on-line process monitoring and electric submetering at six ......technologies. a combination of...

120
On-Line Process Monitoring and Electric Submetering at Six Municipal Wastewater Treatment Plants Final Report 98-12 July 1998 New York State Energy Research and Development Authority

Upload: others

Post on 08-Nov-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

  • On-Line Process Monitoring and Electric Submetering at Six

    Municipal Wastewater Treatment Plants

    Final Report 98-12 July 1998

    New York State Energy Research and Development Authority

  • The New York State Energy Research and Development Authority (NYSERDA) is a public benefit corporation created in 1975 by the New York State Legislature.

    NYSERDA has major programs in energy and environmental research, radioactive and hazardous waste management, tax-exempt bond financing, energy analysis and planning, and energy efficiency grants. Its responsibilities include:

    • Conducting a multifaceted energy and environmental research and development program to meet New York State's diverse needs;

    • Helping industries, schools, hospitals, and not-for-profits implement energy efficiency measures;

    • Providing objective, credible, and useful energy analysis to guide decisions made by major energy stakeholders in the private and public sectors;

    • Managing the Western New York Nuclear Service Center at West Valley, including: (1) overseeing the State's interests and share of costs at the West Valley Demonstration Project, a federal/State radioactive waste clean-up effort, and (2) managing wastes and maintaining facilities at the shut-down State-Licensed Disposal Area;

    • Participating in the Malta Rocket Fuel Area "Superfund" site clean-up and managing facilities at the site on behalf of the State;

    • Coordinating the State's activities on nuclear matters, and designing, constructing, and operating State facilities for disposal oflow-Ievel radioactive waste, once siting and technology decisions are made by the State; and

    • Financing energy-related projects, reducing costs for ratepayers.

    NYSERDA derives its basic research revenues from an assessment levied on the intrastate sales ofNew York State's investor-owned electric and gas utilities. Additional research dollars come from limited corporate funds and a voluntary annual contribution by the New York Power Authority. More than 245 ofNYSERDA's research projects help the State's businesses and municipalities with their energy and environmental problems. Since 1990, NYSERDA has successfully developed and brought into use more than 60 innovative, energyefficient, and environmentally acceptable products and services. These contributions to the State's economic growth and environmental protection are made at a cost ofless than $1 per New York resident per year.

    Federally funded, the Energy Efficiency Services program is working with more than 220 businesses, schools, and municipalities to identify existing technologies and equipment to reduce their energy costs.

    For more information, contact the Technical Communications unit, NYSERDA, Corporate Plaza West, 286 Washington Avenue Extension, Albany, New York 12203-6399; (518) 862-1090, ext. 3250; or on the World Wide Web at http://www.nyserda.org/

    State of New York Energy Research and Development Authority George E. Pataki William R. Howell, Chairman Governor F. William Valentino, President

    http:http://www.nyserda.org

  • ON-LINE PROCESS MONITORING AND

    ELECTRIC SUBMETERING AT SIX MUNICIPAL

    WASTEWATER TREATMENT PLANTS

    Final Report

    Prepared for

    THE NEW YORK STATE

    ENERGY RESEARCH AND DEVELOPMENT AUTHORITY

    Albany,NY

    LaWTence J.Pakenas,P.E.

    Senior Project Manager

    and

    EMPIRE STATE ELECTRIC ENERGY RESEARCH CORPORATION

    and

    ELECTRIC POWER RESEARCH INSTITUTE

    Prepared by

    CH2M HILL INC. Parsippany, NJ

    Linda Ferguson

    Technical Project Leader

    Peter Keenan

    Project Manager

    and

    SAIC-ENERGY SOLUTIONS DIVISION Albany, NY

    Ron Slosberg Technical Project Leader

    3172-ERTER-MW-94 NYSERDA Report 98-12 July 1998

  • NOTICE

    This report was prepared by CH2M HILL Inc. and SAIC - Energy Solutions Division in the course

    of performing work contracted for and sponsored by the New York State Energy Research and

    Development Authority, the Empire State Electric Energy Research Corporation, and the Electric

    Power Research Institute (hereafter the "Sponsors"). The opinions expressed in this report do not

    necessarily reflect those of the Sponsors or the State of New York, and reference to any specific

    product, service, process, or method does not constitute an implied or expressed recommendation

    or endorsement of it. Further, the Sponsors and the State of New York make no warranties or

    representations, expressed or implied, as to the fitness for particular purpose or merchantability

    of any product, apparatus, or service, or the usefulness, completeness, or accuracy of any

    processes, methods, or other information contained, described, disclosed, or referred to in this

    report. The Sponsors, the State of New York, and the contractor make no repre~entation that the

    use of any product, apparatus, process, method, or other information will not infringe privately

    owned rights and will assume no liability for any loss, injury, or damage resulting from, or

    occurring in connection with, the use of information contained, described, disclosed, or referred

    to in this report.

  • ABSTRACT

    An investigation was made of New York State wastewater treatment plants (WWTPs) to

    determine if process audit and electrical submetering techniques are an effective method of

    identifying energy conservation opportunities (ECOs) at municipal wastewater treatment plants.

    The study at six municipal WWTPs included a range of facility sizes, locations, and treatment

    technologies. A combination of online process monitoring, offline sampling, electrical

    submetering, and specific performance efficiency testing techniques was used to obtain real-time

    process and electrical consumption data.

    Recommendations varied for each site. They included piping modifications, pump and/or motor

    replacement, operational procedures changes, modification of online instrumentation and control

    systems, aeration system upgrades, and additional energy reuse options. The energy implications

    (savings or additional costs) were quantified for each item. The simple payback period for

    operational changes and minor capital items ranged from 0 to 15 years. Major capital items were

    recommended for reasons other than energy conservation, including worker health and safety,

    effluent quality, and/or capacity limitations.

    The results of the study indicated that the audit approach, which consists of a systematic and

    rigorous methodology for obtaining accurate performance information, is an appropriate tool for

    identifying ECOs at existing wastewater treatment facilities. Online process data, equipment

    performance characteristics, and electrical submetering information provide a good basis for

    identifying ECOs, quantifying the achievable savings, and predicting the impact of implemen

    tation on facility performance.

    iii

  • TABLE OF CONTENTS

    Section Page

    1. Introduction....................................................................................................................................... 1-1

    Project Objectives ............................................................................................................................... 1-1

    Test Methodology .............................................................................................................................. 1-2

    Test Sites ............................................................................................................................................. 1-3

    2. Wastewater Treatment Plant Configurations and Performance .............................................. 2-1

    Sodus Village WWTP ........................................................................................................................ 2-1

    Performance History .................................................................................................................. 2-4

    Field Test. ..................................................................................................................................... 2-5

    Village of Goshen WWTP ................................................................................................................. 2-9

    Performance History ................................................................................................................ 2-11

    Field Test. ................................................................................................................................... 2-13

    Marsh Creek WWTP ....................................................................................................................... 2-15

    Performance History ................................................................................................................ 2-18

    Field Test. ................................................................................................................................... 2-19

    Arlington Sewage Treatment Plant ............................................................................................... 2-22

    Performance History ................................................................................................................ 2-26

    Field Test. ................................................................................................................................... 2-27

    Bergen Point WWTP ........................................................................................................................ 2-30

    Performance History ................................................................................................................ 2-33

    Field Test .................................................................................................................................... 2-34

    Yonkers Joint WWTP ....................................................................................................................... 2-38

    Performance History ................................................................................................................ 2-41

    Field Test. ................................................................................................................................... 2-43

    3. Wastewater Treatment Plant Energy Usage ................................................................................. 3-1

    Electrical Usage Profile ..................................................................................................................... 3-1

    Sodus WWTP .............................................................................................................................. 3-1

    Goshen WWTP ............................................................................................................................ 3-3

    Marsh Creek WWTP .................................................................................................................. 3-3

    Arlington STP .............................................................................................................................. 3-6

    Bergen Point WWTP .................................................................................................................. 3-6

    Yonkers Joint WWTP ................................................................................................................. 3-9

    Standardized Electrical Usage ......................................................................................................... 3-9

    4. Energy Conservation Opportunities ............................................................................................. 4-1

    Sodus Village WWTP ........................................................................................................................ 4-1

    Village of Goshen WWTP ................................................................................................................. 4-4

    Marsh Creek WWTP ......................................................................................................................... 4-5

    Arlington STP ..................................................................................................................................... 4-8

    Bergen Point WWTP ........................................................................................................................ 4-11

    Yonkers Joint WWTP ....................................................................................................................... 4-14

    5. Conclusions ....................................................................................................................................... 5-1

    Appendix A Equipment Used in the Submetering Program

    v

  • TABLES

    Number Page

    1-1 Six Municipal Wastewater Treatment Plants Included in the Test Program ........................... 1-3

    2-5 Village of Goshen WWTP - Summary of Unit Process Loading During Field Test

    3-1 Standardized Electrical Consumption of the Major Unit Processes at the Six Wastewater

    3-2 Electrical Consumption of Secondary Treatment at the Six Wastewater Treatment

    4-2 Sodus Village WWTP - Costs of Small Capital and Operational Changes

    4-3 Sodus Village WWTP - Life Cycle Cost Analysis of Major Recommended Capital

    4-5 Village of Goshen WWTP - Costs of Small Capital and Operational Changes (in priority

    4-12 Bergen Point WWTP - Costs of Recommended Small Capital and Operational Changes

    2-1 Sodus Village WWTP - Summary of Unit Processes ................................................................... 2-3

    2-2 Sodus Village WWTP - Summary of Unit Process Loading During Field Test Program....... 2-6

    2-3 Sodus Village WWTP - Field Test Program .................................................................................. 2-7

    2-4 Village of Goshen WWTP - Summary of Unit Processes .......................................................... 2-11

    Program........................................................................................................................................... 2-13

    2-6 Village of Goshen WWTP - Field Test Program ......................................................................... 2-14

    2-7 Marsh Creek WWTP - Summary of Unit Processes .................................................................. 2-17

    2-8 Marsh Creek WWTP - Summary of Unit Process Loading During Field Test Program ...... 2-20

    2-9 Marsh Creek WWTP - Field Test Program ................................................................................ 2-21

    2-10 Arlington STP - Summary of Unit Processes ............................................................................. 2-24

    2-11 Arlington STP - Summary of Unit Process Loading During Field Test Program.................. 2-28

    2-12 Arlington STP - Field Test Program ............................................................................................ 2-29

    2-13 Bergen Point WWTP - Summary of Unit Processes ................................................................... 2-32

    2-14 Bergen Point WWTP - Summary of Unit Process Loading During Field Test Program ...... 2-35

    2-15 Bergen Point WWTP - Field Test Program ................................................................................. 2-36

    2-16 Yonkers Joint WWTP - Summary of Unit Processes ................................................................. 2-40

    2-17 Yonkers Joint WWTP - Summary of Unit Process Loading During Field Test Program ..... 2-44

    2-18 Yonkers Joint WWTP - Field Test Program ................................................................................ 2-46

    Treatment Plants ............................................................................................................................ 3-11

    Plants ............................................................................................................................................... 3-13

    4-1 Sodus Village WWTP - Identified Energy Conservation Opportunities .................................. 4-2

    (in priority order) ............................................................................................................................. 4-3

    Improvement .................................................................................................................................... 4-5

    4-4 Village of Goshen WWTP - Identified Energy Conservation Opportunities ........................... 4-6

    order) ................................................................................................................................................. 4-6

    4-6 Village of Goshen WWTP - Life Cycle Cost Analysis of Major Capital Improvements ......... 4-8

    4-7 Marsh Creek WWTP - Identified Energy Conservation Opportunities .................................... 4-8

    4-8 Arlington STP - Identified Energy Conservation Opportunities ............................................. 4-11

    4-9 Arlington STP - Costs of Small Capital and Operational Changes (in priority order) ......... 4-12

    4-10 Arlington STP - Life Cycle Cost Analysis of Major Capital Improvements ........................... 4-15

    4-11 Bergen Point WWTP - Identified Energy Conservation Opportunities ................................. 4-16

    (in priority order) ........................................................................................................................... 4-17

    4-13 Bergen Point WWTP - Life Cycle Cost Analysis of Major Capital Improvement ................. 4-19

    4-14 Yonkers Joint WWTP - Identified Energy Conservation Opportunities ................................ 4-20

    4-15 Yonkers Joint WWTP - Costs of ECO (in Priority Order) ......................................................... 4-22

    vi

  • FIGURES

    Number Page

    2-1 Sodus WWTP - Process Flow Schematic ....................................................................................... 2-2

    2-2 Goshen WWTP - Process Flow Schematic .................................................................................. 2-10

    2-3 Marsh Creek WWTP - Process Flow Schematic ......................................................................... 2-16

    2-4 Arlington STP - Process Flow Schematic .................................................................................... 2-23

    2-5 Bergen Point WWTP - Process Flow Schematic ......................................................................... 2-31

    2-6 Yonkers Joint WWTP - Process Flow Schematic ........................................................................ 2-39

    3-1 Sodus WWTP - Energy Use of the Major Unit Processes ........................................................... 3-2

    3-2 Goshen WWTP - Energy Use of the Major Unit Process ............................................................ 3-4

    3-3 Marsh Creek WWTP - Energy Use of the Major Unit Processes ............................................... 3-5

    3-4 Arlington STP - Energy Use of the Major Unit Processes ........................................................... 3-7

    3-5 Bergen Point WWTP - Energy Use of the Major Unit Processes ................................................ 3-8

    3-6 Yonkers Joint WWTP - Energy Use of the Major Unit Processes ............................................. 3-10

    vii

  • ABBREVIATIONS

    BODs 5-day biochemical oxygen demand

    BFP belt filter press

    Btu British thermal units

    cBODs carbonaceous biochemical oxygen demand

    COD chemical oxygen demand

    OAF dissolved air flotation

    DO dissolved oxygen

    ECO energy conservation opportunities

    F/Mv food to microorganism ratio

    gpd gallons per day

    gpm gallons per minute

    hp horsepower

    HRT hydraulic residence time

    kW kilowatts

    kWh kilowatt hours

    Ibid pounds per day

    mgd million gallons per day

    mg/L milligram per liter

    mL/g milliliter per gram

    MLSS mixed liquor suspended solids

    MLVSS mixed liquor volatile suspended solids

    ~-N ammonia as nitrogen

    N02-N nitrite as nitrogen

    N03-N nitrate as nitrogen

    P04 orthophosphate

    sBODs soluble biochemical oxygen demand

    RAS return activated sludge

    SOR surface overflow rate

    SOTE standard oxygen transfer efficiency

    SRT solids residence time

    SVI sludge volume index

    TKN total Kjeldahl nitrogen

    TP total phosphorus

    TS total solids

    TSS total suspended solids

    VS volatile solids

    VSD variable speed drive

    VSS volatile suspended solids

    WAS waste activated sludge

    viii

  • SUMMARY

    The New York State Energy Research and Development Authority (NYSERDA), the Empire State

    Electric Energy Research Corporation (ESEERCO), and the Electrical Power Research Institute

    (EPRI) funded an investigation of New York State wastewater treatment plants (WWTPs). The

    purpose of the investigation was to determine if process audit and electrical submetering tech

    niques are an effective method of identifying energy conservation opportunities (ECOs) at

    municipal wastewater treatment plants. Phase 1 consisted of screening 80 potential WWTPs to

    identify six test sites to include in the study program. The sites were selected to provide a

    representative sample of the existing wastewater treatment facilities in New York State in terms

    of size (flow rate), location, treatment technologies, and sludge management practices. Table 1

    lists the sites and their rated capacities. Table 2 lists the various treatment technologies included

    in the test program. Phase 2 consisted of an intensive four- to six-week field study at each site

    including operating data reviews, online process monitoring, offline sampling, performance

    efficiency testing, and electrical submetering. The objectives of the field testing were to quantify

    the energy consumption and process performance on a process-by-process and whole plant basis,

    to examine the dynamic interrelationships among the unit processes to determine load/response

    and effect on performance, and to identify areas for process improvements.

    The ECOs identified during the study can be divided into four categories:

    • maintenance and housekeeping items,

    • operating and control procedures,

    • electrical equipment replacement, and

    • capacity-related issues.

    TABLEt

    SIX MUNICIPAL WASTEWATER TREATMENT FACILITIES INCLUDED IN THE TEST PROGRAM

    Name of Facility Utility Rated Capacity

    SodusWVVTP, Sodus, NY Rochester Gas and Electric 0.5 mgd

    Goshen WWTP, Goshen, NY Orange and Rockland 1.5mgd

    Marsh Creek WWTP, Geneva, NY New York State Electric and Gas Corp. 4.0mgd

    Arlington STP, Poughkeepsie, NY Central Hudson Gas and Electric 4.0mgd

    Bergen Point WWTP, Babylon, NY Long Island Lighting Company 30.0mgd

    Yonkers Joint WWTP, Yonkers, NY New York Power Authority 90.0mgd

    S-l

  • TABLE 2

    LIQUID AND SOLIDS TREATMENT TECHNOLOGIES INCLUDED IN THE TEST PROGRAM

    Liquid Treatment Technology Solids Treatment Technology

    Pump stations Thickeners

    Gravity belt Aerated grit chambers Gravity

    Primary clarifiers Dissolved air flotation

    Activated sludge Dewatering

    Extended aeration Belt filter press Contact stabilization CentrifugeConventional activated sludge

    Anaerobic digestion Aeration systems

    Sludge composting Coarse bubble Fine bubble Incineration Membrane panels Fluidized bed

    Multiple hearthTrickling filters

    Tertiary filtration

    Effluent polishing lagoons/wetlands

    Chlorination

    Several maintenance and housekeeping items were identified during the study. Common items

    included inoperable or worn backflow prevention valves on pumps, inappropriate or worn

    pressure relief valves on aeration blowers, inappropriate valve or gate settings, and worn pumps.

    The capital costs of replacing these items were usually very small and the payback period was

    usually less than two years.

    The study recommended changes to operating procedures at several of the plants. These included

    changes to pump control strategies, provision of measurement and control of miscellaneous air

    use for common air supply systems, and changes to solids handling procedures. The capital costs

    for these changes were usually small to moderate and the payback period was usually less than

    five years.

    All of the wastewater treatment plants included in the study were more thart 20 years old, and

    there have been technological advances since the original electrical equipment was installed. At

    several sites the study recommended replacing older electrical motor and drive systems with

    more efficient units. The capital costs of these recommendations were moderate and the payback

    period was usually less than five years.

    S-2

  • Excess capacity in one or more unit process was identified as contributing to increased energy

    consumption at many of the sites. Excess blower capacity as a result of upgrading from coarse- to

    fine-bubble aeration, excess aeration basin volume, and excess solids stabilization capacity were

    identified. Recommendations included taking basins out of service, downsizing equipment, and

    providing intermediate storage between processes to allow for different loading rates. At two of

    the sites the study recommended that the facility use the excess capacity in the solids handling

    and treatment systems to treat hauled sludge from neighbouring facilities as an income

    generating opportunity. The capital costs of these recommendations varied from very low (taking

    units out of service) to high (constructing hauled sludge receiving facilities). The payback period

    varied from less than one year to more than 10 years.

    This project used a combination of process audit, energy audit, and electrical submetering

    techniques to identify low-capital-cost methods of improving the performance and energy

    efficiency of six WWTPs in New York State. The plants were selected to provide a representative

    sample in terms of size, location, and treatment technologies. The plants were operating well

    within their effluent discharge requirements and provided good to excellent levels of treatment.

    One of the primary objectives of the study was to determine if this approach is an effective

    method of reducing WWTP operating costs and improving WWTP performance. There were

    several advantages to this approach:

    • Real-time data provides a greater understanding of the dynamic response characteristics

    of the treatment processes. The impact of energy conservation recommendations on

    treatment performance is easier to foresee if the real-time process performance data is

    available.

    • Measured electrical consumption data is required to determine the potential energy

    savings associated with implementing ECOs. Using a single power draw measurement

    may over- or underestimate the potential savings.

    • Real-time process and performance data is required to evaluate theoretical versus

    achievable energy savings associated with implementing ECOs. The data can also

    indicate methods of increasing the achievable savings.

    8-3

  • • Discrepancies or unexpected results in the data generated are good indicators of potential

    areas of improved performance that may be overlooked using more traditional

    approaches.

    The audit approach, which consists of a systematic and rigorous methodology for oqtaining

    accurate performance information, is an appropriate tool for identifying ECOs at existing

    wastewater treatment facilities. Online process data, equipment performance characteristics, and

    electrical submetering information are required to predict the effects of implementing ECOs. The

    conceptual approach used for this project was quite simple. Measure what you have, what you

    are using, and the performance achieved, and base decisions for improving performance

    efficiency on the measured data.

    5-4

  • Section 1

    INTRODUCTION

    PROJECT OBJECTIVES

    The New York State Energy Research and Development Authority (NYSERDA), the Empire State

    Electric Energy Research Corporation (ESEERCO), and the Electric Power Research Institute

    (EPRI) jointly funded an investigation of New York State wastewater treatment plants (WWTPs).

    The purpose of the investigation was to determine if process optimization of the WWTPs without

    major capital expenditure and the identification of potential energy-saving measures within

    existing facilities were effective methods of reducing plant operating costs and improving plant

    performance.

    The project was conducted in two phases. Phase I, which was completed in 1995, consisted of

    screening 80 potential WWTPs to identify six test sites for the field monitoring portion of the

    project. The intent was to provide a representative sample of the WWTPs in New York State in

    terms of size (flow rate), treatment technologies, and sludge management practices.

    Phase 2 used a combination of operating data review, online process monitoring, offline

    sampling, electrical submetering, and specific performance efficiency testing techniques to

    quantify the treatment provided and energy consumed on a unit process and whole plant basis.

    The overall objectives of the field testing were to:

    • quantify the energy consumption and process performance on a process

    by-process and whole plant basis at each WWTP;

    • examine the dynamic interrelationships among the various unit

    processes at each site, including loading response and its effect, on unit

    process and whole plant energy use, performance, and treatment

    efficiency;

    • identify areas for process improvements including making changes to

    treatment process control and operating procedures or installing electro

    technologies, and low-capital-cost equipment changes, to improve

    energy efficiency, treatment performance, and capacity at each WWTP.

    1·1

  • TEST METHODOLOGY

    The facility performance was evaluated in detail over a four- to six-week period. A minimum of

    12 months of operating data was reviewed to determine the current baseline unit process loading

    and performance and energy consumption pattern, and to identify factors that may be limiting

    the facility performance.

    The offline sampling consisted of collection and analysis of 24-hour composite samples from

    upstream and downstream of each unit process supplemented with grab samples from various

    locations. The analytical results were used to determine unit process loading and performance on

    a daily basis and to characterize recycle streams through the plant. The offline sampling also

    provided a quality control check for the online process data collected.

    Real-time data was collected from the existing and temporary online process monitoring

    equipment. The types of online process data collected varied between sites. In general, the data

    included wastewater flow, air flow, aeration basin dissolved oxygen concentration, mixed liquor

    concentration, return activated sludge flow, and effluent suspended solids concentration. The

    online process data was used to quantify the dynamic load/response characteristics of the unit

    processes.

    The whole-facility energy use was recorded on a IS-minute basis by the local utility. The energy

    use of the process-related equipment was monitored with temporary submetering equipment

    installed during the field test period. For motors where the load was not expected to vary

    significantly during use, time-in-use loggers were installed to record off!on events. Current

    transducers and voltage-potential wires were installed at the breaker panel for motors that

    experience significant variations in loading during normal operation.

    Specific performance tests were conducted on the major energy end users to obtain in situ

    performance data. Performance testing consisted of oxygen transfer efficiency testing, digester

    tracer testing, and IIwire to waterll efficiency testing of the major process equipment.

    The detailed results of the field work are presented in a separate site report for each facility.

    Copies of the individual site reports are available through NYSERDA. This report presents a

    summary of results from the six wastewater treatment plants included in the study.

    1·2

  • TEST SITES

    Table 1-1 lists the six municipal wastewater treatment plants and the corresponding treatment

    technologies included in the study. The facilities ranged in size from 0.5 mgd to 90 mgd capacity

    and included two small « 2 mgd), two medium (2 to 10 mgd), and two large (> 10 mgd) plants.

    All of the sites provided a minimum of secondary level treatment. The two smaller sites also

    provided tertiary treatment.

    TABLE 1-1

    SIX MUNICIPAL WASTEWATER TREATMENT PLANTS

    INCLUDED IN THE TEST PROGRAM

    Name Capacity Liquid Treatment (mgd) Processes

    Sodus Village 0.5 Grit channel WWTP Primary clarification

    Trickling filter Extended aeration Fine bubble aeration Tertiary sand filter

    Village of Goshen 1.5 Grit channel WWTP Primary clarification

    Trickling filter Treatment wetlands Chlorination

    Marsh Creek 4.0 Aerated grit removal WWTP Primary clarification

    Complete mix AS Panel membrane aeration Chlorination

    Arlington STP 4.0 Aerated grit removal Primary clarification Plug flow AS Coarse bubble aeration Chlorination

    Bergen Point 30 Scavenger waste facility WWTP Raw sewage pumping

    Aerated grit removal Primary clarification Step feed AS Panel membrane aeration Chlorination

    Yonkers Joint 90 Aerated grit removal WWTP Primary clarification

    Plug flow AS Coarse bubble cross roll

    aeration Chlorination

    Solids Treatment Processes

    Anaerobic digestion Sludge drying

    Anaerobic digestion Sludge drying

    Gravity thickening Anaerobic digestion Beltpress dewatering Composting

    Gravity thickening Beltpress dewatering Fluidized bed incineration

    Gravity thickening Gravity belt thickening Belt press dewatering Multiple hearth incineration

    Gravity thickening Dissolved air flotation Anaerobic digestion Centrifuge dewatering

    1-3

  • Section 2

    WASTEWATER TREATMENT PLANT CONFIGURATIONS AND PERFORMANCE

    The six wastewater treatment plants included in the study were chosen to provide a representative

    sample of the range of facility sizes, locations, and treatment technologies currently operating in

    New York State. The following sections provide a brief description of each facility, its recent

    perfonnance history, and the field test procedures and results.

    Field testing consisted of offline sampling, online monitoring, and perfonnance testing of specific

    equipment and processes. The offline sample results are based on 24-hour composite samples and

    grab samples taken at various points in the process. The online data consists of data measured from

    temporary instruments installed for the test period, supplementing the data collected by the existing

    pennanent online metering equipment at each site.

    SODUS VILLAGE WWTP

    Figure 2-1 presents a flow schematic and Table 2-1 summarizes the unit processes of the Sodus

    Village WWTP. The rated capacity of the WWTP is 0.5 mgd and the current measured average-day

    flow is 0.38 mgd. The WWTP discharge permit has seasonal limits for 5-day biochemical oxygen

    demand (BODs), total suspended solids (TSS), and ammonia-nitrogen (NH,-N). During the summer

    months the criteria are 5 mg/L, 10 mg/L, and 2.0 mg/L, for BODS' TSS, and NH,-N, respectively.

    The dissolved oxygen (DO) concentration of the final effluent must be greater than 7 mg/L. During

    the winter months the criteria are 25 mg/L and 30 mg/L for BODs and TSS, respectively. There is no

    NH,-N discharge criterion for the winter months.

    Raw wastewater flows by gravity through a grit channel prior to entering the primary clarifier. Grit

    removed from the wastewater in this channel is disposed of offsite. The degritted wastewater flows

    by gravity to a single primary clarifier. Filter backwash from the tertiary sand filter, digester

    supernatant, and sludge concentrator supernatant is mixed with degritted wastewater upstream of

    the primary clarifier. Sludge from the primary clarifier is pumped to the sludge well.

    Following primary clarification, the wastewater flows by gravity to the trickling filter. Trickling filter

    effluent is pumped back through the filter as recycle. Alternatively, the trickling filter can be

    bypassed, in which case primary effluent flows by gravity directly to the aeration basin.

    2·1

  • SAND

    04/JLW"1

    RAW BACKWASH ~ BLOWERS

    0-=-TRICKUNG FILTER BYPASS AERATION SECONDARY

    TRICKLING BASiN CLARIFIER FILTER

    I I I

    .... : 0 : II:: :0 :0. DID 0 00 • 0000000 DODoO Q

    --00.0 0 0 III_ODD

    I FILTERI I I AERATION BASIN BYPASS : __ 1 -' I I I I

    ~R

    =:llI 0-__'-_~I __ =~~"-=--im ___ ISUPERNATANT

    RETURNS ~_________________ I----------------

  • TABLE 2-1

    SODUS VILLAGE WWTP - SUMMARY OF UNIT PROCESSES

    Unit Process Number Description

    Primary clarifier 1 Area =616 ft2

    Volume =32,224 gal.

    Diameter =28 ft

    Trickling filter 1 Media depth =5 ft 3 in.

    Diameter =35 ft

    Aeration basin 1 Area =2,640 fe

    Depth =15 ft

    Volume =296,208 gal.

    Diffusers Fine bubble

    Rubber sock

    Submergence depth =14 ft

    Aeration blowers 5 lOhpeach

    Secondary clarifier 1 Area =616 ft2

    Volume =32,224 gal.

    Diameter =28 ft

    Tertiary sand filter 1 Area =352 ft2 total

    2 blowers at 10 hp each

    Digester 1 Volume =95,000 gal. Sludge concentrator 1 Screw conveyor

    The trickling filter effluent is pumped to the aeration basin. Air is supplied through fine-pore rubber

    sock diffusers by five 10-hp blowers. There is also a bypass of the aeration basin that sends trickling

    filter effluent flow directly to the secondary clarifier. Bypassing is done to reduce the solids loading

    on the secondary clarifier during high flow conditions. The solids concentration in the trickling filter

    effluent is significantly less than the solids concentration in the aeration basin. The operator

    estimates that approximately 50 percent of the total plant flow bypasses the aeration basin.

    The wastewater flows by gravity from the aeration basin to the secondary clarifier. Sludge from the

    secondary clarifier is removed from the bottom of the clarifier, the return activated sludge (RAS) is

    returned to the head of the aeration basin, and the waste activated sludge (WAS) is pumped to the

    sludge well. The RAS and WAS flow rates are not measured.

    Secondary effluent is pumped to the effluent sand filter. Backwash operations of the filter are

    controlled by level sensors and each cell is backwashed at least once a day. There are two 10-hp

    backwash blowers. One blower operates continuously to provide reaeration of the filter effluent.

    2-3

  • Sludge is pumped from the sludge well to the anaerobic digester. The sludge is recirculated through

    a heat exchanger and is continuously mixed in the digester. The digested sludge is pumped from the

    digester to a sludge concentrator for dewatering. The dewatered sludge is disposed of offsite.

    Performance History

    The average monthly flow to the Sodus Village WWTP between January 1986 and December 1995

    was 0.34 mgd. Since 1986, the flow has been increasing at a rate of approximately 0.013 million

    gallons per year. The average monthly BODs and the TSS loads to the plant between January 1986

    and December 1995 were 495 and 470 lb/day, respectively. The average TSS and BODs

    concentrations in the raw sewage were 168 and 174 mg/L, respectively.

    When the aeration basin at the Sodus Village WWTP went online in January 1991, the final effluent

    quality improved dramatically. Prior to 1991, the average concentrations were 31 mg/L for BODs,

    23.4 mg/L for TSS, and 19.2 mg/L for ~-N. After 1991, the effluent concentrations improved to

    7.9 mg/L for BODs,S mg/L for TSS, and 3.7 mg/L for ~-N.

    During the summer months between 1991 and 1995, average monthly final effluent concentrations

    were 5.0 mg/L, 4.3 mg/L, and 1.7 mg/L, for BODs, TSS, and ~-N, respectively. These compare

    with the summer discharge criteria of 5 mg/L for BOD5' 10 mg/L for TSS, and 2.0 mg/L for ~-N.

    During the winter months the average monthly final effluent concentrations were 9.0 mg/L, 5.9

    mg/L, and 4.5 mg/L, for BOD5' TSS, and ~-N, respectively. These compare to the winter

    discharge criteria of 25 mg/L for BODs and 30 mg/L for TSS. There is no discharge criterion for

    ~-N during the winter.

    The average removal efficiencies of BODs, TSS, and ~-N for the Sodus WWTP between January

    1986 and December 1995 were 78 percent for BODs, 85 percent for TSS, and 58 percent for NH3-N.

    After 1991 the removal efficiencies improved to an average of approximately 96 percent for both

    BODs and TSS, and 82 percent for ~-N.

    The current discharge permit for the Sodus WWTP requires 85 percent removal efficiency for both

    BODs and TSS. The removal efficiency for BODs was in excess of 85 percent 95 percent of the time

    and for TSS was in excess of 85 percent 98 percent of the time.

    The mixed liquor suspended solids (MLSS) concentration for the aeration basin at the Sodus WWTP

    was 3,852 mg/L. High MLSS concentrations during the winter months of 1995 were the result of

    2-4

  • solids-handling limitations during the winter. The sludge concentrator was not in a heated facility

    and therefore the WWTP operator was not able to remove solids from the aeration basin. This

    situation has been corrected and the MLSS concentrations have since decreased.

    The average sludge volume index (SVI) for the Sodus WWTP from January 1995 to October 1996

    was 139 mL/g. The SVI is used as an indicator of the settling characteristics of a sludge. Values

    greater than 200 mL/g are associated with poorly settling sludge. The maximum SVI between

    January 1995 and October 1996 was 176 mL/g.

    The monthly average sludge volume feed to the digester was approximately 88,850 gallons, and the

    monthly average discharge from the digester was 41,150 gallons. The difference between the

    volume of sludge pumped to and the volume of sludge discharged from the digester (approxi

    mately 47,700 gallons) is the amount of supernatant returned to the head of the plant from the

    digester.

    The average monthly electrical usage for the Sodus Village WWTP between July 1995 and October

    1996 was 22,815 kWh/month, and the average monthly natural gas usage was 670 therm/month

    (1 therm = 100,000 Btu). During the winter months the natural gas consumption increased to 1,113

    therm/month. Natural gas is used to heat the digesters.

    Field Test

    The Sodus Village WWTP field test program was conducted from June 4 to June 28, 1996. Table 2-2

    presents the unit process loadings and effluent quality during the field test program and historical

    values for the facility. The hydraulic and organic loading during the field test program was similar

    to the historical data for the facility. However, the final effluent characteristics were significantly

    different. The field test final effluent characteristics were determined based on 24-hour composite

    samples collected every second day. These concentrations are likely a more accurate reflection of the

    loading and treatment provided by the Sodus Village WWTP.

    Field testing consisted of offline sampling, online monitoring, and performance testing of specific

    equipment and processes. The offline sampling results were based on 24-hour composite samples

    and grab samples taken at various points in the process. The online data consists of data measured

    from temporary instruments installed for the test period and from existing permanent metering

    equipment onsite. The temporary instruments included DO probes installed in the aeration basin, a

    solids probe in the aeration basin to measure mixed liquor suspended solids concentration, and a

    2·5

  • TABLE 2-2

    SODUS VILLAGE WWTP - SUMMARY OF UNIT PROCESS LOADING DURING FIELD TEST PROGRAM

    Unit Process Units Field Test Historical Average Maximum Average Maximum

    Loading Hydraulic Organic

    BODs BODs TSS TSS ~-N

    Mgd

    mg/L lb/d

    mg/L lb/d

    mg/L

    0.34

    126 339 172 475 NA

    0.46

    280 710 500

    1,691 NA

    0.38

    174 613 168 530 24

    0.48

    260 949 310 849 32

    Effluent Quality BODs TSS NH,.-N

    mg/L mg/L mg/L

    19 11 6.7

    40 28 19

    7.9 5

    3.7

    Primary Clarifier Area ff 616 616 Surface overflow rate gpd/ff 551 750 620 780

    Aeration Basin Volume BODs loading HRT

    fe lb / day*l,OOO fe

    hour

    39,600 8.3 21

    18 15

    39,600 NA 18.7

    NA 14.8

    MLSS concentration SVI F/M

    mg/L mL/g days·!

    3,763 NA 0.06

    4,800 NA 0.1

    3,852 139 NA

    8,904 176 NA

    Secondary Clarifiers Area ff 616 616 Surface overflow rate gpd/ff 551 750 620 780

    Tertiary Sand Filter Area ff 352 352 Hydraulic loading gpm/ff 0.66 0.9 0.75 0.95

    Digesters Primary volume Feed Discharge HRT

    gal. gal./month gal./month

    days

    95,000 44,300 30,500

    65

    95,000 88,840 41,140

    33

    solids probe in the secondary effluent well to measure secondary effluent suspended solids

    concentration. The total plant flow was measured by the existing plant flow meter. The performance

    testing consisted of oxygen transfer efficiency testing of the aeration equipment and pump

    performance tests.

    2·6

  • Table 2-3 presents a summary of the field test activities. Detailed test descriptions and results are

    presented in the Sodus Village WWTP Site Report (CH2M IDLL, 1998e).

    Sample Location

    Raw sewage

    Primary effluent

    Trickling filter effluent

    Secondary effluent

    Sand filter effluent

    Sludge concentrator supernatant

    Filter backwash

    Digester supernatant

    Raw sludge

    Digested sludge

    Digester profile (5 ports)

    MLSS

    RAS

    Location

    Aeration basin

    Secondary effluent

    Raw sewage

    Location

    Aeration basin

    Pumps

    TABLE 2-3 SODUS VILLAGE WWTP - FIELD TEST PROGRAM

    Offline Sampling Program

    Frequency Type of Sample Analysis

    2nd day 24h cBOD5, TSS, VSS

    2nd day 24h cBOD5I ~-N, TKN, TSS, VSS

    2nd day 24h cBOD5, NH3-N, TKN, TSS, VSS

    2nd day 24h cBOD5I ~-N, TKN, TSS, VSS

    2nd day 24h cBOD5I TSS, VSS

    1I operation grab cBOD5I TSS, VSS

    1I week grab cBOD5, TSS

    grab cBOD5I TKN, TSS

    grab TS, TVS

    grab TS, TVS

    grab TS, TVS

    2/week grab TSS, VSS

    2/week grab TSS

    Online Monitoring Program

    Type Data

    Dissolved oxygen 4 temporary meters

    Suspended solids 1 temporary meter

    Suspended solids 1 temporary meter

    Flow 1 existing meter - flume

    Performance Testing

    Type Analysis

    Offgas Oxygen transfer efficiency

    Performance "Wire to water" efficiency

    2·7

  • The major conclusions from the field study period for the Sodus Village WWTP were:

    • The average BODs and TSS removal efficiencies were 25 and 38 percent,

    respectively. Typical BODs and TSS removal efficiencies for primary clarifiers are

    35 and 65 percent, respectively. The poor performance was likely due to solids

    buildup in the clarifier. The solids were removed once or twice per week.

    • The trickling filter was providing only minimal treatment under current loading

    conditions.

    • The aeration basin operated as an extended aeration facility. The existing

    aeration equipment was able to maintain the DO concentration over 1.0 mg/L at

    all times. The average DO was greater than 3.0 mg/L for significant periods

    during the study.

    • The measured standard oxygen transfer efficiency (SOTE: 20oe, a mg/L ~O) of the existing aeration equipment was 21 percent.

    • Pressure relief valves on the air piping were open between the aeration blowers

    and the aeration basin, resulting in a constant venting of pressurized air to

    atmosphere.

    • The secondary clarifiers were not performing as expected. This was likely due to

    a solids flux failure and bottlenecks in removing settled solids from the clarifier.

    • The secondary effluent solids concentration regularly increased during the day.

    The pattern observed indicated a solids flux limitation in the clarifier. The solids

    removal mechanisms and RAS pumps should be upgraded if the secondary

    clarifier remains in service.

    • The NH3-N concentration in the final effluent averaged 6.7 mg/L, which is

    greater than the effluent discharge requirement of 2.0 mg/L. This was likely the

    result of directing flow from the trickling filter to the secondary clarifier, thus

    bypassing the aeration basin. The operators bypassed the aeration basin to

    reduce the solids loading to the secondary clarifier. The trickling filter did not

    provide nitrification under current loading conditions.

    2·8

  • • The check valves on the secondary pumps were not operating correctly, resulting

    in pumped secondary effluent being returned to the wet well through the

    standby pump.

    • The biogas collection system for the anaerobic digester was inoperable. The

    digester cover was corroded and leaked biogas to the atmosphere. The gas

    collection system was plugged and the digester was venting through the

    emergency overflow vent. This represented a significant health and safety

    concern for the site, as well as a loss of useable energy.

    VILLAGE OF GOSHEN WWTP

    Figure 2-2 presents a flow schematic and Table 2-4 summarizes the unit processes of the Village of

    Goshen WWTP. Wastewater, consisting mainly of domestic, institutional, and commercial sewage,

    flows by gravity to the WWTP. The design capacity of the WWTP is 1.5 mgd and the current

    measured average day flow is 1.23 mgd. The discharge criteria for the facility are 25 mg/L BODs

    and 25 mg/L TSS.

    The wastewater flows by gravity through a manually cleaned bar screen and grit chamber to a

    distribution box that divides the flow among three primary clarifiers. The screenings and grit are

    transported to a landfill. After primary clarification, the wastewater flows by gravity through two

    trickling filters to the trickling filter wet well, where it is pumped to the secondary clarifiers.

    Wastewater from the secondary clarifiers flows by gravity through the chlorine contact chamber to

    the two effluent polishing lagoons. The effluent polishing lagoons are operated in series. The treated

    effluent is discharged into the Rio Grande Creek.

    Solids from the secondary clarifiers are pumped on a continuous basis to the primary clarifier

    distribution box for co-settling in the primary clarifier. The combined sludge from the primary

    clarifier is pumped twice per day to the primary anaerobic digester. A dual fuel gas boiler is used to

    heat the digester contents. The digester is mixed for approximately 16 hours per day with a digester

    recirculation pump. The primary digester mixing pumps are switched off for approximately eight

    hours each day when the combined sludge is pumped into the primary digester.

    Digested sludge flows by gravity from the primary to the secondary digester. Supernatant from the

    secondary digester flows by gravity to the primary clarifier distribution box. Digested sludge is

    2·9

  • ../JUN/U

    BAR

    SCREENS

    TRICKLING .fB!.MAIr! FILTER SECONPARY CHLORINE ~

    GRIT CHAMBER CLARIFIER CLARifiER ~ SYSTEM BAY1

    SEWAGE

    I I I I I I I I

    FILTER RECYCLECOMMINUTOR I I I I I I

    DISPOSAL ~------:--------------~~~~~~~~~=------------j.----------- ------- I DIGESTERI SUPERNATANT ...----'. I I I I

    I SlUDGE _~--------~ .1l--e----

    --, r- I I SLUDGE DRYING

    BEDSl$~ DISPOSAL SOUDS • I I ~DlOESTE~ •-E1 ~~~~~~ L10UID

    SECONDARY ~ DIGESTER DRYING BED SUPERNATANT

    flQUFE 2-2 GOSHEN W.W.T.P.

    PROCESS ROW SCHEMATIC 2OOK1a1OD.OJ PfUClLDWG

    C> ~

    http:2OOK1a1OD.OJ

  • TABLE 2-4

    VILLAGE OF GOSHEN WWTP - SUMMARY OF UNIT PROCESSES

    Unit Process Number Description

    Bar screen 1 Manual cleaned

    Grit chamber 1 Circular

    Primary clarifier 2 Area = 768 fe (per unit) 64 ft x 12 ft; 7.25 ft deep

    1 Area = 960 fe (per unit) 60 ft x 16 ft; 7 ft deep

    Trickling filter 2 Area = 2,827 fe (per unit) Volume = 19,792 fe Dia. = 60 ft; rock 7 ft deep

    Secondary clarifier 2 Area = 936 fe 52 ft x 18 ft; 6.5 ft deep

    Chlorine contact chamber 1 Area = 828 fe Volume = 4,140 fe

    Polishing lagoons 1 Area = 10.5 acres Volume = 3.85 million gal.

    1 Depth 12 to 15 inches Area = 10.5 acres Volume = 15.4 million gal. Depth 4.5 feet

    Digester 1 Primary digester - fixed roof Max volume = (25,450 fe) 190,400 gal. Dia. = 45 ft; SWD = 16 ft

    1 Secondary digester - floating roof Max volume = (35,000 fe) 261,800 gal. Dia. = 45 ft; SWD = 19 ft

    Sludge drying beds 4 Area =11,250 fe (per unit)

    removed from the secondary digester every 45 to 60 days. Approximately 25 to 30 cubic feet of

    digested sludge are removed from the secondary digester and placed on sludge drying beds. The

    drainage from the sludge drying beds is pumped to the primary clarifier distribution box.

    Performance History

    The average-day flow for the Village of Goshen WWTP for June 1995 to June 1996 was 1.23 mgd.

    However, the flow is highly variable. During dry weather periods (June through September 1995) it

    averaged between 0.7 and 1.0 mgd. During wet weather it increased to over 3.0 mgd. The flow

    2-11

  • distribution pattern indicated there was a significant contribution from infiltration/inflow in the raw

    sewage flow to the plant.

    The historical TSS and BODs loadings to the Village of Goshen WWTP averaged 1,350 and 1,190

    lb/day, respectively. The Sorrento cheese factory is the only major industrial source in the sewerage

    area. During the first quarter of 1995, Sorrento's pretreatment system (activated sludge) experienced

    process upsets, resulting in an increase in the organic load to the plant. As a result, the TSS and

    BODs loadings were significantly greater during the first quarter of 1995. The average TSS and BODs

    concentrations for January, February, and March 1995 were 241 and 173 mg/L, respectively. The

    average TSS and BODs concentrations for the 19-month period of record examined were 135 and 124

    mg/L, respectively.

    The TSS and BODs concentrations in the final effluent from the Village of Goshen WWTP from

    January 1995 to June 1996 were 3.8 and 2.8 mg/L, respectively. This is well below the effluent

    discharge requirement of 25 mg/L for BODs and 25 mg/L for TSS. The average TSS and BODs

    removal efficiencies were 96.6 percent and 97.2 percent, respectively. The WWTP provides a very

    high standard of treatment. The BODs and TSS removal efficiencies were greater than 90 percent for

    more than 98 percent of the time over the 18-month period examined.

    The average daily volume of sludge pumped to the primary digester was 8,083 gallons per day. The

    solids concentration in the co-settled sludge was not measured. The flow control gate on the sludge

    withdrawal line from each clarifier is opened manually.

    The average electrical consumption from November 1994 to July 1995 was 870 kWh per day. The

    energy use remained significantly higher during the winter months. This was likely due to the

    increase in flow rate and electrical heating requirements during the winter.

    The average propane consumption from 1993 to 1996 was 9,925 gallons per year. Propane is used to

    heat the primary digester. During the summer months of 1993 and 1994, biogas collected from the

    primary digester was used for most of the heating requirements. During 1995 and 1996, the WWTP

    was not able to collect biogas and therefore average propane consumption increased from 20.3 to

    34.1 gallons per day.

    2·12

  • Field Test

    The Village of Goshen WWTP field test program was conducted from July 16 to August 15,1996.

    Table 2-5 presents a comparison between the unit process loadings and effluent quality during the

    field test program and historical values for the facility. The hydraulic loading to the treatment plant

    was similar to the historical values. However, the raw sewage BODs and TSS concentrations were

    significantly lower. The average BODs and TSS concentrations during the test period were 67.2 and

    88.9 mg/L, respectively. Therefore, the organic loading on the Village of Goshen WWTP was

    approximately half of the historical average for the facility.

    TABLE 2-5 VILLAGE OF GOSHEN WWTP - SUMMARY OF UNIT PROCESS LOADING DURING FIELD TEST PROGRAM

    Unit Process Units Field Test Historical

    Average Maximum Average Maximum

    Loading

    Hydraulic Mgd 1.16 3.28 1.23 3.41

    Organic

    BODs Mg/L 67.2 96 124 Ibid 571 829 1,193 2,203

    TSS mg/L 88.9 134 135 Ibid 807 1270 1,352 2,841

    Effluent Quality

    BODs Mg/L 1.9 3.0 2.8

    TSS Mg/L 3.2 6.0 3.8

    Primary Clarifier

    Surface overflow rate Gpd/£e 464 1,314 492 1.362

    Trickling Filter

    Surface wetting rate Gpm/fe 0.14 0.40 0.15 0.42

    BOD. loading rate a Ibid 1,000fe 7.8 16.6 19.6 36.2

    Secondary Clarifiers

    Surface overflow rate Gpd/fe 620 1,752 657 1,822

    Chlorine Contact Chamber

    Hydraulic residence time Min 38 14 36 13

    Effluent Polishing Lagoons

    Lagoon 1 HRT Day 3.3 1.2 3.1 1.1

    Lagoon 2 HRT Day 13.3 4.7 12.5 4.5

    Total Day 16.6 5.9 15.6 5.6

    Primary Digester

    Hydraulic residence time b Day 23.8 23.5

    VS loading C VSSlb/day 400

    Notes:

    a Based on primary effluent average and maximum BODs of 311 and 658lb/day, respectively

    b Based on measured sludge pump rate

    C Based on mass balance around the primary clarifier

    2·13

  • Field testing consisted of offline sampling, online monitoring, and performance testing of specific

    equipment and processes. The offline sampling results were based on 24-hour composite samples

    and grab samples collected at various points in the process. The online data consisted of data from

    existing flow metering equipment supplemented with a temporary solids concentration meter in the

    secondary clarifier effluent. The performance testing consisted of stress testing of the primary and

    secondary clarifiers, a mixing evaluation of the primary digester, and performance testing of the

    secondary effluent pumps. Table 2-6 summarizes the work done. Detailed test descriptions and

    results are presented in the Village of Goshen WWTP Site Report (CH2M HILL, 1998c).

    TABLE 2-6

    VILLAGE OF GOSHEN WWTP - FIELD TEST PROGRAM

    Offline Sampling Program

    Sample Location Frequency Type of Sample Analysis

    Raw sewage 2nd day 24h cBODs' TSS, VSS, ~-N, BODs, N02-N, N03-N, TKN

    Primary effluent 2nd day 24h cBODs' NH3-N, TKN, TSS, VSS, BODs, Nq-N, N03-N

    Trickling filter effluent 2nd day 24h TSS, VSS, cBODs' BODs, ~-N, N02-N, N03-N

    Secondary effluent 2nd day 24h cBODS' ~-N, TKN, TP, TSS, VSS, BODS' N02-N, N03-N

    Digester supernatant l/week grab cBODS' TKN, TP, TSS

    Co-settled sludge 2/week grab TSS, VSS

    Online Monitoring Program

    Location Type Data

    Secondary effluent Flow 1 existing meter - weir Suspended solids 1 temporary meter

    Performance Testing

    Location Type Analysis

    Primary clarifier Stress test Capacity

    Secondary clarifier Stress test Capacity

    Pumps Performance "Wire to water" efficiency

    Digester Profile Mixing

    2·14

  • The main conclusions from the field study of the Village of Goshen WWTP were:

    • Primary clarifier performance was poorer than expected. This was partly due to

    poor hydraulic distribution among the three clarifiers.

    • The secondary sludge pumps operated continuously, recycling an excessive

    amount of water through the plant.

    • The secondary pump on/off operation resulted in frequent pump cycling and

    continual small hydraulic perturbations to the secondary clarifier. This had a

    significant negative impact on clarifier performance.

    • The hydraulic throughput of the plant was less than 3.5 mgd. Significant

    hydraulic bottlenecks occurred at the plant headworks, between the primary

    clarifier and trickling filter, and at the chlorine contact chamber outfall.

    • The measured capacity of the primary clarifiers was 1.5 mgd. The capacity could

    be increased by improving the flow distribution between the clarifiers.

    • The measured capacity of the secondary clarifiers was 3.0 mgd. The secondary

    clarifier performance was reduced due to the on/off operation of the secondary

    pumps.

    MARSH CREEK WWTP

    Figure 2-3 presents a flow schematic and Table 2-7 summarizes the unit processes of the Marsh

    Creek WWTP. Wastewater flows by gravity to the WWTP and consists mainly of domestic and

    commercial sewage. Hauled leachate is brought to the plant and mixed with the raw sewage

    upstream of the primary clarifier. The rated capacity is 4.0 mgd and the average day flow is 3.35

    mgd. There are no bypass structures. All wastewater generated by the catchment area must be

    treated by the plant. The discharge criteria for the facility are 30 mg/L BODs, 30 mg/L TSS, and 1.0

    mg/L total phosphorus (TP).

    The wastewater flows by gravity through the primary clarifiers, aeration basins, and the secondary

    clarifiers, and receives chlorination before discharge. Primary sludge pumped from the primary

    2-15

  • 04/JUN/O.

    CHLORINATION ..ERl.MARY AE~ A~N S&E1lN~ARYCLARifiER ~ I RIIER

    RAW SEWAGE PRIIiARY EFFLUENT

    D 0 0 0 0 ••• °000° 0 1 OODODOOOOOOo·ooo.:oooo --lI aD OOOClOO~O o:~.: 0°0"0000°••SUPERljATANT ,RETURNS

    I , I , IPRIIiARY SWDGE : I I

    I I I

    I

    I

    1""---------- --""'8--' ~----------~---~~~~~~~~-~!:~-I--------------f I I

    I I

    I I

    I ,...-----I ----------------------------------~---~~~~~~~~~~~~--I--------------; I I

    I I

    I I I COMPOST

    I AMENDMENTI

    I

    I

    b ,-I I I II I OFT-GAS I II ,III

    I I

    ,

    I

    I

    T~,~~~lJRI t.I ________ _ I DISPOSAL

    BELT FI~ER :

    I

    I

    ~ ,I

    I .>T=r< l tI _____ _

    CLASSIFIER L----H-

    SECONpARY COMPOSTL._____ sW! ~DIGESTER PI AL

    SOUDS

    UQUID

    AGUREH MARSH CREEK W.W.T.P.

    PROCESS A.OW SCl-EMAlIC :1(101(10100.05 PIa211JYNG

    COMPOST

    STORAGE

    .fIID.Wrl DIGESTER

    ~ '"

    http:1(101(10100.05

  • TABLE 2-7

    MARSH CREEK WWTP - SUMMARY OF UNIT PROCESSES

    Unit Process

    Primary clarifier

    Aeration basin

    Diffusers

    Aeration equipment blowers

    Secondary clarifier

    Gravity thickener

    Digester

    Belt filter press

    Compost facility

    Number Description

    2 Area = 707 fe (per unit)

    Volume = 211,792 gal. (total)

    Diameter = 30 ft

    2 Area = 3,384 fe (per unit)

    Volume = 750,000 gal. (total)

    Depth = 14' 5"

    Fine bubble Area per diffuser = 48 ft2 Number per tank = 38 Submergence = 13' 11"

    2 60hp Variable speed, manually controlled

    1 100hp Variable speed, manually controlled

    2 Area = 707 ft2 (per unit)

    Volume = 211,792 gal. (total)

    Diameter = 30 ft

    2 Volume = 77,141 gal. (per unit) Dia. = 25 ft2 Side wall depth = 16.5 ft

    1 Primary

    Volume = 500,000 gal.

    1 Secondary

    Volume = 500,000 gal.

    1 Width =6ft

    1 Capable of producing 2.5 dry tons of finished product per day

    clarifiers passes through a grit classifier and then is pumped to a gravity thickener. Grit removed by

    the classifier is disposed of offsite.

    Air is supplied to the aeration basin by one 100-hp and two 60-hp blowers through fine bubble

    membrane panel diffusors. WAS removed from the secondary clarifier is pumped to a gravity

    thickener prior to being pumped to the primary digester.

    There is one primary digester and one secondary digester. Sludge is fed to and removed from the

    digesters by pumps. Hot water circulation is used to maintain the temperature in both digesters.

    2·17

  • Methane gas produced by the digesters is used as the fuel source for heating, supplemented with

    natural gas on an as-needed basis.

    Sludge from the secondary digester is pumped to a belt filter press (BFP) for dewatering. Filtrate

    from the BFP is fed back to the headworks of the plant. Dewatered sludge is moved by conveyor

    from the BFP to the compost facility. The compost facility is a batch feed facility. Wood chips are

    added to the sludge as an amendment material prior to composting. Three local businesses are

    contracted to purchase the compost produced by the WWTP for use as a soil conditioner in

    agricultural and horticultural activities.

    Performance History

    The average-day flow to the Marsh Creek WWTP between January 1995 and May 1996 was 3.35

    mgd. There is a pronounced seasonal variation in flow, with low flows occurring during the dry

    weather period of June to September. The minimum and maximum day flows for the period were

    1.75 and 12 mgd, respectively. The hydraulic peaking factor was over 4.0. This high value indicates

    an inflow and infiltration problem within the collection system.

    The average BODs and TSS concentrations in the raw sewage flow to the WWTP for January 1995 to

    May 1996 were 228 and 176 mg/L, respectively. The BODs concentration was reasonably consistent

    over the period of record, but the TSS concentration fluctuated widely. The high BODs and the TSS

    concentrations can be attributed to the introduction of leachate and hauled waste to the raw sewage

    at the headworks of the plant as well as sewage from local food processing plants. The average ortho

    phosphate (P04) concentration of the raw sewage between January 1995 and May 1996 was 2.7

    mg/L. The average BODs and TSS loads to the plant were 6,032 lb/day and 4,908 lb/day,

    respectively.

    The average final effluent concentrations for BODs, TSS, and P04 were 22 mg/L, 10 mg/L, and 0.4

    mg/L, respectively. The average concentrations for BODs and TSS are below the discharge criteria of

    30 mg/L for both parameters. The average removal efficiencies were 90 percent, 90 percent, and 82

    percent for BODy TSS, and P04' respectively.

    The average MLSS concentration for the aeration basins at the Marsh Creek WWTP from January

    1995 to May 1996 was 2,275 mg/L. The average solids residence time (SRT) for the WWTP was 3.9

    days. The SRT was less than 6 days for over 95 percent of the time. The average food to

    2·18

  • microorganism (F/Mv) ratio, based on the ratio of BODs loading to the aeration basin and the mixed

    liquor volatile suspended solids (MLVSS) concentration, was 0.31 dail.

    The RAS flow rate for the Marsh Creek WWTP is controlled by two single-speed pumps, each rated

    for a capacity of 1 mgd. The flow is not measured but can be controlled by adjusting the pump

    speed setting.

    The average SVI was 84 mL/g. The low SVI indicated a very well-settling sludge.

    The percentages of total dry solids that were volatile for both the raw and digested sludge were 69

    percent and 55 percent, respectively. The volatile destruction in the primary digester was 45 percent.

    The average hydraulic residence time (HRT) of the primary digester was 42 days.

    The BFP is used to dewater the digested sludge prior to composting. The average percentage of

    solids of the digested sludge feed to and from the BFP was 2.95 percent and 21 percent, respectively.

    The average monthly electrical usage for the Marsh Creek WWTP was 124,235 kWh between

    January 1995 and May 1996. There appeared to be a trend of increasing electrical usage by the

    WWTP over the 15-month period. This was likely due to increased influent flow and increased

    organic load to the aeration basin.

    Field Test

    The Marsh Creek WWTP field test program was conducted from May 28 to June 28,1996. Table 2-8

    presents a comparison between the unit process loadings and effluent quality during the field test

    program and historical values for the facility. The unit process loadings were similar to historical

    values.

    Field testing consisted of offline sampling, online monitoring, and performance testing of specific

    equipment and processes. The offline sampling results were based on 24-hr composite samples and

    grab samples taken at various points in the process. The online data consists of data from permanent

    plant monitoring equipment supplemented with temporary instruments. The following parameters

    were measured using permanent instrumentation: plant flow, RAS flow, WAS flow, and air flow.

    The temporary instruments included DO probes and an MLSS probe in the aeration basins.

    Performance testing included oxygen transfer efficiency testing of the aeration equipment and a

    2·19

  • TABLE 2-8

    MARSH CREEK WWTP - SUMMARY OF UNIT PROCESS LOADING DURING FIELD TEST PROGRAM

    Unit Process Units Field Test Historical

    Average Maximum Average Maximum

    Loading Hydraulic Organic

    BODs

    TSS

    Mgd

    Ibid mg/L Ibid

    mg/L

    3.63

    6,015 199

    7,255 240

    12.64

    NA 282 NA 425

    3.35

    6,032

    4,908

    12

    9,762'

    13,026'

    Primary Clarifier (1,414 ff) Surface overflow rate Gpd/fe 2,567 8,939 2,369 8,486

    Aeration Basin (200,520 fe) BODs loading rate MLSS concentration

    lbI d per 1,000 fe mg/L

    17.0 1,942

    33.5 2,340

    18.7 2,275

    Secondary Clarifiers (1,414 fe) Surface overflow rate Solids loading rate

    Gpd/fe lb/hper fe

    2,567 2.7

    8,939 3.9

    2,369 1.9

    8,486 6.7

    Belt Filter Press Solids concentration in Solids concentration out

    % %

    2.7 23.2

    2.9 21

    Note: Maximum values are 95th percentile values from historical review.

    tracer test on the primary digester. Table 2-9 presents a summary of the field test activities. Detailed

    test descriptions and results are presented in the Marsh Creek WWTP Site Report (CH2M HILL,

    1998d).

    The major conclusions from the field study of the Marsh Creek WWTP were:

    • The organic loading to the Marsh Creek WWTP was highly variable. This was

    likely the result of the hauled leachate and industrial wastewater received at the

    site.

    • The increase in organic loading that started Monday mornings had a negative

    impact on the DO concentration in the aeration basins. The DO was less than 1.0

    mg/L for most of the day and recovered at night and on the weekends. BOD

    2·20

  • TABLE 2-9

    MARSH CREEK WWTP - FIELD TEST PROGRAM

    Offline Sampling

    Sample Location Frequency Type of Sample Analysis

    Raw sewage Daily 24h CBODs, TSS, VSS, TP

    Primary effluent Daily 24h CBODs, NJ\-N, TSS, VSS, TP

    Secondary effluent Daily 24h CBODS' TKN, TSS, TP, N03-N, N02-N, NH3-N

    Gravity thickener l/week grab TS/TSS, VSS info & eff.

    Gravity thickener l/week grab CBODS' TS/TSS, TP, TKN recycle

    Belt press in & out l/week grab TS

    BFP filtrate l/week grab TKN, TP, cBODs, TSS, NJ\-N

    MLSS 2/week grab TSS, VSS

    RAS 2/week grab TSS

    Leachate NA grab CBODS' NJ\-N, TSS, VSS

    Online Monitoring Program

    Location Type Data

    Raw sewage Flow 1 existing meter - magmeter

    RAS Flow 2 existing meters - magmeter

    WAS Flow 1 existing meter - magmeter

    Air Flow 1 existing meter - orifice plate

    Aeration basin Dissolved oxygen 5 temporary meters Solids (MLSS) 1 temporary meter

    Performance Testing

    Location Type Analysis

    Aeration basin Offgas Oxygen transfer efficiency

    Digester Tracer Mixing

    breakthrough occurred occasionally. Final effluent concentrations were greater

    than 60 mg/L.

    • The measured standard oxygen transfer efficiency (SOTE: 20°C, 0 mg/L DO) of

    the membrane panel aeration system was 18 percent.

    2-21

  • • Marsh Creek WWTP provided partial nitrification during the first two weeks of

    the study period, and almost complete nitrification during the second two weeks.

    The switch from partial to full nitrification did not have a negative impact on the

    effluent quality.

    • Hydraulic loading increased rapidly during storm events, from an average of

    3.35 mgd to 12 mgd. However, the sudden increase in flow did not have a

    negative impact on the TSS concentration in the final effluent.

    • The digester provided 45 percent volatile solids destruction. The level of volatile

    destruction was lower than expected. Expected reduction in volatile solids was

    between 50 and 55 percent. This may have been the result of poor mixing in the

    digester.

    • The measured active volume of the primary digester was 79 percent of the total

    volume available. Approximately 6 percent of the pumped sludge short-circuited

    the digester volume.

    ARLINGTON SEWAGE TREATMENT PLANT

    Figure 2-4 presents a flow schematic and Table 2-10 summarizes the unit processes of the Arlington

    sewage treatment plant (STP). Wastewater, consisting mainly of domestic, institutional, and com

    mercial sewage, flows by gravity to the STP. The design capacity of the STP is 4.0 mgd and the

    current average-day flow is 3.44 mgd. The discharge criteria for the facility are 30 mg/L BODs and

    30 mg/L TSS. The plant does not have an ammonia removal requirement. However, operators are

    required to measure the ammonia concentration and include the result as part of the monthly

    summary report to the NYSDEC.

    The wastewater flows by gravity through a coarse bar screen to the aerated grit chamber and

    comminutor. The screenings and grit are transported to a landfill. The degritted sewage flows by

    gravity to a primary clarifier distribution chamber. Supernatant from sludge thickeners and filtrate

    from the BFP are combined with the raw sewage and the combined flow is distributed to four

    primary clarifiers. The primary sludge is pumped from the primary clarifiers to the gravity

    thickeners.

    2·22

  • ../JUN/a6

    .flAB ~ SCREENS ~RIT CHAMBER

    RAW

    SEWAGE

    ~

    ,..----I

    I

    I

    I

    I

    I

    I

    I

    I

    I

    I

    I

    I

    I

    I

    I

    I

    I

    I

    I

    I

    .YB!I --------t.-----D--.llRII

    SEPARATOR

    SOUDS

    LIQUID

    BYPASS

    2QOK101DO.OS Pl8007.dwll

    STORNWATER BYPASS .--------------------------,. . AERATION BruSS COMMINUTOR ! PRIMARY r---~~~~;;,-----T- --;E~~~~~--: CHLORINE

    I CLARIFIER I ~ I CLARIFIER I CONTACT .1 •Lj -W

    r :0: 00:: :0: D. °0 00°0

    000000 0 00 0 0

    °jPDjOjOOp oj i

    I

    SUPERNATANT I AERATION R£TURNS I BLOWERS

    I

    ________________ JI

    I

    I

    I

    I

    I

    ~--~~~!~~~~~~~~~---L-------~-~~!~~~~~-~~~~--~ OFr-GAS.HtAI

    EXCHAllrGER

    SCRUBBER GRAVITY

    THICKENER

    L BELT FILTER PRESS

    I f--EI- • ( ) ( D~L.tT~RED Jat. ------~-~--I DISPOSAL-------~

    INCINERATOR

    INCINERATOR ~

    AQUAE 2-4

    AFUNGTON STP

    PROCESS FLOW SCHEMAlIC

    c.:>

    I\)

    '"

    http:2QOK101DO.OS

  • TABLE 2-10

    ARLINGTON STP - SUMMARY OF UNIT PROCESSES

    Unit Process

    Bar screen

    Grit chamber

    Primary clarifier

    Aeration basin

    Diffusers

    Aeration equipment blowers

    Secondary clarifier

    Chlorine contact chamber

    Gravity thickener

    Belt filter press

    Incinerator

    Number

    2

    1

    2

    2

    3

    (2 in service)

    2 1

    3

    3

    2

    1

    1

    Description

    Mechanical clean

    Aerated with dedicated blower

    Area =2,088 fe (per unit) 116 ft x 18 ft; 8.67 ft deep Area =891 ft2 (per unit) 49.5 ft x 18 ft; 8.33 ft deep

    Area =3,942 fe (per unit) Volume =45,176 ft3 (per unit) Depth =12ft Coarse bubble Area per diffuser =14 fe Number per tank =280 Submergence =11.5 ft 60hp Positive displacement, variable speed drive 60hp Positive displacement, split ring drive

    Area =2,088 fe (per unit) 116 ft x 18 ft; 8.67 ft deep

    Area =695 fe (per unit) Volume =4,517 fe (per unit) Volume =5,772 fe (per unit) Dia. =26 ft; depth =10 ft Width =1m Fluidized bed 800 lb Ihr dry solids

    The primary clarifier effluent is recombined in a common primary effluent channel that connects the

    three aeration basins. Under loading conditions prior to and during the test, two of the three

    aeration basins were in service. The aeration basins can be operated as plug-flow or step-feed basins.

    Air is provided to the aeration basins by three positive displacement blowers. Two of the three

    blowers have variable-frequency drive systems, and the third blower has a manually operated split

    disk drive system. The Arlington STP has an automatic DO control system, which operates the

    blowers based on the DO measurement in the aeration basin.

    2-24

  • The Arlington STP has three rectangular secondary clarifiers. There is an approximately lO-foot

    hydraulic drop between the aeration basins and the secondary clarifiers. In the past, air entrainment

    due to the free-fall discharge and turbulence in the aeration basin discharge channel was a problem.

    The operators use an automated valve to control the water surface level in the aeration basin

    discharge channel to ensure that the aeration basin outfall remains flooded and the pipe to the

    secondary clarifier is submerged at all times.

    The RAS is pumped from the secondary clarifier to the head of the aeration basin. Two RAS pumps

    service three clarifiers. The RAS is measured with magnetic flow meters located at the entrance to

    each aeration basin. Sludge is wasted from the RAS line using a manually operated bypass valve

    located on the combined RAS line. The WAS is combined with the primary sludge in the gravity

    thickeners.

    The secondary effluent flows by gravity through the chlorine contact chamber and to final discharge

    in the Hudson River.

    The Arlington STP has two bypass systems, the stormwater bypass and the secondary bypass. The

    stormwater bypass uses an overflow weir to divert raw sewage from the primary clarifier

    distribution chamber to the inlet channel for the secondary clarifiers. The secondary bypass uses an

    overflow weir to divert primary effluent from the aeration basin inlet channel to the chlorine contact

    chamber. During a storm event, flows in excess of 4.5 mgd receive primary clarification and

    disinfection only, and flows in excess of 6.0 mgd receive secondary clarification and chlorination

    only. The maximum flow to the Arlington STP is 8.0 mgd. Therefore, the maximum flow to the

    primary clarifiers is 6.0 mgd, the maximum flow to the aeration basins is 4.5 mgd, and the

    maximum flow to the secondary clarifiers is 6.5 mgd (4.5 mgd from the aeration basin and 2.0 mgd

    from the stormwater bypass).

    Solids from the primary clarifiers are pumped to the gravity thickener for co-thickening with the

    WAS. The thickened sludge is then pumped to the BFP and into the sludge incinerator. Since

    February 1996, the BFP and sludge incinerator have operated for approximately six hours every day

    (during the evening shift). Prior to this date, the belt press and incinerator operated approximately

    once per week.

    2·25

  • Performance History

    Ihe average-day flow to the Arlington SIP was 3.45 mgd between January 1995 and June 1996, and

    the maximum instantaneous flow recorded was 8.9 mgd. Therefore, the hydraulic peak factor is

    approximately 2.5 for the period of record.

    The ISS and BODs concentrations in the raw sewage flow to the Arlington SIP for January 1995 to

    June 1996 were 124 and 130 mg/L, respectively. The average ISS and BODs loadings to the

    treatment plant were 3,542 and 3,6741b/day, respectively.

    The average ISS and BODs concentrations in the final effluent from the Arlington SIP from January

    1995 to June 1996 were 7.5 and 6.7 mg/L, respectively. This is well below the effluent discharge

    requirement of 30 mg/L for each parameter. The average BODs and ISS removal efficiency for the

    facility was 94 percent. The Arlington SIP provides a good standard of treatment. The BODs and

    ISS removal efficiencies were greater than 90 percent approximately 80 percent of the time between

    January 1995 and June 1996.

    The average MLSS concentration in the two aeration basins in service was 1,050 mg/L. The MLSS

    concentration was significantly lower in the warmer period (wastewater temperature) of June

    through October. During this time, operators have reduced the solids inventory in the aeration basin

    by reducing the MLSS concentration in an attempt to prevent nitrification. The average MLSS

    concentration for the months of November through June was 1,150 mg/L; the average MLSS

    concentration for the months of July through October was 720 mg/L.

    The F/Mv ratio for the Arlington SIP during the 18-month period was 0.65 dail. The F/Mv ratio

    was very high in September and October 1995 due to the low MLSS concentration in the aeration

    basin at the time. The SRI for the plant from January 1995 to June 1996 was 4.9 days. Other than on

    a few days, the SRI remained below six days for the period of record.

    The average solids concentrations for the thickened and dewatered sludge from January 1995 to

    December 1995 were 3.6 and 20.6 percent dry solids, respectively. Starting in February 1996, the

    Arlington SIP operated the dewatering and incineration process every day during the evening shift.

    Prior to February, the dewatering and incineration process was operated once a week for

    approximately 36 hours. Ihe change in operation resulted in an increase in the dewatered sludge

    solids concentration from 20.6 percent dry solids in 1995 to 25.6 percent dry solids in July 1996. The

    2-26

  • solids concentration in the dewatered sludge had a significant impact on the fuel consumption in the

    incineration process.

    The average electrical consumption for the Arlington STP from December 1993 to June 1996 was

    5,270 kWh/day. The average oil consumption from January 1995 to June 1996 was 180 gallons per

    day. The fuel oil was primarily used for the sludge incineration process. The average oil

    consumption per pound of solids processed was 65 gallons/lb during 1995 and 12 gallons/lb in July

    and August 1996. As noted above, the incinerator oil consumption was influenced by the solids

    concentration in the dewatered sludge.

    Field Test

    The Arlington STP field test program was conducted from July 17 to August 25, 1996. Table 2-11

    presents a comparison between the unit process loadings and effluent quality during the field test

    program and historical values for the facility. The hydraulic and organic loadings to the treatment

    plant were similar to the historical values.

    Field testing consisted of offline sampling, online monitoring, and performance testing of specific

    equipment and processes. The offline sample results were based on 24-hour composite samples and

    grab samples taken at various points in the process. The online data consists of data measured from

    temporary instruments installed for the test period and the existing online metering equipment at

    the site. The temporary instruments included 00 meters installed in the aeration basin, solids

    concentration meters in the aeration basin, and solids concentration meters in the final effluent. Plant

    metering was used to monitor raw sewage flow, RAS flow, WAS flow, and total air flow. The

    performance testing consisted of oxygen transfer efficiency testing of the existing aeration

    equipment, and "wire to water" performance testing of the aeration blowers, incinerator fan, and

    the RAS pumps. Table 2-12 summarizes the work done. Detailed descriptions and results are

    presented in the Arlington STP Site Report (CH2M HILL, 1998a).

    The main conclusions from the field study period for the Arlington STP were:

    • The primary clarifiers performed well. The average BODs and TSS removal

    efficiencies were 47 percent and 65 perce