operational performance july’12

11
OPERATIONAL PERFORMANCE JULY’12 Month Carried Tonnage Monthly Traffic projection based on ATP Variation % (Over 2011 – 12) 2012-13 2011- 12 For July 0.26 0.19 0.26 38% Cumula tive – till July 1.34 1.00 1.39 34% Tonnage - MT

Upload: lan

Post on 23-Jan-2016

20 views

Category:

Documents


0 download

DESCRIPTION

OPERATIONAL PERFORMANCE JULY’12. Tonnage - MT. COMMODITY-WISE LOADING – FOR THE MONTH OF JULY’12. Tonnage in Lakhs. COMMODITY-WISE REVENUE – FOR THE MONTH OF JULY’12. ` - Crores. Commodity wise Net Revenue Including OH. ` - Crores. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: OPERATIONAL PERFORMANCE  JULY’12

OPERATIONAL PERFORMANCE JULY’12

Month Carried Tonnage Monthly Traffic projection based

on ATP

Variation % (Over 2011 – 12)2012-13 2011-12

For July 0.26 0.19 0.26 38%

Cumulative – till July

1.34 1.00 1.39 34%

Tonnage - MT

Page 2: OPERATIONAL PERFORMANCE  JULY’12

COMMODITY-WISE LOADING – FOR THE MONTH OF JULY’12

Particulars Carried Tonnage 2012-13

Carried Tonnage 2011-12

Variation Over

Commodity July’12 Apr’12-July’12

July’11 Apr’11- July’11

Las t Yr July’11

Last Yr

Apr’11-July’12

Iron Ore/ Export

Domestic

Total

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.42

0.42

0.00

3.51

3.51

0%

-100%

-100%

0%

-100%

-100%

Cement 0.73 3.40 0.31 1.49 139% 128%

Fertilizer 0.75 1.73 0.56 2.47 35% -30%

Food Grains 0.05 0.59 0.11 0.45 -52% 31%

LPG/POL 0.26 1.02 0.31 1.06 -15% -4%

Coal 0.81 6.33 0.15 0.68 431% 828%

Gypsum 0.00 0.31 0.04 0.31 -100% 1%

Iron Sheet/Wood 0.00 0.00 0.00 0.03 0% -100%

Auto/Cont 0.00 0.00 0.00 0.00 0% 0%

Total 2.60 13.39 1.89 9.99 38% 34%

Tonnage in Lakhs

Page 3: OPERATIONAL PERFORMANCE  JULY’12

COMMODITY-WISE REVENUE – FOR THE MONTH OF JULY’12

Particulars Gross Revenue

2012-13

Gross Revenue

2011-12

Variation % Over

Commodity July’12 Apr’12-July’12

July’11 Apr’11- July’11

Las t Yr July’11

Last Yr

Apr’11-July’12

Iron Ore/ Export

Domestic

Total

0.00

0.00

0.00

0.00

0.00

0.00

0.00

1.00

1.00

0.00

8.98

8.98

0%

-100%

-100%

0%

-100%

-100%

Cement 1.84 9.39 0.61 3.18 203% 195%

Fertilizer 1.55 3.71 0.86 4.09 79% -9%

Food Grains 0.10 1.09 0.13 0.60 -23% 80%

LPG/POL 0.85 3.60 1.03 3.82 -17% -6%

Coal 1.89 16.53 0.27 1.31 590% 1161%

Gypsum 0.00 0.86 0.07 0.64 -100% 34%

Iron Sheet/Wood 0.00 0.00 0.00 0.07 0% -100%

Auto/Cont 0.00 0.04 0.00 0.01 0% 279%

TOTAL 6.24 35.22 3.99 22.70 56% 55%

` - Crores

Page 4: OPERATIONAL PERFORMANCE  JULY’12

Commodity wise Net Revenue Including OH

Particular July 2012 July 2011 Net Rev

Commodity Gross Reve

O&M Cost `. 164/T

* Net Reve

Gross Reve

O&M Cost `.188/T

Net Reve

Varation %

Iron Ore/ Export

Domestic0.00

0.00

0.00

0.00

0.00

0.00

0.00

1.00

0.00

0.78

0.00

0.22

0%

-100%

Cement 1.84 1.20 0.64 0.61 0.58 0.03 2128%

Fertilizer 1.55 1.24 0.31 0.86 1.05 -0.19 267%

Food Grains

0.10 0.08 0.02 0.13 0.20 -0.07 134%

LPG/POL 0.85 0.43 0.42 1.03 0.58 0.45 -5%

Coal 1.89 1.32 0.57 0.27 0.29 -0.02 3611%

Gypsum 0.00 0.00 0.00 0.07 0.07 0.00 -100%

Iron Sheet/ Wood

0.00 0.00 0.00 0.00 0.00 0.00 0%

Auto/Cont 0.00 0.00 0.00 0.00 0.00 0.00 0%

TOTAL 6.24 4.27 1.97 3.99 3.55 0.44 348%

` - Crores

•July’12 - Net Revenue Includes OH of `. 73 Lakhs , O&M Cost Inclusive of OH - ` 192/T•July’11 – Net Revenue Includes OH of `. 59 Lakhs, O&M Cost Inclusive of OH - ` 219/T

Page 5: OPERATIONAL PERFORMANCE  JULY’12

Commodity wise Gross & Net Revenue Including OH (Per Tonne)

Particular July 2012 July 2011 Net Rev

Commodity Gross Rev

O&M Cost /T

Net Rev

Gross Rev

O&M Cost /T

Net Rev Varation %

Iron Ore

Export

Domestic

0

0

0

0

0

0

0

242

0

188

0

54

0%

-100%

Cement 253 164 89 199 188 11 706%

Fertilizer 206 164 42 155 188 -33 225%

Food Grains 202 164 38 126 188 -62 161%

LPG/POL 325 164 161 331 188 143 13%

Coal 234 164 70 181 188 -7 1042%

Gypsum 0 0 0 195 188 7 -100%

Iron Sheet /Wood

0 0 0 0 0 0 0%

Auto/Cont 0 0 0 0 0 0 0%

Amt - `

•July’12 - Net Revenue Includes OH of `. 28/T , O&M Cost Inclusive of OH - ` 192/T•July’11 – Net Revenue Includes OH of `. 31/T, O&M Cost Inclusive of OH - ` 219/T

Page 6: OPERATIONAL PERFORMANCE  JULY’12

Operating Ratio for the month of July 2012For July

2012To End of July 2012

Gross Revenue 6.24 35.22

Total Income 6.24 35.22

Operating Expenses

O&M Costs (Inc of Def. OH) 5.59 26.56

Administrative Expenses 0.08 0.29

Depreciation 2.83 11.32

Total Expenses (i) 8.50 38.17

Operating Ratio (%) 136% 108%

Cost of Maintenance works (ii) 0.00 0.00

Total Expenses (I) + (II) 8.50 38.17

Operating Ratio (Cumulative) 136% 108%

Surplus/Deficit -2.26 -2.95

Surplus % -36% -8%

` - Crores

NOTE : In O&M costs, cost of fuel is calculated as per service & direction wise

Page 7: OPERATIONAL PERFORMANCE  JULY’12

COST OF FUEL (SERVICE WISE/ DIRECTION WISE) for July’12

Cost of Fuel From April ’12 – July’12 – 11.74 Cr

Particulars No of Wagons Cost of Fuel ` - Crores

Total ` - Crores

Wagon Type UP DN UP DN UP + DN

BCN Load 1342 1253 0.79 0.27 1.06

BOXN Load 1233 0 0.57 0.00 0.57

BTPG Load 475 0 0.25 0.00 0.25

BTPN Load 204 0 0.09 0.00 0.09

BLCA/BFKN Load 0 0 0.00 0.00 0.00

BCNHL Ld 0 0 0.00 0.00 0.00

BOXN Empty 0 1647 0.00 0.11 0.11

BTPG Empty 0 510 0.00 0.12 0.12

BTPN Empty 0 457 0.00 0.07 0.07

BLCA/BFKN Empty 0 0 0.00 0.00 0.00

BRN Empty 43 0 0.01 0.00 0.01

Cost of Fuel of CLE + Other (UP+DN) 0.00 0.00 0.01

TOTAL 3297 3867 1.71 0.57 2.29

Cost of Lube Oil + Others 0.15

TOTAL 2.44

Page 8: OPERATIONAL PERFORMANCE  JULY’12

Line Capacity Utilization for the month of July’12 :

Direction Loaded Empties Total No of Trains

*CLE *Others Total

UP Trains 71 1 72 48

(68)

2

(5) 205Down Trains 31 52 83

102 53 155 48 2 205

Permissible Capacity : 240

Utilized : 205

Percentage of Utilization : 85%

Percentage of Utilization Loaded : 43%

Engine Hour Cost : 44.77 Lakhs

NOTE:

* Moved between SKLR-SBHR-SKLR

Page 9: OPERATIONAL PERFORMANCE  JULY’12

WAGON DAYS – JULY 2012

No of Days

TotalUP Down

Actual 1914 1804 3718

Abnormal Detention

326 132 458

Rate per Day in terms of 8 wheeler : ` 967.75

Wagon Hire Charges (Actual) : ` 35.99 Lakhs

Wagon Hire Charges for Abnormal : ` 4.43 Lakhs

Detention (Avoidable)

*Abnormal Detention : Time taken for completing the journey > 15 Hrs

Page 10: OPERATIONAL PERFORMANCE  JULY’12

Details of Payments Received from Mysore Division after adjusting O&M Costs

Months Due Date Actual date of Receipt

Amount Rs - Cr

Prov. Pay Final Pay (Prov Pay)

April ’12 05.05.12 31.05.12 02.06.12 4.22

May ’12 05.06.12 30.06.12 01.08.12 4.19

June’12 05.07.12 30.07.12 01.08.12 3.64

July’12 05.08.12 30.08.12

Page 11: OPERATIONAL PERFORMANCE  JULY’12

Details of Payments made by HMRDC to SWR

Particulars For the month of July’12

To the End

(Crores)

Contractual payment for maintenance works (Provisional bill from --)

----- ----