    SHEET   1   OF   5    

708 Heartland Trail, Suite 3000 (53717)      Madison, WI      (608) 826‐3600      FAX: (608) 826‐3941  

PROJECT/PROPOSAL NAME  PREPARED  CHECKED  PROJECT/PROPOSAL NO. 

Dairyland Power Cooperative; Phase IV 

Alma Off‐site Disposal Facility 

By:  Date:  By:  Date: 243332.0002 

J. Hotstream  11/9/2016  T. Martin  11/22/2016 

 

\\NTAPB‐MADISON\MSN‐VOL6\‐\WPMSN\PJT2\243332\0002\Z2433320002‐002.DOCX   12/15/16 

INSPECTION REPORT 

Landfill Annual Inspection Report 

Purpose: 

This inspection checklist has been developed to meet the requirements for inspections by a 

qualified professional engineer for a coal combustion residual (CCR) landfill.  This checklist 

exceeds the requirements for 40 Code of Federal Regulations 257.84(b).  This inspection of the 

Alma Off‐Site Disposal Facility Phase IV Landfill was performed by TRC Environmental 

Corporation on behalf of Dairyland Power Cooperative (DPC). 

The goal of the inspection is to ensure that the design, construction, operation, and maintenance 

is consistent with recognized good engineering practices.  In addition, the inspection looked for 

conditions of structural weakness or conditions that may affect the safe operation of the CCR 

unit. 

The following were performed for the inspection of the CCR unit. 

Review of Available Information:  

The following documents were reviewed in preparation of the site visit. 

Health and Safety Plan 

Fugitive Dust Control Plan (10/14/2015) 

Plan of Operation (October 2000) 

Annual Landfill Inspection Report (12/21/15) 

Post‐Closure Plan (10/2016) 

Closure Plan (10/2016) 

Run‐on and Run‐off Control System Plan (10/2016) 

Corrective Measures Report for Storm Water Runoff Event of Aug 8, 2015 

Weekly inspections performed by qualified personnel (11/23/2015 through 11/2/2016) 

Comments on the Operating Record:  Electronic system, well organized, accessible in office   

Summary of the Site Conditions (based on document review): 

DPC operates a CCR landfill (Alma Off‐Site Disposal Facility Phase IV Landfill) located in the 

NE 1/4 of the NE 1/4 of Section 19 and portions of Sections 18 and 20, T21N, R12W, Town of 

Belvidere, Buffalo County, Wisconsin (see Figure 1).  The location of the Phase IV landfill is in a 

valley along with three phases of non‐contiguous closed landfills.  This inspection addresses 

 

    SHEET   2   OF   5    

708 Heartland Trail, Suite 3000 (53717)      Madison, WI      (608) 826‐3600      FAX: (608) 826‐3941  

PROJECT/PROPOSAL NAME  PREPARED  CHECKED  PROJECT/PROPOSAL NO. 

Dairyland Power Cooperative; Phase IV 

Alma Off‐site Disposal Facility 

By:  Date:  By:  Date: 243332.0002 

J. Hotstream  11/9/2016  T. Martin  11/22/2016 

 

\\NTAPB‐MADISON\MSN‐VOL6\‐\WPMSN\PJT2\243332\0002\Z2433320002‐002.DOCX   12/15/16 

INSPECTION REPORT 

only the Phase IV landfill, because the Phase 1, II, and III landfills were closed prior to the 

promulgation of the federal CCR rule (40 Code of Federal Regulations 257.50 through 107). 

The Phase IV landfill is permitted through the state of Wisconsin.  To date the liner system 

Cells 1, 2A, 2B, 3A and 3B have been constructed with final cover installed over a portion of 

Cells 1, 2A, and 2B.  Cell 3B of the Phase IV landfill was constructed during 2015.  The landfill 

construction included a composite liner system, composite cover system, leachate collection 

system, leachate storage tank, and storm water controls (diversion berms, sedimentation basin, 

ditching, and downslope flumes).  During summer of 2016, 2.8 acres of final cover were 

installed over the remaining portion of Cell 1 and portions of Cells 2A and 2B.  

Changes to the unit since the previous report: 

Since the inspection in 2015, CCR placement has begun in Cell 3B and final cover was installed 

over a portion of Cells 1 and 2. 

Approximate volume of CCR in the unit at the time of the inspection:  Approximately    

975,300 cubic yards (based on November 2, 2016 topographic survey)   

Visual Inspection: 

A site visit and visual inspection were performed by Jonathan Hotstream (TRC Environmental 

Corporation) on November 9, 2016. 

Time arrived on site:  10:20 AM ______________________________   

Time departed from site:  12:15 PM ___________________________   

DPC Personnel Present:  Leif Tolokken, Rick Loppnow _________   

Weather Conditions:  Sunny, ~ low to mid 50s ˚F, slight wind ____   

Summary of Items Visually Inspected:  Electronic operating record, weekly inspection forms,  _   

final cover areas including diversion berms, flumes, vegetation; perimeter run‐on controls  ____   

including culverts, ditches, rock checks, riprap; working area conditions; access roads; ________   

sedimentation basin; leachate pipe cleanouts; and surface conditions at the leachate collection  _   

tank. _______________________________________________________________________________   

Site Operations during Inspection:  Trucks hauling CCR from JPM plant and placement of CCR   

in landfill.  Contractor on‐site repairing storm water controls downstream of SB‐1.  Watering  __   

ash on working face. _________________________________________________________________   

  ___________________________________________________________________________________   

 

    SHEET   3   OF   5    

708 Heartland Trail, Suite 3000 (53717)      Madison, WI      (608) 826‐3600      FAX: (608) 826‐3941  

PROJECT/PROPOSAL NAME  PREPARED  CHECKED  PROJECT/PROPOSAL NO. 

Dairyland Power Cooperative; Phase IV 

Alma Off‐site Disposal Facility 

By:  Date:  By:  Date: 243332.0002 

J. Hotstream  11/9/2016  T. Martin  11/22/2016 

 

\\NTAPB‐MADISON\MSN‐VOL6\‐\WPMSN\PJT2\243332\0002\Z2433320002‐002.DOCX   12/15/16 

INSPECTION REPORT 

Appearance of structural conditions: 

Final Cover Conditions (Cell 1 and 2A/2B areas): 

Vegetation Condition:  Very Good _____________________  

Evidence of Erosion:   Yes:      None:   X      

Evidence of slumping, sloughing, or slope distress:   Yes:      None:   X     

Evidence of seepage:   Yes:      None:   X    

Comments:  Vegetation emerging in areas of new final cover construction, continued good   ___   

growth on areas of existing final cover (state approved tall grass prairie vegetation) __________   

Perimeter Berm: 

Vegetation Condition:  Good __________________________________________________________   

Evidence of Erosion:   Yes:      None:     X   

Cracking along crest:  Access road along crest  Yes:      None:     X   

Evidence of slumping, sloughing, or slope distress:   Yes:      None:     X   

Evidence of seepage:   Yes:      None:     X   

Phase Delineation Berms:  Good, separation of CCR from exposed geomembrane ____________   

Comments:  Minor rutting and sedimentation in perimeter ditch.  Sediment to be removed   ___   

during cooler weather when area is accessible.  __________________________________________   

Storm Water Controls: 

Run‐on Controls:  Well controlled via perimeter berms and final cover slopes.  _______________   

Perimeter Drainage Ditches:  Good condition, well maintained, minor sediment   ______   

deposition ____________________________________________________________________   

 _____________________________________________________________________________   

Comments:  This sediment will be removed when areas dry/freeze sufficiently for  _____   

equipment access. _____________________________________________________________   

 _____________________________________________________________________________   

 

    SHEET   4   OF   5    

708 Heartland Trail, Suite 3000 (53717)      Madison, WI      (608) 826‐3600      FAX: (608) 826‐3941  

PROJECT/PROPOSAL NAME  PREPARED  CHECKED  PROJECT/PROPOSAL NO. 

Dairyland Power Cooperative; Phase IV 

Alma Off‐site Disposal Facility 

By:  Date:  By:  Date: 243332.0002 

J. Hotstream  11/9/2016  T. Martin  11/22/2016 

 

\\NTAPB‐MADISON\MSN‐VOL6\‐\WPMSN\PJT2\243332\0002\Z2433320002‐002.DOCX   12/15/16 

INSPECTION REPORT 

Run‐off Controls:  Final Cover 

Diversion Berms:  Well‐maintained, clear of obstructions, and no ponding observed.   __   

Downslope Flumes:  Well maintained and clear.   __________________________________   

Ditching:  Some minor accumulated sediment that will be removed once drying/freezing  

allows equipment access. _______________________________________________________   

Comments:  Storm water controls are well maintained at the site.  Areas with  _________   

accumulated sediment will be cleared as they become accessible.  Storm water  ________   

successfully managed to prevent run‐on into the active area of the landfill.____________   

Sedimentation Basin No. 1: 

Outlets Operational:  Yes, maintenance cleaning being performed during inspection. ___   

Culverts Operational:  Yes, clear and operational __________________________________   

Comments:  Some minor sediment accumulated in the basin.  This cleanup is scheduled   

during the winter. _____________________________________________________________   

Operating Conditions:  

Changes in Operation since the previous annual inspection:  Began placing CCR in Cell 3B.  ___   

Access Road Conditions:  Very good access road conditions, good aggregate cover, no rutting  _   

observed. ___________________________________________________________________________   

Landfill Operations: 

Temporary Storm Water Controls:  Well maintained controls of sufficient capacity.  Buffer  ____   

between CCR placement and delineation berms  _________________________________________   

  ___________________________________________________________________________________   

Working Face Conditions:  Well maintained, watered as needed with water truck, trucking in  _   

CCR and spreading. __________________________________________________________________   

Access roads: Well maintained, tracking pad installed to remove CCR from trucks exiting  ____   

landfill. _____________________________________________________________________________    

  ___________________________________________________________________________________   

 

    SHEET   5   OF   5    

708 Heartland Trail, Suite 3000 (53717)      Madison, WI      (608) 826‐3600      FAX: (608) 826‐3941  

PROJECT/PROPOSAL NAME  PREPARED  CHECKED  PROJECT/PROPOSAL NO. 

Dairyland Power Cooperative; Phase IV 

Alma Off‐site Disposal Facility 

By:  Date:  By:  Date: 243332.0002 

J. Hotstream  11/9/2016  T. Martin  11/22/2016 

 

\\NTAPB‐MADISON\MSN‐VOL6\‐\WPMSN\PJT2\243332\0002\Z2433320002‐002.DOCX   12/15/16 

INSPECTION REPORT 

Fugitive Dust Observed:   Yes:      No:     X    

Comments:  Watering working face with water truck  ______________________________   

 _____________________________________________________________________________   

Leachate Management:  System operational, minor ponding will be addressed with on‐site  ___   

operations.  _________________________________________________________________________   

Ash Tracked Out on Access Road?  Yes:      None:    X   

Leachate Collection System:  Pipes buried, not visible _____________________________________   

  ___________________________________________________________________________________   

Pipe Cleanouts:  Clean & accessible ______________________________________________   

Tank:  No concern _____________________________________________________________   

Loadout Area:  Accessible ______________________________________________________   

Comments:  Well maintained ___________________________________________________   

 _____________________________________________________________________________   

Conditions that may potentially impact safety:  None  ___________________________________   

  ___________________________________________________________________________________   

  ___________________________________________________________________________________   

Observed Deficiencies and Proposed Corrective Actions:   _________________________________   

Sediment to be removed from perimeter ditches as they become accessible by equipment. _____    

Sediment to be removed from Sedimentation Basin 1 as it dries out.  ________________________   

DPC has scheduled these activities to occur when the areas become accessible.  ______________   

  ___________________________________________________________________________________   

  ___________________________________________________________________________________   

Future Action: 

Update Item 9 – Site Operations on the Weekly Inspection Form to reflect current conditions. __   

Continued monitoring and maintenance of storm water controls ___________________________   

Continued implementation of dust control practices. _____________________________________   

  

\\NTAPB‐MADISON\MSN‐VOL6\‐\WPMSN\PJT2\243332\0002\Z2433320002‐001.DOCX  1 

Photographic Log 

Client Name:  Site Location: Project No.:

Dairyland Power Cooperative  Phase IV Off‐Site Disposal   243332.0002 

Photo No.  Date 

1  11/9/2016 

Description 

Perimeter access road with final 

cover on left side of frame. 

 

Photo No.  Date 

2  11/9/2016 

Description 

Final cover installed during 

2016.  Vegetation emerging.  

Diversion berms covered. 

 

  

\\NTAPB‐MADISON\MSN‐VOL6\‐\WPMSN\PJT2\243332\0002\Z2433320002‐001.DOCX  2 

Photographic Log 

Client Name:  Site Location: Project No.:

Dairyland Power Cooperative  Phase IV Off‐Site Disposal   243332.0002 

Photo No.  Date 

3  11/9/2016 

Description 

Active area of the landfill 

(Cells 2 and 3).  Exposed 

geomembrane phase delineation 

berm on right side of frame. 

 

Photo No.  Date 

4  11/9/2016 

Description 

Perimeter access road and 

perimeter ditch. 

 

  

\\NTAPB‐MADISON\MSN‐VOL6\‐\WPMSN\PJT2\243332\0002\Z2433320002‐001.DOCX  3 

Photographic Log 

Client Name:  Site Location: Project No.:

Dairyland Power Cooperative  Phase IV Off‐Site Disposal   243332.0002 

Photo No.  Date 

5  11/9/2016 

Description 

View of access road into active 

area of landfill.  Tracking pad is 

located prior to exiting landfill 

to remove CCR from vehicle 

tires.