oil industry safety directorate - fipi uprety.pdf · present affiliation oil industry safety...
TRANSCRIPT
RAJESH UPRETY
Present Affiliation OIL INDUSTRY SAFETY DIRECTORATE
Academic Qualification B.TECH (MECHANICAL), PGDBM (Specialization in
Marketing)
Area of Specialization
PIPE AND COATING
Achievements / Awards
INSTRUMENTAL IN INTRODUCING DUAL FBE
COATING IN INDIA
Authors PIPELINE INTEGRITY MANAGEMENT FOR
PIGGABLE & NON-PIGGABLE PIPELINES
Presenting
Author Photo
OBJECTIVES OF PIPELINE INTEGRITY MANAGEMENT SYSTEM ARE:
• TO MAINTAIN INTEGRITY OF CROSS COUNTRY PIPELINES.
• AT ALL TIMES TO ENSURE PUBLIC SAFETY,
• PROTECT ENVIRONMENT AND
• ENSURE CONTINUOUS AVAILABILITY OF PIPELINE FOR TRANSPORTATION WITHOUT INTERRUPTIONS, THEREBY MINIMIZING THE BUSINESS RISKS AND THROUGHPUT LOSS.
PIPELINE INTEGRITY MANAGEMENT SYSTEM
3 3
PIPE TRIANGLE
PIPE
PLEASURE PAIN
4 4
TOTAL PIPELINE NETWORK IN INDIA
• PIGGABLE PIPELINE : 40,000 KM
• NON-PIGGABLE PIPELINE : 5000 KM (EXCLUDING GAS/ OIL FLOW LINES)
• SUB-SEA SPM LINES (SINGLE LINES)
5 5
Onsite Incidents – Trend last three years N
um
be
r o
f O
nsi
te In
cid
en
ts
2011-12
2012-13
2013-14
2014-15 (till date)
0
10
20
30
40
50
60
70
80
Ref &GPP
PLMO
E& PTotal
2011-12
2012-13
2013-14
2014-15 (till date)
6 6
Fatalities in Onsite Incidents - Trend
* Ref & GPPs : 28 Fatalities in a single Incident in 2013-14 ** Marketing Operations (MO): 05 Fatalities in a single incident in 2012-13 *** E&P: three children drowned at well site in 2013-14
Nu
mb
er
of
Fata
litie
s
2011-12
2012-13
2013-14
2014-15 (till…
0
5
10
15
20
25
30
35
40
45
Ref & GPP PLMO
E& P
2011-12
2012-13
2013-14
2014-15 (till date)
PIPELINE INTEGRITY
EXAMPLE : TWO CASES OF SEAM FAILURE IN A CRUDE PL WITHIN 18 YEARS OF SERVICE (SURGE ANALYSIS, HYDRAULICS, LDS, VALVES, WT)
EXAMPLE : FLASH FIRE DURING GRINDING OPERN AT NIGHT IN A TANK FARM (MISSING BOUNDARY PILLARS/TP/TLP, SOP, ESD, CP MONITORING, COATING SUEVEY)
EXAMPLE : FIRE & EXPLOSION IN A NATURAL GAS PIPELINE LEADING TO MULTIPLE FATALTIES (PIGGING, COATING)
CATAGORIES OF PIGGABLE/ NON-
PIGGABLE LINES
FROM PIGGING POINT OF VIEW THERE ARE FOUR CATAGORIES
OF PIPELINES :
1. PIGGABLE LINES IN WHICH REGULAR CLEANING PIGGING
IS CARRIED OUT.
2. PIGGABLE LINES IN WHICH CLEANING PIGGING IS NOT
CARRIED OUT.
3. NON-PIGGABLE PIPELINES SUCH AS WELL FLOW LINES/
JETTY LINES.
4. SPM / SUB-SEA LINES HAVING NO LOOP.
BASIC CONCERN FOR PIGGABLE
PIPELINES(PIGGING DONE REGULARLY)
1. PIGGABLE LINES IN WHICH REGULAR CLEANING PIGGING
IS CARRIED OUT.
• PIG RESIDUE ANALYSIS IS NOT CARRIED OUT REGULARLY.
• PROPER STATISTICAL ANALYSIS IS NOT CARRIED OUT TO
ESTABLISH TREND OF INTERNAL CORROSION.
BASIC CONCERN FOR PIGGABLE
PIPELINES(PIGGING NOT DONE REGULARLY)
2. PIGGABLE LINES IN WHICH CLEANING PIGGING IS NOT
CARRIED OUT.
• BASIC DETAILS ABOUT THE HEALTH OF THE PIPELINE
ARE NOT AVAILABLE.
• PRIODICITY FOR MAINTENANCE IS NOT FOLLOWED OR
IGNORED.
• SINCE COMMISSIONING PROPER CLEANING PIGGING HAS
NOT BEEN DONE. HIGH APPREHENSION OF CONDENSATE
AND WAX DEPOSITION CANNOT BE OVER RULED.
BASIC CONCERN FOR NON-PIGGABLE PIPELINES
3. NON-PIGGABLE PIPELINES SUCH AS FLOW LINES/ JETTY
LINES.
• THERE IS NO FOCUSSED ATTENTION ON THESE PIPELINES.
• THERE IS NO CATHODIC PROTECTION FOR SOME UNDERGROUND
PIPELINES.
• MONITIORING SYSTEM NOT IN PLACE IN LINE WITH OISD-GDN-233.
• IN SOME PIPELINES IT HAS BEEN OBSERVED THAT EVEN CORROSION
PROBES/ COUPONS ARE NOT USED.
CHALLENGES FOR MONITORING INTERNAL
CORROSION OF NON-PIGGABLE PIPELINES
4. SPM / SUB-SEA LINES HAVING NO LOOP.
• FIT FOR PURPOSE SUBJECT TO VARIOUS CONDITIONS IS
NOT A SOLUTION.
• AWARENESS ABOUT VARIOUS TECHNIQUES AVAILABLE
FOR ASSESSING INTERNAL CORROSION SUCH AS DIRECT
ASSESSMENT.
• EXPLORING POSSIBILITY OF PIGGING THE LINE BY USING
MODERN TECHNOLOGY.
• EXPLORING POSSIBILITY OF CONVERTING THE LINE TO A
PIGGABLE LINE.
CHALLENGES FOR MONITORING INTERNAL
CORROSION OF NON-PIGGABLE PIPELINES
THREATS IN LACK OF PIGGING
• IT MAY RESULT IN HEAVY DEPOSITION OF WAX IN CASE
OF CRUDE PIPELINES.
• IT MAY RESULT IN DEPOSITION OF CONDENSATE IN CASE
OF NATURAL GAS PIPELINES, WHICH MAY SPEED UP
INTERNAL CORROSION RATE.
OVERVIEW OF OISD-STD-233
a) INSPECTION PROCEDURE FOR CROSS-COUNTRY
PIPELINES :
i. INTERNAL INSPECTION
ii. PRESSURE TESTING SUCH AS HYDROTESTING
iii. COMBINATION OF i) & ii)
b) INSPECTION PROCEDURE FOR NON-PIGGABLE PIPELINES
:
i. EXTERNAL CORROSION DIRECT ASSESSMENT (ECDA)
ii. INTERNAL CORROSION DIRECT ASSESSMENT (ICDA)
iii.STRESS CORROSION CRACKING DIRECT ASSESSMENT
(SCCDA)
OVERVIEW OF OISD-STD-233
c) INTERNAL CORROSION :
a) EFFECTIVENESS OF CORROSION MITIGATION
MEASURES SHOULD BE CHECKED ONCE IN SIX
MONTHS BY ANALYSING CORROSION COUPON.
b) ER PROBES/ ECN PROBES/ LPR (LINEAR POLARISATION
TECHNIQUE) PROBES SHOULD BE INSTALLED.
c) IF RATE OF INTERNAL CORROSION IS > 1 mpy,
CORROSION INHIBITOR SHALL BE USED.
d) WHENEVER REPLACEMENT OF PIPELINE IS CARRIED
OUT, INTERNAL VISUAL INSPECTION SHALL BE
CARRIED OUT.
OVERVIEW OF OISD-STD-233
d) STRESS CORROSION CRACKING (SCC) :
a) PRESENCE OF H2S CAN LEAD TO SERIOUS SULPHIDE
STRESS CRACKING OF STEELS, WHICH CAUSES
STEPWISE CRACKING IN STEEL. ITS MITIGATION CAN
BE DONE IN TWO WAYS – BY INJECTING CHEMICAL
INHIBITORS & BY TREATING STEEL WITH CERTAIN
ALLOYING ELEMENTS & CONTROLLING ITS
HARDNESS.
B) SCC IS A SELECTIVE EXTERNAL CORROSION ATTACK
RESULTING FROM A COMBINATION OF DISBONDED
COATING, TENSILE STRESS, AND CERTAIN
ENVIRONMENTAL FACTORS.
OVERVIEW OF OISD-STD-233
e) PIPELINE DATA REQUIRED FOR DIRECT ASSESSMENT :
a) HISTORICAL DATA
b) PIPELINE MAPS & GEO DETAILS (DEPTH, LAND
PROFILE ETC.,)
c) BASIC TECHNICAL DATA SUCH AS PIPE DIA,
WT,GRADE, FLOW RATE, DESIGN PRESSURE, COATING
TYPE, CP PARAMETERS ETC.,
d) PRESENCE OF LIQUID WATER
e) PRESENCE OF H2S, CO
2 OR O
2.
f) CORROSION MONITORING DATA INCLUDING TYPE OF
MONITORING (E.G., COUPONS, ELECTRIC RESISTANCE
ETC.,)
g) PIPELINE SURVEY DATA : SOIL RESISTIVITY DATA,
COATING SURVEY DATA
OVERVIEW OF OISD-STD-233
f) DIRECT ASSESSMENT (DA) METHOD
g) INSPECTION PROCEDURE FOR PIPELINE HAVING
EXTERNAL COATING BUT WITHOUT CATHODIC
PROTECTION SYSTEM (IMPRESSED CURRENT BASED OR
SACRIFICIAL CURRENT BASED).
h) INSPECTION PROCEDURE FOR PIPELINE HAVING
EXTERNAL COATING BUT WITH CATHODIC PROTECTION
SYSTEM (IMPRESSED CURRENT BASED OR SACRIFICIAL
CURRENT BASED).
i) HYDROTESTING
FEW CASE STUDIES
(1) CASE-I :
THE LINE WAS COMMISSIONED IN 1999 AND IPS WAS
CARRIED OUT IN THE YEAR 2013. THE IPS REPORT WAS
NOT MADE AVAILABLE AS IT WAS INFORMED THAT THE
SAME IS UNDER REVIEW BY TPI. PIG RESIDUE ANALYSIS
SHOWED IRON CONTENT AS HIGH AS 49%. THERE WAS
NO ACTION TAKEN BY THE OPERATOR.
FEW CASE STUDIES
(2) CASE-II :
SUB-SEA LINE WAS COMMISSIONED IN 2006, HOWEVER, PIGGING
OPERATION NOT YET CARRIED OUT AS THERE WAS NO SCRAPPER
LAUNCHING BARREL OR SCRAPPER RECEIVER BARREL.
(3) CASE-III :
IN ONE OF THE JETTY LINE, THERE WAS NO CATHODIC PROTECTION
IN THE UNDERGROUND PIPELINE EVEN THOUGH EXTERNAL COATING
WAS IN PLACE.
FEW CASE STUDIES
(4) CASE-IV :
OFF-SHORE CRUDE LINE WAS COMMISSIONED IN 2005,
HOWEVER, PIGGING OPERATION NOT YET CARRIED OUT.
OTHER MAJOR INCIDENTS
MAJOR INCIDENTS OCCURRED IN
RECENT PAST
LOCATION MAP NARMADA SITE
SCHEMATIC VIEW OF THE NARMADA RIVER SITE
TOTAL NO. OF PIPELINES PASSING THROUGH NARMADA RIVER
S.No. Pipeline Operator Pipe Size Remarks
(1) Reliance (RGTIL) Natural Gas
48” OD x 1.000” WT (25.4 mm), API 5L X70 Gr.
Line is intact
(2) GAIL India
Natural Gas
30” OD x 19.1/11.9 mm WT, API 5L X 70 Gr.
Snapped & burst
(3) Reliance Industries Limited (RIL)
Ch. 29.150 KM (NG)
Natural Gas
26” OD x 0.500” WT, API 5L X 60
Gr.
Snapped & burst. Pipe has got
stuck in the nearby electrical
tower
(4) Reliance Industries Limited
(RIL)(NG)
Ch. 29.150 KM
24” OD x 0.500” WT API 5L X 60
Gr.
Snapped & burst.
TOTAL NO. OF PIPELINES PASSING THROUGH NARMADA RIVER
S.No. Pipeline Operator Pipe Size Remarks
(5) Gujarat State Petronet Ltd., (GSPL
– NG)
Ch. 17.000 KM
24” OD x 0.688” (17.5 mm) WT, API
5L X 60 Gr.
About 100 m pipeline is exposed.
(6) ONGC (Ch. 14.200 KM) CRUDE OIL 8.625” OD x 0.375” (9.53 mm) WT,
API 5L X 46 Gr.
Leakage in line
(7) IOCL (Amod Hazira Pipeline) 12.75” OD x 0.219” WT, API 5L X 60
Gr.
Line is intact
(8) ONGC (OPAL)
Naptha
12.75” OD x 0.25” WT, API 5L X 46
Gr.
Under construction
ROOT CAUSE OF THE INCIDENT
S.No CAUSE OF THE INCIDENT
(1) IT WAS A NATURAL CALAMITY. UNPRECEDENTED SUDDEN FLOODS DUE TO HEAVY RAINS AND LARGE QUANTITY OF DISCHARGE OF WATER FROM SARDAR SAROVAR DAM.
(2) THE RIVER BANK (SOUTH SIDE) WAS NOT REINFORCED, WHICH RESULTED IN HEAVY SOIL EROSION.
(3) REMOVAL OF PLANTS AND VEGETATION DURING THE CONSTRUCTION OF ELECTRICAL TRANSMISSION TOWER OF TORRENT POWER CLOSE TO THE RIVER BANK, WHICH HAS RESULTED IN LOOSENING OF THE PARENT SOIL.
(4) IRRIGATION DEPT. DID NOT PROVIDE ANY PRIOR WARNING BEFORE RELEASE OF ABRUPT WATER DISCHARGE IN SUCH A LARGE QUANTITY.
(5) SOIL EROSION IS A GRADUAL PROCESS, WHICH TAKES NUMBER OF YEARS. PIPELINE OPERATORS SHOULD CLOSELY MONITOR SUCH BEHAVIOR OF THE RIVER COURSE AND THE ADJOINING BANKS ON A REGULAR BASIS.
ROOT CAUSE OF THE INCIDENT
S.No CAUSE OF THE INCIDENT
(6) IT WAS A NATURAL CALAMITY. UNPRECEDENTED SUDDEN FLOODS DUE TO HEAVY RAINS AND LARGE QUANTITY OF DISCHARGE OF WATER FROM SARDAR SAROVAR DAM.
(7) BECAUSE OF THE EROSION OF THE SOIL FROM THE RIVER BANK, PIPE LINE, WHICH WAS BURIED IN THE GROUND BECAME EXPOSED AND PIPE LINE IN THE ERODED PORTION BECAME UNSUPPORTED. DUE TO THE FORCE OF WATER ON THIS EXPOSED PORTION OF PIPE LINE, IT STARTED OSCILLATING AND FINALLY ONE OF THE PIPELINES GOT SNAPPED DUE TO HEAVY OSCILLATION EFFECT IN HANGING PIPE LINE SECTION. THE VELOCITY OF WATER AND TURBULENCE IN THE RIVER WAS EXTREMELY HIGH AT THE TIME OF INCIDENT.
12
NATURAL GAS PIPELINE
RIVER BRIDGE
SV-1 SV-2
18" (API 5L X-60)
SV-5 SV-4/ I P HIGHWAY X-ING SV-3
(PIGGING STATION)
(CANAL)
POWER PLANT RIVER X-ING
SV-6 SV-7 SV-8
ORIGINATING
STATION
Leak/Burst site
Date/Time of incident 27th June 2014 at about 0545 hours
No. of fatalities 22
Operating pressure 42 to 45 Kg/cm2
Design pressure 72 Kg/cm2
Pipeline size and grade 18” OD API 5L X60 Grade
34
ANALYSIS / OBSERVATIONS OF THE FIRE INCIDENT
• CROSS COUNTRY PIPELINE – SUPPLYING NATURAL GAS TO POWER PLANT
• THE PIPELINE WAS BEING OPERATED AT A LOWER FLOW RATE AND LOWER PRESSURE W.R.T. THE DESIGN PARAMETERS.
• PIPELINE WAS TRANSPORTING WET GAS WHILE IT WAS ORIGINALLY DESIGNED FOR TRANSPORTING DRY NATURAL GAS.
• THE GAS CONTAINED CO2 AND SOME TRACES OF SULPHUR.
• LEAKAGE TOOK PLACE AT THE LOWEST POINT WHERE THE PIPELINE WAS CROSSING A CANAL AT 6 O’CLOCK POSITION.
35
FURTHER OBSERVATIONS OF THE FIRE INCIDENT
• IT WAS RAINING ON THE DAY OF THE INCIDENT, SO IT IS INFERRED THAT VAPOUR CLOUD FORMED DUE TO HEAVY WEATHER.
• A TEA STALL OWNER. WHO TURNED ON THE STOVE IN THE MORNING, POSSIBLY PROVIDED THE SOURCE OF IGNITION.
• THERE HAS BEEN A HISTORY OF PREVIOUS LEAKS NEAR THE PLACE OF ACCIDENT.
36
ROOT CAUSE OF THE FIRE INCIDENT
• LEAK DUE TO INTERNAL CORROSION – PRESENCE OF CO2 LED TO FORMATION OF H2CO3.
• DURING EARLIER REPAIRS EXTERNAL COATING GOT DAMAGED RESULTING IN
EXTERNAL CORROSION.
• IMPROPER PIGGING – FOAM PIG USED INSTEAD OF SCRAPPER PIGS.
• PIG RESIDUE ANALYSIS NOT CARRIED OUT.
• IPS CARRIED OUT IN 2010 - MAXIMUM METAL LOSS REPORTED IN IPS IS EQUIVALENT OF 50% OF WALL THICKNESS.
• USE OF WET NATURAL GAS INSTEAD OF DRY NATURAL GAS.
• NOT USING CORROSION INHIBITOR.
37
RECOMMENDATIONS
• PROPER CLEANING PIGGING TO BE CARRIED OUT REGULARLY FOLLOWED BY PIG RESIDUE ANALYSIS.
• INSTRUMENTED PIG SURVEY TO BE CARRIED OUT REGULARLY AND THE ANOMALY RECTIFICATION TO BE CARRIED OUT AS PER THE RECOMMENDATIONS .
• PROPER PROCEDURE TO BE MADE FOR REPAIR OF PIPELINE.
• ANY CHANGE FROM THE INITIAL CHANGE SHOULD BE ROUTED THROUGH A MANAGEMENT OF CHANGE PROCEDURE AFTER PROPER TECHNICAL ANALYSIS.
• CORROSION INHIBITOR TO BE USED IN THE LINE AS PER REQUIREMENT.
• IN ADDITION TO OFC COMMUNICATION THERE SHOULD ALSO BE ANOTHER STAND BY MODE OF COMMUNICATION.
• PROPER MAINTENANCE AND INSPECTION PRACTICE TO BE FOLLOWED.
• CHANGING DESIGN SERVICE WITHOUT PROPER TECHNICAL ANALYSIS OR WITHOUT PROPER MANAGEMENT OF CHANGE PROCESS.
• NOT LEARNING FROM PAST FAILURES & NOT CARRYING OUT PROPER ROOT CAUSE ANALYSIS.
• NOT CARRYING OUT PROPER CLEANING PIGGING & INTELLIGENT PIGGING SURVEY; NOT IMPLEMENTING RECOMMENDATIONS OF IPS SURVEY IN TIME.
• HIGH DEPENDENCY ON THIRD PARTY AGENCIES WITHOUT PROPER CONTROL.
• INADEQUATE LINE-PATROLLING.
MAJOR LAPSES NOTED OF-LATE IN THE PIPELINE INDUSTRY ON THE BASIS OF SOME MAJOR ACCIDENTS
• LACK OF S.O.P. FOR MAJOR ACTIVITIES LIKE REPAIR OF PIPELINE, COLD CUTTING, MUD PLUGGING, PIGGING, HOT-TAPPING ETC.,
• NOT USING CORROSION-COUPONS/ CORROSION INHIBITORS.
• NON-AVAILABILITY OF A PROPER LEAK DETECTION SYSTEM.
• MANUAL OPERATION OF SECTIONALIZING VALVES.
• DIRECT CURRENT VOLTAGE GRADIENT (DCVG) SURVEY / CURRENT ATTENUATION TEST (CAT) SURVEY/ CP SURVEY NOT CARRIED OUT REGULARLY FOR ASSESSING CONDITION OF COATING.
MAJOR LAPSES NOTED OF-LATE IN THE PIPELINE INDUSTRY ON THE BASIS OF SOME MAJOR ACCIDENTS
ELEMENT OPERATIONS INTEGRITY MANAGEMENT SYSTEM
RIGOROUS INTEGRITY MANAGEMENT SYSTEM PROVIDES FRAMEWORK FOR :
(1) MANAGEMENT LEADERSHIP, COMMITMENT AND ACCOUNTABILITY
(2) RISK ASSESSMENT AND MANAGEMENT (3) FACILITIES DESIGN & CONSTRUCTION –
SPECS, CODES, STANDARDS (4) INFORMATION / DOCUMENTATION
(5) PERSONNEL & TRAINING
(6) OPERATIONS & MAINTENANCE (7) MANAGEMENT OF CHANGE
(8) THIRD PARTY SERVICES
(9) INCIDENT INVESTIGATION &
ANALYSIS
(10) COMMUNITY AWARENESS & EMERGENCY PREPAREDNESS
(11) OPERATIONS INTEGRITY ASSESSMENT AND IMPROVEMENT
THREATS TO OPERATING PIPELINE INTEGRITY
THREATS TO OPERATING PIPELINE INTEGRITY
EFFECTIVE INTEGRITY MANAGEMENT OF AN ASSET COMPRISES OF :
1. DESIGN INTEGRITY (ASSURANCE THAT FACILITIES ARE DESIGNED IN ACCORDANCE WITH GOVERNING STANDARDS AND MEET SPECIFIED OPERATING REQUIREMENTS),
2. TECHNICAL INTEGRITY (APPROPRIATE WORK PROCESSES FOR INSPECTION AND MAINTENANCE SYSTEMS AND DATA MANAGEMENT TO KEEP THE OPERATIONS AVAILABLE) AND
3. OPERATIONAL INTEGRITY (APPROPRIATE KNOWLEDGE, EXPERIENCE, SOPS, COMPETENCE AND DECISION MAKING TO OPERATE THE PLANT AS INTENDED THROUGHOUT ITS LIFECYCLE.)
PIPELINE INTEGRITY MANAGEMENT SYSTEM
DESIGN INTEGRITY :
• DESIGN OF A CROSS-COUNTRY PIPELINE IS VERY DIFFERENT FROM THAT OF PLANT PIPING SINCE IT
IS NOT CONFINED TO A LIMITED AND PROTECTED AREA AND MAY PASS THROUGH DIFFERENT TYPES OF TERRAIN OVER WHICH THE OPERATOR HAS NO CONTROL.
• THEREFORE, ITS DESIGN HAS TO TAKE INTO CONSIDERATION BOTH NATURAL PHENOMENON AS WELL AS HUMAN ACTIVITIES ALONG THE ROUTE AND PROVIDE A SYSTEM ENSURING ITS LONG LIFE, OPERATABILITY AND EASE OF MAINTENANCE.
• WHILE CONCEPTUALIZING A NEW PIPELINE PROJECT MORE TIME SHOULD BE DEVOTED TO FREEZING DETAILED DESIGN AND ENGINEERING.
• STRESS ANALYSIS, SURGE RELIEF ANALYSIS, HYDRAULIC ANALYSIS, NETWORK ANALYSIS ETC., SHOULD BE DONE IN THE INITIAL STAGES AND NECESSARY DESIGN CHANGES TO BE CARRIED OUT REGARDING SELECTION OF PIPE, PIPE FITTINGS, VALVES, LAYOUT, P&ID ETC.,
PIPELINE INTEGRITY MANAGEMENT SYSTEM
SAFETY FACTORS IN DESIGN IS ACHIEVED BY : • APPLICATION OF THE APPROPRIATE CODES AND SYSTEM HARDWARE COMPONENTS (ASME STANDARD
& OISD STANDARDS).
• SELECTION OF PIPE MATERIAL AND ITS WALL THICKNESS, MATERIAL OF CONSTRUCTION FOR VALVES AND OTHER PIPE FITTINGS.
• CONSIDERING THE LOADS & STRESSES IMPOSED ON THE PIPELINE BY PHYSICAL PRESSURES AND FORCES, SUCH AS INTERNAL PRESSURE, STATIC LOADINGS AND WEIGHT EFFECTS.
• CONSIDER DYNAMIC LOADING, WHERE APPLICABLE, WIND, WAVES, EARTHQUAKE ETC.,
• IDENTIFYING HIGH CONSEQUENCE AREAS & LOCATION CLASS.
• SPECIAL PROTECTIONS AT CROSSING LIKE RIVER/CANAL, RAIL, ROAD ETC.,
DESIGN INTEGRITY
SAFETY FACTORS IN DESIGN ACHIEVED BY:
(A) PIPE THICKNESS :
• THE NOMINAL WALL THICKNESS “T” FOR THE STEEL PIPE, SHALL BE CALCULATED IN ACCORDANCE WITH ASME B 31.4 - CONSIDERS LONGITUDINAL JOINT FACTOR FOR TYPE OF PIPELINE MANUFACTURING, FACTORS FOR RAIL, ROADS, RIVER CROSSINGS, PIPES ON BRIDGES, LOCATION CLASS ETC.
• CORROSION ALLOWANCE ADDED TO THE CALCULATED THICKNESS.
(B) ALL PIPING JOINTS ARE WELDED
(C)THE HAZOP AND RISK ANALYSIS
(D) LOCATING “SECTIONALIZING VALVES” AT IDENTIFIED LOCATIONS FOR ISOLATIONS EASILY APPROACHABLE. SECTIONALIZING VALVES SHALL BE REMOTE OPERATED.
DESIGN INTEGRITY
SAFETY FACTORS IN DESIGN ACHIEVED BY:
(E) SURGE ANALYSIS TO PREVENT OVER-PRESSURIZATION ON CLOSURE.
(F) FEATURE OF DE-PRESSURIZATION, SHUTDOWN & ISOLATION LOGIC AT PUMP STATIONS.
(G) METERING STATIONS AND SCADA SYSTEMS PROVIDE CONTINUOUS MONITORING OVERSIGHT OF PIPELINE OPERATIONS.
(H) LEAK DETECTION SYSTEM WITH PROVISION FOR IDENTIFICATION / LOCATION OF LEAK AND ISOLATION OF AFFECTED SECTION.
(I) EXTERNAL COATING & CATHODIC PROTECTION FOR EXTERNAL CORROSION CONTROL.
(J) INHIBITOR INJECTION FOR INTERNAL CORROSION CONTROL CASE.
DESIGN INTEGRITY
INTERNAL HEALTH MONITORING
PIPELINE PIGGING - PIGS ARE INSERTED INTO THE PIPELINE WHILE IT IS OPERATIONAL AND ARE CARRIED ALONG BY THE FLUID BEING PUMPED.
TECHNICAL INTEGRITY
CLEANING PIGS
INTERNAL HEALTH MONITORING THEIR BASIC PURPOSE OF PIGGING IS THREEFOLD: (1) CLEANING PIG - PROVIDE A WAY TO CLEAN DEBRIS AND SCALE FROM
THE INSIDE OF THE PIPE, (2) INTELLIGENT PIG - INSPECT OR MONITOR THE CONDITION OF THE
PIPE, (3) OR ACT AS A PLUG OR SEAL TO SEPARATE PRODUCTS IN MULTI-
PRODUCT COMMERCIAL PIPELINES OR TO ISOLATE A SEGMENT FOR REPAIR WITHOUT DEPRESSURIZING THE REMAINDER OF THE PIPELINE.
(4) PIG RESIDUE ANALYSIS TO BE CARRIED OUT REGULARLY TO MONITOR THE TREND OF INTERNAL CORROSION RATE.
TECHNICAL INTEGRITY
TECHNICAL INTEGRITY
INTERNAL HEALTH MONITORING : INTELLIGENT PIG – • PIGS THAT MONITOR THE CONDITION OF THE PIPE ARE IN-LINE INSPECTION TOOLS.
• MONITORING PIGS, ALSO CALLED “INSTRUMENT PIGS” OR “SMART PIGS”.
• GEOMETRY PIGS : CHECKS DEFORMATION, MISALIGNMENTS, BENDS, ELEVATION CHANGES AND DIRECTIONAL CHANGES TO THE PIPE.
• MAGNETIC FLUX LEAKAGE AND ULTRASONIC TECHNOLOGIES : FOR CRACKS DETECTION AND THICKNESS MEASUREMENT, CORROSION DETECTION, LEAK DETECTION.
EXTERNAL HEALTH MONITORING - PIPELINE COATING & CATHODIC PROTECTION:
• PROTECTIVE COATING : TO PREVENT DIRECT CONTACT BETWEEN THE PIPE & THE ENVIRONMENT & TO PREVENT ITS PARTICIPATION IN ELECTROCHEMICAL REACTIONS
• PROPERTIES REQUIRED
(A) ELECTRICAL – INSULATING PROPERTIES,
RESISTANCE TO MOISTURE
(B) MECHANICAL- ADHESION, ABRASION RESISTANCE,
FLEXIBILITY, IMPACT RESISTANCE
(C) STABILITY AGAINST TEMP CHANGE
• 3 LAYER POLYETHYLENE / POLYPROPYLENE OR FUSION BONDED EPOXY COATING IS PROVIDED
TECHNICAL INTEGRITY
FOLLOWING COATING SURVEYS ARE DONE ON UNDERGROUND PIPELINES ONE MONTH AFTER THE COMMISSIONING OF IMPRESSED CURRENT SYSTEM:
a. CLOSE INTERVAL COMPUTERIZED [“ON” & “OFF”] POTENTIAL LOGGING (CIPL) @ EVERY 1M OF PIPELINE ROW.
b. PEARSON SURVEY ALONG PIPELINE ROW.
c. CAT (CURRENT ATTENUATION TEST) SURVEY @ EVERY 50M OF PIPELINE ROW.
d. DCVG ( DIRECT CURRENT VOLTAGE GRADIENT) SURVEY AT DEFECT LOCATIONS INDICATED BY PEARSON, CIPL, CAT SURVEYS
e. COATING CONDUCTANCE SURVEY AT AND MIDWAY BETWEEN CP STATIONS.
f. CASING & CARRIER SHORT SURVEYS.
TECHNICAL INTEGRITY
ALL THE PIPELINE OPERATORS MUST HAVE A CORPORATE POLICY TO IMPROVE PIPELINE AND FACILITY INTEGRITY TO PROTECT THE SAFETY OF THE PUBLIC, THE ENVIRONMENT AND ITS EMPLOYEES.INTEGRITY MANAGEMENT GOALS SHALL INCLUDE :
• PROMOTE THE LONG TERM INTEGRITY OF THE PIPELINE SYSTEM
• CONDUCT BUSINESS IN A SAFE AND ENVIRONMENTALLY RESPONSIBLE MANNER
• COMPLY WITH APPLICABLE REGULATIONS AND STANDARDS
• DEMONSTRATE CONTINUOUS IMPROVEMENT THROUGH THE MONITORING OF PERFORMANCE MEASURES AND THROUGH ANNUAL RISK ASSESSMENTS
• ONLY ADEQUATELY TRAINED, SKILLED AND COMPETENT MANPOWER SHALL BE DEPLOYED FOR PIPELINE OPERATIONS.
• COMPLY WITH ALL THE STANDARD OPERATING PROCEDURES (SOP)
OPERATIONAL INTEGRITY
• PRESSURE SET POINTS SHOULD BE APPROPRIATELY DEFINED AND BUILT IN THE OPERATION PHILOSOPHY.
• ESD LOGIC (CAUSE AND EFFECT DIAGRAM) SHOULD BE PROPERLY DEFINED.
• CLEANING PIGGING HAS TO BE CARRIED OUT AS PER OISD GUIDELINES AND PIG-RESIDUE ANALYSIS SHOULD BE CARRIED OUT REGULARLY. THE RESULTS OF THE PIG-RESIDUE ANALYSIS SHOULD BE ANALYSED WITH THE HELP OF STATISTICAL TECHNIQUES TO WORK OUT THE TREND OF INTERNAL CORROSION RATE.
• NO SAFETY SYSTEMS SHOULD BE BY-PASSED.
OPERATIONAL INTEGRITY
ROU INSPECTION
• INSPECTIONS CAN INVOLVE INDIVIDUALS WALKING THE ROU AND ALSO AERIAL SURVEILLANCE.
A) NO DWELLING OR PERMANENT STRUCTURE IN ANY FORM SHALL BE PERMITTED WITHIN THE RIGHT OF USER
B) CONTROLLING VEGETATION GROWTH IN THE FORM OF TREES,
C) PREVENTING ENCROACHMENT FROM ABOVE AND BELOW GROUND STRUCTURES,
D) MAINTAINING VISIBILITY OF PIPELINE MARKERS
PATROLLING ( GROUND / AERIAL ) OF ROW / ROU
• TO BE CARRIED OUT REGULARLY (URBAN AREAS AND NON-URBAN AREAS)
• OBSERVE SURFACE CONDITIONS, LEAKAGE, CONSTRUCTION ACTIVITY, ENCROACHMENTS, WASHOUTS AND ANY OTHER FACTORS AFFECTING THE SAFETY AND OPERATION OF THE PIPELINE.
OPERATIONAL INTEGRITY
MANAGEMENT OF CHANGE • MONITORING & REVIEW OF OPERATING PARAMETERS TO WORK WITHIN THE
OPERATING BARRIERS.
• STANDARD OPERATING PROCEDURES (SOP) INCLUDING EMERGENCY ISOLATIONS.
• SAFETY CONTROL SYSTEM MONITORING & PROOF TESTS OF ESD SYSTEMS.
• INTERPRETATION OF CATHODIC MONITORING RESULTS.
• INTERPRETATION OF PIGGING RESULTS & ACTIONS THERE OF.
• COATING HEALTH SURVEY & CORRECTIVE MEASURE.
OPERATIONAL INTEGRITY
• A CLASS LOCATION CAN CHANGE AS POPULATION GROWS AND MORE PEOPLE LIVE OR WORK NEAR THE PIPELINE.
• WHEN A CLASS LOCATION CHANGES, PIPELINE OPERATORS :
– MUST EITHER REDUCE THE PIPE'S OPERATING PRESSURE TO REDUCE STRESS LEVELS IN THE PIPE;
– REPLACE THE EXISTING PIPE WITH PIPE THAT HAS THICKER WALLS OR HIGHER YIELD STRENGTH TO YIELD A LOWER OPERATING STRESS AT THE SAME OPERATING PRESSURE;
– WHERE THE CLASS IS CHANGING ONLY ONE CLASS RATING, SUCH AS FROM A CLASS 1 TO CLASS 2 LOCATION, CONDUCT A PRESSURE TEST AT A HIGHER PRESSURE
CLASS LOCATION
OTHER IMPORTANT ASPECTS OF THE PIPELINE INTEGRITY MANAGEMENT SYSTEM ARE :
• THE INLINE INSPECTION & MAINTENANCE PROCEDURES FOR ENSURING HEALTH INTEGRITY OF PIPELINES,
• STANDARD OPERATING PROCEDURES,
• THE CONTROL FOR MANAGEMENT OF CHANGE INCLUDING THE PROCESS SAFETY ASPECTS
PIPELINE INTEGRITY MANAGEMENT SYSTEM
PIPES LAID UNDERGROUND CANNOT SPEAK, IT IS OUR DUTY TO CARE FOR THE PIPE & GIVE EITHER PAIN OR PLEASURE. NEED OF THE HOUR TO IS TO HAVE A SENSITIVITY TOWARDS PIPE.
PIPELINE INTEGRITY MUST CONSIDER ALL ASPECTS OF DESIGN, CONSTRUCTION & OPERATION PHASES.
PIPELINE INTEGRITY REQUIRES ADOPTING A “FAILURES ARE PREVENTABLE” MINDSET.
ADOPTION OF CORROSION MANAGEMENT BEST PRACTICES CAN IMPROVE OVERALL PERFORMANCE OF PIPELINE OPERATIONS.
CONCLUSION