Illinois Route 490 Tollway Project Update
January 11, 2019
![Page 2: O’Hare Noise Compatibility Commission](https://reader030.vdocuments.site/reader030/viewer/2022012722/61b48197c757a725fb4d6d25/html5/thumbnails/2.jpg)
Part of a dynamic transportation network • Connects to regional transit
network• Supports three international
airports• Part of one of the nation’s largest
interstate systems
Five roadways294‐mile system across 12 countiesServes more than 1.6 million vehicles a day
About The Tollway
2January 11, 2019
![Page 3: O’Hare Noise Compatibility Commission](https://reader030.vdocuments.site/reader030/viewer/2022012722/61b48197c757a725fb4d6d25/html5/thumbnails/3.jpg)
Move Illinois Program 15‐year, $14 billion capital program
3
Taking care of existing system ‐ $4 billion• Repair roads, bridges and interchanges
Illinois Route 390, I‐490 Tollway ‐ $3.4 billion• Provide access to O’Hare International Airport
Central Tri‐State Tollway (I‐294) ‐ $4 billion• Reconstruct 22 miles at heart of the system
Jane Addams Memorial Tollway (I‐90) –$2.5 billion
• Rebuild and widen 62 miles with transit options
I‐294/I‐57 Interchange ‐ $719 million• Connect two major interstates
January 11, 2019
![Page 4: O’Hare Noise Compatibility Commission](https://reader030.vdocuments.site/reader030/viewer/2022012722/61b48197c757a725fb4d6d25/html5/thumbnails/4.jpg)
I‐490 Interchange – Enhanced Western Access
January 11, 2019 4
![Page 5: O’Hare Noise Compatibility Commission](https://reader030.vdocuments.site/reader030/viewer/2022012722/61b48197c757a725fb4d6d25/html5/thumbnails/5.jpg)
I‐490 Interchange/Western Access Construction
January 11, 2019 5
33 I‐490 Interchange – Western access ramp constructionScheduled: 2019 ‐ 2023
I‐490 Interchange – Illinois Route 83 to York Road construction Scheduled: 2019 – 2020
11
O’Hare Airport perimeter fence and road relocation Completed: June 2018
33
221122
![Page 6: O’Hare Noise Compatibility Commission](https://reader030.vdocuments.site/reader030/viewer/2022012722/61b48197c757a725fb4d6d25/html5/thumbnails/6.jpg)
I‐490 Tollway North Segment Construction
January 11, 2019 6
11 I‐490/I‐90 Interchange bridgesScheduled: 2018 – 2019
22 I‐490/I‐90 Interchange bridges and fuel station removal Scheduled: 2018 – 2020
33 Touhy Avenue Reconstruction Project – Cook CountyScheduled: 2019 – 2021
11
2233
![Page 7: O’Hare Noise Compatibility Commission](https://reader030.vdocuments.site/reader030/viewer/2022012722/61b48197c757a725fb4d6d25/html5/thumbnails/7.jpg)
January 11, 2019 7
I‐490/I‐90 Interchange
![Page 8: O’Hare Noise Compatibility Commission](https://reader030.vdocuments.site/reader030/viewer/2022012722/61b48197c757a725fb4d6d25/html5/thumbnails/8.jpg)
January 11, 2019 8
I‐490/I‐294 Interchange
![Page 9: O’Hare Noise Compatibility Commission](https://reader030.vdocuments.site/reader030/viewer/2022012722/61b48197c757a725fb4d6d25/html5/thumbnails/9.jpg)
THANK YOU
January 11, 2019 9