of building stone quarryenvironmentclearance.nic.in/writereaddata/district/...rules-1994. the quarry...
TRANSCRIPT
OF
BUILDING STONE QUARRY
TO Sri. B. M Shadakshari,
S/o. B. C. Mahalingappa, Rice Flour Mill,
Beeranahalli Post, Hiriyur Taluk, Chitradurga District,
Karnataka. Over an extent of 2-00 Acres (Government Kharab Land)
In part of Sy No. 03,
Mallanakatte village, Chitradurga Taluk
Chitradurga District, Karnataka.
Submitted Under Rule 8 I, 8C, 8D, 8F and 8 H (1) of KMMC.Rules-1994
Prepared
By Ganapati S. Hegde
RQP/GOA/144/2002/A # 517, SAGAR REGAL, VI Main, Maruti Layout, Vasanthapura,
Bangalore-61 December - 2017
Contents CERTIFICATE BY APPLICANT .......................................................................................................iii
INTRODUCTION: ............................................................................................................................... 4
1. GENERAL ..................................................................................................................................... 4
a) Details of the Area: ................................................................................................................ 5
b) Topo sheet No. with Latitude and longitude: ......................................................................... 5
c) Land use pattern (Forest, Agricultural, Grazing, Barren etc): ............................................... 6
d) General location and vicinity map showing the area boundaries: ...................................... 6
PART-A ................................................................................................................................................. 7
2. GEOLOGY & EXPLORATION .................................................................................................. 7
3. QUARRYING ............................................................................................................................. 10
4. BLASTING .................................................................................................................................. 14
5. MINE DRAINAGE .................................................................................................................... 16
6. STACKING OF MINERAL REJCETS AND DISPOSAL OF WASTE: ................................ 17
7. USE OF MINERAL: ................................................................................................................... 17
8. OTHERS: ..................................................................................................................................... 17
9. MINERAL PROCESSING: ........................................................................................................ 18
PART-B ................................................................................................................................................ 19
10. ENVIRONMENTAL MANAGEMENT PLAN : ................................................................. 19
i) Base line information: ............................................................................................................. 19
ii) Water Regime: .................................................................................................................. 19
iii) Flora and Fauna: .............................................................................................................. 19
iv) Quality of air, ambient noise level and water: ..................................................................... 20
a) Air Quality: ....................................................................................................................... 20
b) Ambient noise level: ........................................................................................................ 20
c) Water quality: ................................................................................................................... 20
v) Climatic Conditions: ........................................................................................................ 20
vi) Human Settlement: .............................................................................................................. 20
vii) Public buildings, places and monuments: ................................................................... 21
b) Environment Impact assessment statement: ................................................................... 21
1) Landscape: ........................................................................................................................ 21
2) Soil and Land use pattern: .............................................................................................. 21
3) Agriculture: ....................................................................................................................... 21
4) Forest: ................................................................................................................................ 21
5) Vegetation: ........................................................................................................................ 21
ii) Air quality: ........................................................................................................................ 22
iii) Water Quality: .................................................................................................................. 22
iv) Noise Levels .......................................................................................................................... 22
v) Vibration levels (due to blasting) ........................................................................................ 22
vi) Water Regime:....................................................................................................................... 23
vii) Socio/ Economic: ................................................................................................................ 23
1) Socio and demographic profile: ..................................................................................... 23
2) Occupational health and safety: .................................................................................... 23
viii) Public buildings, places and monuments: ................................................................ 23
c) Environmental Management plan: ....................................................................................... 24
i) Storage and preservation of the top soil: ......................................................................... 24
ii) Proposals for reclamation of land affected by abandoned quarries and other mining activities during first five years. ................................................................................. 24
iii) Programme of year-wise afforestation for the initial five years: .............................. 24
iv) Stabilisation and vegetation of dumps along with waste dump management year-wise for the first five years: ....................................................................................................... 24
v) Measures to control erosion/ sedimentation of water course: ................................. 24
vi) Treatment and disposal of water from mine: ................................................................... 24
ii) Measures for minimizing adverse effects on water regime: ..................................... 24
viii) Protective measures for ground vibrations/ air blast caused by blasting. ......... 24
ix) Measures for protecting historical monuments and for rehabilitation of human settlement, likely to be disturbed due to quarrying activity: .............................................. 25
x) Socio-Economic benefits arising out of mining: .......................................................... 25
Monitoring schedules for different environmental components after the commencement of mining and other related activities: .................................................................................... 25
PART-C ................................................................................................................................................ 26
PROGRESSIVE MINE CLOSURE PLAN (PMCP) ........................................................................ 26
1. Introduction .................................................................................................................................... 26
1.1) Reasons for Closure: ........................................................................................................... 26
1.2) Statutory obligations: ......................................................................................................... 27
1.3) Closure plan preparation: .................................................................................................. 27
2. Mine Description: ....................................................................................................................... 28
2.1 Geology: ................................................................................................................................ 28
2.2 Reserves: ............................................................................................................................... 28
2.3 Mining Method: ........................................................................................................................ 29
3. Review of implementation of Mining Plan / Scheme of Mining including five years Progressive Closure Plan up to the final closure of mine : .......................................................... 29
4. Closure Plan: ............................................................................................................................... 30
4.1 Mined-Out land: ..................................................................................................................... 30
4.2 Water Quality Management: ............................................................................................. 30
4.3 Air Quality Management: .................................................................................................. 30
4.4 Waste management: ............................................................................................................ 31
4.5 Topsoil Management: ......................................................................................................... 31
4.6 Tailing Dam Management: ................................................................................................ 31
4.7. Infrastructures: ..................................................................................................................... 31
4.8 Disposal of Mining Machinery: ......................................................................................... 32
4.9 Safety &Security: ................................................................................................................. 32
4.10 Disaster Management and Risk Assessment: .............................................................. 32
4.11 Care and maintenance during temporary discontinuance: ....................................... 32
5. Economic repercussions of closure of mine and manpower retrenchments:................. 33
5.1 Number of local residents employed in the mine, status of the continuation family occupation and scope of joining the occupation back: ............................................................ 33
5.2 Compensation given or to be given to the employees connecting with sustenance of himself and their family members:.............................................................................................. 33
5.3 Satellite occupations connected to the Quarrying industry number of persons engaged therein continuance of such business after mine closes: .......................................... 33
5.4 Continued engagement of employees in the rehabilitated status of mining License area and any other remnant activities: ........................................................................................ 33
5.5 Envisaged repercussions on the expectation of the society around due to closure of Quarry: ............................................................................................................................................. 33
6. Time scheduling for abandonment : ....................................................................................... 34
Photographs of site ............................................................................................................................ 38
ANNEXURES ..................................................................................................................................... 39
CERTIFICATE
The provisions of Karnataka minor Mineral Concession (Amendment) rules 2014 have been observed in the preparation of Quarrying plan for Notification No: GABHUE:UNICHI.BE:KAGU:2017-18:1899 dated 14-12-2017, for Building Stone over an Extent of 2-00 acres situated in in part of Sy No. 03, Mallanakatte village, chitradurga Taluk, Chitradurga District, Karnataka of Sri B. M. Shadakshari. Whenever specific permissions are required the applicant will approach the concerned authorities of the Department of Mines & Geology.
The provisions of Mines Act, rules & Regulations made there under have been observed in preparation of this Quarrying plan. Whenever specific permission is required, the applicant will approach DGMS for approval. It is also certified that information furnished in the “Quarrying plan" is true and correct to the best of my knowledge
Date: 26/12/2017 Ganapati S. Hegde Place: Bangalore RQP/GOA/144/2002/A
CERTIFICATE BY APPLICANT
This is to certify that the Quarrying Plan for grant of quarrying lease in respect of Building Stone notification no. GABHUE:UNICHI:KAGA:2017-18/1899 dated 14-12-2017, ver an extent of 2-00 Acres situated in part of Sy No. 03, Mallanakatte village, Chitradurga Taluk, Chitradurga District, Karnataka has been prepared by Ganapati S. Hegde RQP/GOA/144/2002/A, qualified person of Indian Bureau of mines for preparation of Quarrying Plan and I agree to follow the same in accordance to the provisions of law. Place: Chitradurga Date: 26/12/2017 (Sri B. M. Shadakshari) (Authorized Signatory)
Building Stone Quarry
Page 4
QUARRYING PLAN OF SRI B M SHADAKSHARI FOR EXTRACTION OF
BUILDING STONE IN THE VILLAGE LIMITS OF MALLANAKATTE, CHITRADURGA TALUK OF CHITRADURGA DISTRICT, KARNATAKA.
INTRODUCTION:
Sri B M Shadakshari, has applied for quarry license for extraction of Building Stone
in part of Sy No. 03, Mallanakatte village, Chitradurga Taluk, Chitradurga District,
Karnataka over an extent of 2-00 Acres for production capacity Of 25,000 Tonnes/Annum.
Department of Mines and Geology, Chitradurga has notified the area in the name of
Sri B M Shadakshari to an extent of 2-00 Acres in Sy No. 03, Mallanakatte village,
Chitradurga Taluk, Chitradurga District, Karnataka. The Notified sketch is attached as
annexure 2.
Quarrying Plan is being prepared under rule 8I, 8C, 8D, 8F and 8H (1) of KMMC
Rules-1994. The quarry plan is prepared with the main emphasis on systematic and
scientific method of working with an aim to ensure sustainable orderly development of the
quarry and conservation of Building Stone deposits and protection of environment.
1. GENERAL
a) Name of the Applicant:
Sri. B. M Shadakshari,
S/o. B. C. Mahalingappa,
Rice Flour Mill,
Beeranahalli Post, Hiriyur Taluk,
Chitradurga District.
(Address Proof enclosed as Annexure)
b) Status of Applicant: The applicant is an individual
c) Minerals which are occurring in the area and which the applicant intends to mine:
Mineral occurring in the area is Granite as building stone. The applicant intends to
mine granite as building stone.
d) Period for which this mining license is granted / renewal proposed to be applied:
The Quarrying license is to be granted for 20 years for Quarrying Building Stone.
Building Stone Quarry
Page 5
e) Name of RQP preparing mining plan:
Name: Ganapati S. Hegde
RQP/GOA/144/2002/A Address # 517, SAGAR REGAL, VI Main, Maruti Layout, Vasanthapura, Bangalore-61 Mob: 9164516629
(RQP Certificate enclosed. Valid up to: 09-05-2022 as Annexure 8)
f) Name and address of the Prospecting Agency:
The applicant himself is the prospecting agent.
g) Reference No. and date of consent letter from the state Govt:
DMG letter GABHUE:UNICHI:KAGA:2017-18/1899 dated 14-12-2017
LOCATION & ACCESSIBILITY
a) Details of the Area:
The applied area is demarcated on the Topo-sheet No 57 B / 8 of the Survey of India and
enclosed vide Plate. No.1 as key plan.
State District Taluk Village Sy.No.
Area in Acres
Ownership
Karnataka Chitradurga
Chitradurga Mallanakatte 03 2-00 Government Kharab land
Existence of public road / railway line, if any nearby and approximate distance:-
The nearest human habitation is Mallanakatte village, which is at a distance of 1.00 km from
the proposed quarry site. The nearest railway station is at Chitradurga Railway station
which is at a distance of 3.30 kms (S) from the applied area.
b) Topo sheet No. with Latitude and longitude:
Topo sheet No 57 B / 8
Building Stone Quarry
Page 6
WGS 84 DATUM
Sl. No. Latitude Longitude 1 N 14° 15’ 28.7” E 76° 22’ 25.4” 2 N 14° 15’ 24.1” E 76° 22’ 25.3” 3 N 14° 15’ 24.1” E 76° 22’ 23.5” 4 N 14° 15’ 28.7” E 76° 22’ 23.3”
c) Land use pattern (Forest, Agricultural, Grazing, Barren etc):
The applied area is a Government Kharab land.
LANDUSE DETAILS: The present land use details is as follows.
Particulars Existing land
(acres)
Total land use during
plan period (Acres)
Area for Mining -- 1-06
Roads 0-02 0-02
Overburden dump -- 0-02
Infrastructure -- 0-02
Mineral Storage --
Topsoil Yard --
Safety Zone -- 0-28
Vacant Land 1-38 -
Total 2-00 2-00
d) General location and vicinity map showing the area boundaries:
Key Plan of the area is enclosed, showing the existing roads, village, Nalla,
agricultural land, etc. as Plate. No. 1.
Building Stone Quarry
Page 7
PART-A 2. GEOLOGY & EXPLORATION
a) Briefly describe the topography and General Geology and local mine Geology of the
mineral deposit including drainage pattern:
i) Topography:
From the Topo sheet No. 57 B / 8 following topographic features can be observed.
The applied area is located in Government Kharab land.
The terrain is slightly undulated due North.
No roads pass through the applied area.
No human settlements within or in the vicinity of the applied area. The nearest
village is at 1.00 kms distance.
A Seasonal Nalla has been found in the North direction flowing to South- West which
joins the nearby Tank.
The highest elevation at North portion of the site and lowest elevation at South corner
in the area are 769 mts and 781 mts respectively, having an elevation difference of
12.0 mts.
For survey purposes, a temporary bench mark (TBM) with 771.2 mts RL is considered
at South-East corner of the area and the same is shown in the Plate. No.3 & 4 (Surface
& Geological plan).
ii) Regional Geology:
Regionally the area is of Grey and other varieties of Granites and granitic gneiss
found in Chitradurga Taluk, of homogenous, soft Grey Granites with uniform color
and structure formed of gneiss and Granites exposed in the form of hillocks, boulders
outcrops followed by sheet rocks. Some Dykes are generally running North-South
direction and are cutting across the country rock and runs for several kilometers as
Building Stone Quarry
Page 8
discontinuous outcrop along the strike direction. The granitic gneisses huge
formations spread all over the Taluk.
iii) Local / Mine Geology:
Chitradurga Taluk, formation consists of series of slightly hilly ridges of granite and
gneissic Granites, some dykes are also intruded. The general formation is striking N-S
direction and showing foliation and banded in nature. The availability of Grey Granitic
in the area is Light bluish in color running N-S direction with uniform color, medium
to coarse grain. The exposures are seen as boulders with bedded formations and
followed by sheet rock. Grey Granitic sheet rock outcrops are exposed in the surface in
the trial pit.
The geological setting of the area is composed of gneisses and granitic gneiss of heavy
terrain of both these formations is intruded by Dykes. The different lithogical units in
this area are as follows:
Soil Cover
Dolerite Dyke
Quartz / Pegmatites
Granites
Amphibolites
Granites quartz magnetic
Granitic gneisses.
Older Metamorphic rocks.
The Grey granitic gneissic rocks are found granitic gneissic complex spread all over the
Taluk. Some Dykes are also found cutting across peninsular gneissic complex. The
Grey Granitic deposits are found in the form of boulders on the surface, followed by
Grey Granite sheet rocks. Even the sheet rocks also have discontinuous layers which
enable for easy quarrying.
(i) The Topographic plan of the applied area is prepared in 1:1000 RF with 1 mts contour
interval. For survey purpose, a temporary bench mark (TBM) with an elevation of 771.2 mts
Building Stone Quarry
Page 9
RL is considered in the area and the same is used as base for the preparation of surface and
geological plan and shown in Plate. No.3 & 4.
(ii) Details of exploration already carried out:
As already discussed the thickness of granite varies from 30 mts to 100 mts, no need to do
any further exploration. Road cuttings and cuttings in the Bore wells show the presence of
granite extensively in the surrounding areas.
c) Geological cross sections are drawn on a scale of 1:1000 RF. All the exposures are marked
on the section and enclosed as Plate. No.5.
d) Future programme of exploration:
Since the thickness of granite varies from 30 mts to 100 mts, covers very vast area, no need
to do any further exploration.
e) Method of Estimation of Reserves:
The reserves estimation has been made based on potential zone marked on the
geological plan and cross sections. The norms of Reserve estimation are of counting
squares of sectional areas marked on the cross sections. About 14,21,134 Ts of
‘Geological Reserves’ are estimated. In order to meet the various statutory
requirement some part of the License area cannot be excavated i.e 7.5 mtrs safety
zone area along the Mining license boundary & after deducting the quantity of Non
Mineable area, Mineable reserves estimated are 8,97,447 Ts. The details of reserve
estimation are as follows:
Building Stone Quarry
Page 10
Category Wise Reserves Calculation of
Building Stone Quarry - 2-00 Acres of
Sri BM Shadakshari
Section Sectional
area (Sq.m.)
Sectional Influence
(m)
Volume (Cu.m.)
ROM @2.66t/cmt
Saleable Building
stone (95%)
Intercalated Waste (5%)
Proved reserves
LL' 7,948 57
4,53,036 12,05,076
11,44,822
60,254
Probable reserves
LL' 1,425 57
81,225 2,16,059
2,05,256
10,803
TOTAL 9,373 57 5,34,261 14,21,134 13,50,078 71,057
Mineable Reserves Calculation of
Building Stone Quarry - 2-00 Acres of
Sri BM Shadakshari
Section Sectional
area (Sq.m.)
Sectional Influence
(m)
Volume (Cu.m.)
ROM @2.66t/cmt
Saleable Building
stone (95%)
Intercalated Waste (5%)
Proved reserves
LL' 6,866 42
2,88,372 7,67,070
7,28,716
38,353
Probable reserves
LL' 1,167 42
49,014 1,30,377
1,23,858
6,519
TOTAL 8,033 42 3,37,386 8,97,447 8,52,574 44,872
3. QUARRYING
a) An open cast semi Mechanized method will be adopted to operate the area. Since, the
annual production is about 26,136 TPA, the Open cast method will be followed during the
plan period.
A Quarrying plan for production and development is shown in Plate.No.6.
For production, it is proposed to work from South East to North West (ref. Drg. No.6). It is
proposed to work LL’ section during the Plan period.
Building Stone Quarry
Page 11
b) The Tonnages of saleable Granite and intercalated waste during the plan period
is as given below
Production and Development Calculation of
Building Stone Quarry - 2-00 Acres of
Sri BM Shadakshari
Section Sectional
area (Sq.m.)
Sectional Influence
(m)
Volume (Cu.m.)
ROM @2.66t/cmt
Saleable Building
stone (95%)
Intercalated Waste (5%)
I year
LL' 236 42 9,893 26,316 25,000 1,325
Sub-Total 236 42 9,893 26,316 25,000 1,325
II year
LL' 254 39 9,893 26,316 25,000 1,325
Sub-Total 254 39 9,893 26,316 25,000 1,325
III year
LL' 275 36 9,893 26,316 25,000 1,325
Sub-Total 275 36 9,893 26,316 25,000 1,325
IV year
LL' 300 33 9,893 26,316 25,000 1,325
Sub-Total 300 33 9,893 26,316 25,000 1,325
V year
LL' 330 30 9,893 26,316 25,000 1,325
Sub-Total 330 30 9,893 26,316 25,000 1,325
TOTAL 1,394 30 49,466 1,31,579 1,25,000 6,625
c)Composite plan showing pit layout at the end of every year for 5 years and sectional
views showing production schemes for 5 years are enclosed vide Plate No. 6.
d)About 6,625 tonnes of intercalated waste is required to be handled during the plan period,
which will be utilized for strengthening the approach road.
e)Proposed rate of production when the mine is fully developed and the life of the mine:
From the above it may be seen that during plan period, it is proposed to maintain a suitable
Building Stone production of about 26,136 tonnes per year.
Building Stone Quarry
Page 12
At the given rate of proposed production of 26,136 TPA, the life of the mine is more than 20
years.
i) Extent of mechanization:
The Method of mining shall continue to be semi Mechanized method. There will be no
changes in the proposed method of mining and deployment of machinery.
The following machines are proposed to be hired and used in the mines.
List of Machineries are as under.
Type Nos. Capacity Make Motive Power
Excavator 1 0.5cum JCB Diesel Engine
Tippers 1 10 tonnes Tata Diesel Engine
Compressors 1 33 VT4 Atlas Diesel Engine Compressed Air
Water tanker 1 3000 liters Tata Diesel Engine
Jeep 1 4x4 Mahindra Diesel Engine
1) Drilling
Type Nos. Size of hole mm
Size of Capacity
Make Motive Power
1) Tractor Mounted compressor
2) Jack Hammers
1
1
-
33
140cum
-
VT4 Atlas
-
Diesel (Fuel)
Compressed Air
2)Loading Equipment & 3) Haulage and Transport Equipment
Building Stone and intercalated waste are loaded by excavator into the tipper. Both
excavators and tippers may be purchased or hired to handle the tonnage.
Building Stone Quarry
Page 13
Equipment:
0.5 Cum excavator ………………………………………… 1 No
10 tonnes tipper …………………………………………..…1 No
Justification for requirement of haulage equipment with calculations:
Total max., tonnage handling per year 26,136
Number of working days 300
Number of shifts /day 1
Daily average handling in tonnes 87
Capacity of shovel 0.5 Cum
Effective handling hours/day 6.5
Bucket fill factor 0.80
Swell factor 0.80
System utility factor 0.50
Cycle time of shovel 45sec
Hence handling in 6.5 hrs shift 0.8x0.8x0.5x0.5=0.16 x2.66 (B.D.) =0.4256
in 45 seconds. i.e. = 0.4256 x 60/45
=0.57x390minutes=222 tons
For 1 shovel 222 tonnes
Building Stone Quarry
Page 14
Number of dumpers required
Average hauling distance 1.0km
Back 1.0km
Total 2 kms
Average speed of dumper 10km/hour
For travelling 2kms 12 min
Loading time and unloading time 9 min
Total time required/trip 12+9=21 min
Hence each dumper will make 2.8 trips say 3
trips/hour
In 6.5 hours 3x6.5=19.5x10tonnes=195
To Handle 87 tonnes/day 1 Number
3) Haulage and Transport equipment
a. Haulage within the Quarrying License hold:
Type Nos. Size of Capacity Make Motive Power
Tippers 1 10 Tonnes Tata Diesel Engine
b. Transport from mine head to the destination:
The transport from mine head to the consumer is trough hired tippers / trucks /
tractor trailer by road.
4. Miscellaneous: - Nil –
4. BLASTING
a) & b) Broad blasting parameters & type of explosives to be used:
Building Stone Quarry
Page 15
Considering the facts that the Building Stone requires blasting for its extraction and
that class II explosives are to be used, the powder factor can be estimated to be 6
tonnes per Kg. of explosives.
The explosive required per annum at a powder factor of 6 tonnes/ kg will be
26,136/6t/kg = 4,356 Kgs (say). It is proposed to use slurry explosive. The charge per
hole is 500gms; charging will be by safety fuse with the combination of Ordinary
detonators and slurry explosive; handling – tie up with the explosive suppliers (sale,
possesses and use of explosives); system of initiation – ordinary detonators.
Depending upon the requirement of the size of lumps, to dislodge the same, drilling
will be done in a single row by jack hammer. Drilled holes will be filled by the
Cracking agent, where next day the lumps gets dislodge by the main rock mass.
In addition, we require about 12,289 mts of safety fuse and 8,193 number of ordinary
detonators for initiation purpose. As only few holes (max 10 / round) will be blasted
at one time, no significant air blast or vibrations will be envisaged. However, since
the area is surrounded by an agricultural land, if required, sand bags/ mud bags will
be kept on holes and will be muffled in order to prevent the flying rocks.
c) Powder factor: The detailed calculations showing the powder factor in this area is as
follows.
Spacing 1.00m
Burden 1.00m
Depth of the hole 1.50m
Bulk density 2.66t/Cum
Blasting efficiency 80%
Therefore, the powder factor 1.00mx1.00mx1.5mx0.8x2.66 t/cum=3.19 tonnes for 0.5kg explosive
For 1 kg Explosive 6.38 say 6 t/kg
Therefore each hole give us 1.00mx1.00mx1.5mx0.80x2.66 t/cum=3.19 tonnes ROM
The ROM to be handled 26,136 TPA
No of holes required 26,136/3.19 = 8,193 Nos
Building Stone Quarry
Page 16
Total drilling required 8,193 x 1.5m= 12,289 mts
One Jack Hammer can give 40,000 m/Annum
No of Jack Hammer required 1Nos
d) Whether secondary blasting is needed, if so, describe in brief:
In case of boulders bigger than half a cubic meter, are broken after an initial blasting.
25 mm x 200mm cartridges of 140 gms shall be used for such secondary blasting.
e) Storage of Explosive:
Explosive will not be stored in the mine since the entire Handling and blasting
operations will be carried out by a licensed contractor who sell, possess and use of
explosives having a magazine with license. Blasting operations will be carried out
where ever it is permitted in the quarry License. Otherwise the extraction is by
heating and cracking process.
However, if it becomes necessary, applicant will take necessary permission from the
Competent Authority for using and storage of explosives. Explosive magazine of
25kg will be installed with the permission to use 10 kg ammonium nitrate/day.
5. MINE DRAINAGE
a) On the observation from nearby bore wells, likely depth of water table is 90 mts from
surface. But the License area is in a hilly terrain and the mining will not reach the
ground level.
b) Working expected to reach 764 mts RL level during plan period
c) Quantity and quality of water likely to be encountered, their pumping arrangement
and places where this mine water is finally proposed to be discharged.
As such there is no possibility for encountering any underground water source
during the plan period. Any rain water, accumulated in the pit during monsoon, will
be naturally drained within 2 or 3 days.
Building Stone Quarry
Page 17
6. STACKING OF MINERAL REJCETS AND DISPOSAL OF WASTE:
a) The nature and quality of top-soil, over burden waste and mineral rejects likely to be
removed during the next five years:
Soil of 1.0 m will be generated from the Quarry area. It is proposed to handle about
2633 tonnes of waste, and will be utilized for strengthening the approach roads
7. USE OF MINERAL:
a) The Granite from this quarry will be used as building stone.
8. OTHERS:
a) Site services:
Since Chitradurga is at a distance of 3.20 kms, most of the repairs of equipment will
be undertaken there and hence, no workshop will be maintained at mine head.
Office, stores, first-aid station, rest shelter, latrines and urinals will be constructed
and maintained outside the license area.
Potable Drinking water will be supplied to the persons working in the quarry by
disinfected and cleaned water tank/cans. No colony is maintained within the quarry
as the workers come from the adjoining villages.
b) Employment Potential
In all, there will be about 10 face workers for the Building Stone production of
26,136 tonnes/Annum (saleable production of 25,000 tonnes) @ 10 tonnes face OMS,
each worker contribute 300 man shifts per annum, it requires 26,136 /300/10 = 9+1
(15%leave/absent) workers. All others required are shown in manpower chart.
Building Stone Quarry
Page 18
The break –up of the above employment is given below.
1. Mine supervisors 01
2. Blaster 01
3. Excavator & Tipper Operators 01
4. Driller & Drilling Helper 01
5. Face workers 10
6. Watch & Ward 01
7. Supervisors 01
Total 16
9. MINERAL PROCESSING:
No mineral processing is proposed except manual sizing.
Ganapati S. Hegde RQP/GOA/144/2002/A
Building Stone Quarry
Page 19
PART-B
10. ENVIRONMENTAL MANAGEMENT PLAN :
i) Base line information:
a) Existing Land use pattern :
The extent of the License block to be granted is 2-00 Acres.
About 1-06 Acres land will be used for quarrying in the plan period. The present
land use pattern is given bellow. Statutory buildings will be away from the License
area.
Particulars Existing land
(acres)
Total land use during
plan period (Acres)
Area for Mining -- 1-06
Roads 0-02 0-02
Overburden dump -- 0-02
Infrastructure -- 0-02
Mineral Storage --
Topsoil Yard --
Safety Zone -- 0-28
Vacant Land 1-38 -
Total 2-00 2-00
The surrounding area is dry land, where some seasonal crops like Jowar, Paddy,
Wheat and pulses are grown.
ii) Water Regime:
There are no natural springs in the area.
The water table is about 90 m generally below the ground level. The drainage
pattern is dendritic to sub-dendritic in nature.
iii) Flora and Fauna:
The area is completely barren and devoid of any vegetation. Only few thorny bushes
are seen. As there is no forest cover, no wild life is seen in the area.
Building Stone Quarry
Page 20
iv) Quality of air, ambient noise level and water:
So far, the study on quality of air, ambient noise level and water is not carried out in
the specific area. However, the area around the applied area is devoid of any
industry.
a) Air Quality:
In general the SPM, SO2 and NOx concentration in the region may be within the
permissible limits, as it is a small scale quarrying.
b) Ambient noise level:
The noise levels are very low in this vicinity.
c) Water quality:
The quality of ground water is fairly good. There is no liquid waste discharge from
mining activity, which is likely to pollute water.
v) Climatic Conditions:
The normal annual rainfall in the district based on 30years is 574mm. However, in
the last decade (1996-2005) the district received an average annual rainfall of
631.7mm. Further analysis of rainfall data indicate that the there was deficient rainfall
in the years 2003, whereas the year 2005 received excess rainfall. The taluks of
Chellakere & Chitradurga faced deficit rainfall in the years of 2002 & 2004 as well,
most of the other taluks had deficit rainfall during two successive years 2002 and
2003. Post-monsoon rainfall had failed in the district during 2001 and 2004. During
the year 2003 the pre- and post-monsoon season, rainfall had failed. Rainfall is lowest
in Challakere taluk and highest in Hosadurga taluk.
vi) Human Settlement:
There is no habitation in the area. No villages are situated within the area. Workmen
and staff come from the nearby villages. So, there is no displacement involved. The
Building Stone Quarry
Page 21
villages falling within the buffer zone of 5 Kms from the License boundary are given
in key plan (Plate No. 1)
vii) Public buildings, places and monuments:
No public buildings, places, monument etc., exist within the applied area or in the
vicinity.
viii) Whether the area falls under notified area under water Act. 1974: Entire Karnataka falls under the notified area of the above act. Suitable action and remedial steps will be taken in case any obligation arises from the above said Act by the applicant.
b) Environment Impact assessment statement:
1) Landscape:
The area forms a hilly terrain.
2) Soil and Land use pattern:
There is about 1.0 m of soil in the applied area. Soil will be utilized for plantation
purposes.
About 1-06 acres land will be used for quarrying Building Stone in the License
period. Statutory buildings will be away from the license area.
3) Agriculture:
Due to quarrying agriculture will not be affected around the License area. Only
seasonal rain fed crops are grown such as jawar, sunflower, cotton, etc.
4) Forest:
As there is no forest area in the vicinity, and hence, there can be no effect on the
forest area
5) Vegetation:
The area is barren and devoid of any vegetation.
Building Stone Quarry
Page 22
ii) Air quality:
Only pollution in the air is due to dust which gets airborne due to the vehicular
movement and while loading granite, etc. Therefore, the SPM count in the air will
increase to a very small extent.
Nox, SO2 and CO values are expected to be within the permissible limits due to
proposed quarrying. Effect of quarrying is minimal. There is not much fuel burn
during mining except during transportation of granite and waste of vehicles plying
and compressor used for drilling the JH-holes.
iii) Water Quality:
Since it is rocky terrain, no ground water is found. However rain water is the source
for surface water. There is no toxic or poisonous discharge in to the drains from
mining operations. So, quality of water shall not be affected. But, in the surface
water some suspended silt particles may find their way during rainy season
iv) Noise Levels
Since it is a small scale quarrying, drilling and blasting are proposed, the back
ground noise levels will be slightly high at the site while drilling and blasting. The
area is away from roads where frequent traffic is encountered. General noise levels
are expected to be less than 80 dBa in working of the mine.
v) Vibration levels (due to blasting)
Only 8,193 jack hammer holes/annum of 1.5 mts depth will be drilled and blasted.
As, only few holes will be blasted at one time, not more than 10 holes / round, no
significant air blast or vibrations will take place. The blasting will be done during the
lunch interval of the workers, or before or after the working hours.
Building Stone Quarry
Page 23
vi) Water Regime:
1) Surface Water:
Here, surface water is the rain water. The chemical analysis of the Granite does not
show any hazardous parameters. Therefore, the rain water passing from the mine
working does not affect water quality.
2) Ground Water:
The ground water will not be affected as the mining operations will be conducted at
much higher levels than the ground water level. The ground water table is about 90
mts below the general ground level.
vii) Socio/ Economic:
1) Socio and demographic profile:
There are 9 villages including hamlets within the buffer zone (5km) and they all
depend on agriculture and related activities. Since the quarrying is on small scale, no
health problems are anticipated as well as safety due to quarrying operations.
2) Occupational health and safety:
Some quantity of dust will be generated during drilling operations and the
movement of trucks etc. As the quarrying is on a small scale, no appreciable impact
due to generation of small quantity of dust will be there. Regarding safety all the
precautions such as proper benches, use of safety belts, etc., will be maintained. All
the eligible workers will be provided with safety shoes and helmets.
viii) Public buildings, places and monuments:
The impact of the proposed quarrying is nil as there are no public buildings, places
and monuments in the vicinity.
Building Stone Quarry
Page 24
c) Environmental Management plan:
i) Storage and preservation of the top soil:
Soil of 3 m will be generated which will be used for plantation purposes.
ii) Proposals for reclamation of land affected by abandoned quarries and other mining activities during first five years.
There is no vegetation in the area. Therefore, it is not likely that there will be a loss of
vegetation in the area due to quarrying operation.
It will not be possible to go for reclamation concurrent to quarrying operations,
however, the pit can be used as irrigation pond.
iii) Programme of year-wise afforestation for the initial five years:
Afforestation will be made in the license area along the buffer zone. Plantation along approach road and village roads will be taken. About 100 saplings will be planted every year.
iv) Stabilisation and vegetation of dumps along with waste dump management year-wise for the first five years:
No dumps will be formed as all waste will be used for approach roads.
v) Measures to control erosion/ sedimentation of water course:
Since, it is a slightly undulated land with no water courses there can be no erosion /
sedimentation.
vi) Treatment and disposal of water from mine:
No mineral beneficiation will be conducted using water and hence, the question of
treating water does not arise.
ii) Measures for minimizing adverse effects on water regime:
As such, water regime is not affected. Hence, measures for minimizing adverse
effects on water regime do not arise.
viii) Protective measures for ground vibrations/ air blast caused by blasting.
As quarry is operated with controlled blasting with only 10 holes will be blasted at a
time, the Vibration due to blasting will not be much.
Building Stone Quarry
Page 25
ix) Measures for protecting historical monuments and for rehabilitation of human settlement, likely to be disturbed due to quarrying activity:
There is no historical monuments within or in the vicinity of the license area. There is
no habitation in the area. No villages are situated within the area. Work-men and
staff come from the nearby villages. So, there is no displacement of men involved.
x) Socio-Economic benefits arising out of mining:
People residing in the near-by villages are benefited by the direct and indirect
employment opportunity created by the quarrying activity, vocational training etc.
Monitoring schedules for different environmental components after the commencement of mining and other related activities:
No applicable as the quarry comes under ‘B’ category
Ganapati S. Hegde
RQP/GOA/144/2002/A
Building Stone Quarry
Page 26
PART-C
PROGRESSIVE MINE CLOSURE PLAN (PMCP)
1. Introduction Name of the Mine: Building Stone Quarry
Location of License applied area:. In part of Sy No. 03, Mallanakatte village, Chitradurga Taluk, Chitradurga District, Karnataka.
Extent of area recommended for grant of Quarry License: 2-00 Acres.
The type of License area (forest, non forest etc): Government Kharab land. The present
land use pattern and additional requirement for Plan period is as below.
Particulars Existing land
(acres)
Total land use during
plan period (Acres)
Area for Mining -- 1-06
Roads 0-02 0-02
Overburden dump -- 0-02
Infrastructure -- 0-02
Mineral Storage --
Topsoil Yard --
Safety Zone -- 0-28
Vacant Land 1-38 -
Total 2-00 2-00
The method of Quarrying and mineral processing operations: Open Cast Quarrying. No
Mineral Processing.
1.1) Reasons for Closure:
The reasons for closure of mining operations in relations to exhaustion of mineral,
lack of demand, uneconomic operations, natural calamity, directives from statuary
organization or court etc. should be specified:
There is no proposal for closure and the Quarrying thrives for a period till the
mineral can be exploited economically i.e. for 20 years minimum. As such there will
Building Stone Quarry
Page 27
be closure of the quarry; it will be due to direction from Government authorities or
due to non-renewal of the License.
1.2) Statutory obligations:
The legal obligations, if any which the lessee is bound to implement like special
conditions imposed while execution of License deed, approval of mining plan,
directives issued by the Indian Bureau of Mines, conditions imposed by the Ministry
of Environment & Forests, State or Central Pollution Control Board of by any other
organization describing the nature conditions and compliance position thereof
should be indicated here (the copies of relevant documents may be attached as
Annexure):
The applicant will abide by the terms & conditions imposed in the License deed,
comply with statutory directions of the Department of Mines & Geology, DGMS,
MOEF & Forest Dept., & other State / Central Govt. agencies from time to time.
Blasting permissions will be obtained.
1.3) Closure plan preparation:
The Names and addresses of the applicant:
Sri. B. M Shadakshari,
S/o. B. C. Mahalingappa,
Rice Flour Mill,
Beeranahalli Post, Hiriyur Taluk,
Chitradurga District,
Karnataka.
Recognized qualified person who prepared the Mine Closure Plan:
Ganapati S. Hegde RQP/GOA/144/2002/A
Address # 517, SAGAR REGAL, VI Main, Maruti Layout, Vasanthapura, Bangalore-61 Mob: 9164516629
(RQP Certificate enclosed)
Building Stone Quarry
Page 28
The name of the executing agency should be furnished A copy of the resolution of the board or Directors of any other appropriate administrative authority as the case may be on the decision of closure of mine should be submitted:
Owner of the Quarry is the executing agency himself. However, the Certificate is enclosed with the plan to work according to plan and hence, it is obvious that execution related responsibility lies.
2. Mine Description:
2.1 Geology:
Briefly describe the topography and general geology indicating rock types available, the chemical constituents of the rocks/ minerals including toxic elements if any, at the mine site:
The study area consists of Deccan Granite. The exposures are seen as small boulders.
By and large these continental granites are tholeiitic in composition and exhibit flow
characters. Integrated geomagnetic, geochemical tectonic and radiometric studies
indicate the age of their outpouring was in the range of 65 to 67 million years
2.2 Reserves:
Indicate the mineral reserves available category wise in the License are estimated in the last mining plan/ mining scheme approved along with the balance mineral reserves at the proposed mine closure including its quality av ailable (for final mine closure plan only):
Category Wise Reserves Calculation of
Building Stone Quarry - 2-00 Acres of
Sri BM Shadakshari
Section Sectional
area (Sq.m.)
Sectional Influence
(m)
Volume (Cu.m.)
ROM @2.66t/cmt
Saleable Building
stone (95%)
Intercalated Waste (5%)
Proved reserves
LL' 7,948 57
4,53,036 12,05,076
11,44,822
60,254
Probable reserves
LL' 1,425 57
81,225 2,16,059
2,05,256
10,803
TOTAL 9,373 57 5,34,261 14,21,134 13,50,078 71,057
Building Stone Quarry
Page 29
Mineable Reserves Calculation of
Building Stone Quarry - 2-00 Acres of
Sri BM Shadakshari
Section Sectional
area (Sq.m.)
Sectional Influence
(m)
Volume (Cu.m.)
ROM @2.66t/cmt
Saleable Building
stone (95%)
Intercalated Waste (5%)
Proved reserves
LL' 6,866 42
2,88,372 7,67,070
7,28,716
38,353
Probable reserves
LL' 1,167 42
49,014 1,30,377
1,23,858
6,519
TOTAL 8,033 42 3,37,386 8,97,447 8,52,574 44,872
2.3 Mining Method:
Describe in brief mining method followed to win the mineral, extent of mechanization, mining machinery deployed, production level etc:
Open cast semi Mechanised Quarrying method will be adopted.
3. Review of implementation of Mining Plan / Scheme of Mining including five years Progressive Closure Plan up to the final closure of mine :
This is a new project & the quarry plan is submitting for the first time. Hence the review of previous quarry plan & implementation does not arise. The various proposals made in the present quarrying plan inclusive of progressive mine closure plan for the plan period of five year are as follows & the same will be implemented during the this plan period 1) The rain water flowing from the pits is proposed to be regulated through garland Channels. 2) Bunds will be built all along the license boundary, which will restrict the flow of silt through water. 3) Afforestation will be taken up all along the safety zone area over an extent of 0-26 Acres and approach road with 375 saplings. 4) Regular Monitoring of Air, water & Noise tests. 5) Plantation will be done in stability of dump yard.
Building Stone Quarry
Page 30
4. Closure Plan:
4.1 Mined-Out land:
Describe the proposals to be implemented for reclamation and rehabilitation of mined-out land including the manner in which the actual site of the pit will be restored for future use. The Proposals should be supported with relevant plans and sections depicting the method of land restoration/reclamation/ rehabilitation: At the end of the life of the Quarry, depth of Quarry will be more. So back filling is neither warranted nor feasible. Since one side of the Quarry area is surrounded by the agricultural lands, this pit may be utilized as Irrigation pond by providing proper outlet for excess rain water. Proper bunding will be made around the License area. Barbed wire fencing around mined out area (at the end of License period) will be made as safety & security measures to prevent access.
4.2 Water Quality Management:
Describe in detail the existing surface and ground water bodies available in the License areas and the measures to be taken for protection of the same including control of erosion, sedimentation, siltation, water treatment, diversion of water courses, if any, measures for protection of contamination of ground water from leaching etc. Quantity and quality of surface water bodies should also be indicated and corrective measures proposed described. Report of hydrological study carried out in the area many also be submitted. The water balance chart should be given. If there is potential of Acid Mine Drainage the treatment method should be given:
No surface & ground water bodies are available in the License area. Hence, no protection or control of erosion, siltation, water treatment, diversion of water courses is required.
4.3 Air Quality Management:
Describe the existing air Quality status. The corrective measures to be taken for prevention of pollution of air should be described: Only pollution in the air due to dust which gets airborne due to the vehicular movement, drilling etc. therefore, the SPM count in the air will increase to a very small extent. NOx, SO2 and CO values are expected to be within the permissible limits due to proposed small scale Quarrying. Effect of the small scale Quarrying is minimal. There is not much fuel burn during mining except during transportation of Building Stone and waste by vehicles plying and compressor used for drilling the JH-holes. However, corrective measures will be taken.
Building Stone Quarry
Page 31
4.4 Waste management:
Describe the type, quality and quantity of overburden, mineral reject etc. available and their disposal practice. If no utilization of waste material is proposed, the manner in which the waste material will be stabilized should be described. The protective measures to be taken for prevention of siltation, corrosion and dust generation from these waste material should also be described. If toxic and hazardous elements present in the waste material the protective measures to be taken for prevention of their dispersal in the air environment, leaching in the surface and ground water etc should be described:
There is 1.0 m of soil which will be utilized for plantation purposes. There is 6,625
tonnes (5%) of waste to be produced which will be used for haul road and approach
road
4.5 Topsoil Management:
There is 1.0 m of soil which will be utilized for plantation purposes.
4.6 Tailing Dam Management:
The steps to be taken for protection and stability of tailing dam, stabilization of tailing material and its utilization, periodic distillation measures to prevent water pollution from tailings etc, arrangement for surplus water overflow along with detail design, structural stability studies, the embankment seepage loss into the receiving environment and ground water contaminant if any should be described :
Not applicable as there can be no tailing dam.
4.7. Infrastructures:
The existing infrastructural facilities available such as roads aerial ropeways, conveyer belts, railways, power lines, building and structures, water treatment plant, transport, water supply sources in the area etc. And their future utilization should be evaluated on case-to case basis. If retained, the measures to be taken for their physical stability and maintenances should be described. If decommissioning proposed, dismantling and disposal of building structures, support facilities and other infrastructure like electric transmission line, water line, gas pipeline, water works, sewer link, telephone cables underground tanks transportation infrastructures like electrical cable, transformers to be described in connection with restoring land of further use :
The existing infrastructural facilities available are approach roads. Water for drinking
& dust suppression will be purchased from nearest village bore wells, the rest shelter
will be provided outside the License area.
Building Stone Quarry
Page 32
4.8 Disposal of Mining Machinery:
The decommissioning of mining machineries and their possible post mining utilization, if any, to be described:
Hired machineries will be removed by contractor as and when not required and
applicant’s own machineries will be shifted to other projects.
4.9 Safety &Security:
Explain the safety measures Implemented to prevent access to surface openings, excavation etc and arrangements proposed during the mine abandonment plan and up to the site being opened for general public should be described:
Proper bund will be made around the License area. Barbed wire fencing around
mined out area (at the end of License period) will be made as safety & security
measures to prevent access.
4.10 Disaster Management and Risk Assessment:
This should deal with action plan for high risk accidents like landslides, subsidence flood, and inundation in underground mines, fire, seismic activities, tailing dam failure etc. and emergency plan proposed for quick evacuation, ameliorative measures to the taken etc. The capability of lessee to meet such eventualities and the assistance to be required from the local authority should also be described:
Since it is hard rock Quarrying, high risk accidents are very rare in these type of
Quarrying, as the area is free from earthquake zone and also major water body. Even
if there is any such event, the lessee is quite capable to meet such high risk accidents.
4.11 Care and maintenance during temporary discontinuance:
For every five yearly review (as given is the mining Scheme), an emergency plan for the
situation of temporary discontinuance or incomplete programme due to court order or due to
statutory requirements or any other unforeseen circumstances, should include a plan
indicating measures of care, maintenance and monitoring of status of unplanned discontinued
mining operations expected to re-open in near future. They should detail item wise status
monitoring and maintenance with periodicity and objective:
During temporary discontinuance proper bund will be made not to allow any rain
water to fill the pit. Also proper fencing will be erected around the pit as a safety
measure to enable the pit to re-open immediately in shortest possible time.
Building Stone Quarry
Page 33
5. Economic repercussions of closure of mine and manpower retrenchments:
Manpower retrenchment, compensation to be given, socio-economic repercussions and remedial measures consequent to the closure of mines should be described, specifically stating the following:
There will be limited socio-economic repercussions due to closure of the Quarry
activities as it is a small quarry. Since, the labours are from surrounding areas who
are basically agricultural labours, in case of closure, they will go back to their family
occupation. They will get compensation as per the Govt. rules.
5.1 Number of local residents employed in the mine, status of the continuation family occupation and scope of joining the occupation back:
Around 16 local persons will be used as labours. Most of the labours will be from the
surrounding areas who are basically Agricultural. Labours In case of closure, they
will go back to their family occupation.
5.2 Compensation given or to be given to the employees connecting with sustenance of himself and their family members:
As they are daily wages employees, they will get compensation as per the
government rules.
5.3 Satellite occupations connected to the Quarrying industry number of persons engaged therein continuance of such business after mine closes:
There can be no satellite occupation connected to the Quarrying industry. Not
applicable.
5.4 Continued engagement of employees in the rehabilitated status of mining License area and any other remnant activities:
Not Applicable
5.5 Envisaged repercussions on the expectation of the society around due to closure of Quarry:
There cannot be any repercussion on the expectation of the society around due to
closure of the Quarry as it is a very small Quarry and is well away from habitations
Building Stone Quarry
Page 34
6. Time scheduling for abandonment : The details of time schedule of all abandonment operations as proposed in Para 4 should be
described here. The manpower and other resources required for completion of proposed job should be described. The schedule of such operations should also be supplemented by PERT (Programme Evaluation & Review Technique), Bar Chart etc
It is proposed to carry out the following activities with an anticipated duration with PMCP.
Item
s
Details
Area (Ha) proposed year
Quantity Proposed year
Expenditure Proposed
1 2 3 4 5 1 2 3 4 5 1 2 3 4 5
(A)
Recl
am
ati
on
an
d R
eh
ab
ilit
ati
on
of
min
ed
ou
t p
it a
nd
are
a
i) Backfilling (within the License as per PMCP)
ii) Afforestation on the backfilled area
iii) Other (Please Specify e.g. Afforestation on exhausted benches
iv) Pisciculture
v) Converting into water reservoir
vi) Picnic spot
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
Building Stone Quarry
Page 35
Item
s
Details
Area (Ha) proposed year
Quantity Proposed year
Expenditure Proposed
1 2 3 4 5 1 2 3 4 5 1 2 3 4 5
(B)
Sta
bil
izati
on
an
d
reh
ab
ilit
ati
on
of
du
mp
s
i) Terracing
ii) Pitching
iii) Construction of parapet walls
iv)Construction of check dams
v) Construction of settling ponds (drains etc)
vi) Desitling of settling ponds, Channels
vii)Afforestation on dumps
viii) Others (Please specify)Fence/Bund
--
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
--
-
-
-
-
-
-
-
--
-
-
-
-
-
-
-
-
-
-
-
- - - - - - - - -
C)R
eh
ab
ilit
ati
on
of
Barr
en
are
a w
ith
in
Lic
en
se
i) Afforestation
ii) others
a) Strengthening
100
100
100
100
100
20
,000
20
,000
20
,000
20
,000
20
,000
Building Stone Quarry
Page 36
Item
s
Details
Area (Ha) proposed year
Quantity Proposed year
Expenditure Proposed
1 2 3 4 5 1 2 3 4 5 1 2 3 4 5
D)
En
vir
on
men
tal
mo
nit
ori
ng
(co
re z
on
e a
nd
bu
ffer
zo
ne s
ep
ara
tely
i) Ambient Air Quality
ii) Water Quality
iii) Noise Level Survey
iv) Ground vibration
v) Other (Please Specify)
Rs.50,000/year
7.0 Abandonment Cost: Cost to be estimated based on the activates required for implementing the protective and rehabilitation measures including their maintenance and monitoring programme: Estimated cost for activities required for implementing the protective and rehabilitation measures including their maintenance and monitoring (in Rupees). Yearly Rs. 50,000/- will be spent. 8.0 Financial Assurance: The financial assurance can be submitted indifferent forms as stated in rules 23(F)(2) of Mineral Conservation and Development (amendment) Rules, 2003. In the mine closure plan, the manner in which financial assurance has been submitted and its particulars have to be indicated: The total area to be degraded by the mining and related activities during plan period will be 2-00 Acres. The financial assurance @ INR 5,000/- per acre is estimated to be Rs. 10,000/-. 9.0 Certificate: Certificate Enclosed.
10.0 Plans, Sections etc: The chapters at 1,2,3 and 4 should be supported with plans and sections. The closure plan may also be submitted depicting photography, satellite images on compact disc etc. Wherever possible:
The following plans and section have been enclosed
Building Stone Quarry
Page 37
KEY PLAN Plate No.1
LICENSE SKETCH Plate No.2
SURFACE PLAN Plate No.3
GEOLOGICAL PLAN Plate No.4
GEOLOGICAL CROSS SECTION Plate No.5
PRODUCTION AND DEVELOPMENT PLAN AND SECTIONS Plate No.6 & 7
PROGRESSIVE MINE CLOSURE PLAN Plate No.8
ENVIRONMENTAL PLAN Plate No.9
Date: 26-12-2017
Ganapati S. Hegde
RQP/GOA/144/2002/A
Study Zone :-
Area covered under village limits of Mallanakatte village. There areno Wildlife Sanctuaries or National parks within 5 kms radius. Q.L. Area
5 K.M. Radius
GENERAL I N D E X
TOPO SHEET No. 57 B 7 & 8
KEY PLAN
Scale :- 1 : 50000 R.F.
Lessee
Plate No.
Project Title
Location
Dwg. Title1
Scale - 1 cm = 500 mtr
0 1 2 3 4 5
Ganapati S. HegdeRQP/GOA/144/2002/A
E 76°20'00"
N 14°15'00" N 14°15'00"
E 76°25'00"
E 76°20'00" E 76°25'00"
Sri. B. M Shadakshari
Area :- 2-00 Acres Date of Survey:- 22/12/2017
Sy No. 03, Mallanakatte village, Chitradurga TalukChitradurga District, Karnataka.
0
Scale :- 1cm=10m
10 20 4030 50100
GENERAL INDEX
TBM
Q.L.Boundary
Safety zone
Mine Road
T. Bench Mark
ContoursSURFACE PLAN
Scale :- 1 : 1000 R.F.
Sri. B. M Shadakshari
Area :- 2-00 Acres Date of Survey:- 22/12/2017
Lessee
Plate No.
Project Title
Location
Dwg. Title3
Ganapati S. HegdeRQP/GOA/144/2002/A
Sy No. 03, Mallanakatte village, Chitradurga TalukChitradurga District, Karnataka.
GPS READING OF CORNER PILLARS
CORNER
PILLAR
LATITUDE LONGITUDE
BP-1 N 14°15'28.1" E 76°22'25.4"
BP-2 N 14°15'24.1" E 76°22'25.3"
BP-3 N 14°15'24.1" E 76°22'23.5"
BP-4 N 14°15'28.7" E 76°22'23.3"
MAP DATUM - WGS-84
769
770
771
772
773
774
775
776
777
778
779
780
781782
BP-1
0
Scale :- 1cm=10m
10 20 4030 50100
Scale :- 1 : 1000 R.F.
Lessee
Plate No.
Project Title
Location
Dwg. Title
Ganapati S. HegdeRQP/GOA/144/2002/A
Ultimate pit limit
Building stone
GEOLOGICAL INDEX
GEOLOGICAL PLAN4
GENERAL INDEX
TBM
Q.L.Boundary
Safety zone
Mine Road
T. Bench Mark
Contours Sri. B. M Shadakshari
Area :- 2-00 Acres Date of Survey:- 22/12/2017
Sy No. 03, Mallanakatte village, Chitradurga TalukChitradurga District, Karnataka.
Soil Cover
769
770
771
772
773
774
775
776
777
778
779
780
781782
GEOLOGICAL CROSS SECTION
Lessee
Plate No.
Project Title
Location
Dwg. Title5
Proved Reserves
Probable Reserves
Q. L. Boundary
Safety Zone
Ultimate Pit Limit Scale :- 1 : 500 R.F.
Ganapati S. HegdeRQP/GOA/144/2002/A
0
Scale :- 1cm=5m
5 10 2015 2550
Sri. B. M Shadakshari
Area :- 2-00 Acres Date of Survey:- 22/12/2017
Sy No. 03, Mallanakatte village, Chitradurga TalukChitradurga District, Karnataka.
Ultimate pit limit
Building stone
GEOLOGICAL INDEX
Soil Cover
0
790
780
770
760
750
DATUM 700 m
740
730
720
710
PRODUCTION AND DEVELOPMENT PLAN
Lessee
Plate No.
Project Title
Location
Dwg. Title6
Scale :- 1 : 1000 R.F.
0
Scale :- 1cm=10m
10 20 4030 50100
Ganapati S. HegdeRQP/GOA/144/2002/A
Ultimate pit limit
GEOLOGICAL INDEX
5 Years Workingarea
ProposedRetaining Wall
ProposedDumping Yard
ProposedBenches
Building stone
GENERAL INDEX
TBM
Q.L.Boundary
Safety zone
Mine Road
T. Bench Mark
Contours
Workings
Sri. B. M Shadakshari
Area :- 2-00 Acres Date of Survey:- 22/12/2017
Sy No. 03, Mallanakatte village, Chitradurga TalukChitradurga District, Karnataka.
769
770
771
772
773
774
775
776
777
778
779
780781
782
776 m level779 m level
773 m level770 m level767 m level
764 m level
Proposed workingfor 5 years764 m level
Lessee
Plate No.
Project Title
Location
Dwg. Title7
Development for 5 years
I year
II year
III yearQ. L. Boundary
Safety Zone
Ultimate Pit Limit
PRODUCTION AND DEVELOPMENT SECTIONS
Scale :- 1 : 500 R.F.
Ganapati S. HegdeRQP/GOA/144/2002/A
0
Scale :- 1cm=5m
5 10 2015 2550
IV year
V year
Sri. B. M Shadakshari
Area :- 2-00 Acres Date of Survey:- 22/12/2017
Sy No. 03, Mallanakatte village, Chitradurga TalukChitradurga District, Karnataka.
Ultimate pit limit
Building stone
GEOLOGICAL INDEX
Soil CoverSECTION ON - LL'
10
Distance in m.
20 30 40 50 60 70 80 90 100 110 120 130 142 m
Lessee
Plate No.
Project Title
Location
Dwg. Title
Scale :- 1 : 1000 R.F.
0
Scale :- 1cm=10m
10 20 4030 50100
PROGRESSIVE MINE CLOSURE PLAN8
Ganapati S. HegdeRQP/GOA/144/2002/A
0-02
1-06
--
2-00Total 2-00
--
0-02
0-02
0-02
0-28
Landuse pattern at the end of 5 years
--
--
1-38
--
ParticularsExistingLanduse(Acres)
FinalLanduse(Acres)
MiningRoadsOverburden DumpInfrastructureMineral StorageTop soil yardSafety ZoneVacant Land
Ultimate pit limit
GEOLOGICAL INDEX
ProposedRetaining Wall
ProposedBenches
Soil cover
Building stone
GENERAL INDEX
TBM
Q.L.Boundary
Safety zone
Mine Road
T. Bench Mark
ContoursSri. B. M Shadakshari
Area :- 2-00 Acres Date of Survey:- 22/12/2017
Sy No. 03, Mallanakatte village, Chitradurga TalukChitradurga District, Karnataka.
769
770
771
772
773
774
775
776
777
778
779
780781
782
776 m level779 m level
773 m level770 m level767 m level
764 m level
Proposed workingfor 5 years
764 m level
ENVIRONMENTAL PLAN
Lessee
Plate No.
Project Title
Location
Dwg. Title9
0
Scale :- 1cm=50m
50 100 200150 250500
Scale :- 1 : 5000 R.F.
Ultimate pit limit
LEGENDQ.L.Boundary
Safety zone
Mine Road
TBM T. Bench Mark
60 m Buffer
500 m Buffer
Agricultural Land
Top soil yard
Infrastructure
Overburden dump
Mineral Storage area
Quarry Area
Buffer Zone
Proposed retaining wall
Rocky area
Plain Land
Ganapati S. HegdeRQP/GOA/144/2002/A
Other Quarry Workings
Sri. B. M Shadakshari
Area :- 2-00 Acres Date of Survey:- 22/12/2017
Sy No. 03, Mallanakatte village, Chitradurga TalukChitradurga District, Karnataka.
769
770
771
772
773
774
775
776
777
778
779
780781
782
776 m level
779 m level
773 m level
770 m level
767 m level
764 m level
Proposed working for 5 years