offshore renewable energy in scottish...
TRANSCRIPT
Offshore Renewable Energy in Scottish Waters
Policy, Planning and Licensing for the Present and Future
Licensing context: Development applications for wind farms in the Moray Firth and the requirement
for CIA
Gayle HollandMarine Scotland, Marine Laboratory, Aberdeen
The Moray Firth Wind Farms
BOWL application:• up to 1000 MW (277 turbines) • received April 2012• addendum submitted May 2013
MORL – 3 wind farm applications • Telford, Stevenson and MacColl• total of up to 1500 MW (339 turbines)• received August 2012 • additional information submitted June 2013
Rochdale envelope and CIARochdale (design) envelope approach made CIA even more challenging• Numbers and dimensions of turbines• Foundation types• Installation methods
Both developments consented March 2014Consents granted: • BOWL 750 MW (140 turbines) • MORL 1,116 MW (186 turbines)
CIA – issues to be resolvedThroughout the consultation CIA was identified as the main concern:
• Marine mammals• Birds• Migratory fish• Marine fish and commercial fisheries• Navigation• Aviation • Defence• Visual impacts
Basis for Cumulative Impact Assessment for Moray Firth
offshore wind farms
Ian Davies
Marine Scotland Science
Planning authority
Licensing authority
Science support
Marine Scotland’s roles in renewable energy
EC EIA Directive. Assess effects on:
Human beingsFauna and flora
Landscape/seascapeMaterial assetsCultural heritage
EC Habitats Directive: Effects on protected sites and species
Special Protection AreasSpecial Areas of Conservation
Requirement for CIA
Moray Firth wind farms
Marine mammal cumulative impact assessments
Species and SACs considered
© University of Aberdeen© University of Aberdeen
© University of Aberdeen
Seabird species of negligible concern
Black‐legged kittiwake, Northern fulmar, Great skua and Arctic skua
SNCBs advised no adverse effect on site integrity using a qualitative assessment due to the minimal predicted effects.
Great black‐backed gull, Herring gull, Puffin, Razorbill and Guillemot)
Full quantitative assessment required
Seabird species of greater concern
• Kate Brookes –Marine mammals
• Jared Wilson ‐Seabirds
Details of issues and approaches
Cumulative Impact Assessment of effects of renewables developments on mammals in the Moray Firth
Kate Brookes
Marine mammal cumulative impact assessments
Structure
• Species and SACs considered
• Methodology 1: seal assessment framework
• Methodology 2: fine scale “days of disturbance”
• Addressing gaps in understanding
Marine mammal cumulative impact assessments
Species and SACs considered
© University of Aberdeen
© University of Aberdeen
© University of Aberdeen
Developed by Aberdeen University and Moray Firth wind farm developers
Assess effects to individuals and puts into the context of the wider population
Used by each development individually and also cumulatively
Marine mammal cumulative impact assessments
Methodology 1: seal assessment framework
Overlays noise contours on species abundance and distribution maps, in order to calculate the number of animals exposed to particular “doses” of noise
Marine mammal cumulative impact assessments
Methodology 1: seal assessment framework
Marine mammal cumulative impact assessments
Methodology 1: seal assessment framework
Consequence of noise exposure at different levels is determine by expert judgement, in the absence of empirical data
Reduced survival and breeding success included as parameters in population model with the effects applied throughout the period of construction
Harbour seal scenarios, run on simultaneous piling at MORL and BOWL for 4 years
Sensitivity of PTS and disturbance levels tested by running with different parameters
Marine mammal cumulative impact assessments
Methodology 1: seal assessment framework
Marine mammal cumulative impact assessments
Methodology 2: Fine scale “days of disturbance”
25 days piling
36 days piling
4 years piling
Increased vessel traffic
Marine mammal cumulative impact assessments
Methodology 2: Fine scale “days of disturbance”
For the whole east coast population, more than 50% of simulations had recovered to original size by the time wind farm piling ended
For subset of population within the SAC, declined by between 4 and 6 individuals compared with undisturbed model runs
Invergordon and Nigg both committed to significant reductions in impact piling
Marine mammal cumulative impact assessments
Methodology 2: Fine scale “days of disturbance”
East coast passive acoustic monitoring, carried out by Marine Scotland Science
Provides baseline of dolphin and porpoise distribution
Developers’ site specific monitoring can supplement to assess changes in distribution resulting from pile driving
Marine mammal cumulative impact assessments
Addressing gaps in understanding
Public/private funding – Scottish Government funded baseline data collection prior to consent being granted
Marine mammal cumulative impact assessments
Addressing gaps in understanding
CIA of effects of renewables developments on mammal & seabirds in the Moray Firth:
Ornithological Common Approach
Jared Wilson
Seabird speciesSpecies East
Caithness Cliffs SPA
North Caithness Cliffs SPA
Hoy SPA
Fulmar
Shag
Red‐throated diver
Great black‐backedgull
Herring gull
Kittiwake
Great skua
Arctic skua
Guillemot
Razorbill
Puffin
Different ApproachesDisplacement Collision% of birds displaced avoidance ratebirds on water or all potentially vulnerable breeding season% of birds adult nocturnal activity% of adults breeding flap/ gliding flight% of adults from Colony X, Y and Z Flight speedmean, peak or mean peak abundance estimate attraction to survey vessels% of displaced birds that fail to breed successfully rotor speed – annual mean, seasonal meanApportioning ThresholdsSNH guidance note Population Viability Analysis (PVA)At‐sea flight direction information Potential Biological Removal (PBR)GPS tracking data Starting population usedStarting populations used What is acceptable effectSPA vs non‐SPA colonies included Maintain +ve trajectory
f‐value for use in PBRPBR in relation to productivity effects
Does it matter?
• Difficult to identify differences in approaches taken.• Lack of transparency if different approaches used without clear
rationale• Unclear whether different approaches can be combined for CIA• May artificially bias conclusions for/ against one project• May result in CIA conclusions being opaque or open to challenge
Common Currency• Discussions between developers, SNCBs and MSS
• Aim to reconcile any differences where possible
• Clarification of reasons for any remaining differences
• Re‐running collision or displacement effect assessments using Common Currency as required
Collision ExampleHERGU ECC HERGU ECC
CRM MORLRunning
Total BOWLRunning
TotalBird ParametersBird Length 0.61 0.61Wing span 1.44 1.44Flight speed 12.8 12.8Noct Activity 2 2Flap/Glide Flapping FlappingOption 1, 2, 3 3 3Avoidance Rate 98% 98%Windfarm scenario WCS MLSAnnual Collisions 136.1 182.09Breeding Season Collisions 20.4 12.72Non breeding season Collisions 115.7 169.37
Collision ApportioningCRM collisions 20.4 20.40 12.72 12.72Prop from SPA 0.375 3.83 0.851 5.41Prop immature birds 0.43 1.64 0.625 3.38Prop adults 0.57 2.18 0.375 1.32exclude sabatical adults 0.35 1.42 0.35 0.46Total SPA birds 3.83 5.41
Thresholds of Change
ABC Tool
Likelihood Term Likelihood of the occurrence Probability (P)
Virtually certain > 99.1% >0.991
Extremely likely 95.1-99.0% 0.951-0.990
Very likely 90.1-95.0% 0.901-0.950
Likely 66.1-90.0% 0.661-0.900
About as likely as not 33.0-66.0% 0.330-0.660
Unlikely 10.1-32.9% 0.101-0.329
Very unlikely 5.1-10.0% 0.051-0.100
Extremely unlikely 1.1-5.0% 0.011-0.050
Exceptionally unlikely < 1% <0.01
What Next?
• Lessons learned to feed into advice and guidance.
• More strategic approach e.g. PVAs for key colonies/ populations, estimating effects at a regional scale?
Licensing context: Development applications for wind farms in the Moray Firth and the requirement
for CIA
Roger MayMarine Scotland, Marine Laboratory, Aberdeen
Migratory fish• ISSUES – HRA. Concerns principally around Construction Noise and EMF Fields.
Whilst the ES did not raise serious issues the stakeholders involved were concerned about the high level of unknowns.
• ACTIONS – Developer interaction with stakeholders did not provide a way forward and ASFB objected. Marine Scotland Science therefore took forward the need for a strategy to provide reassurance to stakeholders and a means to identify and mitigate against impacts.
• SOLUTIONS‐ Group‐ Following publication of a Marine Scotland scoping report, Marine Scotland initiated a process to develop a national strategy to coordinate and align research and monitoring in this area. The overall aim is to develop a national strategy to investigate the potential for interactions between diadromousfish and wind, wave and tidal renewable energy developments. This process was commenced in May 2013 with facilitated stakeholder engagement. The areas of research and monitoring prioritised through this engagement process are being incorporated in to proposed National Strategy work packages. The work packages identified in the proposed national strategy will be assessed and scoped to identify project feasibility and costing's by MSS. The National Strategy is currently being finalised for publication shortly.
• CONSENT CONDITIONS – Annex D/annex 2/30, Piling strategy Annex D/annex 2/11
Marine fish• ISSUES ‐ EIA assessment found impacts from the two projects on fish and shellfish
species to be primarily around construction. Herring (Spawning), Cod, Scallops, Sandeels.
• ACTIONS – Developer engaged with stakeholders principally Marine Scotland Science. Additional surveys were carried out prior to ES submission.
• SOLUTIONS – Individual ‐Monitoring post consent to include further monitoring (dependent on Rochdale Envelope if gravity bases used do not require herring Spawning to be monitored). Potential Limits on activities around spawning times. To be captured as part of Project Environmental Monitoring Programme Plan (PEMP). Covers Birds, Cod, Herring, Sandeels, Diadramous Fish, Benthic Communities and Seabed Scour.
• Group‐ To be established Moray Firth Regional Advisory Group (MFRAG) to advise on outputs of monitoring. (27)
• Group – Scottish Strategic Marine Environment Group (SSMEG) (28)• CONSENT CONDITIONS ‐ Annex D/annex 2 /26, 33, 34
Commercial fisheries• ISSUES – EIA – Commercial fishing takes place both on the area of the
developments and along the cable routes to shore. Whitefish, Squid, Scallops and Shellfish
• ACTIONS – Developers met with local fishermen and established the working group
• SOLUTIONS Group – Moray Offshore Wind Developers Group‐ Commercial Fisheries Working Group. Marine Scotland will model socio economic impacts on fishermen of reduced fishing opportunities both short and longer term. Marine Scotland will commission a report to look into the real impacts of the construction and operation of offshore windfarms.
• CONSENT CONDITIONS‐ Annex D/ annex 2/ 31, Fisheries Liaison Annex D/ annex 2/ 32
Navigation
• ISSUES – EIA – Chamber of Shipping stated that the projects were in an area of relatively low shipping but raised concerns over cumulative impacts of the two projects. NLB unable to finalise requirements (Rochdale envelope) for lighting but will feed into the Development Specification and Layout Plan.
• ACTIONS – Did not require additional actions post ES• SOLUTIONS – Individual developer to provide DSLP for consultation, Navigational
Safety Plan, Lighting and Marking Plan (LMP)• CONSENT CONDITIONS Annex D/ annex 2/ 12, NSP Annex D/ annex 2/ 17, LMP
Annex D/ annex 2/ 19
Aviation
• ISSUES – EIA – Principal issue was impact on Radar but also concerns on Helicopter routes National Air Traffic Services (NATS) objected 28/08/2012 removed 2/12/13 (16 months from submission). Major Risk to timelines. No major problems from CAA for individual airports
• ACTIONS‐ Developer worked with NATS to agree and formalise a mitigation system this required not just an agreement in principal but a formal legal agreement.
• SOLUTIONS –Individual – Agreement between NATS and Developer• CONSENT CONDITIONS –Annex D/ annex 2/ 21, 22
Defence MOD/DIO
• ISSUES – EIA – Defence Infrastructure Organisation (DIO) Principal issue was impact on Radar objected 1/11/2012 removed final 3/6/2013 (10 months from submission). Major Risk to timelines.
• ACTIONS‐ Developer worked with DIO to agree and formalise a mitigation system this required not just an agreement in principal but a formal legal agreement.
• SOLUTIONS –Individual – Agreement between DIO and Developer. Whilst combined solutions might be feasible consented projects may not be built out on time or at all.
• CONSENT CONDITIONS –Annex D/ annex 2/ 20
Visual impacts
• ISSUES – EIA – The cumulative visual impact of the two projects was assessed in the context of their individual Rochdale Envelopes.
• ACTIONS – In early phases of the EIA this required a lot of cooperation between principal stakeholders (SNH/JNCC/Local Authorities) to agree methodologies and viewpoints. Did not require additional actions post ES.
• SOLUTIONS – Individual ‐ Development Specification and Layout Plan – to give final details of what is being built (remove Rochdale envelope). Design Statement (DS) to show final visual layout. Ensure removal at end of use decommissioning plan to DECC. Ensure that inactive turbines are repaired or removed. NB while the cumulative visual impact was looked at there is no attempt to co‐ordinate the combined visual impact of the two projects.
• CONSENT CONDITIONS DSLP Annex D/ annex 2/ 12, DS Annex D/ annex 2/ 13, Decommissioning Annex D/ annex 2/ 3, removal of devices that do not operate Annex D/ annex 2/ 5
Good Practice for CIA
• Greater emphasis on the pre‐application process
• Regional developer groups
• Work collaboratively to address key issues
• Early engagement and continued communication with stakeholders
• Sharing/standardising approaches and information gathering – across agencies and industry
• Using lessons learned from the Moray Firth to inform future applications
Contact
• Marine Scotland – Licensing Operations Team• Marine Laboratory PO Box 101• 375 Victoria Road Aberdeen AB11 (DB• Direct Line +44 (0)1224 285579• Fax +44 (0) 1224295524• [email protected]• Web:
http://www.scotland.gov.uk/Topics/marine/Licensing/marine/Applications
Scenario Mapping for Offshore Renewable Energy in Scottish Waters
David PrattProject Lead – Sectoral Marine Planning & Scenario Mapping for Offshore Renewable Energy
Blues Seas Green Energy (BSGE)Plan for Offshore Wind Energy ‐ 2011
Projects at LicensingStage‐ Islay‐ Inch Cape‐ Neart na Gaoithe ‐ Forth Array‐ Beatrice
25 Medium-Term Areas of Search – starting point for current Sectoral Plan development process
In addition to BSGE:- 2 Round 3 Zones
- Seagreen- MORL
Draft Sectoral Marine Plans – Wind, Wave & Tidal Options - 2013
• Ports– National Renewables Infrastructure Plan– National Renewables Infrastructure Fund
• Strategic Grid– Route to Market ‐Marine Grid – Cable landing corridors?
• Raw materials– Aggregate extraction – marine / terrestrial?
• Human Resources– Colleges / Re‐training?
• Community Engagement– Implications? Benefits?
Offshore Renewables – Onshore Planning
‘ Tiree Scenario Mapping’
Argyll Array – Tiree Scenario MappingOnshore implications due to proposed offshore development
Scenario 1 – O&M Base Scenario 2 – Offshore Platform
Scenario 3 – Offshore Mothership Scenario 4 – O&M Base / Mothership
Scenario 1‐4Projected needs
4321
Jobs on Tiree
Houses on Tireenew build
School Pupilsprimary & secondary
Built Development
Helicopter Flightsper day return flights
Population Growth
‘ Potential Roll‐out Scenario Mapping / Masterplanning’
October 2012 1
2
3
4
5
6
1. Forth & Tay
2. Moray Firth
3. Pentland Firth & Orkney Waters
4. Solway Firth?
5. Western Isles
6. Shetland?
7. Argyll?
• Pan Scotland and Regional Issue ‐ Realising economic development potential – Consultants appointed Sept 2013 – CH2M Hill
• Scottish Public Sector Initiative– Marine Scotland, The Scottish Government, The Crown
Estate, East Coast Renewables, Scottish Enterprise, and Highlands & Islands Enterprise
• Need to: – Respect confidentiality – Enterprise Agency initiatives – Respect Local Government competitiveness to attract
manufacturing
• Timetable for completion – Summer 2014
Project – East and North East Regions
Project Scenarios
• Mapping of Developer Scenarios• 4 Offshore Wind Developers
– EDPR, Repsol, Mainstream, SSE• Competition vs Co‐operation, time to work together• Developers will benefit from local supply chain evidence Base
• Project EIAs –• Scope of Rochdale Envelopes• Socio‐economic Impact Chapters• Access development phasing• Project pipeline and orders profiling
• Supply Chain, Resource Mapping & Assessment
East and North East Regions• Manufacturing and Assembly Port Strategies
• Developers, Manufacturers, Ports and Local Government • SE, HIE and SDI
– GEG identified exemplar, but others well placed
• However, there are significant market challenges….• EMR ‐ Developers require CfD to achieve FID
– Grid Connection– Environmental Consent– Economic Case
• Reduce CAPEX and OPEX, bigger turbines, less structures• Access to greater wind resource• Improve ‘affordability’ ‐ increased Rates of Return
– Supply Chain Plan
• Benefit realisation – master‐planning?
Questions?
• Further Information ‐
• Offshore Renewable Energy Planning Webpage• http://www.scotland.gov.uk/Topics/marine/marineenergy/Planning
• Offshore Renewable Energy Planning Mailbox• [email protected]