Project Update November 14 th , 2011

Upload: city-of-pearland

Post on 28-Mar-2016

218 views

Category:

Documents


3 download

DESCRIPTION

October 2011 Monthly Report Presentation

TRANSCRIPT

Page 1: October 2011 Monthly Report Presentation

Project Update

November 14th, 2011

Page 2: October 2011 Monthly Report Presentation

Roadway Projects

Page 3: October 2011 Monthly Report Presentation

Phase I • Electrical acceptance is the only outstanding item

remaining on TxDOT’s list for acceptance. Staff waiting for invitation to this acceptance walk-through

Phase II • TxDOT accepted bids in August • Construction scheduled to begin in late November • Duration is 16 months (March 2013)

Cullen Parkway

Page 4: October 2011 Monthly Report Presentation

Phase II – Mary’s Creek Bypass to SH35 • CPE’s new cost for streetlight installation

will save approx. $22,000 • Completed signal pre-emption work south

of FM 518 and 2 intersections • No active work on punchlist work by

contractor

Dixie Farm Road

Page 5: October 2011 Monthly Report Presentation

• Asphalt overlay between Austin and McLean is 85% complete

• BNSF has relocated and installed the software for their signal house

• TxDOT contractor has pulled all of the necessary conduit for the completion of the pre-emption work

• Substantial completion scheduled for late October • Full opening of SH35 intersection is dependent upon

TxDOT completion of the new signal

Walnut Reconstruction

Page 6: October 2011 Monthly Report Presentation
Page 7: October 2011 Monthly Report Presentation

Construction Phase III – Morgan to Harkey and CR 89

• Contractor reported completion of punchlist items; review pending

• Engineers working on red-line/record drawings

Magnolia Road

Page 8: October 2011 Monthly Report Presentation

• All utility conflicts at the intersection of Mykawa and Orange have been resolved

• Traffic signal poles at Mykawa have been installed. The mast arms and signal heads are to be installed by November 18th

• WB pavement completed from Mykawa to ?? • Orange is open to eastbound traffic only

between Hatfield and Mykawa until the end of November at which time the traffic will shift to westbound only.

Orange Street

Page 9: October 2011 Monthly Report Presentation
Page 10: October 2011 Monthly Report Presentation

• Met with design team to discuss comments

from TxDOT regarding FM 1128. Design may be revised to reduce impacts to FM 1128 configuration and reduce TxDOT requests for modifications of the ROW

• Enterprise Pipeline completed relocation of 16” pipeline adjacent to Bailey Road

Bailey Road (Veterans to FM1128)

Page 11: October 2011 Monthly Report Presentation

McHard Road (Soundwall Construction)

• Punch-list items have been completed • Closing out contract

Page 12: October 2011 Monthly Report Presentation

• 90% plans were submitted and are under review

• Continued coordination with developer, County staff and CR59 designers

• Held coordination meeting with County to discuss intersection at CR 59

Business Center Drive

Page 13: October 2011 Monthly Report Presentation

• Contractor is completing sidewalks, driveways and street light foundations on west side

• FM518 intersection delay continues due to contamination investigation

• TxDOT conducting a Phase II ESA; new core samples taken

• Traffic switch to new lanes is being scheduled for late November

• Mitigation Ponds out for bids

SH35 – BW8 to FM518

Page 14: October 2011 Monthly Report Presentation

• Shoulder pavement is complete • Drill shafts for signal foundations completed • Traffic switched to new pavement at Kirby

Drive, Kingsley, and Business Center Drive • Project is on schedule for completion in

January 2012

FM 2234 Widening

Page 15: October 2011 Monthly Report Presentation

• The controlling server has been installed in the computer room at Hillhouse and is now functional

• Fiber link between Hillhouse and PSB was completed and tested in early Nov. This will allow the camera data to be viewed by anyone within the City with authorized access

• Computer controller has been turned over

Adaptive Traffic Signal Improvements

Page 16: October 2011 Monthly Report Presentation

Drainage Projects

Page 17: October 2011 Monthly Report Presentation

Diversion Ditch • DD4 continued excavation of diversion ditch west of CR

143 Pump Station • Recommendation report received from the consultant.

Currently under review by City staff. • Design completion proposal under review Re-grading of Roadside Ditches • Scheduling a meeting with Brazoria County to review

plans

Cowart Creek Diversion

Page 18: October 2011 Monthly Report Presentation

Facility Projects

Page 19: October 2011 Monthly Report Presentation

• Adaptive Signal Servers installed • Completed installation of fuel island

equipment; final testing and connection to the Public Works Service Center completed

• Completed installation of security system • Building is occupied • Punch list is completed

Hillhouse Road Service Center

Page 20: October 2011 Monthly Report Presentation
Page 21: October 2011 Monthly Report Presentation

• Contractor has closed in the building • Interior work ongoing • December 7th latest completion date

Fire Station #6

Page 22: October 2011 Monthly Report Presentation
Page 23: October 2011 Monthly Report Presentation

• Project Bid on October 13th • Prepared Bid Award for Council • KPB funding $5,000 of project • Terracon donating the material testing cost

Pearland Gateway – Project Stars

Page 24: October 2011 Monthly Report Presentation

Parks

Page 25: October 2011 Monthly Report Presentation

• Trail section from Ryan Acres Dr to Mary’s Creek poured

• Drainage west of McLean installed • Contractor forming trail sections along

property across from SWEC and within Centennial Park

Trail Connectivity

Page 26: October 2011 Monthly Report Presentation
Page 27: October 2011 Monthly Report Presentation

• Interlocal and MOU with BDD4 will be on 11/28 Council agenda

• Drafted developer agreement with MUD engineer and developer on CR 403 and future subdivision utility and drainage needs

• Engineer working on 90% Pond & 90% CR403 plans and H&H report

• Property acquisition ongoing • Engineer submitted geotechnical report for review

Sports Complex at Max Road

Page 28: October 2011 Monthly Report Presentation

Utility Projects

Page 29: October 2011 Monthly Report Presentation

30” Waterline Interconnect

• HMI will begin flushing & disinfection the 30” water line system this week

• Water is anticipated to be available from the City of Houston in the first part of December 2011

City of Houston Interconnect

Page 30: October 2011 Monthly Report Presentation
Page 31: October 2011 Monthly Report Presentation

City of Houston Interconnect

Alice Street Water Plant • Contractor and their subcontractors continued to work

on the remaining punchlist items from the August 30th preliminary inspection of the facilities

Page 32: October 2011 Monthly Report Presentation
Page 33: October 2011 Monthly Report Presentation

• Submitted 60% plans and Specs October 24th

• Held filter spec meeting with Nova Filters

Longwood WWTP Rehabilitation

Page 34: October 2011 Monthly Report Presentation

• Reviewing 90% plans • Working on Instrumentation and Operation

plans • Operations staff approved a second

centrifuge manufacturer as an alternate supplier.

Barry Rose WWTP Rehabilitation

Page 35: October 2011 Monthly Report Presentation

• Survey and geotechnical, and Phase 1 ESA work ongoing

• Finalized Phase 1 ESA • Will need a Nationwide Permit for the Mary’s

Creek Crossing • Refined alternate route along Centennial Village

and Corrigan Pond.

Hatfield Basin Trunk Sewer

Page 36: October 2011 Monthly Report Presentation

• Engineer continued design phase services • Anticipating 60% review to begin in

November

Twin Creek Regional Lift Station

Page 37: October 2011 Monthly Report Presentation

Far Northwest Wastewater Treatment Plant Improvements

• Consultant finalized the report on the Decanter System • Make improvements per the manufacturer’s

recommendation (mfg’s cost) • Replace butterfly valves with plug valves

(City’s cost) • Replace system at next plant expansion

• UV system will be replaced • Scoping design contract with consultant

Page 38: October 2011 Monthly Report Presentation

Old Alvin 20” Waterline

• Received PER; currently in review process with staff

• Phase II ESA field work performed; contaminated soils issues identified near FM518 and Old Alvin

Page 39: October 2011 Monthly Report Presentation

BellaVita Waterline Interconnect

• Reviewing previous environmental reports from Harris County Pct. 1

• Will probably need USACE to provide a wetland delineation verification

• Survey work ongoing

Page 40: October 2011 Monthly Report Presentation

Project Update

Questions/Comments

November 14th, 2011