ofgem eco 1.2 consultation summary of district heating workshop 13 august 2014
TRANSCRIPT
Ofgem ECO 1.2 consultationSummary of district heating workshop
13 August 2014
Amending Order (ECO1.2)• CERO target reduction• Changes to CSCO areas• New CERO primary measures• Early CERO delivery uplift• Optimum carry forward of excess actions• Interim provision
Changes up to March 31 2015 First obligation period (OP1) Laid 22 July 2014 Coming into force ~ Nov 2014 Applying from 1 April 2014
Proposed legislative changes in ECO 1.2 – based on the legislation laid by DECC
3
Key areas of our consultation• ECO 1.2 changes:
• New CERO primary measures: minimum insulation level to support a secondary measure
• Connections to a district heating system: pre-conditions under CERO and CSCO
• In addition we are also consulting on the following issues unrelated to the ECO 1.2 changes:• Compliance with building regulations: installation of a measure• General comments on our guidance (version 1.2)
ECO 1.2 consultation timeline
Key dates Activity
22 July DECC laid amending Order
11 August Ofgem launch consultation
22 September Ofgem close consultation
Late October Ofgem publish response to consultation and final guidance
Early November Amending Order comes into force
5
Connections to a DHS: DECC• ECO amending Order:
“a connection to a district heating system where that connection is made to premises which— i. do not include the top floor of the building in which those premises are
located, and where the walls of those premises cannot be insulated; orii. have flat roof, loft, rafter, room-in-roof or wall insulation”
• The policy intent is for premises which are being connected to a DHS under CERO or CSCO to be insulated
NB For (i) we refer to “those premises” as premises within a multi-storey building which are not located on the top floor.
6
Connections to a DHS: Ofgem
• Ofgem’s consultation:“Pre-conditions for premises which are being connected to a DHS, for the measure to be claimed under CERO or CSCO:1. The premises must have either ‘roof-space insulation’ or ‘wall insulation’ in
place.2. For premises in a multi-storey building, which are not located on the top floor
of the building, the total exterior-facing walls must be insulated unless they cannot be insulated.”
• We must judge if a roof-space area or exterior-facing wall area “cannot be insulated”
NB ‘Roof-space’ insulation is flat-roof insulation, loft insulation, rafter insulation or room-in-roof insulation. ‘Wall insulation’ is external wall insulation, internal wall insulation or cavity wall insulation.
7
Pre-condition 1
We will consider that this is met if:– the total roof-space area or exterior-facing wall area of the premises is
insulated,or
– if part of the total roof-space area or exterior-facing wall area (not exceeding 50%) cannot be insulated then the remaining part is insulated.
PRE-CONDITION 1: The premises must have either ‘roof-space insulation’ or ‘wall insulation’ in place.
8
Pre-condition 2
We will consider that this is met if:– the total exterior-facing wall area of the premises is insulated,
or– if part of the exterior-facing wall cannot be insulated then the remaining part
is insulated,or
– all of the exterior-facing wall cannot be insulated.
PRE-CONDITION 2: For premises in a multi-storey building, which are not located on the top floor of the building, the total exterior-facing walls must be insulated unless they cannot be insulated.
9
Defining ‘roof-space area’
• ‘Roof-space area’ means:– for loft insulation, the area of the floor of the loft– for rafter insulation, the area of the rafters– for flat roof insulation, the area of the roof – for room-in-roof, the area of the room-in-roof including the common
walls, gable walls and ceiling– for properties with more than one roof type, and/or more than one
type of roof-space insulation installed, the sum of the areas as explained above.
10
Pre-conditions for connections to DHS under CERO and CSCO
Type of premises
Roof-space insulation(% of area insulated)
Wall insulation(% of area insulated)
DHS eligible under CERO or CSCO?
Most premises (including
premises located on the top floor of a multi-storey
building)
100% 100% Yes
0-49% 100% Yes
100% 0-49% Yes
50-99% 0-49%Yes, if we judge the
uninsulated roof-space area cannot be insulated
0-49% 50-99%Yes, if we judge the uninsulated
wall area cannotbe insulated
Premises within a multi-storey
building which is not located on the top floor
n/a 100% Yes
n/a 0-99%Yes, if we judge the
uninsulated wall area cannot be insulated
11
Reasons for our proposals
• We are proposing that there must be a minimum level of insulation installed to meet the intent of the legislation. Without this, DHS connections could be installed at a property where only a nominal amount of insulation had been installed.
• This is also consistent with our current pre-conditions for a premises being connected to a DHS under CSCO which we consulted on at the start of ECO.
12
Defining “cannot be insulated”• Proposed reasons for judging that a roof-space area cannot be insulated:
– it is not possible to access an area of the roof space in order to install the insulation
– the occupier (or landlord, as applicable) of the premises refuses to consent to installing the insulation on reasonable grounds other than cost
• Proposed reasons for judging that an exterior-facing wall area cannot be insulated:– it is not possible to access the wall in order to install the insulation– it would be unlawful to install the insulation– the occupier (or landlord, as applicable) of the premises refuses to consent to
installing the insulation on reasonable grounds other than cost
13
Questions for the break-out sessions• Do you agree that insulation must be installed to at least 50%
of the roof-space or exterior-facing wall area to support a connection to the DHS?
• Do you agree with our proposed reasons for why a roof-space or exterior-facing wall area cannot be insulated?
• Are there any other reasons/scenarios that we haven’t considered?
• If so, how could suppliers demonstrate for compliance purposes that the roof-space or exterior-facing wall area cannot be insulated in these scenarios?
14
Break-out sessions
The following slides summarise the main discussion points of the workshop participants in
each of the breakout groups
15
Main points: group 1• Debate across all groups about whether costs should be a
good enough reason for not being able to insulate• Considered how the pre-conditions could apply for non-
standard multi-storey buildings• General agreement with the 50% de minimis level• Would like Ofgem to provide examples of acceptable evidence• The cost of planning permission could become a problem if
planning becomes a method of evidencing• Discussed if pre-conditions should have to apply for upgrades
to a DHS
16
Main points: group 2• Generally agreed with the 50% minimum. Suggested it could even
be higher• How to define “reasonable grounds”• Discussion about standards of pre-existing insulation and what
“adequately filled” means• Issues with insulating the top floors of multi-storey buildings• How projects started under ECO 1.1 rules are affected• Possibilities for aligning ECO with RHI
17
Main points: group 3• Conventions required for measuring wall area (including or
excluding openings?) and roof-space area• It can be unlawful to insulate a roof space if there are
protected species living there• How to determine the threshold for “cannot gain access”• Discussion about insulating non-standard properties• How to get at pre-existing rafter/room in roof insulation to
find out what standard it has been installed to. How to check the standard of this insulation and evidence it
18
Next steps
• Written responses to our consultation should be submitted by 9am Monday 22 September
• We will publish a response and final guidance at the end of October