operational excellence case study
TRANSCRIPT
Accelerating Supply Chain Performance
Operational Excellence Case Study
1
SEA 2011 All Rights Reserved
Kenny Heifner VP, Quality and Organizational Development, SMS Technologies
In the past few years Kenny has led two organizations to
ISO 9001:2000 registration and three organizations to ISO/TS 16949:2002 registration. Of these 5
organizations, Total Electronics went on to become one of seven National Finalists for the American Association
for Manufacturing Excellence (AME) award in October of
2005. Master of Business Administration, MBA from Anderson University, a Master of Arts in Education, MAE
from Ball State University, and a Bachelor of Science, BS from Purdue University.
SMS Technologies, Inc.
2009 Supplier Excellence Alliance
Supply Chain Innovation Winner�
And
2010 Supplier Excellence Alliance
Operational Excellence Winner�
Workforce Development Finalist�
Employees - 100 in San Diego
Low volume / high mix EMS - Electronic Manufacturing Services including Design, Layout, Rapid Proto-Typing, DFM & DFT, RF Technology, Supply Chain Management
AS9100, ISO/TS 16949, ISO 9001 & 13485
Aerospace & Military Customers:
SMS Technologies, Inc.
Results of USAF Implementation�
Customer-Focused Process Approach
Workforce
Development
Operational
Excellence
ISO/TS 16949:2002
Customer-
Oriented
Process
Approach
AS9100C:2009
Customer-
Oriented
Process
Approach
Leadership
And
Culture
Build Quality In With APQP (Advanced Product Quality Planning)
Process Flow
Diagram
Process Failure Mode
Effects Analysis
Work Instruction Qualification Control Plan
Customer
Requirements
Special / Key
Product
Characteristics ( )
Launch Lean With 3P
Note: Each color represents a different operator’s work cycle
Production Preparation Process
VSM From Raw Material to USAF
CUSTOMER LOCATIONS
LONG - LEAD ITEMS USAF
RAW
ALUMINUM
SUPPLIER
CUSTOMER LOCATIONS SEI
CUSTOMER LOCATIONS SMS
CUSTOMER LOCATIONS ADC
SHIPPED AS AS NEEDED
SHIPPED AS 1x DAY
SHIPPED AS 1x DAY
FINISHED GOODS
SHIPPED AS WEEKLY
ADC�PRODUCTION
CONTROL
SEI�SALES ORDER
BANK
SMS�PRODUCTION
CONTROL
100 Day 100 Day 100 Day
Results of NSA Implementation�
Trouble In The Beginning�
NSA business was acquired by SMS in 2007
Volume was 260 sets (13-PCBAs) per month
Many of the key components were obsolete
Consigned material was furnished sporadically by our Tier 1 customer
Low incoming yield from a key directed-source resulted in quality problems throughout
Material handling costs were left out of the quote
SMS was losing >175% of the quoted margin�
The 1st SMS Current State Map
Prod. Ctrl.
Final Insp. & Pack-out
Coating
Outside
Supplier
Source Inspection
Wash 2nd Assy & Wave
Wash SMT & Test
Shipping
Tier 1
Weekly
Boards &
Components
5-days .5 day 1 day .25 day .5 day
5 1 40 1 40 20 20
LT ~8 days
VA =127 min. 1
9 – Operators 1st Shift
1 – Inspector 1st Shift
1 – Operator 2nd Shift
Weekly
SMS WH
.25 day .25 day .25 day
No Clean In-Circuit
Test
Lead Time ~ 8 Days
VA Time = 127 Minutes
The NSA Customer-Focused Team�
Program Manager
Manufacturing / Quality Engineer
Test Engineer
Value-Stream Manager
Production Planner
Procurement Specialist
Cell Leads
The Turn-A-Round Begins�
Our customer agreed to let SMS manage the supply chain including obsolete components
SMS qualified a second source to provide key flex cables & helped them improve the process
Quality improved significantly throughout the entire value-stream as a result (98.4% SMS)
The SMS Customer-Focused Team conducted a Kaizen event to develop a mixed-model cell around the wave soldering process
The Team built every PCBA every week
The NSA Cell Lay-out�
The New SMS Current State Map
Prod. Ctrl.
Conformal Coating
No Clean In-Circuit
Test
Wash 2nd Assy & Wave
Wash SMT & Test
Final Assy Pack-out &
Shipping
Tier 1
Weekly
Boards &
Components
.3 hrs.
5 1 40 1 40 20
LT ~8 hrs.
VA =107 min.
5 – Operators 1st Shift
1 – Inspector 1st Shift
Weekly
SMS WH
4.4 hrs. .5 hrs.
max. 10
pcs.
FIFO FIFO
max. 6
pcs.
FIFO FIFO
max. 6
pcs.
FIFO FIFO
max. 6
pcs.
FIFO FIFO
max. 6
pcs.
FIFO FIFO
.3 hrs. .3 hrs. .3 hrs.
Lead Time ~ 8 Hours
VA Time = 107 Minutes
LIFE, Quality & Margin Improves�
The New SMS Future State Map
Prod. Ctrl.
SMT, Test & Wash
Tier 1
Twice Weekly
Boards &
Components
5 min. 90 min.
LT <4 hrs.
VA = 95 min.
4 – Operators 1st Shift Twice Weekly
SMS WH
2.2 hrs.
2nd Assy., Wave, Test, Conformal Coating, Pack-out & Ship
Combine 2nd Assembly Combine
Lead Time < 4 Hours
VA Time = 95 Minutes
NSA Current-State Value Stream Map 2-19-10
0145
Final Insp.
& Rpt. 120s
0140
Battery Cover
Dust C. 600s
0135
QAA ATP
& Rpt.
45min
0125
2nd INSP
& Rpt.
180s
0115
2nd ATP
& Rpt.
45min
0100-10
Open Insp. Close 720s
0075
45min
0070
Close Unit
45s
0065
INSP V/M #1
& Rpt. 135s
0060
PWAs Rec. SNs 120s
0055
INSP & Rpt.
60s
0050
Back Plane
Rec SN 240s
0045
120s
0040
Install Shield
240s
0035
120s
0020-30
Black & Red PWAs 660s
V/M #3
0095
Burn In
72 hrs.
0085
Vib- ration
2700s
c/o 1hr. c/o 1hr. (Between Batches)
(Between Products)
~95% up
~90% up
2 per 2 per 2 per
1st ATP
& Rpt.
INSP & Rpt.
INSP & Rpt.
27 25 14 6 35
6 18
9
3 10
0145
QAA INSP.
120s
0015
INSP. Labels / Travele
r 900s
0010
Pull Kit & Print Docs. 900s
0150 Stock
30-day Sample
Tests 1-60-day
0155-75
0180-85
Pack Ship
Final
Various NSA Locations
250
60-65 Units Per Week
SMS Technologies
<400 Units / 2 - Months
Production Control 400 Units /
2 - Months 200 Units Per Month
Work Orders 400 Units /
2 - Months
660s 240s 240s 120s 45s 1350s 720s 1350s 1350s 600s VA=121min
LT=21.7days
13 – People 1-10-Hour Shift 4:30 AM – 3:00
PM ½-Hour Lunch 2-15 Minute
Breaks 15 Minutes Set-up Total 9.25
Hours
2.7d 2.5d 1.4d .6d 3.5d 6.6d .3d 1.0d
- max 36 units
0095
120s
0090
Knobs &
Screws 240s
0080
120s
0075
60s
0070
60s
0060
Install Key-
board
180s
Interface PWA
INSP & Rpt.
Install Shield
INSP & Rpt.
5 11 10
VA=10min
LT=2.6d
Lead Time = 21.7 Days
VA Time = 121 Minutes
~1500 Square Feet �
NSA Future-State Value Stream Map 2-26-10
0140-0145
Install Battery, Dust Cover &
Final Inspection 720s
0135
QAA ATP
& Rpt. 45min
0125
2nd INSP
& Rpt. 180s
0115
2nd ATP
& Rpt. 45min
0100-10
Open Insp. Close 720s
0075
45min
0020-0070
Build, Inspect & Close Unit
1740s
V/M #3
0095
Burn In
72 hrs.
0085
Vib- ration
2700s
c/o 1hr. c/o 1hr. (Between Batches)
(Between Products)
~95% up
~90% up
2 per 2 per 2 per
1st ATP
& Rpt.
0145
QAA INSP.
120s
0015
INSP. Labels / Travele
r 900s
0010
Pull Kit & Print Docs. 900s
0150 Stock
30-day Sample
Tests 1-60-day
0155-75
0180-85
Pack Ship
Final
Various NSA Locations
50
50 Units Per Week
SMS Technologies
<400 Units / 2 - Months
Production Control 400 Units /
2 - Months 200 Units Per Month
Work Orders
400 Units / 2 - Months
1305s 1350s 720s 1350s 1350s 600s VA=121min
LT=3.2days
max 19
units
- Empty Daily
- max 36 units
Week-end
Buffer
7 – People 1-10-Hour Shift 4:30 AM – 3:00
PM ½-Hour Lunch 2-15 Minute
Breaks 15 Minutes Set-up Total 9.25
Hours
55 1
3.1d .1d
721-1 0060-0095
Build / Inspect Panel Assembly
780s
- Trouble-Shooter / Rework
- Also help with Rework
VA=10min
LT=13min
Lead Time = 3.2 Days
VA Time = 121 Minutes
020-030
035-040
055-060
Repaired
Failed
065-070
045-050
080
120
125
130
140
145
Failed
3rd ATP 2nd ATP 1st ATP
Finished Units
Rework ATP
Failed
100-115
To Vibration
Return From
Burn-In To
Finished Goods
Start
Panel Assembly060-095
Trouble-Shooter / Rework -
Also help with Rework -
Projected LIFE Improvements�
Actual LIFE Improvements�
Pitfalls to Improvement�
The power of a disciplined lean culture should not be underestimated
Workforce development is also a critical component of a successful lean transformation
Independent inspection requirements forced us to continuously move operators from station to station
The customer shut down SMS operations for 4 weeks after the event to use up excess inventory
The assembly process lacked enough burn-in capacity to keep pace with the projected rate
The burn-in chamber is a monument
12 / Day In 12 / Day Out
36 Unit Max.
Maximum 84 Unit Throughput in 7 Days (24/7)
20 Unit Max.
Overflow
Overflow FIFO Overflow Out
Bottlenecks / Constraints�
Potential Future Improvements�
Combine inspections steps
Combine functional test operations
Pack-out at the end of the cell
Locate all assembly & test in one place
Ship to NSA every month vs. 2 months
Add more visual controls
Develop returnable shipping kanbans
Make milk-runs twice a week
KANBAN Box 1 Full Board Set
with Front Cover
Daily, Weekly & Monthly Output (For 10 & 12-hour Shifts)
Lessons Learned�
The significance of lean culture and workforce development on the ease of implementation
The power of the SEA Roadmap
Removing the blinders and “learning to see”
Having faith when it is not easy to see the way
Supply chain partners can team-up to turn a losing proposition into a sustaining asset
Operational Excellence is multiplied many times over when it is applied to the entire value stream
VSM From Raw Material to NSA
CUSTOMER LOCATIONS
LONG - LEAD ITEMS NSA
RAW
FLEX CABLE
SUPPLIER
CUSTOMER LOCATIONS Customer
CUSTOMER LOCATIONS SMS
CUSTOMER LOCATIONS Supplier
SHIPPED AS AS NEEDED
SHIPPED AS 1x Week
SHIPPED AS 1x Week
FINISHED GOODS
SHIPPED AS WEEKLY
Supplier�PRODUCTION
CONTROL
Customer�SALES ORDER
BANK
SMS�PRODUCTION
CONTROL
</= 260 Mo </= 260 Mo </= 260 Mo