nyserda’s peak load reduction program pon 835
DESCRIPTION
NYSERDA’s Peak Load Reduction Program PON 835. Embassy Suites Hotel New York, NY October 7, 2004. Increase grid reliability by reducing/curtailing demand (NYISO DR programs) Base load reductions and enable demand response - PowerPoint PPT PresentationTRANSCRIPT
NYSERDA’s Peak Load Reduction Program PON 835
Embassy Suites Hotel New York, NY
October 7, 2004
Program Objective• Increase grid reliability by
reducing/curtailing demand (NYISO DR programs)
• Base load reductions and enable demand response
• Demand reductions for the period of May through October – 11:00 AM-7:00 PM
• Open to end users and third party aggregators, etc. (LSE, CSP, utilities, etc.)
• PON 835 application deadline 11/1/04, I&O by 3/31/05
NYISO"Hub of the Northeast""Hub of the Northeast"
* = Peak Load in Megawatts
IMO23,857 MW*
Hydro Quebec19,410 MW*
ISO - New England25,158 MW*
New York ISO30,983 MW*
PJM / PJM West64,300 MW*
NYSERDA/NYISO Relationship• NYISO administers three demand
response programs that pay for demand response
• NYSERDA supports participation in these programs by reimbursing a portion of costs associated with technology installation that enables demand response/reduction
NYISO’s Demand Response ProgramsNYISO’s Demand Response Programs
• EDRP• Low Risk• Low/Moderate
Return
Risk
Return
EDRP
DADRP
SCR
• ICAP/SCR• Moderate/High Risk• Moderate/High
Return
• DADRP• Moderate Risk• Moderate/High
Return
Customer
NYISO
NYSERDAPermanent Demand
Reduction
NYSERDA/NYISO Relationship
Load Shifting/
Curtailment
DispatchableEmergencyGenerator
Interval Meter
DADRP
ICAP/SCR
EDRP
NYSERDA’s Peak Load Reduction Program
NOTE: Contractors will be reimbursed the lesser of 70% of the Eligible Project Costs or the incentive caps set forth in Table 1. The Facility owner/operator must contribute no less than 30% of Eligible Project Costs.
PDRE LC/S DEGI IM
Con EdisonService Territor
y
Non-Con
EdisonService
Territory
Con EdisonService
Territory
Non-Con
EdisonService
Territory
Con EdisonService
Territory only
Statewide PSC
Approved
StatewideNYISO
Compliant
$475/kW $225/kW $175/kW $45/kW $125/kW $2,500 per meter
$1,200 per meter
Permanent Demand Reduction Efforts
• Implement projects that result in long term demand reduction
• 20 kW minimum demand reduction (can be aggregated)
• Common measures include lighting, motors, cooling system upgrades, etc
• 70% of eligible costs up to $475/kW by 3/31/05
Permanent Demand Reduction• 41 story commercial
property in Manhattan• 28-tank ice storage
system• Ice Slurry is created at
night, and circulated through cooling coils during daytime
• Shifted 4,000 ton-hours of cooling off-peak
• $300,000 in incentives
The Durst Organization
• Upgraded Lighting from T12 to T8 technology
• 39 Locations retrofitted• Demand Reduction – 379 kW• Energy Savings – 1.9 Million kWh• NYSERDA incentive - $142,000
Load Curtailment/Shifting• Identify and control discretionary loads • Supports Utility/NYISO Demand Response
Programs• Common measures include duty cycling,
process shifting, lighting reductions, etc• 100 kW minimum (may be aggregated)• 70% of eligible costs up to $175/kW by
3/31/05• Direct load control encouraged (100%
reimbursement up to $175/kW in Con Edison)
Load Curtailment/Shifting
• Direct Load Control – Load centrally controlled from a single source through bldg EMS, which activates pre-programmed curtailment settings
– 21 BJ’s Wholesale Club locations (1 MW)
– 16 Stop & Shop Supermarkets (0.8 MW)
– 36 Home Depot locations (4.4 MW)
Home Depot Demand Curtailment (2002)
0
100
200
300
400
500
600
0:1
5
1:1
5
2:1
5
3:1
5
4:1
5
5:1
5
6:1
5
7:1
5
8:1
5
9:1
5
10
:15
11
:15
12
:15
13
:15
14
:15
15
:15
16
:15
17
:15
18
:15
19
:15
20
:15
21
:15
22
:15
23
:15
Time of Day
De
ma
nd
(k
W)
30-Jul 29-Jul curtailed load
Dispatchable Emergency Generator Initiatives
• Energy & environmental controls & enhancements to improve operations and reliability
• Supports NYISO EDRP & SCR, or TO DRP• Eligibility limited to facilities in Con-Edison service
territory and machines with NOx emissions less than 35 lbs/MWh (18 lbs/MWh for new installations)
• Common measures include switchgear, controls, test & tunes, dual fuel conversions, etc
• 70% of eligible costs up to $125/kW by 3/31/05
AT&T Generator
• AT&T could not run generators due to high emissions (opacity of 80%)
• Faulty fuel injectors, allowing unburned fuel in the exhaust
• New fuel injectors and turbo chargers were installed, allowing 7 MW of generation to run significantly cleaner (less than 20% opacity)
• NYSERDA provided over $400,000
Interval Meters• Interval metering intended for
primary electric service • Required registration in NYISO
and/or Utility Demand Response Programs
• $2,500 for “socket meters”, or $1,200 for “shadow meters”
• 70% of eligible costs up to $2,500 or $1,200 by 3/31/05
3-D Metered Data
NYSERDA’s Interval Meter (8/15/03)
PON 835 Participation• Apply• NYSERDA sends PO• Submit a Technical Assessment (TA)• NYSERDA reviews TA and issues notice to
proceed• Complete the job and notify NYSERDA• NYSERDA does site visit to verify
installation• Invoice NYSERDA• NYSERDA provides payment
Program Funding/Timeframe
• $10.5 million available, program year nearly over
• Applications accepted through November 1, 2004, or until funds committed
• Applications accepted on a first come, first serve basis
• Projects must be completed and field verified by March 31, 2005
PLRP for Summer 2005PON 903
• Similar to PON 835 – 4 components• Retro-active back to projects
contracted for after 11/01/04• Funding amount could be less –
end of program• Planned release December 2004
Questions?• Albany 1-866-NYSERDA (697-3732)
– Pete Savio ext 3334– Chris Smith ext 3360– Lee Smith ext 3313
• New York City 212-971-5342– Elizabeth Perry ext 3017
• http://www.nyserda.org/835pon.pdf