o&m contract management

72
SUMMER INTERNSHIP REPORT ON Developing a Strategic Business Model of Operation & Maintenance Contract Services for Thermal Power PlantStudy done at: Thermax Limited, Pune (MS) Submitted By: PRAVEEN THAKRE ROLL NO. 63, II Year MBA (POWER MANAGEMENT) August-2011 Affiliated to: MAHARSHI DAYANAND UNIVERSITY, ROHTAK (HARYANA)

Upload: vineetawasthi

Post on 01-Oct-2015

325 views

Category:

Documents


9 download

DESCRIPTION

o&m of power plant

TRANSCRIPT

  • SUMMER INTERNSHIP REPORT

    ON

    Developing a Strategic Business Model of Operation &

    Maintenance Contract Services for Thermal Power Plant

    Study done at:

    Thermax Limited,

    Pune (MS)

    Submitted By:

    PRAVEEN THAKRE

    ROLL NO. 63, II Year

    MBA (POWER MANAGEMENT)

    August-2011

    Affiliated to:

    MAHARSHI DAYANAND UNIVERSITY, ROHTAK (HARYANA)

  • 2

    DECLARATION

    I, Praveen Thakre, Roll no. 63, student of MBA (Power Management, 2010-2012) of Centre

    for Advanced Management and Power Studies at National Power Training Institute,

    Faridabad (Haryana), declare that the Summer Training Report entitled Developing a

    Strategic Business Model of Operation & Maintenance Contract Services for Thermal

    Power Plant is an original work and has not been submitted to any other institute for the

    reward of any other degree.

    A seminar presentation of the training report was made on..and the suggestions as

    approved by the faculty were duly incorporated.

    Dr. Rohit Verma Praveen Thakre

    Project Incharge MBA (Power Mgmt)

    NPTI Faridabad NPTI Faridabad

    Counter Signed

    Director/Principal of the Institute

  • 3

    CERTIFICATE

    This is to certify that Mr. Praveen Thakre student of MBA (Power Management), IX-Batch

    (2010-12), of Centre for Advanced Management and Power Studies, at National Power

    Training Institute, Faridabad (Haryana), has successfully undergone 8 weeks professional

    summer training from 13th-June-2011 to 5

    th-August-2011 at our Pune Head Office.

    During the training he has worked on the project entitled Developing a Strategic Business

    Model of Operation & Maintenance Contract Services for Thermal Power Plant.

    He took keen interest in this assignment and also actively participated in development activities

    related to other projects.

    We wish him all the best in his future endeavour.

    (Santosh Katkar)

    Dy. Manager, O&M Group

    Thermax India Ltd. Pune

  • 4

    ACKNOWLEDGEMENT

    Words shall never be able to pierce through the Gamuts of emotions that are suddenly exposed

    during the routine of our life. They shall never be able, neither to describe the spirit with which we

    worked together nor shall they ever be able to express the feeling I felt towards my guide

    Mr. Santosh Katkar (Deputy Manager, O&M Group).

    On the behalf of my MBA career, first of all, I am highly obliged to Mr. J.S.S. Rao, Principal

    Director (CAMPS) NPTI, MR. D.M. Lokhande, Director (CAMPS) NPTI, Mrs. Manju

    Maam, Deputy Director (CAMPS) NPTI, and Mrs. Indu Maheshwari, Deputy Director

    (CAMPS) NPTI, who gave me the opportunity to do summer internship in a pioneer organization

    like Thermax Ltd. I am also thankful to my internal guide Dr. Rohit Verma, Deputy Director

    (CAMPS) NPTI, for his constant encouragement and valuable advice during the course of my

    project.

    I take the opportunity to thank Mr. Anurag Chincholkar (Assistant Manager, O&M Group);

    Mr. S.K. Jit (Associate Manager, O&M Group); Mr. Aseem Barkule (Associate Manager, SPP

    Group); Mr K.P. Narayanan (Sr. Executive, O&M Group) and all those who have been

    instrumental in completion of my training and also sincere thanks to Mr. P.K. Das (HOD, O&M

    Division, Thermax) for showing me the appropriate path to follow.

    I am very much thankful to my Facultys Ms. Farida Khan, Senior Fellow (Economics),

    Mr. K.P.S. Parmar, Mr. Amit Mishra and to all my seniors for their overall support and

    guidance.

    At last but not the least, I am also very much grateful to my PARENTS for their moral support as

    this project was a struggle that was made much more difficult due to numerous reasons; some of

    error corrections were beyond our control. Sometimes we were like rudderless boat without

    knowing what to do next. It was then the timely guidance of that has seen us through all these

    odds. We would be very grateful to then for their inspiration, encouragement and guidance in all

    phases of the discretion.

    PRAVEEN THAKRE

  • 5

    ABBREVIATIONS

    TL Thermax Limited

    OEM Original Equipment Manufacturers

    O&M Operation and Maintenance

    CPP Captive Power Plants

    IPP Independent Power Producers

    SBU Strategic Business Unit

    T&T Tools and Tackles

    PO Purchase Order

    OTF Order Transfer Form

    EHS Environment, Health & Safety

    FY Financial Year

    SPP Small Power Plants

    MPP Medium Power Plants

    LPP Large Power Plants

    BOP Balance of Plant

    BTG Boiler, Turbine & Generator

    AFBC Atmospheric Fluidized Bed Combustion

    CFBC Circulating Fluidized Bed Combustion

    PF Pulverized Fuel

    LSTK Lump Sum Turn Key

    EPC Engineering, Procurement & Construction

    BOO Build, Own & Operate

    OPEX Operation Expenditure

    PAT Profit After Tax

  • 6

    Ha Hectare

    MoU Memorandum of Understanding

    NOC No Objection Certificate

    CAPEX Capital Expenditure

    CAGR Compound Annual Growth Rate

    SOP Standard of Performance

    PF Provident Fund

    EBITDA Earnings Before Interest, Taxes, Depreciation and Amortisation

    EPCOM Engineering, Procurement, Construction, Operation & Maintenance

    PFC Power Finance Corporation

    BHEL Bharat Heavy Electricals Limited

    OHSAS Occupational Health and Safety Assessment System

    MoEF Ministry of Environment and Forests

    SPCB State Pollution Conservation Board

    CRZ Central Regulation Zone

    DPR Detailed Project Report

    CWC Central Water Commission

    AAI Airport Authority of India

    BCG Boston Consulting Group

    EIA Environmental Impact Assessment

    IAA Impact Assessment Agency

    EMP Environmental Management Plan

  • 7

    TABLE OF CONTENTS

    S. No. Topic Page No.

    1 Executive Summary 9

    2 About the Organisation 10

    2.1 Thermaxs Profile 10

    2.2 Business Areas 13

    2.3 Joint Ventures and Strategic Alliances 13

    2.4 Realizing The Vision 14

    2.5 Power Division 15

    2.6 Operation and Maintenance Group 16

    2.7 Thermax Quality (EHS) Policy and Customer Focus 17

    2.8 Firms SWOT Analysis 18

    3 Project Objective 20

    4 Significance of The Study 21

    5 Introduction 22

    6 Review of the Initial Base 23

    6.1 Operation and Maintenance Business 23

    6.2 Operation and Maintenance Experience 26

    6.2.1 Current Revenues 26

    6.2.2 Profit and Loss Calculations 27

    6.2.3 Analysis of Variances 28

    6.2.4 Learnings from the Operational Proceedings 29

    6.3 Critical Assessment and Evaluation of Operation and

    Maintenance Business (SWOT)

    30

    7 Conceptualization 32

    7.1 Spend Analysis in Operation and Maintenance Contracts 32

    8 Focus on the problem 33

    8.1 Operation and Maintenance Contract Management 33

    8.2 Sub Contract Scope 35

    8.3 Various Regulations 36

    8.4 Statutory Compliance at Site 37

    8.5 Sub Contractor Selection 47

    8.6 Sub Contractor Performance Rating Index 48

    8.7 SOP for new site mobilisation - w.r.t. Compliance 50

  • 8

    TABLE OF CONTENTS

    9 Mandatory Clearances- Initial set-up of Thermal Power Plant 52

    10 Research Methodology 57

    10.1 Survey 57

    10.2 Data Collection 59

    10.3 Value Chain Analysis 59

    11 Results and Discussion 60

    11.1 Entrepreneurship Opportunity in Operation and

    Maintenance Business

    60

    11.2 Suggestions and Recommendations 61

    12 Limitations of the Study 62

    13 References 63

    13.1 Websites 63

    13.2 Books and Journals 63

    14 Annexure 64

    14.1 Order Transfer Form (OTF) 64

    14.2 Manpower Rate Comparison 65

    14.3 Data for all Running Sites 66

    14.4 Site wise Budgets 67

    14.5 General & Administrative Breakup 68

    14.6 Statutory Audit Checklist 69

  • 9

    1. Executive Summary:

    1.1. As a student of MBA Power management at CAMPS, National Power training Institute

    (Faridabad), I worked as a summer trainee with Thermax Ltd. for a period of two

    months from 13th

    -June-2011 to 05th-Aug.-2011. During this tenure I was directly

    involved in the live projects of Thermax.

    1.2. As a part of my summer training I got the opportunity to work as a team member of

    O&M group of Thermax due to which I was able to extract all the knowledge about

    O&M Contract Management as well as the Spend Analysis of a SBU (O&M division).

    This project is the outcome of excellent communication and interaction with higher

    dignitaries as well as with vendors, contractors and engineers.

    1.3. This report deals with the effective management of O&M contract through its different

    phases viz. Mobilization, Stabilization etc, and shall be able to make you aware about

    the different statutory compliance existing and cost reduction potential of a power

    plant with upcoming and totally new financial valuation method called as Spend

    Analysis.

    1.4. This report says that the primary objective of every power plant owner is to get

    constructed and to operate the plant as cost-effectively as possible to maximize profit.

    This means that the owner has to minimize besides the investment costs for

    construction the life cycle costs, which are influenced by different- factors. One of

    them is the operation and maintenance cost incurrent in course of operation period of

    the power plant.

    Cost reduction by outsourcing of O&M activities is one opportunity to meet

    such requirements. Outsourcing Operation & Maintenance (O&M) of the power

    station means optimum performance and utilisation of the power plant.

    1.5. High availability, reliability & reduced risks: are the key objectives of a power plant

    operator. Outsourcing the complete operations and maintenance of the plant to the

    Original Equipment Manufacturer (OEM) can be the best solution for maximising the

    performance of the power plant.

    anurag rawatHighlight

    anurag rawatHighlight

    anurag rawatHighlight

  • 10

    2. About the Organisation:

    2.1. Thermaxs Profile:

    Thermax Limited-Exploring new opportunities for growth:

    Thermax Limited is an engineering multinational headquartered in India with its

    subsidiaries and offices spread over 25 locations in 13 countries across the globe.

    Over the past three decades, Thermax Limited has established itself as a leading

    equipment supplier in the energy & environment space. The company, which has so far

    catered primarily to the captive power generation segment, is now looking to enter the

    utility market. Thermax took the initial steps towards this by winning its first

    equipment supply contract from an independent power producer in September 2009,

    and is currently setting up a 3000 MW supercritical boiler manufacturing facility in

    Maharashtra. The company also plans to expand its presence in the renewable segment

    with a number of innovative projects in the pipeline.

    Thermax Power-Where Experience meets Expertise:

    The first to commission captive power projects and cogen systems on

    EPC basis across a wide spectrum of industries like steel, sponge iron,

    cement, textiles and chemicals.

    Dedicated and well staffed functions exclusively for EPC.

    Completed largest number of plants with high plant availability,

    delivered on time.

    Expertise in wide range of fuels including waste heat recovery solutions

    especially for cement & steel.

    Over ` 3500 crore worth (over 900MW) power projects on EPC basis

    alone.

  • 11

    Thermax Firsts-Leading the EPC revolution with Indias first:

    EPC based power project on CFBC boiler, and combined cycle cogen

    plant in captive segment.

    Pioneered the EPC concept in mid-range for power.

    Waste heat recovery project on EPC in Steel & Cement Industry.

    Petcoke based power plant on EPC basis.

    Gas/Naphtha fed EPC plant with zero liquid effluent discharge.

    The unique distinction of completing CPP projects ahead of schedule and

    winning series of bonuses.

    Only experienced EPC Company offering O&M (EPCOM) contracts.

    Performance Matrix-

    In the Power Sector, Thermax has contracted over 60 turnkey projects aggregating over

    1600 MW of capacity. In addition, the company has installed boilers aggregating over

    4500 MW of capacity and baggasse-based boilers aggregating 1400 MW.

    Thermaxs total order book stood at ` 57.94 billion in 2009-10, which was 62% higher

    than the previous years order book of ` 35.57 billion. With this the companys order

    backlog increased by about 86% to ` 56.81 billion as on March 31, 2011. By the end of

    third quarter of 2010-11, Thermaxs total order backlog increased to ` 63.54 billion.

    This comprised ` 52.95 billion and ` 10.59 billion from its energy and environment

    solutions businesses respectively. The order backlog from its power division stood at `

    27.4 billion as of December 2010.

    The lower order book during 2009-10 was also reflected in the companys financials.

    Thermaxs total income during the year declined marginally to ` 32.35 billion from `

    33.35 billion in 2008-09. Profit after tax (PAT) declined significantly during the period

    owing to a one-time expense of ` 1.15 billion towards a business settlement. During

    the period 2005-10, the total income of the company increased at a compound annual

    growth rate (CAGR) of about 21 per cent, while PAT grew by 3.5 per cent.

  • 12

    The companys financials have improved in the current fiscal year. During the

    December 2010 quarter, it posted an operating income of ` 12.41 billion, which was 66

    per cent higher than the ` 7.48 billion registered during the corresponding quarter of

    the preceding year. The companys profit before tax also increased to ` 1.47 billion in

    the December 2010 quarter from ` 0.86 billion in the corresponding quarter of 2009.

    Financial Performance (Rs. Billion) Financials 2005-06 2006-07 2007-08 2008-09 2009-10 2010-11

    (April-

    December)

    Total Income 14.98 22.1 32.46 33.03 32.35 31.12

    EBITDA 2.09 3.16 4.51 4.53 4.34 3.39

    PAT 1.23 1.88 2.81 2.87 1.14 2.56

    Investments 4.17 5.78 5.8 1.76 3.78 --

    EBITDA: Earnings Before Interest, Taxes, Depreciation and

    Amortisation

    Source-Thermax

    Limited

  • 13

    2.2. Business Areas:

    Thermax Limited-Improving your Business is our Business: Thermax offers products,

    systems and solutions in energy and environment engineering to industrial and

    commercial establishments around the world. Its business expertise covers:

    Boilers and Heaters

    Absorption Cooling

    Waste and Water Solutions

    Chemicals for Energy and Environment applications

    Captive Power and Cogeneration Systems

    Air Pollution and Purification

    Power Plant Construction on Turnkey Basis

    Power Plant Operation & Maintenance Services

    Thermax brings to customers extensive experience in industrial applications, and

    expertise through technology partnership and strategic alliances.

    Operating from its headquarters in Pune, Maharashtra (Western India), Thermax has

    built an international sales and service network spread over South East Asia, Middle

    East, Africa, Russia, UK and the US. It has a fully fledged manufacturing setup that is

    certified for ISO 9001:2000, ISO 14001 and safety management according to OHSAS

    (ISO 18000).

    2.3. Joint Ventures and Strategic Alliances:

    Thermax has sourced cutting-edge technologies for its business operations through

    joint ventures and alliances with world technology majors, like Babcock & Wilcox,

    USA; Kawasaki Thermal Engineering Company, Japan; Eco Tech, Canada;

    Honeywell, USA; Bloom Engineering, Germany; Balcke Durr, Germany; Struthers

    Wells and Ozone Systems, USA.

    Thermax has 5 manufacturing facilities including one in China. The company has also

    developed a technology research and development facility, and has 120 patents, and 82

    national and 16 international trademarks to its credit.

  • 14

    2.4. Realizing the Vision:

    Our Vision:

    To be a globally respected high performance organization offering sustainable

    solutions in energy and environment.

    To become a leader in Operation and Maintenance of power plants, delivering

    high value to the customers.

    A commitment to excellence in what we do.

    Our Mission:

    We aspire to become a leading technology company with a global outlook

    delivering world-class products and services to customers.

    We exist to fulfil the needs of our customers best understood through an

    enlightened partnership with him.

    Our challenge is to continually expand and define new markets by expanding

    the frontiers of research and engineering and customer applications in our

    chosen field of business.

    We seek dependable partnership with our suppliers to generate a strong

    mutual interest in each others welfare.

    We live by high value of integrity and excellence in management.

    We strive to contribute substantially to the global priority areas of energy

    conservation, environment protection and enrichment of society.

    Our commitment is to create an organisation, which nurtures the talent and

    enterprise of our people, helping them to grow and find fulfilment, in an open

    culture.

  • 15

    2.5. Power Division:

    The Power Division of Thermax was set up in 1995 to address Indias burgeoning need

    for Power. The division single mindedly focused, pioneered and popularized the EPC

    (Engineering, Procurement and Construction) concept of setting power plants in mid-

    segment.

    The Power Division is divided into following groups:

    1. SPP (Small Power Plants) < 12 MW

    2. MPP (Medium Power Plant) 12-60 MW

    3. LPP (Large Power Plant) > 60 MW

    4. O&M (Operation and Maintenance) Group Up to any Size

    It offers captive power systems including cogeneration. The power plants from

    Thermax can utilize fuels like Coal, lignite, husk, and even agricultural waste (like

    baggasse in Sugar Power plants) to generate inexpensive energy, thus reducing overall

    energy costs up to 50%.

    Backed by strong competencies in thermal engineering, energy management and its

    close familiarity with a wide range of fuels, Thermax provides competitive power

    solutions. The Thermax Power Division offers captive power and cogeneration

    systems on EPC or LSTK basis.

  • 16

    2.6. Operation and Maintenance Group:

    O&M division was set up in the FY 2005 with the understanding of need arises

    due to lack of knowledge to non-power players in operating the power plant.

    It was felt that through O&M, Thermax can create a close and ongoing

    relationship with the customer, and be the first to know the of additional

    business opportunities from the existing customers.

    The operating data collected from power plants would also provide a deeper

    insight to improve the quality and reliability of power plants that will planned

    for future.

    The key objective is to keep the customers investment productive by

    continuously optimizing their operations with an aim to enhance availability,

    output, efficiency, plant life and hence indirectly creating a resource of revenue

    stream for TL.

    Being in a position to operate and maintain the power plants, and thus assuring

    the customer of long term asset productivity.

    Thermax offers special customer oriented single window features:

    Dedicated team of Managers, Engineers & Experienced Technicians.

    Routine, preventive and scheduled maintenance activities.

    Periodic overhauling.

    Complete plant management by Thermax professionals ensuring:

    Measurement and Recording of operational data.

    Monitoring of operating costs.

    Spares management.

    anurag rawatHighlight

    anurag rawatHighlight

  • 17

    Key customer benefits:

    Improvement in overall efficiency.

    Increased equipment availability.

    Single source service provider for all products.

    Data related to Key Performance Indicator ( KPI)

    Co-ordination with statutory bodies like Boiler Inspectorate, PCB,

    insurance etc.

    2.7. Thermax Quality (EHS) Policy and Customer Focus:

    Thermaxs quality policy starts and ends with the customer as a focal point:

    understanding the customers requirements, designing optimal solutions to meet those

    requirements, building systems and processes in place to ensure quality at every stage,

    and achieving our commitments on delivery and service before & after sales.

    It is our endeavour to create the culture of Total Quality where continuous

    improvement of our people, our processes and our products becomes a way of life.

    Customer Focus: The Company depends upon customers for its survival, and hence it

    believes that everyone can contribute to customer satisfaction.

  • 18

    2.8. Firms SWOT Analysis:

    A scan of internal and external environment is an important part of strategic planning

    process. Environmental factors internal to the firms usually can be classified as

    strengths (S) or weakness (W) or opportunities (O) or threats (T). Such an analysis of

    strategic environment is referred to as a SWOT Analysis.

    The SWOT analysis provides information that is helpful in matching the firms

    resources and capabilities to competitive environment in which it operates. As such it

    is instrumental in strategic formulation and selection.

    Strengths:

    The major source of companys revenue and profit comes from project

    divisions. The major divisions are Boilers & Heaters, Absorption

    Cooling Division, Waste & Water Solutions, and Chemicals for

    environment and energy applications, Captive Power and Cogeneration

    Systems, and Air Pollution and Purification. They altogether contribute

    60% to the company revenue.

    The company has created niche in the market through its several brands

    like hot water generation- Aquamatic & Aquatherm, coil type steam

    boilers- Steamatic, Revotherm, and Revotherm plus, shell type

    boilers- Shellmax, thermal oil/thermic fluid heaters- Deltatherm and

    various solid fired boilers - Woodpac, Combipac, Multipac,

    Multimax, Huskpac, Multitherm.

    Thermax has a very rich technical expertise. The companys long

    involvement in energy business has led to very deep understanding of

    fuels. The Thermax offer to the industry on fuels: you name it, well

    burn it.

    Thermax has excellent management information system in the form of

    dedicated intranet called THERMNET and E-mail system called

    LOTUS. Thermax sales engineers can immediately load an order with

    complete specification from any part of the world through Thermanet.

  • 19

    Weaknesses:

    The company requires steel as raw material. The steel prices have

    shown a sharp increase, hence affecting the profit margin.

    The company has to pay high compensation to retain talented engineers;

    accountants, this can be seen from the balance sheet of the company.

    Unavailability of strategic information on Thermax website, which

    causes threat to communicate the brand name of Thermax among

    seekers.

    Opportunities:

    Thermax Ltd. has established itself in energy solutions. Now its the

    correct time to expand & diversify their business in Power Generation,

    Transmission and Distribution.

    The company should try to recruit multi-skilled technocrats. This would

    reduce the redundancy level for the company.

    Company can improve quality of operations, products and inventory

    management by taking the help of expert consultants.

    The manufacturing operations should try to standardize so that output

    of the company can be improved.

    Threats:

    The profit margin of the company is under pressure. The other boiler

    manufacturers are giving Thermax a stiff competition. This restricts the

    company from increasing margin.

    Some of the major orders which company failed to grab, directly point

    towards the presence of another good competitor in the market.

  • 20

    3. Project Objective:

    The O&M division (a sub-group of Power Division) of Thermax Ltd had been facing some

    problem with management of contracts, mobilisation of the plant and some other issues

    related to the statutory compliance etc.

    So as part of their live project at 20+ sites across India, I was awarded with the following

    objectives to develop an appropriate Business Development Model or say Strategy by

    matching steps with them, and hence in this way, I got the fantastic opportunity to explore

    and utilize my MBA skills in this project. Here are the tasks:

    To study about O&M Contract Mobilisation.

    To construct a unique Mobilisation Master depicting streamlined process.

    To prepare guidelines for action steps taken for mobilisation of New Site.

    To construct Order Transfer Form (OTF), essential for proper flowing of

    information when a new order comes.

    To provide the platform for Sub-contractor selection and appraisal.

    To review the Statutory Compliance of the sub-contractor.

    To prepare Statutory Checklist for Auditing of plant site.

    To construct a Financial Model of O&M division.

    To prepare Spend Analysis in O&M Contracts.

    To analyse Manpower Rate Comparison across various sites, right from the

    Day 1 of Purchase Order (PO).

    Mandatory Clearances to be taken for setting up of a Thermal Power Plant.

  • 21

    4. Significance of the Study:

    It is a very common saying that, To achieve a TOP position is very easy but difficult is to

    maintain that position. Similarly to build a Power Plant is a one-time expenditure but to

    run the Power Plant in a cost-effective manner for years of time is the major task.

    Centuries after electricity was discovered, the power struggle across India continues

    unabated. While capacity addition is taking place, a plethora of other critical issues have

    raised their collective heads crying for attention. Among these is the burning issue of

    What is the best way to build and run the power plant?

    Now a days everyone needs power to survive. For any energy intensive company in non-

    power business, in these days of severe crunch of trained manpower, retention of highly

    experienced and dedicated team to set and run power project is a challenge not related to

    core business, exposing the business to unwanted risk. Due to the high availability demand

    and the life cycle cost reduction requirements of power plants, a permanent improvement

    of the O&M services is requested.

    Thermax is amongst top company and also one of the first to offer O&M services of power

    plants in India. Currently they have 20+ live projects in hand for which there is

    continuous development of O&M division is going on and its my fortune to be a part of

    this developing organisation for my two months internship project.

    The study mainly focuses on the O&M of thermal power plant and signifies the value of

    contract management with detailed analysis of contract mobilisation w.r.t. the Statutory

    Compliance and developing a core business opportunity in the relevant field.

    The Biggest Significance of this study is that, now I am aware of:

    Managing an O&M Contract.

    How to mobilise resources for running a Power Plant.

    All Statutory Compliance that need to be focused.

    Auditing of any running site w.r.t. Compliance & Sub Contractor Performance.

    Mobilisation Process to be followed on receiving a new contract.

    Mandatory Clearances taken for setting up of a Power Plant.

  • 22

    5. Introduction:

    The Power sector in India is one of the fastest growing sectors in the world with a huge

    capacity addition in last decade as well as planned for the next decade.

    Power is one of the prime movers of economic development. The basic responsibility of

    power industry is to provide electricity at economic cost, while ensuring reliability and

    quality of supply.

    India offers huge opportunity in the renovation and modernisation, upgrading and life

    extension of old thermal and hydro electric plants. More than 2/3rd

    of the installed capacity

    consists of plants that are at least 10 years old.

    The market for O&M is thus very big, especially in the fields of spare parts or renovation

    and modernisation. It is estimated that the total O&M market is worth b/w $ 2-2.5 billion a

    year.

    In todays scenario the power plant owner move towards the EPCOM type contract of the

    plant means the company which provides Engineering, Procurement & Construction

    Contracts also provides Operation and Maintenance services.

    The ultimate opportunity arises from non-power players requiring only power and thus

    offload their O&M Services, so that they will focus on their core business.

    anurag rawatHighlight

    anurag rawatHighlight

    anurag rawatHighlight

  • 23

    6. Review of the Initial base:

    6.1. Operation and Maintenance Business:

    An O&M type contracts represent long-term partnership agreements, it is important

    that the owner and supplier maintain common goals and incentives throughout the life

    of agreement.

    Thermax ensures that an O&M agreement puts the responsibility of managing the

    power plant into their hands freeing you to concentrate on your core business.

    Outsourcing O&M of the Power Station means optimum performance and utilisation of

    the power plant.

    There are namely 3 phases of an O&M Contract:

    Phase-in Period

    Operational Period

    Phase-out Period

    anurag rawatHighlight

    anurag rawatHighlight

    anurag rawatHighlight

  • 24

    Responsibility in O&M Agreement:

    Mobilisation of the complete O&M organisation

    Management, O&M of the entire plant

    Delivery of all Spare parts

    Delivery of all Consumables

    Other responsibilities include

    Staffing the plant

    Day to Day Management

    Administration

    Training

    Dispatch

    Power production

    Maintenance Planning

    Major Overhauls

    Troubleshooting

    Performance Reporting &

    General Logistics

    Performance guarantees on parameters such as

    Availability

    Production

    Heat Rate

    Lube Oil Consumption

    Emissions

    Advantages for the Power Plant Owner:

    Competitive O&M Costs

    Predictable lifetime cost forecast

    Substantial Risk Mitigating

    Performance guarantees ensure continuous optimisation of the plant

    Sustained asset value through best practices for O&M

    Maximum Return on Investment (ROI)

  • 25

    Financial Benefits:

    Spare parts optimization

    Sustained reduction of OPEX in a very short period of time

    Independent interface b/w OEM & Client will save time and money

    Longer Asset life, leading to postponed decommissioning costs

    HRM Benefits:

    Flexibility

    Increased Safety

    Fewer Human Resource issues

    Improved utilization of Clients own personnel resources

  • 26

    6.2. Operation and Maintenance Experience:

    6.2.1. Current Revenues:

    AR as of End JUN 11

    Rs Lacs

    OC CODE CUSTOMER NAME 0-30 31-60 61-90 91-120 121-180 181-365 366-730 731 & Above TOTAL PROVISION TOTAL

    DDM001 MADRAS CEMENTS LTD 37.88 0.10 0.05 0.00 38.04 38.04

    DDM004 J K LAKSHMI CEMENT LTD 92.65 46.33 0.35 5.45 1.72 0.16 146.66 0.08 146.58

    DDM006 J K CEMENT WORKS 72.34 0.00 0.00 72.34 72.34

    DDM007 MADRAS CEMENTS LTD 81.61 1.25 1.13 2.36 0.00 0.00 86.35 86.35

    DDM009 J K CEMENT WORKS 50.36 0.00 0.00 0.00 0.32 50.68 0.32 50.36

    DDM010 DCW LTD 233.85 3.34 116.93 10.69 0.15 0.13 365.08 0.06 365.02

    DDM011 CHEMPLAST SANMAR LTD 145.71 125.71 5.39 0.25 0.20 277.26 0.10 277.16

    DDM012 SAURASHTRA CEMENTS LIMITED 98.03 45.71 8.22 0.00 151.97 151.97

    DDM013 J K WHITE CEMENT WORKS 86.20 1.72 0.00 87.92 87.92

    DDM014 SANGAM (INDIA) LIMITED 2.40 2.40 2.40

    DDM015 HINDUSTAN ZINC LIMITED 135.12 3.41 0.52 8.03 3.31 0.90 151.29 0.90 150.39

    DDM016 JAYKAYCEM LIMITED 114.07 63.45 0.00 0.76 0.00 0.00 178.28 178.28

    DDM017 BHARAT OMAN REFINERIES LIMITED 158.96 44.30 9.31 212.57 212.57

    DDM018 KAMAL SPONGE STEEL & POWER LTD 21.24 21.24 21.24 -

    DDM022 URJANKUR SHREE DATTA POWER CO LTD 9.59 2.27 11.86 11.86

    DDM023 MADRAS CEMENTS LTD 38.83 0.00 38.83 38.83

    DDM024 ASR MULTIMETALS PRIVATE LIMITED 26.04 0.00 0.26 26.29 26.29

    DDM025 SONA ALLOYS PRIVATE LIMITED 9.64 21.31 30.94 30.94

    DDM028 KUDOS CHEMIE LTD 0.73 0.73 0.73

    TOTAL 1391.61 21.31 333.59 123.23 52.61 5.43 21.73 1.23 1950.74 22.71 1928.03

    DSO - Days 82

  • 27

    6.2.2. Profit and Loss Calculations:

    Source- MIS & Financial Modelling data Thermax Ltd.

    The Vertical Y-Axis represents the cost incurred in Lacs and the Horizontal X-Axis

    represents the O&M sites.

    The Profit margin showed by blue line indicates the profit for various sites maximum

    up to ` 145 Lac and minimum tend towards loss up to ` 20 Lacs.

  • 28

    6.2.3. Analysis of Variances:

    FY 2010-11

    JUN 11 YTDRs Lacs

    PARTICULARSABP ACTUAL VARIANCE REMARKS

    INVOICING 2114.00 2139.44 25.44 Invoicing Less than ABP

    MATERIAL COST 380.52 343.52 37.00

    % 18% 16%

    ODC (Includes Provision for Doubtful debts) 466.79 552.95 -86.16 OVERRUN

    DOE 540.00 459.80 80.20

    GROSS MARGIN 726.69 783.17 56.48

    GROSS MARGIN % 34% 37%

    G&A 96.04 76.79 19.25

    Other Income 0.00 -2.31 2.31

    Depreciation & Interest 21.00 36.26 -15.26

    PBT 609.65 672.43 62.78

    PBT % 29% 31%

    O&M Inventory as on End-June 11 (Gross) 548.75

    O&M Inventory - Days 145

    AR as on End June -11 ( Gross ) 1,950.74

    DSO 83

    Points for O&M Action:

    Review AR & make necessary collection.

    Review - Non Moving Inventory .

    YTD - Year To Date

    AR - Acount Receivables

    ABP - Assumption Based Planning

    ODC - Other Direct Costs

    PBT - Profit Before Tax

    G&A - General and Administration

    DOE - Direct Operational Expenditure

  • 29

    6.2.4. Learnings from the Operational Proceedings:

    By the analysis of financial sheets and the Thermaxs annual report, it is clear that the

    O&M Contract proves to be a profit making business because O&M service doesnt

    depend on the market fluctuation; rather it depends on the plant size and years of

    operation.

    O&M division helps:

    For Customers For Thermax Ltd.

    Non-core (Power ) customers Add Revenue

    Single Window Service Build on Expertise

    HR / Recruitment Savings More Value added to Client

    Turnkey Solution Risk Mitigation

    To verify the Budget Vs Actual Thermax has prepared a chart showing the allocation of

    cost depicting different scope of O&M.

    Scope Cost Head % Manpower +

    Services

    Manpower +

    Services +

    Consumables

    Manpower +

    Services +

    Chemicals +

    Consumables

    Manpower +

    Services +

    Spares +

    Chemicals +

    Consumables Labour % 30 28.5 26 22

    Material % 1 4 9.5 18 Salary % 34 33.5 30.5 26 Total % 66 66 66 66

    anurag rawatHighlight

    anurag rawatHighlight

  • 30

    6.3. Critical Assessment and Evaluation of O&M Business:

    After being familiar with the actual work and our project responsibilities, now we are

    able to evaluate the organizational business through management point of view. So

    here we do the critical assessment by SWOT analysis:

    Strengths:

    To provide the full regulation for power plant is the biggest strength of

    Thermax O&M Business.

    To do the O&M of self EPC plants as well as those EPC which had not

    done by Thermax and this proves that they are mature enough to provide

    O&M to non-EPC plants also.

    To use captive knowledge of existing manpower.

    Expert in handling any type of Boilers.

    Backend support from business vendors to engineering group for

    efficient control and with OEM for in-house accessories, and Chemical

    division for water treatment.

    O&M of Thermax tries their best to mobilize the power plant within 45

    days.

    Thermaxs record book include:

    a) Highest no. of projects finished in time.

    b) Highest no. of repeat orders in category.

    c) Highest no. of bullet bonuses earned.

    Weaknesses:

    Scarcity of experienced manpower.

    Poaching of manpower.

    Engineers moved out due to attraction towards more salary.

    Burgeoning issue of labour laws.

    Inadequate information of non-EPC contract.

    Company has to pay high compensation to retain talented engineers.

  • 31

    Like every giants there is a lack of proper approach and communication

    hence bureaucratic culture exists.

    Absence of adequate skilled support staff and lack of motivation due to

    non-managerial approach

    Opportunities:

    BUILD OWN OPERATE(BOO)- (BOO) is a form of project financing,

    wherein a private entity receives a concession from the private or public

    sector to finance, design, construct, and operate a facility for a specified

    period, often as long as 20 or 30 years. After the concession period ends,

    ownership is transferred back to the granting entity.

    MOTIVATION- To trained lower level employees to give them the

    promotion and acts as the motivation factors for others employee.

    Past performance on O&M will help Thermax to grab more projects.

    Company can go ahead to improve quality of operations, products &

    inventory management by taking the help of expert consultants.

    Threats:

    Increasing competition from foreign as well as Indian companies.

    Poaching of manpower.

    Migration is the key threat, not only at the bottom level but also at the

    top level, as they leave the organization and become entrepreneur.

    Another major factor is coal which is diminishing day-by-day; hence it

    acts as a threat for surviving of small power plants.

  • 32

    7. Conceptualization:

    7.1. Spend Analysis in Operation and Maintenance Contracts:

    Labour & Materials MCL 1 MCL 1 MCL 2 MCL 2 MCL 3 MCL 3 JKL 3X18 JKL 3X18 JKL WHRB JKL WHRB JKCW 22 JKCW 22 USDPCL USDPCL

    Actual till

    July

    Projected

    Aug+Sept

    Actual till

    July

    Projected

    Aug+Sept

    Actual till

    July

    Projected

    Aug+Sept

    Actual

    till July

    Projected

    Aug+Sept

    Actual till

    July

    Projected

    Aug+Sept

    Actual

    till July

    Projected

    Aug+Sept

    Actual

    till July

    Projected

    Aug+Sept

    Regular Serv Provider Charges 28 14 32 16 28 14 36 18 20 9 21 15 22 16

    Cost of Addnl. Services 21 11 41 4 4 2 26 15 1 1 1 35 2 2

    Spare or Consumable cost

    incurred34 9 33 15 23 10 31 30 0 0 21 55 9 9

    Sub Total->> 83 34 106 35 55 26 93 63 21 10 43 105 33 27

    Total->>

    Labour & Materials DCW DCW CSL CSL JKM JKM SCL SCL HZL HZL JKWC JKWC BORL BORL

    Actual till

    July

    Projected

    Aug+Sept

    Actual till

    July

    Projected

    Aug+Sept

    Actual till

    July

    Projected

    Aug+Sept

    Actual

    till July

    Projected

    Aug+Sept

    Actual till

    July

    Projected

    Aug+Sept

    Actual

    till July

    Projected

    Aug+Sept

    Actual

    till July

    Projected

    Aug+Sept

    Regular Serv Provider Charges 39 20 32 16 28 14 20 10 84 52 20 10 60 45

    Cost of Addnl. Services 56 20 17 20 15 8 8 20 6 15 7 20 30 15

    Spare or Consumable cost

    incurred151 80 94 40 35 15 32 20 12 8 7 10 20 40

    Sub Total->> 246 120 143 76 78 37 60 50 102 75 34 40 110 100

    Total->>

    Scope is M,C,S

    Scope is M, C, only

    Site - unstable/pre-commng.

    Actual till

    July

    Projected

    Aug+Sept

    Projected

    for

    Q1+Q2

    TOTAL->> 1207 798 2005

    210

    60

    366 219 115 110 177 74

    O&M - April - July 2011 YTD + projection of Aug and Sept (Rs. Lacs.)

    117 141 81 156 31 148

  • 33

    8. Focus on the Problem:

    8.1. Operation and Maintenance Contract Management:

    To survive in this competitive world, every organisation wants to enter into profit

    making business where there is a continuous flow of earnings takes place. Talking

    about the market uncertainty, when there is a downfall or recession going on, which

    directly affects the companys profit and loss account; it is then necessary for the

    company to avoid its capital expenditure (CAPEX) in order to remain safe in the

    fluctuation period.

    As stated above and keeping in view the market strategy now we shall focus on our

    actual problem of contract management. In the recession period where nobody wants to

    invest their money in the market, sometimes it may happen that many companies

    wants to build their own power plant on EPC contract but they dont have adequate

    amount to invest or say they are not able to invest in this period particularly, which is

    indirectly a loss to Thermax.

    In this condition if Thermax didnt have any EPC contract then how could they

    survive, is a big Question Mark? Also it is said that, when you are not in touch with

    your core field then your boon becomes your curse. Thermax is also one of the experts

    in EPC field, and hence to remain in this field, Thermax put their step forward with a

    clear & broad vision to initiate a unique O&M Division in the year 2006 and started

    taking the O&M Contracts.

    Operation & Maintenance Contract Management refers to the effective management of

    contract to sustain in the field of Power Sector in terms of handling the whole plant and

    its activities so that our knowledge and experience becomes the biggest hallmark

    towards our giant mission and vision.

    At present Thermax O&M Division has 20+ ongoing O&M contracts across India

    helping them to understand the basic problem arising at different sites regarding coal

    supply, unavailability of manpower, poaching of manpower due to unsuitability in

    some parts of India, means North side people finds it difficult to adjust in South and

  • 34

    vice-versa. This type of issues creates panic for the whole process of O&M of Power

    Plants and hence to manage all these problems on-site as well as off-site is termed as

    Contract Management.

    Due to the rapid industrialization which is necessary for countrys economic

    development, all companies need a huge amount of power and as per the present

    scenario the cost of electricity is increasing at a continuous pace and expected to reach

    at its climax within this decade. In order to meet the electricity demand, companies

    move towards setting up their own Captive Power Plant (CPP) or become Independent

    Power Producer (IPP), so that they are able to control their electricity cost and hence

    able to save a handsome amount which they utilize for further development.

    Throw a light on industries setting up CPP & IPP; we came to the conclusion that these

    industries are those who doesnt have knowledge about the running of Power Plant e.g.

    Industries like Cement, Textile, Steel, Chemicals, Sponge & Iron etc. or the industries

    who want to offload their operation and maintenance of Power Plant on contract basis

    to other experienced giants in this field. Now look at this particular point which

    provided the clue and this is the actual reason why we (Thermax) came into picture and

    started providing O&M services to Power Plant and emerged as one of the top O&M

    Service provider.

    anurag rawatHighlight

    anurag rawatHighlight

    anurag rawatHighlight

    anurag rawatHighlight

  • 35

    8.2. Sub Contract Scope:

    After receiving the O&M contract of any Power Plant, Thermax soon started their

    mobilization with all formal clearances and trying their level best to complete it within

    the given time period of 45 days due to which they awarded many times.

    O&M service refers to the complete understanding and working of Power Plant which

    is further divided into lot of subcategories viz. Fuel Handling, Consumables, Waste

    Management, Water Treatment, Ash Utilization, Spare Part Maintenance, Boiler

    Accessories, BTG & BOP maintenance etc. All these activities are not possible for a

    single contractor and here arises the scope for Sub Contract.

    Sub Contract basically means to work under Contractor. The Sub Contractor is then

    responsible for all minor works which are beyond the scope of main contractor or in

    other words if the main contractor shows unwillingness to do some work then it gives

    sub contract to the third party. It is correct in the sense that (taking Thermaxs

    example) the giant firms are not interesting in hiring and recruiting the unskilled

    workforce which are required to work at site as labour.

    After analysing the appropriate problem of Contractor and Sub Contractor management

    we can easily conclude that as EPC Contracts increases there is sudden jump in:

    Industrialization

    O&M Service Provider

    Contract Management

    Sub Contract scope

    Jobs for unskilled workforce

    Literacy level

    anurag rawatHighlight

  • 36

    8.3. Various Regulations:

    Apprentices Act

    (Bombay) Labour Welfare Fund Act

    (Bombay) Industrial Relations Act

    (Bombay) Shops & Establishments Act

    Building & Other Construction Workers Act, 1996 (with Mah. Rules, 2007)

    Contract Labour Act (with Central and Mah. Rules)

    Child Labour Act

    Employers Guide to Labour Laws

    Employees Provident Funds Act with Scheme

    Employees State Insurance Act

    Employment Exchange (Compulsory Notification of Vacancies)

    Equal Remuneration Act

    Factories Act (with Mah. Rules)

    Industrial Disputes Act (with Central and Mah. Rules)

    Industrial Employment (S.O.) Act

    Maharashtra Mathadi, Hamal & Other Manual Workers (Regulation of

    Employment & Welfare) Act, 1969

    Maharashtra Pvt. Security Guards (Regulation of Employment & Welfare) Act,

    1981

    Maharashtra Workmens Minimum House-Rent Allowance Act & Rules

    Maternity Benefit Act

    Minimum Wages Act with Mah. Rules (with Notifications Fixing Revising

    Minimum Rates of Wages in Mah. State for Schedule Employment)

    M.R.T.U. & P.U.L.P. Act

    Payment of Bonus Act

    Payment of Gratuity Act with Mah. Rules

    Payment of Wages Act with Mah. Rules

    Private Security Agencies (Regulation), Act, 2005 with Mah. Rules, 2007

    Sales Promotion Emp. Act

    Trade Unions Act with Mah. Rules

    Weekly Holidays Act

    Workmens Compensation Act with Mah. Rules

  • 37

    8.4. Statutory Compliance at Site:

    Objectives:

    In present global business competition, it is imperative to outsource certain

    independent activities. Such outsourcing can be assigned to vendors / contractor at

    our works as well as customer premises at site.

    To safeguard the organization, vendors & customer from legal prosecution under

    various applicable labour laws as well as other local laws.

    To extend & ensure benefits to all contract labours as prescribed under labour laws

    & other local laws at site.

    To maintain optimum / highest level of statutory compliance at site at all times

    operating following standard procedure and control mechanism.

    Appointment / Selection of Contractor / Vendor:

    Contractors / vendors who possess their own independent registration under

    following acts & who will professionally strong in statutory compliance shall be

    appointed as professional contractor / vendor at site.

    1. Registration under Employees State Insurance Act 1948 (E.S.I.C Code)

    2. Registration under Employees Provident Funds Act 1952 (P.F Code)

    3. Workmen Compensation Insurance Policy under WC Act 1923 in case of

    non ESIC coverage area.

    4. Labour License under Contract Labour Act 1970 if applicable.

    5. Labour License under B & O C W Act 1996 if applicable.

    6. Registration under Labour Welfare Fund Act if applicable.

    7. Firm / Business Registration with local authority (Shop Act).

    8. Professional Tax

    9. Income Tax (Pan No)

    10. Service Tax Registration

  • 38

    Thermax Ltd shall ensure followings while appointing the

    contractor at site:

    1. Agreement with contactors / vendors on 100/- Rs stamp Paper apart from

    purchase order / work order etc

    2. Indemnity bond to be taken from contactors / vendors on 100/- Rs stamp

    paper

    3. Strictly ensure appointment of supervisor by the contractor & to avoid direct

    employee - employer relationships. The said supervisor will monitor day to

    day activities of the contractor. Such supervisor may be one among the

    contract labour also.

    4. Ensure safety training to all contract labors.

    5. To provide personal protective equipments to all contract labors.(PPE)

    6. Strictly adhered all Labour laws which are applicable at site.

    7. Undertaking from the contractors & his employees for observing safety

    norms.

    Contractors should ensure following before entering at site:

    1. To keep bio- data cum application of all workmen with photo.

    2. To keep age proof of all workmen / labors.

    3. To issue identity card with photo to all labors.

    4. To keep records of medical fitness of all labour

    5. To issue appointment letter to all employees

    6. To issue PF numbers to all labours / employees.

    7. To obtain ESIC numbers for all labours / employees.

    8. To appoint supervisor at each site.

    9. To keep copies of all records at site at all times for Govt. Officer Inspection.

  • 39

    Site Location:

    1 Principal Employer is Customer

    2 Contractor is Thermax Ltd

    3 Sub-contractor - Contractor appointed by the Thermax Ltd

    Applicability of the Act:

    Principal Employer, who has directly & in-directly employed (employees of

    contractors & sub-contractors) the persons in his factory premises are too be taken

    in to consideration of applicability of the Act.

    Contractor shall strictly ensure statutory compliance under following labour laws at

    site.

    SN Regular Labour Laws at Site

    S

    N

    Silent Labors Laws at Site

    1 The Contract Labour Act 1970

    1 The Factories Act 1948

    2 The Minimum Wages Act 1948

    2 Labour Welfare Funds Act 1953

    3 ESIC Act 1948

    3 The Maternity benefit Act 1961

    4 PF Act 1952

    4 The Equal Remuneration Act 1976

    5 The Payment of Wages Act 1936

    5 The Industrial Disputes Act 1947

    6 The Payment of Bonus Act, 1965

    6 The Profession Tax

    7 Workmen Compensation Act 1923

    7 House Rent Allowance Act. In

    Maharashtra state it is mandatory

    8

    Building & Other Construction

    Workmen Act 1996 & Cess Act

    1996

    8

    The Child Labour (Prohibition &

    Regulation) Act 1986

    9

    The Interstate Migrant Workmen's

    Act 1979

    9

    The Industrial Employment

    (Standing Order) Act 1946

    10 Other State Acts & Central / State

    Rules if any.

  • 40

    Very Important:

    Every Act contains following three important aspects.

    1 Central Act Applicable to whole India

    2 Central

    Rules

    Applicable to concern state, those who are not having their

    own state rules. All Central Govt. undertakings as well as

    supported by Central Govt. are coming under said rules even

    though they are operating in various states.

    3 State Rules If the concern state is having its own state rules it is mandatory

    to follow state rules including operating procedure like legal

    fees, security deposits, legal forms / formats etc.

    8.4.1. Compliance under Contract Labour Act 1970:

    The said act is applicable to contractors, who are employing 20 or more workmen as

    contract labour. (PI checks individual state applicability). Every Contractor to whom

    the act applies must obtain licence in Form No. VI.

    Procedure for obtaining license under Contract Labour Act 1970 (Central Rules)

    1 Form IV Application in duplicate

    2 Annexure Declaration by the Contractor

    3 Form V To be obtain from Principal Employer

    4 Security Deposit To be deposited in SBI through Govt. Challan.

    5 License Fees To be deposited in SBI through Govt. Challan.

    6 Form VI License issued by the Govt. Authority to the contractor

    7 Form VII Application for renewal of license along with renewal fees

    8 Power of

    Attorney

    If required for signing the documents

    It is mandatory to keep copies of all statutory records in the 3 KM of radius of work

    site.

  • 41

    8.4.2. Compliance under Minimum Wages Act 1948:

    It is mandatory to pay minimum wages applicable to customer location at site.

    Each Sate Govt. is declaring minimum wages as per the category of the industries & as

    per the applicable zones. Before paying minimum wages Pl take following details

    from customer / principal employer.

    1 Type of Industry To be check with customer

    2 Under which zone the said

    industry is coming

    1 or 2 or 3 or 4 To be check with customer

    3 Applicable minimum wages To take from customer as per below format

    Skill Category Un Skilled Semi

    Skilled

    Skilled

    Basic To check To check To check

    Govt. DA / Special All To check To check To check

    Total

    HRA 5% of Basic + DA

    If you are paying more than minimum wages, the amount over & above minimum

    wages should be shown as Conveyance allowance, Washing allowance etc instead of

    other allowance.

    8.4.3. Compliance under Payment of Wages Act 1936:

    It is mandatory to pay wages before 7th

    of every month where the customer is

    employing less than 1,000 persons (Direct & Indirect) & before 10th

    of every month

    where the customer is employing more than 1,000 persons (Direct & Indirect) When

    the employment of any person is terminated, the wages earned by him must be paid

    before the expiry of the second working day from the day of termination.

    8.4.4. Compliance under ESIC Act 1948:

    It is mandatory to cover each labour / employee from day one, those who are drawing

    monthly wages / salary up to ` 15000/-.

  • 42

    Key Benefits under ESIC Act 1948:

    1 Sickness

    benefits

    2 Medical

    benefits

    3 Disablement

    benefits

    4 Funeral

    Benefits

    5 Accident

    benefits

    6 Maternity

    benefits

    7 Depends benefits

    8.4.5. Compliance under PF Act 1952:

    It is mandatory to cover all labours / workmen / employees under said act from day 1.

    It is mandatory to deduct 12% PF on Basic + DA from Rs 0001 to ` 6500/- PM.

    Employee can contribute PF deduction on entire Basic + DA Amt (above ` 6501/-) but

    it is not binding on employer to contribute his share on or above ` 6501/-.

    Key benefits under PF Act 1948

    8.4.6. Compliance under Workmen Compensation Act 1923:

    The said act is applicable to non ESIC coverage area.

    The said act is also applicable to ESIC coverage where employees are getting monthly

    wages more than ` 15000/- (out of preview of ESIC coverage).

    In case of accident it is mandatory to pay following benefits under said act.

    Key benefits under WC Act 1923:

    1 Temporary disablement 3 Permanent Total disablement

    2 Permanent Partial disablement 4 Death

    1 Long life pension to nominees in case of death

    2 One time EDLI benefit in case of death

    2 Pension after completion of superannuation age

    4 Non refundable loan for various reasons

  • 43

    8.4.7. Compliance under Bonus Act 1965:

    The bonus is payable as per financial accounting year from Apr to Mar. It is

    mandatory to pay the 8.33% bonus to the labors / employees those who are drawing

    wage (Basic + DA) up to Rs.10, 000/- per month and who has worked for minimum

    period of 30 days in a accounting year. Bonus must be paid within a period of 8

    months from the close of accounting year.

    Procedure for calculation of bonus Under the said act wage ceiling for bonus

    calculation is locked by Govt. An employee who draw a salary or wage (Basic +DA)

    more than Rs.3500/- to Rs 10,000/- per month, bonus will be calculated on Rs 3500/-

    only. In other words 8.33% bonus will be calculated only on Rs 3500/- PM even

    though his wages (Basic + DA) are more than Rs 3500/- PM.

    Labour /

    employees is

    getting monthly

    wages (Basic +

    DA) Rs 10500/-

    Labour / employees

    is getting monthly

    wages (Basic + DA)

    Rs 2800/- (below Rs

    3500/-)

    Labour /

    employees is

    getting monthly

    wages (Basic +

    DA) Rs 3500/-

    Labour / employees

    is getting monthly

    wages (Basic + DA)

    Rs 6500/- (above Rs

    3500)

    Not eligible for

    bonus

    2800 X 8.33% = Rs

    233/-

    3500 X 8.33% =

    292/-

    3500 X 8.33% =

    292/-

    8.4.8. Compliance Building & Other Construction Workers Act 1996:

    The said act is applicable to every establishment which employs, or had employed 10

    or more building workers in any building or other construction work. The said act is

    mostly applicable to green field areas & upcoming factories those who are not

    registered under the factory act 1948.

  • 44

    8.4.9. Compliance Building & Construction Workers Cess Act 1996:

    The said act is second part of the building & other construction workers act 1996.

    Once registered under the said act, Cess Act is applicable automatically. Under the

    said act we have to pay cess to Govt. Labour Office not exceeding 2% but not less

    than 1% of the cost of construction incurred by the employer. (Excluding cost of land

    & Compensation paid under WC Act 1923)

    8.4.10. Compliance Inter State Migrant Act 1979:

    Every establishment or contractor who employs or who employed five or more inter-

    state migrant workmen (whether or not in addition to other workmen) on any day of

    the preceding 12 months is required to take license / registration under the said act.

    8.4.11. Report of Accident under Factory Act 1948:

    It is mandatory on the principal employer as well as contractor to inform following

    authorities immediately in case of fatal accident & with in 48 hrs in case of other

    accident of Direct or In-direct employee. It is mandatory on each contractor to intimate

    any type of accident to principal employer immediately.

    Factory

    Inspector

    Nearest Police

    Station

    ESIC

    Authority

    Next kin or other

    relatives.

    Principal

    Employer

    8.4.12. Report of Accident under Building & Construction Workers

    act 1996:

    It is mandatory to inform following authorities immediately in case of fatal accident &

    with in 48 hrs in case of other accident of Direct or In-direct employee.

    Regional Labour

    Commissioner

    Nearest

    Police St.

    Districts

    Magistrate

    Next kin or

    other relatives

    Welfare

    Board

    Principal

    Employer

  • 45

    8.4.13. Site Closure Procedure:

    As per the provisions of the respective Acts, Govt. Inspectors are checking party

    ledgers along with supporting documents for verification of payment of PF / ESIC

    dues on labour charges other than regular wage muster. If the payments of PF & ESIC

    dues are not tally with labour charges, inspector will issue non compliance legal notice

    along with dues, interest penalty & damages to the company.

    By considering future legal liabilities under various acts as well as legal prosecution, it

    is mandatory on each site In-charge as well as site contractor to complete following

    site closing procedure. Pl ask contractor to submit followings:

    Site commencement on Site completion on

    Contractor Name Contractor Address

    Site Name Site Location

    Total period of site Number of employees

    PF Code No ESIC Code No

    Govt. Inspectors are asking following information along with supporting documents.

    SN Month Total

    Billing

    Material Cost &

    other cost etc.

    Labour

    Cost

    Total PF

    Paid

    Total ESIC

    Paid

    1

    2

    Total

    The above information will help us to define PF / ESIC liabilities on labour charges

    otherwise the Govt. Inspectors will charge PF / ESIC on entire billing amount.

  • 46

    Check List to be completed by Thermax Officials:

    SN Particulars Y

    e

    s

    N

    o

    NA

    Remark

    1 Has notice of completion of work given to Labour office

    in form VI A. under Contract Labour Act 1970

    2 Has contractor surrendered license to Govt. Auth in form

    VI under Contract Labour Act 1970

    3 Has contractor taken back security deposit from Govt.

    auth after surrendering above license (form VI)

    4 Has notice of completion of work given to Labour office

    in form IV under B & O C W Act 1996

    5 Has contractor surrendered license to Govt. Auth in form

    II under B & O C W Act 1996

    6 Has contractor taken back security deposit from Govt.

    auth after surrendering above license (form II)

    7 Has contractor paid 1% cess under B & O C W W Cess

    Act 1996 to Govt. Auth

    8 Are we holding 10% payment of total contract value of

    the contractor against the statutory compliance

    9 Has contractor submitted copies of all records from site

    start to site end date (Muster Roll, Wage sheet, OT

    Register etc)

    10 Has contractor submitted copies of all PF records? Forms

    2,5,10,12A,3A,6A, PF Challan (PF members list)

    .11 Has contractor submitted copies of all ESIC records?

    forms 1,3,5,7A, ESIC Challan (ESIC member list)

    12 Has contractor properly / legally terminated service of his

    employees

    13 Has contractor taken receipt for payment of full & final

    settlement of his employees?

    14 Are we taking site closing undertaking on 100/- Rs stamp

    paper from the contractor while closing the site for future

    legal & other liabilities if any

    15 Has contractor submitted receipt of bonus paid to his

    employees (site start date to end date)

    16 Has contractor submitted copies of PF settlement claims /

    dues of his employees

  • 47

    8.5. Sub Contractor Selection:

    Statutory Compliance Audit - Check Point STATUS

    SN Registration and Licence

    1 Whether contractor is registered under Labour Contact Act, 1970?

    2 Whether contractor has obtained a licence under the act?

    3 Workmen employee should not exceed maximum no specified in the licence

    4 Wages are payable to workmen as per Minimum Wages act, 1948

    5 Licensee should submit a return to Inspector within 15 days of commencement

    of contract work

    6 Copy of the licence shall be prominently at the premises of work.

    7 No female contract labour employed, before 6 a.m. and after 7 p.m.

    8 Every licence shall be renewed after 12 months.

    9 In case of immediate labour requirement at work place, principal employer

    should apply for temporary registration or lecence to the registering authority.

    Welfare and health care of contract labour

    1 Facilities should be provided by the contractor like First-aid, Wholesome

    drinking water, a sufficient number of toilets, washing facilities etc., within

    seven days of the commencement of work.

    2 If these facilities are not provided by the contractor, then principal employer

    has to provide these facilities.

    Registers and Records

    1 The principal employer shall ensure the presence of his authorized

    representative at the place and time of disbursement of wages by the contractor

    to workman and it shall be the duty of the contractor to ensure the disbursement wages in the presence of such authorized representative.

    2 The authorized representative of the principal employer shall record under his

    signature a certificate at the end of the entries in the register of wages or the

    1[Register of Wages-cum-Muster Roll as the case may be in following form:

    Certified that the amount shown in column No---------- has been paid to the workmen concerned in my presence on -------- at --------- .

    3 Register of contractors:-Every principal employer shall maintain in respect of

    each registered establishment a register of contractors in Form XII.

    4 Register of persons employed.-Every contractor shall maintain in respect of such registered establishment where he employs contract labour a register in

    Form XIII.

    5 Employment card.-(I) Every contractor shall issue an employment card in

    Form XIV to each worker within three days of the employment of the worker.

    6 (II) The card shall be maintained up to date and any change in the particulars

    shall be entered therein.

    7 Service certificate.-On termination of employment for any reason whatsoever

    the contractor shall issue to the workman whose services have been terminated

    a Service Certificate in Form XV.

    8 Following registers and records to be maintained by the contractor under these

    rules, namely:

    9 Muster Roll

    10 Register of wages

    11 Register of deductions

    12 Register of overtime

    13 Register of advances

    14 Register of fines

    15 Wage slip

    Sign by Site Incharge

  • 48

    8.6. Sub Contractor Performance Rating Index:

    Site Name:

    Name of Contractor:

    Performance Appraisal Period: Apr-Sept / Oct-Mar

    (Pink Copy For HO, Yellow Copy For Subcontractor, White Copy For Site Records)

    Sr.

    No. Scaling Attributes Score

    A-Man Power

    1 Qualification of Manpower

    2 Knowledge of Manpower about Operation (CHP, AHP, WTP)

    3 Skills of Manpower in Mechanical Maintenance

    4 Adherence to Safety Practices

    5 Attendance of Manpower

    6 Man Management & Control by Sub-Contractors Site Incharge

    7 Fulfilment of extra Manpower in case of Exigency

    8 Corrective Actions & Improvement done based on past feedback

    9 Consistency in Performance

    B-Tools, Tackles & PPEs

    10 Tools and Tackles supplied as per list given in PO

    11 Training to Manpower for safe use of Tools & Tackles

    12 Supply of all PPEs

    13 Replacement / maintenance of Tools & Tackles

    C-Billing & Documentation

    14 Correctness of Bills

    15 Timely Submission of Bills

    16 Bills submitted along with all mandatory documents, which are

  • 49

    necessary for payments (Attendance, T&T List, PF, WCP / ESI)

    D-Communication

    17 Adequate communication facilities provided at their office

    18 Communication Effectiveness

    19 Timely response to communication from Thermax

    E-Records

    20 Proper record maintenance regarding attendance

    21 Proper record maintenance as per all Statutory Laws

    F-Other Issues

    22 Ability of contractor to mobilize at another site anywhere in India

    23 Capability of contractor to handle bigger size power plant contract

    24 Training and development programs organized by Contractor

    25 Suitability of this contractor for future contracts with Thermax

    TOTAL SCORE

    Instructions:

    1. Every attribute has to be given its proper score as per the assessment of the Station Manager.

    2. Every Attribute should be given score in the range of 0-4.

    (0 = Very Poor, 1 = Poor, 2 = Satisfactory, 3 = Good, 4 = Very Good)

    3. Contractor Performance Score shall be out of 100.

    4. Yellow Copy should be formally handed over to Sub-Contractor.

    Issued by:

    Thermax Station Manager

    Date:

  • 50

    8.7. SOP for new Site Mobilisation w.r.t. Compliance:

    Colour Legend used for Activity Number

    Zero date to Mobilisation Target - 45 days

    Zero Date to Stabilisation

    Post Stabilisation or Review

    Activity

    Colour

    Activity Milestone - Remarks and

    Points for completion

    Target in days Target Date Actual Date Scope

    C = Client

    T = Thermax

    B = Both

    Owner dept. -

    SCM

    Responsibility

    assigned to

    Activity-

    Classification

    Zero Date - Shall be communicated

    by Marketing based on Receipt of

    Advance or Contract or LOI or Notice

    to Proceed - A formal letter from

    Marketing / Commercial approved by

    LV or PKD

    25-Jul-11 Documentation

    OC Creation - Data Entry into

    System, Circulation of Budget

    2 27-Jul-11 Thermax Documentation

    OK from Commercial Dept.- Billing

    and Shipping addresses for material

    movement, Road permits need and

    scope, taxation rules

    2 27-Jul-11 Thermax Documentation

    Labour license formalities for TL as

    well as for the Manpower Contractor

    30 24-Aug-11 Thermax Documentation

    OPMS Circulation - O&M Philosophy,

    Preventive, Periodic, Shutdown,

    Breakdown etc,

    90 23-Oct-11 Thermax Documentation

    Making Spares lists and defining

    scope - Typical terms used are

    Capital Spares, Real Spares,

    Consumable Spares, General Spares,

    OEM Spares etc

    60 23-Sep-11 Thermax TL to submit lists Documentation

    Site Safety Compliance - Site Visit of

    HO safety coordinator, Safety Manual,

    Training, OHSAS, Posters etc

    60 23-Sep-11 Thermax Documentation

    OE visits - Based on As Built and PG

    test reports, Focus on warranty and

    guarantee claims, FOC spares etc,

    here timing is important

    25-Jul-11 Client Expert

    Requirement

    Site Transit House - Quarters from

    client or Rented Facility, Bachelor

    Hostel

    15 09-Aug-11 Thermax Infrastructure

    Site Office Setup - Building and

    Furniture

    30 24-Aug-11 Client Infrastructure

    Site Office Setup - Computers and

    Printer

    30 24-Aug-11 Client Infrastructure

    Depositing of Mobilization Advance

    (Site Fund) to enable commencement

    of Site Operations

    7 01-Aug-11 Thermax Infrastructure

    Site Communication Facilities - Email

    facility, Internet Connection, CUG

    mobiles

    30 24-Aug-11 Both Infrastructure

    Walkie Talkies - Decide quantity and

    license formalities

    20 14-Aug-11 Thermax Infrastructure

    Site Canteen / Mess Facility 45 08-Sep-11 Thermax Infrastructure

    Site Stores - for TL owned material 45 08-Sep-11 Client Infrastructure

    Site Stores - for Client owned

    material? Upkeep of the store?

    Security of the store? Stocking?

    Inventory Management?Inwarding?

    45 08-Sep-11 Client Infrastructure

    Chemical Lab - Building, Lab

    Equipments, Lab ware

    15 09-Aug-11 Client Infrastructure

    Site ERP / EAM - Setup, training etc 90 23-Oct-11 Both Infrastructure

    Manpower (TL) - Org structure,

    Manpower plan, transfer, ID, Roles &

    Responsibilities, Recruitment,

    Interview, Appointment, Induction,

    Deputation

    45 08-Sep-11 Thermax Manpower

    WTP Chemicals and Plan - Boiler

    Water Chemicals / Cooling Water

    Chemicals / RO Chemicals / Anion

    Cation Resins

    30 24-Aug-11 Client Material

    PPE's - First Lot 25 19-Aug-11 Thermax Material

    Consumables - First Lot of Lubricants

    and Oils

    25 19-Aug-11 Client Material

    Consumables - First Lot of

    Maintenance Consumables

    25 19-Aug-11 Client Material

    MOBILISATION MASTER FOR O&M SITE - KAMACHI SPONGE AND POWER CORP

  • 51

    Consumables - First Lot of Fuses 60 23-Sep-11 Client Material

    Consumables - First Lot of Bearings 60 23-Sep-11 Client Material

    Consumables - First Lot of Gaskets 30 24-Aug-11 Client Material

    Consumables - First Lot of CHP and

    AHP Spares

    60 23-Sep-11 Client Material

    Mechanical Tools and Tackles -

    Common Tools, Tools Boxes,

    Contractor Tools TL Scope

    20 14-Aug-11 Thermax Material

    Electrical Lab - Test Equipments 20 14-Aug-11 Both Material

    C&I Lab - Test Equipments 20 14-Aug-11 Both Material

    Scaffolding 20 14-Aug-11 Client Material

    Bed Material - Scope and

    Management

    20 14-Aug-11 Client Material

    Master Spare Plan - Study of plant 90 23-Oct-11 Thermax Review

    Site Taxi Facility 15 09-Aug-11 Thermax Service

    Manpower Contractor - Define Scope

    for Manpoweras well as T&T

    30 24-Aug-11 Thermax Service

    Coal/Fuel Yard Management - Earth

    Moving Equipment, Stacker

    Reclaimer, Yard Area etc

    25-Jul-11 Client Service

    Ash Disposal 25-Jul-11 Client Service

    AMC Pest Control 30 24-Aug-11 Client Service

    AMC - PV and Lifting Tackles Sling

    testing - In case of new eqpt demand

    copy of certificate else schedule

    testing as per need.

    30 24-Aug-11 Both Service

    AMC - DCS and PLC systems 120 22-Nov-11 Client Service

    AMC - Compressors 120 22-Nov-11 Client Service

    AMC - AC Systems 120 22-Nov-11 Client Service

    Testing and reviewing equipment

    performance (Pre commissioning

    onwards)

    Both Taking Over

    Collecting Technical Documents of the

    plant eg O&M manuals, EPC contract

    documents - Focus on "As Built",

    Receive a list of drawings from

    customer, Receive a list of O&M

    manuals, Collect and verify drawings

    and manuals from the customer / EPC

    contractor.

    90 23-Oct-11 Both Taking Over

    Collecting PG test reports of the full

    plant or sub systems, also compiling

    test certificates etc - This is important

    for baseline data. Atleast one copy of

    all the commissioning protocols shall

    be taken from customer or EPC

    contractor if we do not witness /

    certify. Incase we are taking over

    running plant then only operating

    protocols can be verified.Witnessing

    and certifying commissioning

    protocols

    25-Jul-11 Both Taking Over

    Making Base Line study of Rotating

    machines and critical equipments -

    Vibration analysis, oil check, capacity

    checks, coal quality

    60 23-Sep-11 Thermax Taking Over

    Making punch point list from operation

    and maintenance point of view -

    Before Synchronisation and to be

    closed out before stabilsation of the

    plant

    Thermax Taking over

    Making punch point list from safety

    point of view - Before Synchronisation

    and to be closed out before

    stabilsation of the plant

    Thermax Taking over

    Stock verification of spares inventory -

    This is required in case we take over

    a running plant

    Thermax Taking over

    Above information to be classified

    into:

    1. Manpower 2. Materials 3. Facilities 4.Coordinatio

    n Reviews

    5. OEM Service

    / Third Party

    Expertise

    6. Taking Over

    Type of Sites / Clients 1. TL EPC 2. EPC by

    others

    3. Spilt Jobs 4. Running

    Units

    5. Overseas

  • 52

    9. Mandatory Clearances Initial set-up of Thermal Power Plant:

    9.1. Industrial Entrepreneur Memorandum acknowledgement given by

    Ministry of Commerce and Industry.

    9.2. Memorandum of Understanding (MoU) to be signed with State

    Government.

    9.3. Land Acquisition for Power Plant, Ash Dyke, Dam Site, Colony, Coal

    Handling, Cross Country Pipeline, Coal Conveyor etc. which comprises of

    following types of land:

    i) Government Land

    ii) Private Land

    iii) Forest land

    i) Government Land:

    a) Identify the land coming under project site

    b) Meet the Patwari of that Village on which particular land is coming & then

    prepare KHASRA map indicating various location of the land.

    c) List the name of owners coming under that particular area based on Khasra

    Mapping.

    d) Obtain the No Objection Certificate (NOC) from Local Gram Panchayat.

    e) With all the above mentioned information i.e. Khasra Map, List of Land

    Owners, NOC from Gram Panchayat, Land Diversion application if forest

    or agricultural land is coming under construction.

    f) With all the information cited above:- Local Govt. issue Section 4

    Notification stating that so & so govt. land is to be acquired by the Project

    Owner and if any one of the land owner having any sort of objection can

    write to them within 30 days of issue of notification. If any objection is

    received with the time frame specified by the govt. than the issue shall be

    discussed and resolved through public hearing.

    g) Based on the evaluation cost of land required by the Owner (Non-Forest &

    Non-Agricultural) and application fee for diversion of forest or agricultural

    land, Govt. decides the total amount to be paid by the land user and request

    to deposit the actual cost to the govt.

  • 53

    h) Once the applicable fees is paid, govt. issues Section 6 stating the given

    land is acquired by the ultimate user and issues payment cheques to various

    land owners who had sell their land.

    i) Once section 6 is issued, the land is presumed to be under custody of the

    Owner.

    ii) Private Land:

    a) Acquisition of private land is similar to the acquisition of govt. land and

    initial three steps of Govt. land viz. a, b, & c is same for Private also.

    b) Further, after preparation of list of land owners, direct dealing with the land

    owner with negotiations can be performed to purchase the land.

    c) Once the desired land is purchased, than the same shall be communicated to

    the local govt. for their information and records.

    iii) Forest Land:

    a) Diversion of forest is necessary and permission from regional MoEF is

    required if the land is

  • 54

    b) Ministry of Environment & Forests (MoEF): For MoEF clearance following

    procedures has to be done:

    1) PHASE-I Screening: Submit the application for site clearance to MoEF.

    If the site clearance is not granted than search for alternative site and

    again submit the application for site clearance.

    2) The site clearances provided by MoEF have certain conditions, if the site

    selected meets all the conditions than proceed for Environmental

    Clearance Phase-II (Citing, EIA report preparation, public hearing etc).

    3) PHASE-II:

    Step-1: Base line data collection

    Step-2: EIA report preparation and other approvals including

    Central Regulation Zone (CRZ) for coastal area.

    If diversion of forest 5 Ha apply to

    Central MoEF clearance.

    If use of ground water is involved than a hydrological

    report is to be submitted along with EC application.

    Obtain approvals for Electricity, Water Supply (Ground

    Water Board or Irrigation Dept. or Municipal Corporation

    etc.) and Explosives Storage / Hazardous substances (if

    applicable).

    Finalize Application and Environmental Appraisal

    Questionnaire.

    Step-3:

    A public hearing required.

    Submit requisite no. of copies of executive summary.

    Submit 1 copy of EIA, air and water consent application

    Form-1 and Form-13.

    Advertise and conduct public hearing by SPCB.

    Obtain details of public hearing.

    Obtain NOC from SPCB.

    The above mentioned Step-3 involves approx 60 days.

  • 55

    4) PHASE-III:

    Step-1:

    Submission of Documents (EIA-20 copies, EMP, NOC,

    Public Hearing details, DPR) to MoEF.

    Step-2:

    Review by IAA.

    If IAA feels that the data provided is sufficient then, the

    expert committee will submit their assessment over the

    report and application.

    Step-3:

    Expert committee will submit their recommendation to

    IAA.

    Step-4:

    If the project is accepted than MoEF clearance is granted

    for 5 years, however, if the case is rejected than it (case) is

    closed. Reconsideration may be considered in some cases.

    Step-5:

    Step 1 to 3 requires approx 90 days and Step-4 requires

    approx 30 days.

    9.5. Water Drawl Permission:

    Drawl from Perennial River: Approval from State Govt. in which

    river is falling. Data such as Water feasibility Report, Gauge

    Discharge and Index MAP indicating the location of Power

    Plant, River Pump House etc. to be submitted to Principal

    Secretary, Water Resource Department for State clearance.

    If, more than one state is involved in drawl of water from the

    river then in such case permission from Central Water

    Commission (CWC) is required.

    If construction of Dam is required, Const. of Dam Permission,

    Water Drawl Permission, Royalties to be paid etc.

  • 56

    9.6. Fuel Linkage Clearance:

    If coal is to brought from outside agency i.e. no captive coal mine

    is allocated than permission for coal linkage is required, which

    involves following procedures:

    Permission for railway sidings in case rail transportation is

    required from the nearest railway line.

    Way of right for railway sidings.

    Three party agreement etc.

    Allotment of coal blocks as per the requirement from Coal

    Ministry, Govt. of India.

    Coal Mining Plan is to be prepared and approved from State

    Govt.

    9.7. Civil Aviation Clearance:

    For construction of any sky rise building including chimney from Airport Authority

    of India (AAI).

    9.8. Permission from State Govt. for Construction Power.

    9.9. Permission from State Govt. for Construction Water.

    9.10. Permission for use of Explosive.

    9.11. Consent to establish from the State Environmental Board for setting up

    the thermal power plant.

    9.12. Consent to Operate & Maintain from the State Environmental Board for

    setting up the Power Plant.

  • 57

    10. Research Methodology:

    10.1. Survey:

    O&M Services at a site can be sustained over the long term only by satisfying

    the customer and ensuring the running of power plant in a reliable and efficient

    manner.

    Customer is King for us and it is a well known fact that customers demand and

    needs varies according to the situation. Hence to understand and walk with

    customer priority is Thermaxs sole responsibility. Keeping this in view, we

    classify the customers into different groups to aware you about their nature,

    which are as follows:

    1) EPC (TL) Customer:

    O&M contract entered into with an ongoing project of TL EPC. Now EPC

    groups within TL are:

    Small Power Plant (60 MW)

    In LPP segment usually cust