &
Development
3.Production
4.Installation /
Migration
5. Operation & Maintenance
6.Disposal & Recycling
Maintenance Strategy
CM – corrective maintenance
PM – preventive maintenance
OPTIMISATION OF POINT LIFE CYCLE COSTS THROUGH LOAD-DEPENDENT MAINTENANCE > Slide 4Institute of Transportation Systems
Maintenance Strategy - German Railways
Decreasing the probability of failure and the number of corrective maintenance cases (EN 13306)
Preventive maintenance strategies
German Railway infrastructure maintained
Mainly time dependent
Condition-based through monitoring
Time dependent intervals
Condition based intervals
No preventive maintenance
OPTIMISATION OF POINT LIFE CYCLE COSTS THROUGH LOAD-DEPENDENT MAINTENANCE > Slide 5Institute of Transportation Systems
Time dependent maintenance
German Railways
Track components maintained dependent on load figure
Load figure = Number of Trains x Total Tons x 10-6 per week
0-35 low traffic volume
36-600 normal traffic volume
>600 high traffic volume
Load category:
Fix preventive maintenance interval
+ Easy to plan
- Not cost efficient
OPTIMISATION OF POINT LIFE CYCLE COSTS THROUGH LOAD-DEPENDENT MAINTENANCE > Slide 6Institute of Transportation Systems
Points
Railway infrastructure element
Ensuring system flexibility
Maintenance based on
Time
Condition (use of point diagnosis systems)
Wearout highly load-dependent
OPTIMISATION OF POINT LIFE CYCLE COSTS THROUGH LOAD-DEPENDENT MAINTENANCE > Slide 7Institute of Transportation Systems
Idea: Load-dependent Maintenance
Why not use operation simulation information when determining the need for preventive maintenance work?
No falling below the wear-out limit
PMPMPM NcC
100%
Wear-out Stock
Time
Service Life
Maintenance Work
Wear-out limit
System Breakdown
Switch replacement
PMC - Total costs for PM
- Costs per PM case
- Number of PM cases
PMc
PMN
CM – corrective maintenance
PM – preventive maintenance
OPTIMISATION OF POINT LIFE CYCLE COSTS THROUGH LOAD-DEPENDENT MAINTENANCE > Slide 8Institute of Transportation Systems
Simulative Evaluations
Railway operation simulation (e.g. RailSys)
Number of trains
Weight of trains
Load figure = Number of Trains x Total Tons x 10-6 per week
Example
Single way track
Ca. 50 passenger trains per day
Weight of 500 tons
LF = (50 x 7) x (50 x 500 x 7) x 10-6 = 61.25
Number of Trains
Total Tons
OPTIMISATION OF POINT LIFE CYCLE COSTS THROUGH LOAD-DEPENDENT MAINTENANCE > Slide 9Institute of Transportation Systems
Time-dependent vs. load-dependent maintenance
LF = 61.25
Load category
LF = 36 Number of Trains (500 tons) per day = 39
LF = 600 Number of Trains (500 tons) per day = 158
Scheduled Maintenance after 2 months (accordant to guide line)
2379 < Number of trains < 9638
0-35 low traffic volume
36-600 normal traffic volume
>600 high traffic volume
OPTIMISATION OF POINT LIFE CYCLE COSTS THROUGH LOAD-DEPENDENT MAINTENANCE > Slide 10Institute of Transportation Systems
Maintenance Cost Savings
Preventive maintenance cost savings for chosen example (67 points, 5 years period)
Relating to maintenance work after 2 months
Calculated with cost figures from the German Railways
Scenario NPV of PM costs
Time-dependent -
2 months 100 %
Load dependent -
after 6000 vehicle crossings 21 %
Load dependent -
after 9500 vehicle crossings 13 %NPV – Net Present Value
PM – preventive maintenance
OPTIMISATION OF POINT LIFE CYCLE COSTS THROUGH LOAD-DEPENDENT MAINTENANCE > Slide 11Institute of Transportation Systems
Summary
Cost optimisation needed
Infrastructure maintenance costs as cost drivers
Use of train scheduling information instead of additional diagnosis equipment
Maintenance process flexibility needed
Load as a wearout factor
High saving potentials in point maintenance costs
Cost savings particularly high if LF is on the lower bound of the load category
OPTIMISATION OF POINT LIFE CYCLE COSTS THROUGH LOAD-DEPENDENT MAINTENANCE > Slide 12Institute of Transportation Systems >
Thank you for your attention