on-line process monitoring and electric submetering at six ......technologies. a combination of...
TRANSCRIPT
-
On-Line Process Monitoring and Electric Submetering at Six
Municipal Wastewater Treatment Plants
Final Report 98-12 July 1998
New York State Energy Research and Development Authority
-
The New York State Energy Research and Development Authority (NYSERDA) is a public benefit corporation created in 1975 by the New York State Legislature.
NYSERDA has major programs in energy and environmental research, radioactive and hazardous waste management, tax-exempt bond financing, energy analysis and planning, and energy efficiency grants. Its responsibilities include:
• Conducting a multifaceted energy and environmental research and development program to meet New York State's diverse needs;
• Helping industries, schools, hospitals, and not-for-profits implement energy efficiency measures;
• Providing objective, credible, and useful energy analysis to guide decisions made by major energy stakeholders in the private and public sectors;
• Managing the Western New York Nuclear Service Center at West Valley, including: (1) overseeing the State's interests and share of costs at the West Valley Demonstration Project, a federal/State radioactive waste clean-up effort, and (2) managing wastes and maintaining facilities at the shut-down State-Licensed Disposal Area;
• Participating in the Malta Rocket Fuel Area "Superfund" site clean-up and managing facilities at the site on behalf of the State;
• Coordinating the State's activities on nuclear matters, and designing, constructing, and operating State facilities for disposal oflow-Ievel radioactive waste, once siting and technology decisions are made by the State; and
• Financing energy-related projects, reducing costs for ratepayers.
NYSERDA derives its basic research revenues from an assessment levied on the intrastate sales ofNew York State's investor-owned electric and gas utilities. Additional research dollars come from limited corporate funds and a voluntary annual contribution by the New York Power Authority. More than 245 ofNYSERDA's research projects help the State's businesses and municipalities with their energy and environmental problems. Since 1990, NYSERDA has successfully developed and brought into use more than 60 innovative, energyefficient, and environmentally acceptable products and services. These contributions to the State's economic growth and environmental protection are made at a cost ofless than $1 per New York resident per year.
Federally funded, the Energy Efficiency Services program is working with more than 220 businesses, schools, and municipalities to identify existing technologies and equipment to reduce their energy costs.
For more information, contact the Technical Communications unit, NYSERDA, Corporate Plaza West, 286 Washington Avenue Extension, Albany, New York 12203-6399; (518) 862-1090, ext. 3250; or on the World Wide Web at http://www.nyserda.org/
State of New York Energy Research and Development Authority George E. Pataki William R. Howell, Chairman Governor F. William Valentino, President
http:http://www.nyserda.org
-
ON-LINE PROCESS MONITORING AND
ELECTRIC SUBMETERING AT SIX MUNICIPAL
WASTEWATER TREATMENT PLANTS
Final Report
Prepared for
THE NEW YORK STATE
ENERGY RESEARCH AND DEVELOPMENT AUTHORITY
Albany,NY
LaWTence J.Pakenas,P.E.
Senior Project Manager
and
EMPIRE STATE ELECTRIC ENERGY RESEARCH CORPORATION
and
ELECTRIC POWER RESEARCH INSTITUTE
Prepared by
CH2M HILL INC. Parsippany, NJ
Linda Ferguson
Technical Project Leader
Peter Keenan
Project Manager
and
SAIC-ENERGY SOLUTIONS DIVISION Albany, NY
Ron Slosberg Technical Project Leader
3172-ERTER-MW-94 NYSERDA Report 98-12 July 1998
-
NOTICE
This report was prepared by CH2M HILL Inc. and SAIC - Energy Solutions Division in the course
of performing work contracted for and sponsored by the New York State Energy Research and
Development Authority, the Empire State Electric Energy Research Corporation, and the Electric
Power Research Institute (hereafter the "Sponsors"). The opinions expressed in this report do not
necessarily reflect those of the Sponsors or the State of New York, and reference to any specific
product, service, process, or method does not constitute an implied or expressed recommendation
or endorsement of it. Further, the Sponsors and the State of New York make no warranties or
representations, expressed or implied, as to the fitness for particular purpose or merchantability
of any product, apparatus, or service, or the usefulness, completeness, or accuracy of any
processes, methods, or other information contained, described, disclosed, or referred to in this
report. The Sponsors, the State of New York, and the contractor make no repre~entation that the
use of any product, apparatus, process, method, or other information will not infringe privately
owned rights and will assume no liability for any loss, injury, or damage resulting from, or
occurring in connection with, the use of information contained, described, disclosed, or referred
to in this report.
-
ABSTRACT
An investigation was made of New York State wastewater treatment plants (WWTPs) to
determine if process audit and electrical submetering techniques are an effective method of
identifying energy conservation opportunities (ECOs) at municipal wastewater treatment plants.
The study at six municipal WWTPs included a range of facility sizes, locations, and treatment
technologies. A combination of online process monitoring, offline sampling, electrical
submetering, and specific performance efficiency testing techniques was used to obtain real-time
process and electrical consumption data.
Recommendations varied for each site. They included piping modifications, pump and/or motor
replacement, operational procedures changes, modification of online instrumentation and control
systems, aeration system upgrades, and additional energy reuse options. The energy implications
(savings or additional costs) were quantified for each item. The simple payback period for
operational changes and minor capital items ranged from 0 to 15 years. Major capital items were
recommended for reasons other than energy conservation, including worker health and safety,
effluent quality, and/or capacity limitations.
The results of the study indicated that the audit approach, which consists of a systematic and
rigorous methodology for obtaining accurate performance information, is an appropriate tool for
identifying ECOs at existing wastewater treatment facilities. Online process data, equipment
performance characteristics, and electrical submetering information provide a good basis for
identifying ECOs, quantifying the achievable savings, and predicting the impact of implemen
tation on facility performance.
iii
-
TABLE OF CONTENTS
Section Page
1. Introduction....................................................................................................................................... 1-1
Project Objectives ............................................................................................................................... 1-1
Test Methodology .............................................................................................................................. 1-2
Test Sites ............................................................................................................................................. 1-3
2. Wastewater Treatment Plant Configurations and Performance .............................................. 2-1
Sodus Village WWTP ........................................................................................................................ 2-1
Performance History .................................................................................................................. 2-4
Field Test. ..................................................................................................................................... 2-5
Village of Goshen WWTP ................................................................................................................. 2-9
Performance History ................................................................................................................ 2-11
Field Test. ................................................................................................................................... 2-13
Marsh Creek WWTP ....................................................................................................................... 2-15
Performance History ................................................................................................................ 2-18
Field Test. ................................................................................................................................... 2-19
Arlington Sewage Treatment Plant ............................................................................................... 2-22
Performance History ................................................................................................................ 2-26
Field Test. ................................................................................................................................... 2-27
Bergen Point WWTP ........................................................................................................................ 2-30
Performance History ................................................................................................................ 2-33
Field Test .................................................................................................................................... 2-34
Yonkers Joint WWTP ....................................................................................................................... 2-38
Performance History ................................................................................................................ 2-41
Field Test. ................................................................................................................................... 2-43
3. Wastewater Treatment Plant Energy Usage ................................................................................. 3-1
Electrical Usage Profile ..................................................................................................................... 3-1
Sodus WWTP .............................................................................................................................. 3-1
Goshen WWTP ............................................................................................................................ 3-3
Marsh Creek WWTP .................................................................................................................. 3-3
Arlington STP .............................................................................................................................. 3-6
Bergen Point WWTP .................................................................................................................. 3-6
Yonkers Joint WWTP ................................................................................................................. 3-9
Standardized Electrical Usage ......................................................................................................... 3-9
4. Energy Conservation Opportunities ............................................................................................. 4-1
Sodus Village WWTP ........................................................................................................................ 4-1
Village of Goshen WWTP ................................................................................................................. 4-4
Marsh Creek WWTP ......................................................................................................................... 4-5
Arlington STP ..................................................................................................................................... 4-8
Bergen Point WWTP ........................................................................................................................ 4-11
Yonkers Joint WWTP ....................................................................................................................... 4-14
5. Conclusions ....................................................................................................................................... 5-1
Appendix A Equipment Used in the Submetering Program
v
-
TABLES
Number Page
1-1 Six Municipal Wastewater Treatment Plants Included in the Test Program ........................... 1-3
2-5 Village of Goshen WWTP - Summary of Unit Process Loading During Field Test
3-1 Standardized Electrical Consumption of the Major Unit Processes at the Six Wastewater
3-2 Electrical Consumption of Secondary Treatment at the Six Wastewater Treatment
4-2 Sodus Village WWTP - Costs of Small Capital and Operational Changes
4-3 Sodus Village WWTP - Life Cycle Cost Analysis of Major Recommended Capital
4-5 Village of Goshen WWTP - Costs of Small Capital and Operational Changes (in priority
4-12 Bergen Point WWTP - Costs of Recommended Small Capital and Operational Changes
2-1 Sodus Village WWTP - Summary of Unit Processes ................................................................... 2-3
2-2 Sodus Village WWTP - Summary of Unit Process Loading During Field Test Program....... 2-6
2-3 Sodus Village WWTP - Field Test Program .................................................................................. 2-7
2-4 Village of Goshen WWTP - Summary of Unit Processes .......................................................... 2-11
Program........................................................................................................................................... 2-13
2-6 Village of Goshen WWTP - Field Test Program ......................................................................... 2-14
2-7 Marsh Creek WWTP - Summary of Unit Processes .................................................................. 2-17
2-8 Marsh Creek WWTP - Summary of Unit Process Loading During Field Test Program ...... 2-20
2-9 Marsh Creek WWTP - Field Test Program ................................................................................ 2-21
2-10 Arlington STP - Summary of Unit Processes ............................................................................. 2-24
2-11 Arlington STP - Summary of Unit Process Loading During Field Test Program.................. 2-28
2-12 Arlington STP - Field Test Program ............................................................................................ 2-29
2-13 Bergen Point WWTP - Summary of Unit Processes ................................................................... 2-32
2-14 Bergen Point WWTP - Summary of Unit Process Loading During Field Test Program ...... 2-35
2-15 Bergen Point WWTP - Field Test Program ................................................................................. 2-36
2-16 Yonkers Joint WWTP - Summary of Unit Processes ................................................................. 2-40
2-17 Yonkers Joint WWTP - Summary of Unit Process Loading During Field Test Program ..... 2-44
2-18 Yonkers Joint WWTP - Field Test Program ................................................................................ 2-46
Treatment Plants ............................................................................................................................ 3-11
Plants ............................................................................................................................................... 3-13
4-1 Sodus Village WWTP - Identified Energy Conservation Opportunities .................................. 4-2
(in priority order) ............................................................................................................................. 4-3
Improvement .................................................................................................................................... 4-5
4-4 Village of Goshen WWTP - Identified Energy Conservation Opportunities ........................... 4-6
order) ................................................................................................................................................. 4-6
4-6 Village of Goshen WWTP - Life Cycle Cost Analysis of Major Capital Improvements ......... 4-8
4-7 Marsh Creek WWTP - Identified Energy Conservation Opportunities .................................... 4-8
4-8 Arlington STP - Identified Energy Conservation Opportunities ............................................. 4-11
4-9 Arlington STP - Costs of Small Capital and Operational Changes (in priority order) ......... 4-12
4-10 Arlington STP - Life Cycle Cost Analysis of Major Capital Improvements ........................... 4-15
4-11 Bergen Point WWTP - Identified Energy Conservation Opportunities ................................. 4-16
(in priority order) ........................................................................................................................... 4-17
4-13 Bergen Point WWTP - Life Cycle Cost Analysis of Major Capital Improvement ................. 4-19
4-14 Yonkers Joint WWTP - Identified Energy Conservation Opportunities ................................ 4-20
4-15 Yonkers Joint WWTP - Costs of ECO (in Priority Order) ......................................................... 4-22
vi
-
FIGURES
Number Page
2-1 Sodus WWTP - Process Flow Schematic ....................................................................................... 2-2
2-2 Goshen WWTP - Process Flow Schematic .................................................................................. 2-10
2-3 Marsh Creek WWTP - Process Flow Schematic ......................................................................... 2-16
2-4 Arlington STP - Process Flow Schematic .................................................................................... 2-23
2-5 Bergen Point WWTP - Process Flow Schematic ......................................................................... 2-31
2-6 Yonkers Joint WWTP - Process Flow Schematic ........................................................................ 2-39
3-1 Sodus WWTP - Energy Use of the Major Unit Processes ........................................................... 3-2
3-2 Goshen WWTP - Energy Use of the Major Unit Process ............................................................ 3-4
3-3 Marsh Creek WWTP - Energy Use of the Major Unit Processes ............................................... 3-5
3-4 Arlington STP - Energy Use of the Major Unit Processes ........................................................... 3-7
3-5 Bergen Point WWTP - Energy Use of the Major Unit Processes ................................................ 3-8
3-6 Yonkers Joint WWTP - Energy Use of the Major Unit Processes ............................................. 3-10
vii
-
ABBREVIATIONS
BODs 5-day biochemical oxygen demand
BFP belt filter press
Btu British thermal units
cBODs carbonaceous biochemical oxygen demand
COD chemical oxygen demand
OAF dissolved air flotation
DO dissolved oxygen
ECO energy conservation opportunities
F/Mv food to microorganism ratio
gpd gallons per day
gpm gallons per minute
hp horsepower
HRT hydraulic residence time
kW kilowatts
kWh kilowatt hours
Ibid pounds per day
mgd million gallons per day
mg/L milligram per liter
mL/g milliliter per gram
MLSS mixed liquor suspended solids
MLVSS mixed liquor volatile suspended solids
~-N ammonia as nitrogen
N02-N nitrite as nitrogen
N03-N nitrate as nitrogen
P04 orthophosphate
sBODs soluble biochemical oxygen demand
RAS return activated sludge
SOR surface overflow rate
SOTE standard oxygen transfer efficiency
SRT solids residence time
SVI sludge volume index
TKN total Kjeldahl nitrogen
TP total phosphorus
TS total solids
TSS total suspended solids
VS volatile solids
VSD variable speed drive
VSS volatile suspended solids
WAS waste activated sludge
viii
-
SUMMARY
The New York State Energy Research and Development Authority (NYSERDA), the Empire State
Electric Energy Research Corporation (ESEERCO), and the Electrical Power Research Institute
(EPRI) funded an investigation of New York State wastewater treatment plants (WWTPs). The
purpose of the investigation was to determine if process audit and electrical submetering tech
niques are an effective method of identifying energy conservation opportunities (ECOs) at
municipal wastewater treatment plants. Phase 1 consisted of screening 80 potential WWTPs to
identify six test sites to include in the study program. The sites were selected to provide a
representative sample of the existing wastewater treatment facilities in New York State in terms
of size (flow rate), location, treatment technologies, and sludge management practices. Table 1
lists the sites and their rated capacities. Table 2 lists the various treatment technologies included
in the test program. Phase 2 consisted of an intensive four- to six-week field study at each site
including operating data reviews, online process monitoring, offline sampling, performance
efficiency testing, and electrical submetering. The objectives of the field testing were to quantify
the energy consumption and process performance on a process-by-process and whole plant basis,
to examine the dynamic interrelationships among the unit processes to determine load/response
and effect on performance, and to identify areas for process improvements.
The ECOs identified during the study can be divided into four categories:
• maintenance and housekeeping items,
• operating and control procedures,
• electrical equipment replacement, and
• capacity-related issues.
TABLEt
SIX MUNICIPAL WASTEWATER TREATMENT FACILITIES INCLUDED IN THE TEST PROGRAM
Name of Facility Utility Rated Capacity
SodusWVVTP, Sodus, NY Rochester Gas and Electric 0.5 mgd
Goshen WWTP, Goshen, NY Orange and Rockland 1.5mgd
Marsh Creek WWTP, Geneva, NY New York State Electric and Gas Corp. 4.0mgd
Arlington STP, Poughkeepsie, NY Central Hudson Gas and Electric 4.0mgd
Bergen Point WWTP, Babylon, NY Long Island Lighting Company 30.0mgd
Yonkers Joint WWTP, Yonkers, NY New York Power Authority 90.0mgd
S-l
-
TABLE 2
LIQUID AND SOLIDS TREATMENT TECHNOLOGIES INCLUDED IN THE TEST PROGRAM
Liquid Treatment Technology Solids Treatment Technology
Pump stations Thickeners
Gravity belt Aerated grit chambers Gravity
Primary clarifiers Dissolved air flotation
Activated sludge Dewatering
Extended aeration Belt filter press Contact stabilization CentrifugeConventional activated sludge
Anaerobic digestion Aeration systems
Sludge composting Coarse bubble Fine bubble Incineration Membrane panels Fluidized bed
Multiple hearthTrickling filters
Tertiary filtration
Effluent polishing lagoons/wetlands
Chlorination
Several maintenance and housekeeping items were identified during the study. Common items
included inoperable or worn backflow prevention valves on pumps, inappropriate or worn
pressure relief valves on aeration blowers, inappropriate valve or gate settings, and worn pumps.
The capital costs of replacing these items were usually very small and the payback period was
usually less than two years.
The study recommended changes to operating procedures at several of the plants. These included
changes to pump control strategies, provision of measurement and control of miscellaneous air
use for common air supply systems, and changes to solids handling procedures. The capital costs
for these changes were usually small to moderate and the payback period was usually less than
five years.
All of the wastewater treatment plants included in the study were more thart 20 years old, and
there have been technological advances since the original electrical equipment was installed. At
several sites the study recommended replacing older electrical motor and drive systems with
more efficient units. The capital costs of these recommendations were moderate and the payback
period was usually less than five years.
S-2
-
Excess capacity in one or more unit process was identified as contributing to increased energy
consumption at many of the sites. Excess blower capacity as a result of upgrading from coarse- to
fine-bubble aeration, excess aeration basin volume, and excess solids stabilization capacity were
identified. Recommendations included taking basins out of service, downsizing equipment, and
providing intermediate storage between processes to allow for different loading rates. At two of
the sites the study recommended that the facility use the excess capacity in the solids handling
and treatment systems to treat hauled sludge from neighbouring facilities as an income
generating opportunity. The capital costs of these recommendations varied from very low (taking
units out of service) to high (constructing hauled sludge receiving facilities). The payback period
varied from less than one year to more than 10 years.
This project used a combination of process audit, energy audit, and electrical submetering
techniques to identify low-capital-cost methods of improving the performance and energy
efficiency of six WWTPs in New York State. The plants were selected to provide a representative
sample in terms of size, location, and treatment technologies. The plants were operating well
within their effluent discharge requirements and provided good to excellent levels of treatment.
One of the primary objectives of the study was to determine if this approach is an effective
method of reducing WWTP operating costs and improving WWTP performance. There were
several advantages to this approach:
• Real-time data provides a greater understanding of the dynamic response characteristics
of the treatment processes. The impact of energy conservation recommendations on
treatment performance is easier to foresee if the real-time process performance data is
available.
• Measured electrical consumption data is required to determine the potential energy
savings associated with implementing ECOs. Using a single power draw measurement
may over- or underestimate the potential savings.
• Real-time process and performance data is required to evaluate theoretical versus
achievable energy savings associated with implementing ECOs. The data can also
indicate methods of increasing the achievable savings.
8-3
-
• Discrepancies or unexpected results in the data generated are good indicators of potential
areas of improved performance that may be overlooked using more traditional
approaches.
The audit approach, which consists of a systematic and rigorous methodology for oqtaining
accurate performance information, is an appropriate tool for identifying ECOs at existing
wastewater treatment facilities. Online process data, equipment performance characteristics, and
electrical submetering information are required to predict the effects of implementing ECOs. The
conceptual approach used for this project was quite simple. Measure what you have, what you
are using, and the performance achieved, and base decisions for improving performance
efficiency on the measured data.
5-4
-
Section 1
INTRODUCTION
PROJECT OBJECTIVES
The New York State Energy Research and Development Authority (NYSERDA), the Empire State
Electric Energy Research Corporation (ESEERCO), and the Electric Power Research Institute
(EPRI) jointly funded an investigation of New York State wastewater treatment plants (WWTPs).
The purpose of the investigation was to determine if process optimization of the WWTPs without
major capital expenditure and the identification of potential energy-saving measures within
existing facilities were effective methods of reducing plant operating costs and improving plant
performance.
The project was conducted in two phases. Phase I, which was completed in 1995, consisted of
screening 80 potential WWTPs to identify six test sites for the field monitoring portion of the
project. The intent was to provide a representative sample of the WWTPs in New York State in
terms of size (flow rate), treatment technologies, and sludge management practices.
Phase 2 used a combination of operating data review, online process monitoring, offline
sampling, electrical submetering, and specific performance efficiency testing techniques to
quantify the treatment provided and energy consumed on a unit process and whole plant basis.
The overall objectives of the field testing were to:
• quantify the energy consumption and process performance on a process
by-process and whole plant basis at each WWTP;
• examine the dynamic interrelationships among the various unit
processes at each site, including loading response and its effect, on unit
process and whole plant energy use, performance, and treatment
efficiency;
• identify areas for process improvements including making changes to
treatment process control and operating procedures or installing electro
technologies, and low-capital-cost equipment changes, to improve
energy efficiency, treatment performance, and capacity at each WWTP.
1·1
-
TEST METHODOLOGY
The facility performance was evaluated in detail over a four- to six-week period. A minimum of
12 months of operating data was reviewed to determine the current baseline unit process loading
and performance and energy consumption pattern, and to identify factors that may be limiting
the facility performance.
The offline sampling consisted of collection and analysis of 24-hour composite samples from
upstream and downstream of each unit process supplemented with grab samples from various
locations. The analytical results were used to determine unit process loading and performance on
a daily basis and to characterize recycle streams through the plant. The offline sampling also
provided a quality control check for the online process data collected.
Real-time data was collected from the existing and temporary online process monitoring
equipment. The types of online process data collected varied between sites. In general, the data
included wastewater flow, air flow, aeration basin dissolved oxygen concentration, mixed liquor
concentration, return activated sludge flow, and effluent suspended solids concentration. The
online process data was used to quantify the dynamic load/response characteristics of the unit
processes.
The whole-facility energy use was recorded on a IS-minute basis by the local utility. The energy
use of the process-related equipment was monitored with temporary submetering equipment
installed during the field test period. For motors where the load was not expected to vary
significantly during use, time-in-use loggers were installed to record off!on events. Current
transducers and voltage-potential wires were installed at the breaker panel for motors that
experience significant variations in loading during normal operation.
Specific performance tests were conducted on the major energy end users to obtain in situ
performance data. Performance testing consisted of oxygen transfer efficiency testing, digester
tracer testing, and IIwire to waterll efficiency testing of the major process equipment.
The detailed results of the field work are presented in a separate site report for each facility.
Copies of the individual site reports are available through NYSERDA. This report presents a
summary of results from the six wastewater treatment plants included in the study.
1·2
-
TEST SITES
Table 1-1 lists the six municipal wastewater treatment plants and the corresponding treatment
technologies included in the study. The facilities ranged in size from 0.5 mgd to 90 mgd capacity
and included two small « 2 mgd), two medium (2 to 10 mgd), and two large (> 10 mgd) plants.
All of the sites provided a minimum of secondary level treatment. The two smaller sites also
provided tertiary treatment.
TABLE 1-1
SIX MUNICIPAL WASTEWATER TREATMENT PLANTS
INCLUDED IN THE TEST PROGRAM
Name Capacity Liquid Treatment (mgd) Processes
Sodus Village 0.5 Grit channel WWTP Primary clarification
Trickling filter Extended aeration Fine bubble aeration Tertiary sand filter
Village of Goshen 1.5 Grit channel WWTP Primary clarification
Trickling filter Treatment wetlands Chlorination
Marsh Creek 4.0 Aerated grit removal WWTP Primary clarification
Complete mix AS Panel membrane aeration Chlorination
Arlington STP 4.0 Aerated grit removal Primary clarification Plug flow AS Coarse bubble aeration Chlorination
Bergen Point 30 Scavenger waste facility WWTP Raw sewage pumping
Aerated grit removal Primary clarification Step feed AS Panel membrane aeration Chlorination
Yonkers Joint 90 Aerated grit removal WWTP Primary clarification
Plug flow AS Coarse bubble cross roll
aeration Chlorination
Solids Treatment Processes
Anaerobic digestion Sludge drying
Anaerobic digestion Sludge drying
Gravity thickening Anaerobic digestion Beltpress dewatering Composting
Gravity thickening Beltpress dewatering Fluidized bed incineration
Gravity thickening Gravity belt thickening Belt press dewatering Multiple hearth incineration
Gravity thickening Dissolved air flotation Anaerobic digestion Centrifuge dewatering
1-3
-
Section 2
WASTEWATER TREATMENT PLANT CONFIGURATIONS AND PERFORMANCE
The six wastewater treatment plants included in the study were chosen to provide a representative
sample of the range of facility sizes, locations, and treatment technologies currently operating in
New York State. The following sections provide a brief description of each facility, its recent
perfonnance history, and the field test procedures and results.
Field testing consisted of offline sampling, online monitoring, and perfonnance testing of specific
equipment and processes. The offline sample results are based on 24-hour composite samples and
grab samples taken at various points in the process. The online data consists of data measured from
temporary instruments installed for the test period, supplementing the data collected by the existing
pennanent online metering equipment at each site.
SODUS VILLAGE WWTP
Figure 2-1 presents a flow schematic and Table 2-1 summarizes the unit processes of the Sodus
Village WWTP. The rated capacity of the WWTP is 0.5 mgd and the current measured average-day
flow is 0.38 mgd. The WWTP discharge permit has seasonal limits for 5-day biochemical oxygen
demand (BODs), total suspended solids (TSS), and ammonia-nitrogen (NH,-N). During the summer
months the criteria are 5 mg/L, 10 mg/L, and 2.0 mg/L, for BODS' TSS, and NH,-N, respectively.
The dissolved oxygen (DO) concentration of the final effluent must be greater than 7 mg/L. During
the winter months the criteria are 25 mg/L and 30 mg/L for BODs and TSS, respectively. There is no
NH,-N discharge criterion for the winter months.
Raw wastewater flows by gravity through a grit channel prior to entering the primary clarifier. Grit
removed from the wastewater in this channel is disposed of offsite. The degritted wastewater flows
by gravity to a single primary clarifier. Filter backwash from the tertiary sand filter, digester
supernatant, and sludge concentrator supernatant is mixed with degritted wastewater upstream of
the primary clarifier. Sludge from the primary clarifier is pumped to the sludge well.
Following primary clarification, the wastewater flows by gravity to the trickling filter. Trickling filter
effluent is pumped back through the filter as recycle. Alternatively, the trickling filter can be
bypassed, in which case primary effluent flows by gravity directly to the aeration basin.
2·1
-
SAND
04/JLW"1
RAW BACKWASH ~ BLOWERS
0-=-TRICKUNG FILTER BYPASS AERATION SECONDARY
TRICKLING BASiN CLARIFIER FILTER
I I I
.... : 0 : II:: :0 :0. DID 0 00 • 0000000 DODoO Q
--00.0 0 0 III_ODD
I FILTERI I I AERATION BASIN BYPASS : __ 1 -' I I I I
~R
=:llI 0-__'-_~I __ =~~"-=--im ___ ISUPERNATANT
RETURNS ~_________________ I----------------
-
TABLE 2-1
SODUS VILLAGE WWTP - SUMMARY OF UNIT PROCESSES
Unit Process Number Description
Primary clarifier 1 Area =616 ft2
Volume =32,224 gal.
Diameter =28 ft
Trickling filter 1 Media depth =5 ft 3 in.
Diameter =35 ft
Aeration basin 1 Area =2,640 fe
Depth =15 ft
Volume =296,208 gal.
Diffusers Fine bubble
Rubber sock
Submergence depth =14 ft
Aeration blowers 5 lOhpeach
Secondary clarifier 1 Area =616 ft2
Volume =32,224 gal.
Diameter =28 ft
Tertiary sand filter 1 Area =352 ft2 total
2 blowers at 10 hp each
Digester 1 Volume =95,000 gal. Sludge concentrator 1 Screw conveyor
The trickling filter effluent is pumped to the aeration basin. Air is supplied through fine-pore rubber
sock diffusers by five 10-hp blowers. There is also a bypass of the aeration basin that sends trickling
filter effluent flow directly to the secondary clarifier. Bypassing is done to reduce the solids loading
on the secondary clarifier during high flow conditions. The solids concentration in the trickling filter
effluent is significantly less than the solids concentration in the aeration basin. The operator
estimates that approximately 50 percent of the total plant flow bypasses the aeration basin.
The wastewater flows by gravity from the aeration basin to the secondary clarifier. Sludge from the
secondary clarifier is removed from the bottom of the clarifier, the return activated sludge (RAS) is
returned to the head of the aeration basin, and the waste activated sludge (WAS) is pumped to the
sludge well. The RAS and WAS flow rates are not measured.
Secondary effluent is pumped to the effluent sand filter. Backwash operations of the filter are
controlled by level sensors and each cell is backwashed at least once a day. There are two 10-hp
backwash blowers. One blower operates continuously to provide reaeration of the filter effluent.
2-3
-
Sludge is pumped from the sludge well to the anaerobic digester. The sludge is recirculated through
a heat exchanger and is continuously mixed in the digester. The digested sludge is pumped from the
digester to a sludge concentrator for dewatering. The dewatered sludge is disposed of offsite.
Performance History
The average monthly flow to the Sodus Village WWTP between January 1986 and December 1995
was 0.34 mgd. Since 1986, the flow has been increasing at a rate of approximately 0.013 million
gallons per year. The average monthly BODs and the TSS loads to the plant between January 1986
and December 1995 were 495 and 470 lb/day, respectively. The average TSS and BODs
concentrations in the raw sewage were 168 and 174 mg/L, respectively.
When the aeration basin at the Sodus Village WWTP went online in January 1991, the final effluent
quality improved dramatically. Prior to 1991, the average concentrations were 31 mg/L for BODs,
23.4 mg/L for TSS, and 19.2 mg/L for ~-N. After 1991, the effluent concentrations improved to
7.9 mg/L for BODs,S mg/L for TSS, and 3.7 mg/L for ~-N.
During the summer months between 1991 and 1995, average monthly final effluent concentrations
were 5.0 mg/L, 4.3 mg/L, and 1.7 mg/L, for BODs, TSS, and ~-N, respectively. These compare
with the summer discharge criteria of 5 mg/L for BOD5' 10 mg/L for TSS, and 2.0 mg/L for ~-N.
During the winter months the average monthly final effluent concentrations were 9.0 mg/L, 5.9
mg/L, and 4.5 mg/L, for BOD5' TSS, and ~-N, respectively. These compare to the winter
discharge criteria of 25 mg/L for BODs and 30 mg/L for TSS. There is no discharge criterion for
~-N during the winter.
The average removal efficiencies of BODs, TSS, and ~-N for the Sodus WWTP between January
1986 and December 1995 were 78 percent for BODs, 85 percent for TSS, and 58 percent for NH3-N.
After 1991 the removal efficiencies improved to an average of approximately 96 percent for both
BODs and TSS, and 82 percent for ~-N.
The current discharge permit for the Sodus WWTP requires 85 percent removal efficiency for both
BODs and TSS. The removal efficiency for BODs was in excess of 85 percent 95 percent of the time
and for TSS was in excess of 85 percent 98 percent of the time.
The mixed liquor suspended solids (MLSS) concentration for the aeration basin at the Sodus WWTP
was 3,852 mg/L. High MLSS concentrations during the winter months of 1995 were the result of
2-4
-
solids-handling limitations during the winter. The sludge concentrator was not in a heated facility
and therefore the WWTP operator was not able to remove solids from the aeration basin. This
situation has been corrected and the MLSS concentrations have since decreased.
The average sludge volume index (SVI) for the Sodus WWTP from January 1995 to October 1996
was 139 mL/g. The SVI is used as an indicator of the settling characteristics of a sludge. Values
greater than 200 mL/g are associated with poorly settling sludge. The maximum SVI between
January 1995 and October 1996 was 176 mL/g.
The monthly average sludge volume feed to the digester was approximately 88,850 gallons, and the
monthly average discharge from the digester was 41,150 gallons. The difference between the
volume of sludge pumped to and the volume of sludge discharged from the digester (approxi
mately 47,700 gallons) is the amount of supernatant returned to the head of the plant from the
digester.
The average monthly electrical usage for the Sodus Village WWTP between July 1995 and October
1996 was 22,815 kWh/month, and the average monthly natural gas usage was 670 therm/month
(1 therm = 100,000 Btu). During the winter months the natural gas consumption increased to 1,113
therm/month. Natural gas is used to heat the digesters.
Field Test
The Sodus Village WWTP field test program was conducted from June 4 to June 28, 1996. Table 2-2
presents the unit process loadings and effluent quality during the field test program and historical
values for the facility. The hydraulic and organic loading during the field test program was similar
to the historical data for the facility. However, the final effluent characteristics were significantly
different. The field test final effluent characteristics were determined based on 24-hour composite
samples collected every second day. These concentrations are likely a more accurate reflection of the
loading and treatment provided by the Sodus Village WWTP.
Field testing consisted of offline sampling, online monitoring, and performance testing of specific
equipment and processes. The offline sampling results were based on 24-hour composite samples
and grab samples taken at various points in the process. The online data consists of data measured
from temporary instruments installed for the test period and from existing permanent metering
equipment onsite. The temporary instruments included DO probes installed in the aeration basin, a
solids probe in the aeration basin to measure mixed liquor suspended solids concentration, and a
2·5
-
TABLE 2-2
SODUS VILLAGE WWTP - SUMMARY OF UNIT PROCESS LOADING DURING FIELD TEST PROGRAM
Unit Process Units Field Test Historical Average Maximum Average Maximum
Loading Hydraulic Organic
BODs BODs TSS TSS ~-N
Mgd
mg/L lb/d
mg/L lb/d
mg/L
0.34
126 339 172 475 NA
0.46
280 710 500
1,691 NA
0.38
174 613 168 530 24
0.48
260 949 310 849 32
Effluent Quality BODs TSS NH,.-N
mg/L mg/L mg/L
19 11 6.7
40 28 19
7.9 5
3.7
Primary Clarifier Area ff 616 616 Surface overflow rate gpd/ff 551 750 620 780
Aeration Basin Volume BODs loading HRT
fe lb / day*l,OOO fe
hour
39,600 8.3 21
18 15
39,600 NA 18.7
NA 14.8
MLSS concentration SVI F/M
mg/L mL/g days·!
3,763 NA 0.06
4,800 NA 0.1
3,852 139 NA
8,904 176 NA
Secondary Clarifiers Area ff 616 616 Surface overflow rate gpd/ff 551 750 620 780
Tertiary Sand Filter Area ff 352 352 Hydraulic loading gpm/ff 0.66 0.9 0.75 0.95
Digesters Primary volume Feed Discharge HRT
gal. gal./month gal./month
days
95,000 44,300 30,500
65
95,000 88,840 41,140
33
solids probe in the secondary effluent well to measure secondary effluent suspended solids
concentration. The total plant flow was measured by the existing plant flow meter. The performance
testing consisted of oxygen transfer efficiency testing of the aeration equipment and pump
performance tests.
2·6
-
Table 2-3 presents a summary of the field test activities. Detailed test descriptions and results are
presented in the Sodus Village WWTP Site Report (CH2M IDLL, 1998e).
Sample Location
Raw sewage
Primary effluent
Trickling filter effluent
Secondary effluent
Sand filter effluent
Sludge concentrator supernatant
Filter backwash
Digester supernatant
Raw sludge
Digested sludge
Digester profile (5 ports)
MLSS
RAS
Location
Aeration basin
Secondary effluent
Raw sewage
Location
Aeration basin
Pumps
TABLE 2-3 SODUS VILLAGE WWTP - FIELD TEST PROGRAM
Offline Sampling Program
Frequency Type of Sample Analysis
2nd day 24h cBOD5, TSS, VSS
2nd day 24h cBOD5I ~-N, TKN, TSS, VSS
2nd day 24h cBOD5, NH3-N, TKN, TSS, VSS
2nd day 24h cBOD5I ~-N, TKN, TSS, VSS
2nd day 24h cBOD5I TSS, VSS
1I operation grab cBOD5I TSS, VSS
1I week grab cBOD5, TSS
grab cBOD5I TKN, TSS
grab TS, TVS
grab TS, TVS
grab TS, TVS
2/week grab TSS, VSS
2/week grab TSS
Online Monitoring Program
Type Data
Dissolved oxygen 4 temporary meters
Suspended solids 1 temporary meter
Suspended solids 1 temporary meter
Flow 1 existing meter - flume
Performance Testing
Type Analysis
Offgas Oxygen transfer efficiency
Performance "Wire to water" efficiency
2·7
-
The major conclusions from the field study period for the Sodus Village WWTP were:
• The average BODs and TSS removal efficiencies were 25 and 38 percent,
respectively. Typical BODs and TSS removal efficiencies for primary clarifiers are
35 and 65 percent, respectively. The poor performance was likely due to solids
buildup in the clarifier. The solids were removed once or twice per week.
• The trickling filter was providing only minimal treatment under current loading
conditions.
• The aeration basin operated as an extended aeration facility. The existing
aeration equipment was able to maintain the DO concentration over 1.0 mg/L at
all times. The average DO was greater than 3.0 mg/L for significant periods
during the study.
• The measured standard oxygen transfer efficiency (SOTE: 20oe, a mg/L ~O) of the existing aeration equipment was 21 percent.
• Pressure relief valves on the air piping were open between the aeration blowers
and the aeration basin, resulting in a constant venting of pressurized air to
atmosphere.
• The secondary clarifiers were not performing as expected. This was likely due to
a solids flux failure and bottlenecks in removing settled solids from the clarifier.
• The secondary effluent solids concentration regularly increased during the day.
The pattern observed indicated a solids flux limitation in the clarifier. The solids
removal mechanisms and RAS pumps should be upgraded if the secondary
clarifier remains in service.
• The NH3-N concentration in the final effluent averaged 6.7 mg/L, which is
greater than the effluent discharge requirement of 2.0 mg/L. This was likely the
result of directing flow from the trickling filter to the secondary clarifier, thus
bypassing the aeration basin. The operators bypassed the aeration basin to
reduce the solids loading to the secondary clarifier. The trickling filter did not
provide nitrification under current loading conditions.
2·8
-
• The check valves on the secondary pumps were not operating correctly, resulting
in pumped secondary effluent being returned to the wet well through the
standby pump.
• The biogas collection system for the anaerobic digester was inoperable. The
digester cover was corroded and leaked biogas to the atmosphere. The gas
collection system was plugged and the digester was venting through the
emergency overflow vent. This represented a significant health and safety
concern for the site, as well as a loss of useable energy.
VILLAGE OF GOSHEN WWTP
Figure 2-2 presents a flow schematic and Table 2-4 summarizes the unit processes of the Village of
Goshen WWTP. Wastewater, consisting mainly of domestic, institutional, and commercial sewage,
flows by gravity to the WWTP. The design capacity of the WWTP is 1.5 mgd and the current
measured average day flow is 1.23 mgd. The discharge criteria for the facility are 25 mg/L BODs
and 25 mg/L TSS.
The wastewater flows by gravity through a manually cleaned bar screen and grit chamber to a
distribution box that divides the flow among three primary clarifiers. The screenings and grit are
transported to a landfill. After primary clarification, the wastewater flows by gravity through two
trickling filters to the trickling filter wet well, where it is pumped to the secondary clarifiers.
Wastewater from the secondary clarifiers flows by gravity through the chlorine contact chamber to
the two effluent polishing lagoons. The effluent polishing lagoons are operated in series. The treated
effluent is discharged into the Rio Grande Creek.
Solids from the secondary clarifiers are pumped on a continuous basis to the primary clarifier
distribution box for co-settling in the primary clarifier. The combined sludge from the primary
clarifier is pumped twice per day to the primary anaerobic digester. A dual fuel gas boiler is used to
heat the digester contents. The digester is mixed for approximately 16 hours per day with a digester
recirculation pump. The primary digester mixing pumps are switched off for approximately eight
hours each day when the combined sludge is pumped into the primary digester.
Digested sludge flows by gravity from the primary to the secondary digester. Supernatant from the
secondary digester flows by gravity to the primary clarifier distribution box. Digested sludge is
2·9
-
../JUN/U
BAR
SCREENS
TRICKLING .fB!.MAIr! FILTER SECONPARY CHLORINE ~
GRIT CHAMBER CLARIFIER CLARifiER ~ SYSTEM BAY1
SEWAGE
I I I I I I I I
FILTER RECYCLECOMMINUTOR I I I I I I
DISPOSAL ~------:--------------~~~~~~~~~=------------j.----------- ------- I DIGESTERI SUPERNATANT ...----'. I I I I
I SlUDGE _~--------~ .1l--e----
--, r- I I SLUDGE DRYING
BEDSl$~ DISPOSAL SOUDS • I I ~DlOESTE~ •-E1 ~~~~~~ L10UID
SECONDARY ~ DIGESTER DRYING BED SUPERNATANT
flQUFE 2-2 GOSHEN W.W.T.P.
PROCESS ROW SCHEMATIC 2OOK1a1OD.OJ PfUClLDWG
C> ~
http:2OOK1a1OD.OJ
-
TABLE 2-4
VILLAGE OF GOSHEN WWTP - SUMMARY OF UNIT PROCESSES
Unit Process Number Description
Bar screen 1 Manual cleaned
Grit chamber 1 Circular
Primary clarifier 2 Area = 768 fe (per unit) 64 ft x 12 ft; 7.25 ft deep
1 Area = 960 fe (per unit) 60 ft x 16 ft; 7 ft deep
Trickling filter 2 Area = 2,827 fe (per unit) Volume = 19,792 fe Dia. = 60 ft; rock 7 ft deep
Secondary clarifier 2 Area = 936 fe 52 ft x 18 ft; 6.5 ft deep
Chlorine contact chamber 1 Area = 828 fe Volume = 4,140 fe
Polishing lagoons 1 Area = 10.5 acres Volume = 3.85 million gal.
1 Depth 12 to 15 inches Area = 10.5 acres Volume = 15.4 million gal. Depth 4.5 feet
Digester 1 Primary digester - fixed roof Max volume = (25,450 fe) 190,400 gal. Dia. = 45 ft; SWD = 16 ft
1 Secondary digester - floating roof Max volume = (35,000 fe) 261,800 gal. Dia. = 45 ft; SWD = 19 ft
Sludge drying beds 4 Area =11,250 fe (per unit)
removed from the secondary digester every 45 to 60 days. Approximately 25 to 30 cubic feet of
digested sludge are removed from the secondary digester and placed on sludge drying beds. The
drainage from the sludge drying beds is pumped to the primary clarifier distribution box.
Performance History
The average-day flow for the Village of Goshen WWTP for June 1995 to June 1996 was 1.23 mgd.
However, the flow is highly variable. During dry weather periods (June through September 1995) it
averaged between 0.7 and 1.0 mgd. During wet weather it increased to over 3.0 mgd. The flow
2-11
-
distribution pattern indicated there was a significant contribution from infiltration/inflow in the raw
sewage flow to the plant.
The historical TSS and BODs loadings to the Village of Goshen WWTP averaged 1,350 and 1,190
lb/day, respectively. The Sorrento cheese factory is the only major industrial source in the sewerage
area. During the first quarter of 1995, Sorrento's pretreatment system (activated sludge) experienced
process upsets, resulting in an increase in the organic load to the plant. As a result, the TSS and
BODs loadings were significantly greater during the first quarter of 1995. The average TSS and BODs
concentrations for January, February, and March 1995 were 241 and 173 mg/L, respectively. The
average TSS and BODs concentrations for the 19-month period of record examined were 135 and 124
mg/L, respectively.
The TSS and BODs concentrations in the final effluent from the Village of Goshen WWTP from
January 1995 to June 1996 were 3.8 and 2.8 mg/L, respectively. This is well below the effluent
discharge requirement of 25 mg/L for BODs and 25 mg/L for TSS. The average TSS and BODs
removal efficiencies were 96.6 percent and 97.2 percent, respectively. The WWTP provides a very
high standard of treatment. The BODs and TSS removal efficiencies were greater than 90 percent for
more than 98 percent of the time over the 18-month period examined.
The average daily volume of sludge pumped to the primary digester was 8,083 gallons per day. The
solids concentration in the co-settled sludge was not measured. The flow control gate on the sludge
withdrawal line from each clarifier is opened manually.
The average electrical consumption from November 1994 to July 1995 was 870 kWh per day. The
energy use remained significantly higher during the winter months. This was likely due to the
increase in flow rate and electrical heating requirements during the winter.
The average propane consumption from 1993 to 1996 was 9,925 gallons per year. Propane is used to
heat the primary digester. During the summer months of 1993 and 1994, biogas collected from the
primary digester was used for most of the heating requirements. During 1995 and 1996, the WWTP
was not able to collect biogas and therefore average propane consumption increased from 20.3 to
34.1 gallons per day.
2·12
-
Field Test
The Village of Goshen WWTP field test program was conducted from July 16 to August 15,1996.
Table 2-5 presents a comparison between the unit process loadings and effluent quality during the
field test program and historical values for the facility. The hydraulic loading to the treatment plant
was similar to the historical values. However, the raw sewage BODs and TSS concentrations were
significantly lower. The average BODs and TSS concentrations during the test period were 67.2 and
88.9 mg/L, respectively. Therefore, the organic loading on the Village of Goshen WWTP was
approximately half of the historical average for the facility.
TABLE 2-5 VILLAGE OF GOSHEN WWTP - SUMMARY OF UNIT PROCESS LOADING DURING FIELD TEST PROGRAM
Unit Process Units Field Test Historical
Average Maximum Average Maximum
Loading
Hydraulic Mgd 1.16 3.28 1.23 3.41
Organic
BODs Mg/L 67.2 96 124 Ibid 571 829 1,193 2,203
TSS mg/L 88.9 134 135 Ibid 807 1270 1,352 2,841
Effluent Quality
BODs Mg/L 1.9 3.0 2.8
TSS Mg/L 3.2 6.0 3.8
Primary Clarifier
Surface overflow rate Gpd/£e 464 1,314 492 1.362
Trickling Filter
Surface wetting rate Gpm/fe 0.14 0.40 0.15 0.42
BOD. loading rate a Ibid 1,000fe 7.8 16.6 19.6 36.2
Secondary Clarifiers
Surface overflow rate Gpd/fe 620 1,752 657 1,822
Chlorine Contact Chamber
Hydraulic residence time Min 38 14 36 13
Effluent Polishing Lagoons
Lagoon 1 HRT Day 3.3 1.2 3.1 1.1
Lagoon 2 HRT Day 13.3 4.7 12.5 4.5
Total Day 16.6 5.9 15.6 5.6
Primary Digester
Hydraulic residence time b Day 23.8 23.5
VS loading C VSSlb/day 400
Notes:
a Based on primary effluent average and maximum BODs of 311 and 658lb/day, respectively
b Based on measured sludge pump rate
C Based on mass balance around the primary clarifier
2·13
-
Field testing consisted of offline sampling, online monitoring, and performance testing of specific
equipment and processes. The offline sampling results were based on 24-hour composite samples
and grab samples collected at various points in the process. The online data consisted of data from
existing flow metering equipment supplemented with a temporary solids concentration meter in the
secondary clarifier effluent. The performance testing consisted of stress testing of the primary and
secondary clarifiers, a mixing evaluation of the primary digester, and performance testing of the
secondary effluent pumps. Table 2-6 summarizes the work done. Detailed test descriptions and
results are presented in the Village of Goshen WWTP Site Report (CH2M HILL, 1998c).
TABLE 2-6
VILLAGE OF GOSHEN WWTP - FIELD TEST PROGRAM
Offline Sampling Program
Sample Location Frequency Type of Sample Analysis
Raw sewage 2nd day 24h cBODs' TSS, VSS, ~-N, BODs, N02-N, N03-N, TKN
Primary effluent 2nd day 24h cBODs' NH3-N, TKN, TSS, VSS, BODs, Nq-N, N03-N
Trickling filter effluent 2nd day 24h TSS, VSS, cBODs' BODs, ~-N, N02-N, N03-N
Secondary effluent 2nd day 24h cBODS' ~-N, TKN, TP, TSS, VSS, BODS' N02-N, N03-N
Digester supernatant l/week grab cBODS' TKN, TP, TSS
Co-settled sludge 2/week grab TSS, VSS
Online Monitoring Program
Location Type Data
Secondary effluent Flow 1 existing meter - weir Suspended solids 1 temporary meter
Performance Testing
Location Type Analysis
Primary clarifier Stress test Capacity
Secondary clarifier Stress test Capacity
Pumps Performance "Wire to water" efficiency
Digester Profile Mixing
2·14
-
The main conclusions from the field study of the Village of Goshen WWTP were:
• Primary clarifier performance was poorer than expected. This was partly due to
poor hydraulic distribution among the three clarifiers.
• The secondary sludge pumps operated continuously, recycling an excessive
amount of water through the plant.
• The secondary pump on/off operation resulted in frequent pump cycling and
continual small hydraulic perturbations to the secondary clarifier. This had a
significant negative impact on clarifier performance.
• The hydraulic throughput of the plant was less than 3.5 mgd. Significant
hydraulic bottlenecks occurred at the plant headworks, between the primary
clarifier and trickling filter, and at the chlorine contact chamber outfall.
• The measured capacity of the primary clarifiers was 1.5 mgd. The capacity could
be increased by improving the flow distribution between the clarifiers.
• The measured capacity of the secondary clarifiers was 3.0 mgd. The secondary
clarifier performance was reduced due to the on/off operation of the secondary
pumps.
MARSH CREEK WWTP
Figure 2-3 presents a flow schematic and Table 2-7 summarizes the unit processes of the Marsh
Creek WWTP. Wastewater flows by gravity to the WWTP and consists mainly of domestic and
commercial sewage. Hauled leachate is brought to the plant and mixed with the raw sewage
upstream of the primary clarifier. The rated capacity is 4.0 mgd and the average day flow is 3.35
mgd. There are no bypass structures. All wastewater generated by the catchment area must be
treated by the plant. The discharge criteria for the facility are 30 mg/L BODs, 30 mg/L TSS, and 1.0
mg/L total phosphorus (TP).
The wastewater flows by gravity through the primary clarifiers, aeration basins, and the secondary
clarifiers, and receives chlorination before discharge. Primary sludge pumped from the primary
2-15
-
04/JUN/O.
CHLORINATION ..ERl.MARY AE~ A~N S&E1lN~ARYCLARifiER ~ I RIIER
RAW SEWAGE PRIIiARY EFFLUENT
D 0 0 0 0 ••• °000° 0 1 OODODOOOOOOo·ooo.:oooo --lI aD OOOClOO~O o:~.: 0°0"0000°••SUPERljATANT ,RETURNS
I , I , IPRIIiARY SWDGE : I I
I I I
I
I
1""---------- --""'8--' ~----------~---~~~~~~~~-~!:~-I--------------f I I
I I
I I
I ,...-----I ----------------------------------~---~~~~~~~~~~~~--I--------------; I I
I I
I I I COMPOST
I AMENDMENTI
I
I
b ,-I I I II I OFT-GAS I II ,III
I I
,
I
I
T~,~~~lJRI t.I ________ _ I DISPOSAL
BELT FI~ER :
I
I
~ ,I
I .>T=r< l tI _____ _
CLASSIFIER L----H-
SECONpARY COMPOSTL._____ sW! ~DIGESTER PI AL
SOUDS
UQUID
AGUREH MARSH CREEK W.W.T.P.
PROCESS A.OW SCl-EMAlIC :1(101(10100.05 PIa211JYNG
COMPOST
STORAGE
.fIID.Wrl DIGESTER
~ '"
http:1(101(10100.05
-
TABLE 2-7
MARSH CREEK WWTP - SUMMARY OF UNIT PROCESSES
Unit Process
Primary clarifier
Aeration basin
Diffusers
Aeration equipment blowers
Secondary clarifier
Gravity thickener
Digester
Belt filter press
Compost facility
Number Description
2 Area = 707 fe (per unit)
Volume = 211,792 gal. (total)
Diameter = 30 ft
2 Area = 3,384 fe (per unit)
Volume = 750,000 gal. (total)
Depth = 14' 5"
Fine bubble Area per diffuser = 48 ft2 Number per tank = 38 Submergence = 13' 11"
2 60hp Variable speed, manually controlled
1 100hp Variable speed, manually controlled
2 Area = 707 ft2 (per unit)
Volume = 211,792 gal. (total)
Diameter = 30 ft
2 Volume = 77,141 gal. (per unit) Dia. = 25 ft2 Side wall depth = 16.5 ft
1 Primary
Volume = 500,000 gal.
1 Secondary
Volume = 500,000 gal.
1 Width =6ft
1 Capable of producing 2.5 dry tons of finished product per day
clarifiers passes through a grit classifier and then is pumped to a gravity thickener. Grit removed by
the classifier is disposed of offsite.
Air is supplied to the aeration basin by one 100-hp and two 60-hp blowers through fine bubble
membrane panel diffusors. WAS removed from the secondary clarifier is pumped to a gravity
thickener prior to being pumped to the primary digester.
There is one primary digester and one secondary digester. Sludge is fed to and removed from the
digesters by pumps. Hot water circulation is used to maintain the temperature in both digesters.
2·17
-
Methane gas produced by the digesters is used as the fuel source for heating, supplemented with
natural gas on an as-needed basis.
Sludge from the secondary digester is pumped to a belt filter press (BFP) for dewatering. Filtrate
from the BFP is fed back to the headworks of the plant. Dewatered sludge is moved by conveyor
from the BFP to the compost facility. The compost facility is a batch feed facility. Wood chips are
added to the sludge as an amendment material prior to composting. Three local businesses are
contracted to purchase the compost produced by the WWTP for use as a soil conditioner in
agricultural and horticultural activities.
Performance History
The average-day flow to the Marsh Creek WWTP between January 1995 and May 1996 was 3.35
mgd. There is a pronounced seasonal variation in flow, with low flows occurring during the dry
weather period of June to September. The minimum and maximum day flows for the period were
1.75 and 12 mgd, respectively. The hydraulic peaking factor was over 4.0. This high value indicates
an inflow and infiltration problem within the collection system.
The average BODs and TSS concentrations in the raw sewage flow to the WWTP for January 1995 to
May 1996 were 228 and 176 mg/L, respectively. The BODs concentration was reasonably consistent
over the period of record, but the TSS concentration fluctuated widely. The high BODs and the TSS
concentrations can be attributed to the introduction of leachate and hauled waste to the raw sewage
at the headworks of the plant as well as sewage from local food processing plants. The average ortho
phosphate (P04) concentration of the raw sewage between January 1995 and May 1996 was 2.7
mg/L. The average BODs and TSS loads to the plant were 6,032 lb/day and 4,908 lb/day,
respectively.
The average final effluent concentrations for BODs, TSS, and P04 were 22 mg/L, 10 mg/L, and 0.4
mg/L, respectively. The average concentrations for BODs and TSS are below the discharge criteria of
30 mg/L for both parameters. The average removal efficiencies were 90 percent, 90 percent, and 82
percent for BODy TSS, and P04' respectively.
The average MLSS concentration for the aeration basins at the Marsh Creek WWTP from January
1995 to May 1996 was 2,275 mg/L. The average solids residence time (SRT) for the WWTP was 3.9
days. The SRT was less than 6 days for over 95 percent of the time. The average food to
2·18
-
microorganism (F/Mv) ratio, based on the ratio of BODs loading to the aeration basin and the mixed
liquor volatile suspended solids (MLVSS) concentration, was 0.31 dail.
The RAS flow rate for the Marsh Creek WWTP is controlled by two single-speed pumps, each rated
for a capacity of 1 mgd. The flow is not measured but can be controlled by adjusting the pump
speed setting.
The average SVI was 84 mL/g. The low SVI indicated a very well-settling sludge.
The percentages of total dry solids that were volatile for both the raw and digested sludge were 69
percent and 55 percent, respectively. The volatile destruction in the primary digester was 45 percent.
The average hydraulic residence time (HRT) of the primary digester was 42 days.
The BFP is used to dewater the digested sludge prior to composting. The average percentage of
solids of the digested sludge feed to and from the BFP was 2.95 percent and 21 percent, respectively.
The average monthly electrical usage for the Marsh Creek WWTP was 124,235 kWh between
January 1995 and May 1996. There appeared to be a trend of increasing electrical usage by the
WWTP over the 15-month period. This was likely due to increased influent flow and increased
organic load to the aeration basin.
Field Test
The Marsh Creek WWTP field test program was conducted from May 28 to June 28,1996. Table 2-8
presents a comparison between the unit process loadings and effluent quality during the field test
program and historical values for the facility. The unit process loadings were similar to historical
values.
Field testing consisted of offline sampling, online monitoring, and performance testing of specific
equipment and processes. The offline sampling results were based on 24-hr composite samples and
grab samples taken at various points in the process. The online data consists of data from permanent
plant monitoring equipment supplemented with temporary instruments. The following parameters
were measured using permanent instrumentation: plant flow, RAS flow, WAS flow, and air flow.
The temporary instruments included DO probes and an MLSS probe in the aeration basins.
Performance testing included oxygen transfer efficiency testing of the aeration equipment and a
2·19
-
TABLE 2-8
MARSH CREEK WWTP - SUMMARY OF UNIT PROCESS LOADING DURING FIELD TEST PROGRAM
Unit Process Units Field Test Historical
Average Maximum Average Maximum
Loading Hydraulic Organic
BODs
TSS
Mgd
Ibid mg/L Ibid
mg/L
3.63
6,015 199
7,255 240
12.64
NA 282 NA 425
3.35
6,032
4,908
12
9,762'
13,026'
Primary Clarifier (1,414 ff) Surface overflow rate Gpd/fe 2,567 8,939 2,369 8,486
Aeration Basin (200,520 fe) BODs loading rate MLSS concentration
lbI d per 1,000 fe mg/L
17.0 1,942
33.5 2,340
18.7 2,275
Secondary Clarifiers (1,414 fe) Surface overflow rate Solids loading rate
Gpd/fe lb/hper fe
2,567 2.7
8,939 3.9
2,369 1.9
8,486 6.7
Belt Filter Press Solids concentration in Solids concentration out
% %
2.7 23.2
2.9 21
Note: Maximum values are 95th percentile values from historical review.
tracer test on the primary digester. Table 2-9 presents a summary of the field test activities. Detailed
test descriptions and results are presented in the Marsh Creek WWTP Site Report (CH2M HILL,
1998d).
The major conclusions from the field study of the Marsh Creek WWTP were:
• The organic loading to the Marsh Creek WWTP was highly variable. This was
likely the result of the hauled leachate and industrial wastewater received at the
site.
• The increase in organic loading that started Monday mornings had a negative
impact on the DO concentration in the aeration basins. The DO was less than 1.0
mg/L for most of the day and recovered at night and on the weekends. BOD
2·20
-
TABLE 2-9
MARSH CREEK WWTP - FIELD TEST PROGRAM
Offline Sampling
Sample Location Frequency Type of Sample Analysis
Raw sewage Daily 24h CBODs, TSS, VSS, TP
Primary effluent Daily 24h CBODs, NJ\-N, TSS, VSS, TP
Secondary effluent Daily 24h CBODS' TKN, TSS, TP, N03-N, N02-N, NH3-N
Gravity thickener l/week grab TS/TSS, VSS info & eff.
Gravity thickener l/week grab CBODS' TS/TSS, TP, TKN recycle
Belt press in & out l/week grab TS
BFP filtrate l/week grab TKN, TP, cBODs, TSS, NJ\-N
MLSS 2/week grab TSS, VSS
RAS 2/week grab TSS
Leachate NA grab CBODS' NJ\-N, TSS, VSS
Online Monitoring Program
Location Type Data
Raw sewage Flow 1 existing meter - magmeter
RAS Flow 2 existing meters - magmeter
WAS Flow 1 existing meter - magmeter
Air Flow 1 existing meter - orifice plate
Aeration basin Dissolved oxygen 5 temporary meters Solids (MLSS) 1 temporary meter
Performance Testing
Location Type Analysis
Aeration basin Offgas Oxygen transfer efficiency
Digester Tracer Mixing
breakthrough occurred occasionally. Final effluent concentrations were greater
than 60 mg/L.
• The measured standard oxygen transfer efficiency (SOTE: 20°C, 0 mg/L DO) of
the membrane panel aeration system was 18 percent.
2-21
-
• Marsh Creek WWTP provided partial nitrification during the first two weeks of
the study period, and almost complete nitrification during the second two weeks.
The switch from partial to full nitrification did not have a negative impact on the
effluent quality.
• Hydraulic loading increased rapidly during storm events, from an average of
3.35 mgd to 12 mgd. However, the sudden increase in flow did not have a
negative impact on the TSS concentration in the final effluent.
• The digester provided 45 percent volatile solids destruction. The level of volatile
destruction was lower than expected. Expected reduction in volatile solids was
between 50 and 55 percent. This may have been the result of poor mixing in the
digester.
• The measured active volume of the primary digester was 79 percent of the total
volume available. Approximately 6 percent of the pumped sludge short-circuited
the digester volume.
ARLINGTON SEWAGE TREATMENT PLANT
Figure 2-4 presents a flow schematic and Table 2-10 summarizes the unit processes of the Arlington
sewage treatment plant (STP). Wastewater, consisting mainly of domestic, institutional, and com
mercial sewage, flows by gravity to the STP. The design capacity of the STP is 4.0 mgd and the
current average-day flow is 3.44 mgd. The discharge criteria for the facility are 30 mg/L BODs and
30 mg/L TSS. The plant does not have an ammonia removal requirement. However, operators are
required to measure the ammonia concentration and include the result as part of the monthly
summary report to the NYSDEC.
The wastewater flows by gravity through a coarse bar screen to the aerated grit chamber and
comminutor. The screenings and grit are transported to a landfill. The degritted sewage flows by
gravity to a primary clarifier distribution chamber. Supernatant from sludge thickeners and filtrate
from the BFP are combined with the raw sewage and the combined flow is distributed to four
primary clarifiers. The primary sludge is pumped from the primary clarifiers to the gravity
thickeners.
2·22
-
../JUN/a6
.flAB ~ SCREENS ~RIT CHAMBER
RAW
SEWAGE
~
,..----I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
.YB!I --------t.-----D--.llRII
SEPARATOR
SOUDS
LIQUID
BYPASS
2QOK101DO.OS Pl8007.dwll
STORNWATER BYPASS .--------------------------,. . AERATION BruSS COMMINUTOR ! PRIMARY r---~~~~;;,-----T- --;E~~~~~--: CHLORINE
I CLARIFIER I ~ I CLARIFIER I CONTACT .1 •Lj -W
r :0: 00:: :0: D. °0 00°0
000000 0 00 0 0
°jPDjOjOOp oj i
I
SUPERNATANT I AERATION R£TURNS I BLOWERS
I
________________ JI
I
I
I
I
I
~--~~~!~~~~~~~~~---L-------~-~~!~~~~~-~~~~--~ OFr-GAS.HtAI
EXCHAllrGER
SCRUBBER GRAVITY
THICKENER
L BELT FILTER PRESS
I f--EI- • ( ) ( D~L.tT~RED Jat. ------~-~--I DISPOSAL-------~
INCINERATOR
INCINERATOR ~
AQUAE 2-4
AFUNGTON STP
PROCESS FLOW SCHEMAlIC
c.:>
I\)
'"
http:2QOK101DO.OS
-
TABLE 2-10
ARLINGTON STP - SUMMARY OF UNIT PROCESSES
Unit Process
Bar screen
Grit chamber
Primary clarifier
Aeration basin
Diffusers
Aeration equipment blowers
Secondary clarifier
Chlorine contact chamber
Gravity thickener
Belt filter press
Incinerator
Number
2
1
2
2
3
(2 in service)
2 1
3
3
2
1
1
Description
Mechanical clean
Aerated with dedicated blower
Area =2,088 fe (per unit) 116 ft x 18 ft; 8.67 ft deep Area =891 ft2 (per unit) 49.5 ft x 18 ft; 8.33 ft deep
Area =3,942 fe (per unit) Volume =45,176 ft3 (per unit) Depth =12ft Coarse bubble Area per diffuser =14 fe Number per tank =280 Submergence =11.5 ft 60hp Positive displacement, variable speed drive 60hp Positive displacement, split ring drive
Area =2,088 fe (per unit) 116 ft x 18 ft; 8.67 ft deep
Area =695 fe (per unit) Volume =4,517 fe (per unit) Volume =5,772 fe (per unit) Dia. =26 ft; depth =10 ft Width =1m Fluidized bed 800 lb Ihr dry solids
The primary clarifier effluent is recombined in a common primary effluent channel that connects the
three aeration basins. Under loading conditions prior to and during the test, two of the three
aeration basins were in service. The aeration basins can be operated as plug-flow or step-feed basins.
Air is provided to the aeration basins by three positive displacement blowers. Two of the three
blowers have variable-frequency drive systems, and the third blower has a manually operated split
disk drive system. The Arlington STP has an automatic DO control system, which operates the
blowers based on the DO measurement in the aeration basin.
2-24
-
The Arlington STP has three rectangular secondary clarifiers. There is an approximately lO-foot
hydraulic drop between the aeration basins and the secondary clarifiers. In the past, air entrainment
due to the free-fall discharge and turbulence in the aeration basin discharge channel was a problem.
The operators use an automated valve to control the water surface level in the aeration basin
discharge channel to ensure that the aeration basin outfall remains flooded and the pipe to the
secondary clarifier is submerged at all times.
The RAS is pumped from the secondary clarifier to the head of the aeration basin. Two RAS pumps
service three clarifiers. The RAS is measured with magnetic flow meters located at the entrance to
each aeration basin. Sludge is wasted from the RAS line using a manually operated bypass valve
located on the combined RAS line. The WAS is combined with the primary sludge in the gravity
thickeners.
The secondary effluent flows by gravity through the chlorine contact chamber and to final discharge
in the Hudson River.
The Arlington STP has two bypass systems, the stormwater bypass and the secondary bypass. The
stormwater bypass uses an overflow weir to divert raw sewage from the primary clarifier
distribution chamber to the inlet channel for the secondary clarifiers. The secondary bypass uses an
overflow weir to divert primary effluent from the aeration basin inlet channel to the chlorine contact
chamber. During a storm event, flows in excess of 4.5 mgd receive primary clarification and
disinfection only, and flows in excess of 6.0 mgd receive secondary clarification and chlorination
only. The maximum flow to the Arlington STP is 8.0 mgd. Therefore, the maximum flow to the
primary clarifiers is 6.0 mgd, the maximum flow to the aeration basins is 4.5 mgd, and the
maximum flow to the secondary clarifiers is 6.5 mgd (4.5 mgd from the aeration basin and 2.0 mgd
from the stormwater bypass).
Solids from the primary clarifiers are pumped to the gravity thickener for co-thickening with the
WAS. The thickened sludge is then pumped to the BFP and into the sludge incinerator. Since
February 1996, the BFP and sludge incinerator have operated for approximately six hours every day
(during the evening shift). Prior to this date, the belt press and incinerator operated approximately
once per week.
2·25
-
Performance History
Ihe average-day flow to the Arlington SIP was 3.45 mgd between January 1995 and June 1996, and
the maximum instantaneous flow recorded was 8.9 mgd. Therefore, the hydraulic peak factor is
approximately 2.5 for the period of record.
The ISS and BODs concentrations in the raw sewage flow to the Arlington SIP for January 1995 to
June 1996 were 124 and 130 mg/L, respectively. The average ISS and BODs loadings to the
treatment plant were 3,542 and 3,6741b/day, respectively.
The average ISS and BODs concentrations in the final effluent from the Arlington SIP from January
1995 to June 1996 were 7.5 and 6.7 mg/L, respectively. This is well below the effluent discharge
requirement of 30 mg/L for each parameter. The average BODs and ISS removal efficiency for the
facility was 94 percent. The Arlington SIP provides a good standard of treatment. The BODs and
ISS removal efficiencies were greater than 90 percent approximately 80 percent of the time between
January 1995 and June 1996.
The average MLSS concentration in the two aeration basins in service was 1,050 mg/L. The MLSS
concentration was significantly lower in the warmer period (wastewater temperature) of June
through October. During this time, operators have reduced the solids inventory in the aeration basin
by reducing the MLSS concentration in an attempt to prevent nitrification. The average MLSS
concentration for the months of November through June was 1,150 mg/L; the average MLSS
concentration for the months of July through October was 720 mg/L.
The F/Mv ratio for the Arlington SIP during the 18-month period was 0.65 dail. The F/Mv ratio
was very high in September and October 1995 due to the low MLSS concentration in the aeration
basin at the time. The SRI for the plant from January 1995 to June 1996 was 4.9 days. Other than on
a few days, the SRI remained below six days for the period of record.
The average solids concentrations for the thickened and dewatered sludge from January 1995 to
December 1995 were 3.6 and 20.6 percent dry solids, respectively. Starting in February 1996, the
Arlington SIP operated the dewatering and incineration process every day during the evening shift.
Prior to February, the dewatering and incineration process was operated once a week for
approximately 36 hours. Ihe change in operation resulted in an increase in the dewatered sludge
solids concentration from 20.6 percent dry solids in 1995 to 25.6 percent dry solids in July 1996. The
2-26
-
solids concentration in the dewatered sludge had a significant impact on the fuel consumption in the
incineration process.
The average electrical consumption for the Arlington STP from December 1993 to June 1996 was
5,270 kWh/day. The average oil consumption from January 1995 to June 1996 was 180 gallons per
day. The fuel oil was primarily used for the sludge incineration process. The average oil
consumption per pound of solids processed was 65 gallons/lb during 1995 and 12 gallons/lb in July
and August 1996. As noted above, the incinerator oil consumption was influenced by the solids
concentration in the dewatered sludge.
Field Test
The Arlington STP field test program was conducted from July 17 to August 25, 1996. Table 2-11
presents a comparison between the unit process loadings and effluent quality during the field test
program and historical values for the facility. The hydraulic and organic loadings to the treatment
plant were similar to the historical values.
Field testing consisted of offline sampling, online monitoring, and performance testing of specific
equipment and processes. The offline sample results were based on 24-hour composite samples and
grab samples taken at various points in the process. The online data consists of data measured from
temporary instruments installed for the test period and the existing online metering equipment at
the site. The temporary instruments included 00 meters installed in the aeration basin, solids
concentration meters in the aeration basin, and solids concentration meters in the final effluent. Plant
metering was used to monitor raw sewage flow, RAS flow, WAS flow, and total air flow. The
performance testing consisted of oxygen transfer efficiency testing of the existing aeration
equipment, and "wire to water" performance testing of the aeration blowers, incinerator fan, and
the RAS pumps. Table 2-12 summarizes the work done. Detailed descriptions and results are
presented in the Arlington STP Site Report (CH2M HILL, 1998a).
The main conclusions from the field study period for the Arlington STP were:
• The primary clarifiers performed well. The average BODs and TSS removal
efficiencies were 47 percent and 65 perce