ohlone elementary school phase 1 campus replacement

9
OHLONE ELEMENTARY SCHOOL PHASE 1 CAMPUS REPLACEMENT

Upload: kaoru

Post on 07-Jan-2016

48 views

Category:

Documents


0 download

DESCRIPTION

Ohlone Elementary School Phase 1 Campus Replacement. Ohlone Elementary School. Ohlone Elementary School. Ohlone Elementary School. Ohlone Elementary School Project Status Report. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Ohlone  Elementary School Phase 1 Campus  Replacement

OHLONE ELEMENTARY SCHOOLPHASE 1 CAMPUS

REPLACEMENT

Page 2: Ohlone  Elementary School Phase 1 Campus  Replacement
Page 3: Ohlone  Elementary School Phase 1 Campus  Replacement
Page 4: Ohlone  Elementary School Phase 1 Campus  Replacement
Page 5: Ohlone  Elementary School Phase 1 Campus  Replacement

Ohlone Elementary School

Page 6: Ohlone  Elementary School Phase 1 Campus  Replacement

Ohlone Elementary School

Page 7: Ohlone  Elementary School Phase 1 Campus  Replacement

Ohlone Elementary School

Page 8: Ohlone  Elementary School Phase 1 Campus  Replacement
Page 9: Ohlone  Elementary School Phase 1 Campus  Replacement

• Construction Days Elapsed: 233• Construction Days Remaining: 487• Percent of Contract Days Elapsed:

32%

Construction Schedule: 720 days

• Notice to Proceed: 8/1/11• Original Completion Date: 7/20/13• Percent of Construction Completed:

30%

Projected Completion

Date: 7/20/2013

Ohlone Elementary School Project Status Report