Page 1: OPEN – FIN – INFO 2-42 June 13-14, 2013 OPEN – FIN – INFO 2-42 June 13-14, 2013 FY2015 Preliminary State Capital Appropriations Request and Campus Capital

OPEN – FIN – INFO 2-1

June 13-14, 2013

OPEN – FIN – INFO 2-1

June 13-14, 2013

FY2015 Preliminary State Capital Appropriations Request and Campus Capital Project Plans

UM

Board of Curators FINANCE COMMITTEE

June 13, 2013

Page 2: OPEN – FIN – INFO 2-42 June 13-14, 2013 OPEN – FIN – INFO 2-42 June 13-14, 2013 FY2015 Preliminary State Capital Appropriations Request and Campus Capital

OPEN – FIN – INFO 2-2

June 13-14, 2013

OPEN – FIN – INFO 2-2

Capital Planning

All planned projects greater than $5.0 million regardless of funding source & debt funded projects

Criteria used to prioritize projects:› the relationship to the campus strategic plan› facility renewal & reinvestment› functional sustainability› availability of funding› plans for on-going operational support

Additional criteria for projects proposed for state capital funding

2

Page 3: OPEN – FIN – INFO 2-42 June 13-14, 2013 OPEN – FIN – INFO 2-42 June 13-14, 2013 FY2015 Preliminary State Capital Appropriations Request and Campus Capital

OPEN – FIN – INFO 2-3

June 13-14, 2013

Op OPEN – FIN – INFO 2-3

- Includes new construction, renovation, repair, replacement, preservation, additions- Funding sources: state, federal, debt, private, campus reserves

CAMPUS TOP PRIORITY OTHER

MU $ 361.8 m $ 1,289.0 m

MU Healthcare $ 121.7 m $ 0.0 m

UMKC $ 228.6 m $ 276.8 m

S&T $ 74.9 m $ 331.7 m

UMSL $ 198.8 m $ 536.5 m

Total $ 985.8 m $ 2,424.0 m

Capital Plans – Total $3.4 billion

Page 4: OPEN – FIN – INFO 2-42 June 13-14, 2013 OPEN – FIN – INFO 2-42 June 13-14, 2013 FY2015 Preliminary State Capital Appropriations Request and Campus Capital

OPEN – FIN – INFO 2-4

June 13-14, 2013

OPEN – FIN – INFO 2-4

Capital Projects in Process

$423 million in projects underway funded by debt, federal earmark, campus reserves, and gifts

2013 Debt Financed Projects› MU – Mark Twain Hall, Wolpers & Johnston, Virginia Avenue

South Housing, East Campus Chiller Plant, Stadium – East Side & West Side

› MU Health Care – Green Meadows› UMKC – Student Success Center› S&T – Geothermal Energy, Engineering Building› UMSL – Benton Stadler Addition, Wellness Center

Page 5: OPEN – FIN – INFO 2-42 June 13-14, 2013 OPEN – FIN – INFO 2-42 June 13-14, 2013 FY2015 Preliminary State Capital Appropriations Request and Campus Capital

OPEN – FIN – INFO 2-5

June 13-14, 2013

OPEN – FIN – INFO 2-5

State Capital Appropriations

Categories of Funding:› Rehabilitation and New Construction› Engineering Equipment› Critical Facility Capital Repair, Renovation and Renewal Needs

Page 6: OPEN – FIN – INFO 2-42 June 13-14, 2013 OPEN – FIN – INFO 2-42 June 13-14, 2013 FY2015 Preliminary State Capital Appropriations Request and Campus Capital

OPEN – FIN – INFO 2-6

June 13-14, 2013

OPEN – FIN – INFO 2-6

State Support for Capital Projects

FY2001 - FY2014 FY 2001 - MU Life Sciences Building 29.9 m FY 2002 – MU Arena 31.1 m FY 2004 – UMKC Pharmacy/Nursing Building 30.5 m FY 2008 – LCDI Projects: S&T ME Addition, UMKC Pharmacy/Nursing, Dental Equipment, Ag Station Projects. 41.2 m FY 2009 – Ag Station & UMSL Optometry, UMKC Dental

Addition, MU Nursing/Health Professions planning 8.1 m FY 2010 – Mid Mo Renovations 13.0 m

14 YEARS TOTAL CAPITAL SUPPORT 153.8 m= $11.0 m/year or $2.2 m/year/campus

Page 7: OPEN – FIN – INFO 2-42 June 13-14, 2013 OPEN – FIN – INFO 2-42 June 13-14, 2013 FY2015 Preliminary State Capital Appropriations Request and Campus Capital

OPEN – FIN – INFO 2-7

June 13-14, 2013

On OPEN – FIN – INFO 2-7

FY 2015 Capital Appropriations Request(Preliminary)

State Request Campus Total

Total Tier I $ 389,803,000 $ 19,975,000 $ 409,778,000

Total Tier II $ 104,436,000 $ 27,034,000 $ 131,470,000

Total Tier III $ 159,555,000 $ 28,829,000 $ 188,384,000

Total Rehab & New Construction

$ 653,794,000 $ 75,838,000 $ 729,632,000

Total Engineering Equip

$ 1,622,400 $ 1,622,400 $ 3,244,800

Page 8: OPEN – FIN – INFO 2-42 June 13-14, 2013 OPEN – FIN – INFO 2-42 June 13-14, 2013 FY2015 Preliminary State Capital Appropriations Request and Campus Capital

OPEN – FIN – INFO 2-8

June 13-14, 2013

en OPEN – FIN – INFO 2-8

FY 2015 Tier 1 Capital Appropriations RequestRehabilitation & New Construction State Request Campus Total

Critical Facility Needs $194,053,000 $0 $194,053,000

Benton/Stadler Renovation-UMSL $62,800,000 $0 $62,800,000

College of Engineering-Lafferre Hall Reconstruction, Additions & Renovations-MU

$55,901,000 $13,975,000 $69,876,000

School of Medicine Renovation and Health Sciences Education Building Phase II-UMKC

$48,500,000 $6,000,000 $54,500,000

Chemistry and Biological Science Renovation-S&T

$28,549,000 $0 $28,549,000

Total Tier I $389,803,000 $19,975,000 $409,778,000

State Historical Society Building & Museum $50,107,000 $0 $50,107,000

Page 9: OPEN – FIN – INFO 2-42 June 13-14, 2013 OPEN – FIN – INFO 2-42 June 13-14, 2013 FY2015 Preliminary State Capital Appropriations Request and Campus Capital

OPEN – FIN – INFO 2-9

June 13-14, 2013

Op OPEN – FIN – INFO 2-9

FY 2015 Higher Education Capital Fund50/50 Match ProgramNew Construction State Request Campus Total

215 Volker – Entrepreneurial Innovation Center – UMKC

$7,500,000 $7,500,000 $15,000,000

Downtown Fine Arts Campus – UMKC $44,000,000 $44,000,000 $44,000,000

Engineering Lab Building – UMKC $8,000,000 $8,000,000 $16,000,000

College of Business Administration Building – UMSL

$10,000,000 $10,000,000 $20,000,000

Total 50/50 Match Projects $69,500,000 $69,500,000 $139,000,000