oguk conference standardisation mindset - oil &...
TRANSCRIPT
OGUK ConferenceStandardisation MindsetJune 2017
Nicky MasonVP Asset Support, AberdeenAmec Foster Wheeler
Covering
• Illustration of the problem
• Subsea Standardisation Work
• Amec Foster Wheeler’s
Standardisation Mindset
• Examples
• Culture and
2
Example 1: Everything is/was bespoke
Valve bore distribution
for subsea valves
supplied by Bel Valves
3
50+ detail differences on one piece of equipment.
Why so different?
Subsea Standardisation Work
4
Translating this into an Amec Foster Wheeler world
5
• Standardisation of Equipment &
Hardware
• Applying a Simplified and Streamlined Process
• Applying alternative methods & technology
to provide optimised solutions
• Applying a fit for purpose approach
Codes, Standards and Specifications
Alternative Methods & Technology
Equipment and
HardwareProcess
Applying a fit for purpose approachCode, Standards and Specifications
6
Design
• Specify only functional requirements
• Applying only industry standards
• Minimise design cases
• Design for field/plant life
Materials
• Pre-qualified materials
• Supplied to industry standard
requirements
• Fit for purpose or risk based
approach adopted
• Aligned selection to stock
Component, Product and
Qualification Testing
• Apply testing criteria from industry
standards.
• Testing to manufacturer’s
recommendation
• FAT to manufacturer’s
recommendation
• Qualification testing to cover size
ranges
Suppliers, Manufacturing &
Fabrication
• Supplier chooses their preferred
manufacturing and fabrication
processes
• Supplier and manufacturing
tolerance set to manufacturers and
industry standards
7
Example 2 – Supply Chain Component cost analysis
ETF Valves - Efficiency benchmarking
Global Operators
UKCS Focused Operators
Reference Case
200%
600%
Complexity
UKCS Focused Operators
Global Operators
Reference Case
% Cost
% Duration
Applying a Simplified and Streamlined Process
8
Documentation
• Streamlined to supplier’s standard
• Reviewed key documents
Interface Management
• Single focal point assuring
compliance with Scope of Work and
Basis of Design
• Simplified Supplier Documentation
Requirements List
• Culture of ‘no change’
Supply Chain Management
• Approved vendor lists
• The Tender Efficiency Framework
intends to realise savings through
tender optimisation. O&GUK
matrices to be applied.
• Reduce number of suppliers per
package type
• Contractor to manage supplier.
• No restrictions on supplier location
providing ISO 9001 certification
Inspection
• Work to contractor / supplier to
processes
• Limit the presence of inspectors on
site during the manufacture or
fabrication scope
Example 3: Post pricing
9
1) Index for our Manufacturing Record Book(MRB)
2) Weight data sheets – the weight is shown on the drawing
3) Quality Plan
4) Weld Traceability Log
5) Weld Procedure
6) NDE Procedures
7) Surface preparation & painting procedure
8) Weld Procedure approval Form
9) MRB
10) CE Declaration of Conformity
11) Weight report (even though not an offshore item)
12) Certificate of Conformity
13) Inspection and test plan
14) Supporting documents that usually make up our MRB
Plus an independent 3rd party inspector to release.
Applying Alternate Methods and Technology to Provide Optimised Solutions
10
Design
• Apply ‘closest equivalent’
• Reducing levels of redundancy
• Accept alternative materials
• Risk based approach to metallurgy
• Challenge maintenance routines
• Utilisation of close coupled mono-
flanges for field instruments
Manufacture
• Provide fit for purpose materials
• Alternative manufacturing routes
Fabrication
• Engage fabricators early – what can
they supply?
Construction Led Engineering
• ‘CPE’ approach
• Construction function to ‘prove the
build’ and influence the design early
Example 4: Alternate method, Use supply chain skills
145 hrs 34 hrs
= £6,500saving
2016: Reductions beyond norm sets:-
Replacement of 13 spring hanger supports
Standardisation of Equipment and Hardware
1
2
Standard and Modular Designs
• Off-the shelf equipment
• Modularised and building block
approach
• Supply Chain Framework
Agreements
• Standard footprint and sizing
Re-Use
• Re-use of standard / existing
designs
• Re-use of redundant equipment /
surplus capacity in existing
equipment
Interchangeability
• Standard connections and
interfaces
• Plug and play
Communications
• Standard communications protocols
M4L Procurement: “Savings Snapshot ”
25%Average
Savings*
£6.0m Annual
Savings*
*Estimated against 2016 Prices for circa £21.4m annual spend on the above
commodities
>6500Line items
£1.7msavings on Piping Bulks
£0.3m savings on PPE
The aim is for transformational change
14 Source:- Deloitte LLP
Doing the right thing…right
15
Doing the Right thing
Design, Supply Chain, C3 in
Concept/Pre-FEED
Alignment to business case
Benchmarked, Standardised
approach,
Culture of challenge
Efficient and effective
Concept/Pre-FEED
Doing the thing Right
FEED - EPC - Handover
More 4 Less: Our framework for step change in delivery
Conclusion
1
6
Standardisation
Simplification
Less specification Collaboration
Simplification