nusakambangan reforestation project report english version.pdf

Upload: stephanus-mulyadi

Post on 04-Jun-2018

237 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/14/2019 Nusakambangan Reforestation Project Report english version.pdf

    1/12

    2011

    Stephanus Mulyadi

    YSBS CILACAP

    9/8/2012

    Project Report:

    The Reforestation of Nusakambangan Island

  • 8/14/2019 Nusakambangan Reforestation Project Report english version.pdf

    2/12

    YAYASAN SOSIAL BINA SEJAHTERAGedungAMNLt.4, Jl. Kendeng307Sidanegara, Cilacap53223. JawaTengah INDONESIANPWPNo. 01-245-092.0-522.000 - KEPMENHUKUMDANHAMRI NO. AHU-3098AH.01.04.Tahun2011

    Tel.Fax. +62-282-5070004 E-Mail:[email protected]:www.ysbs.or.id

    Narrative Project Report of Reforestation Nusakambangan Island -YSBS | 2

    NARRATIVE REPORT

    Report NumberSubject The Narrative Report Progress of Reforestation Nusakambangan Island

    with Strengthening Local Society Model

    Name of Partner Organization Yayasan Sosial Bina Sejahtera Cilacap

    The Project Title Reforestation of Nusakambangan Island

    Report Period First Report (August 2011)

    Report Summary The Process of this report involved the Foundation staff, project staffand the formers being trained.

    The information was collected through direct interview, visitationand field direct observation.

    Contributors: project staff, local government, and the framers

    Introduction

    As the follow up to the M.O.U. between Central Java Province Law and Human Rights

    Department and The Foundation of the Bringing About of Prosperity and Good Will (YSBS

    Cilacap) No. WUM.01.10-323, dated 7 April 2010, in the same year YSBS started the

    reforestation project in Solok Jero area, in Nusakambangan Island. The purpose of the

    reforestation project is to restore the forest in Nusakambangan Island to the previous

    ecosystem and give a significant contribution on reducing the danger of global warming.

    Therefore, we prioritize the indigenous plants from the Island to be planted and the strategy

    that we use is organizing and recruiting the settlers around the area so that they can

    participate actively in implementing the reforestation program in Nusakambangan Island. To

    keep the sustainability and the success of the project we carry out the system what is called

    tumpang sari, which means in the same area among those main and hard trees which may

    not be cut or logged they also plant and cultivate sorts of vegetable called palawija.

    The project was officially confirmed by the Vice Governor of Central Java Province, Mrs.

    Rustriningsih, and witnessed by the Law and Human Rights Department of Central Java

    Province, Mr. Chairudin Idrus, on May 1st2011.

    The following is our report on the implementation of the project so far. We are also attaching

    some pictures on the project.

  • 8/14/2019 Nusakambangan Reforestation Project Report english version.pdf

    3/12

    YAYASAN SOSIAL BINA SEJAHTERAGedungAMNLt.4, Jl. Kendeng307Sidanegara, Cilacap53223. JawaTengah INDONESIANPWPNo. 01-245-092.0-522.000 - KEPMENHUKUMDANHAMRI NO. AHU-3098AH.01.04.Tahun2011

    Tel.Fax. +62-282-5070004 E-Mail:[email protected]:www.ysbs.or.id

    Narrative Project Report of Reforestation Nusakambangan Island -YSBS | 3

    I. The Improvement of the Project.

    Pic 1. Showing the area which has been covered by the indigenous plant from the island. With the appropriatetreatment the plants grew well and healthily.

    1) SeedlingThe first step of the reforestation is seedling the indigenous plants. The seedling nursery is

    done in the area to guarantee the efficiency and the indigenousness of the plants. The seedling

    planting is done both in the base camp of the project and in the settlers land. The seedlings in

    the base camp functions as the samples, whereas the ones in the settlers land is meant toreduce the distance between the seedling area and the reforestation area which can minimize

    the cost of moving the young plants to the reforestation area.

    Pics 2 and 3, showing the seedling process in the Base Camp of the Coordinator Reforestation Project.

    Foto 2-3

    Foto 1

  • 8/14/2019 Nusakambangan Reforestation Project Report english version.pdf

    4/12

    YAYASAN SOSIAL BINA SEJAHTERAGedungAMNLt.4, Jl. Kendeng307Sidanegara, Cilacap53223. JawaTengah INDONESIANPWPNo. 01-245-092.0-522.000 - KEPMENHUKUMDANHAMRI NO. AHU-3098AH.01.04.Tahun2011

    Tel.Fax. +62-282-5070004 E-Mail:[email protected]:www.ysbs.or.id

    Narrative Project Report of Reforestation Nusakambangan Island -YSBS | 4

    The seedlings in this Base camp gives a very important education to the settlers, for they can

    learn the appropriate seedling process and study how to do the seedlings correctly, also how

    to overcome the plant disease they might encounter. The readied seedlings then are taken tothe settlers area. Until now (2012) we have planted over one million indigenous trees in

    Nusakambangan.

    Pics 6 - 9 show the seedling in the settlers area next to their huts.

    Foto 4-5

    Foto 6-7

    Foto 8-9

  • 8/14/2019 Nusakambangan Reforestation Project Report english version.pdf

    5/12

    YAYASAN SOSIAL BINA SEJAHTERAGedungAMNLt.4, Jl. Kendeng307Sidanegara, Cilacap53223. JawaTengah INDONESIANPWPNo. 01-245-092.0-522.000 - KEPMENHUKUMDANHAMRI NO. AHU-3098AH.01.04.Tahun2011

    Tel.Fax. +62-282-5070004 E-Mail:[email protected]:www.ysbs.or.id

    Narrative Project Report of Reforestation Nusakambangan Island -YSBS | 5

    2) The implementation of tumpang sarisystem to support the project.As we mentioned above that in this reforestation project we carry out Tumpang Sarisystem.

    We chose that system because there has been no better system to support the sustainability of

    the project with the least cost so far. Tumpang Sari system means the settlers can plant

    vegetables /palawijaamong the timber or the fruit trees. So, the settlers who are involved in

    the project do not receive any payment, but they can still harvest from the vegetable and fruit

    trees which they plant among the indigenous plants. This system proves to function very well,

    where the symbiosis take places.

    Pics 10 and 11 show the indigenous plant among the vegetable and fruit trees. Pics 12 - 15 show the young

    indigenous plants after the vegetable was harvested.

    Due to the failure of the paddy harvest the previous year, the Foundation of the Bringing

    About of the Prosperity and Good Will helped the farmers by donating money to buy corn

    seed, lentils kidney beans, and green peas. Those plants grew very well and the first harvest

    yieled a good quality and quantity crop.

    Foto 10-11

    Foto 12-15

  • 8/14/2019 Nusakambangan Reforestation Project Report english version.pdf

    6/12

    YAYASAN SOSIAL BINA SEJAHTERAGedungAMNLt.4, Jl. Kendeng307Sidanegara, Cilacap53223. JawaTengah INDONESIANPWPNo. 01-245-092.0-522.000 - KEPMENHUKUMDANHAMRI NO. AHU-3098AH.01.04.Tahun2011

    Tel.Fax. +62-282-5070004 E-Mail:[email protected]:www.ysbs.or.id

    Narrative Project Report of Reforestation Nusakambangan Island -YSBS | 6

    Pics 16 - 18 show the Palawija which grew very well and gave the farmers the successful way out to

    overcome the problem due to the Paddi Gogo failure.

    3) The Harvest

    The Palawija Harvest helped by the Foundation

    Corn 7,5 ton July 2011

    Kindey Beans 6 ton July 2011

    Green Beans 6 ton July 2011

    Foto 16-18

    Pics 19- 22 show the harvest of Corn and

    beans.

    Pic 23. A farmer thank Father Charlie (the

    Foundation) for the donation which are corn

    seeds, kidney bean seed, and green bean seeds

    that have helped them from the Paddi Gogo

    failure.

    Foto 19-22

    Foto 23

  • 8/14/2019 Nusakambangan Reforestation Project Report english version.pdf

    7/12

    YAYASAN SOSIAL BINA SEJAHTERAGedungAMNLt.4, Jl. Kendeng307Sidanegara, Cilacap53223. JawaTengah INDONESIANPWPNo. 01-245-092.0-522.000 - KEPMENHUKUMDANHAMRI NO. AHU-3098AH.01.04.Tahun2011

    Tel.Fax. +62-282-5070004 E-Mail:[email protected]:www.ysbs.or.id

    Narrative Project Report of Reforestation Nusakambangan Island -YSBS | 7

    4) Instructions for the Non Worker People in Nusakambangan Island

    To maintain the security and the success of the reforestation project in Nusakambangan

    Island, two years before ( in 2009 )Nusakambangan Prison authority issued instructions for

    settlers/non worker people around the Nusakambangan Prison area. There are 5 ( five )

    prohibitions in that instructions that should be obeyed by all non workers people in the area,

    e.g.:

    a) Prohibition to change the function and mission of Nusakambangan forest,b) Prohibition to log the natural trees or planted trees,c) Prohibition to open a new area/settlement,d) Prohibition to sell or buy land/farmer area, ande) Prohibiton to hunt.

    The settlers/farmers who are being trained by the Foundation have always obeyed those five

    prohibitions.

    Unfortunately, those instructions are only directed to the non worker people in

    Nusakambangan area. Some problems still comes up so far, such as there are still timber-

    thieves and hunters who come from outside the Nusakambangan area (they are not the people

    who live in Nusakambangan Island).

    Foto 24

  • 8/14/2019 Nusakambangan Reforestation Project Report english version.pdf

    8/12

    YAYASAN SOSIAL BINA SEJAHTERAGedungAMNLt.4, Jl. Kendeng307Sidanegara, Cilacap53223. JawaTengah INDONESIANPWPNo. 01-245-092.0-522.000 - KEPMENHUKUMDANHAMRI NO. AHU-3098AH.01.04.Tahun2011

    Tel.Fax. +62-282-5070004 E-Mail:[email protected]:www.ysbs.or.id

    Narrative Project Report of Reforestation Nusakambangan Island -YSBS | 8

    5) Planting the SpayingThe Reforestation Project managed by the Foundation of the Bringing About of the

    Prosperity and Good Will in Solok Jero area, Nusakambangan Island has shown a satisfying

    improvement. Tumpangsari system works very well, (warga binaan) the farmers can harvest

    and the indigenous plants have grown very well. These following pictures show some trees

    being planted, namely Jabon trees, have grown very well.

    Pics 25 - 26 show the young indigenous trees (managed to grow well)

    6) Spectacles/ProblemsThe settlers/farmers in Solok jero who are trained by the foundation have some roles. Besides

    as the pioneers who plan the indigenous plants, they also help the forest police to guard the

    Nusakambangan forest from the timber thieves. As a result, sometimes they have a threat

    from the timber thieves. Mr. Memet, the Foundations coordinator of the reforestation

    project, is one of those who have ever been threatened by the timber thieves, because he

    helped the police to catch the thieves. To protect the farmers from the threat, the Foundation

    asked for help from the Marines who post in Klaces, Nusakambangan.

    7) Advisorying and Supptoring for The Farmers

    Foto 25-26

    Foto 27-28

    Pics 27-28 Mr. Memet and the Marines are exchanging the mobile numbers to communicate in case of the

    threats or other dangerous criminal actions.

  • 8/14/2019 Nusakambangan Reforestation Project Report english version.pdf

    9/12

    YAYASAN SOSIAL BINA SEJAHTERAGedungAMNLt.4, Jl. Kendeng307Sidanegara, Cilacap53223. JawaTengah INDONESIANPWPNo. 01-245-092.0-522.000 - KEPMENHUKUMDANHAMRI NO. AHU-3098AH.01.04.Tahun2011

    Tel.Fax. +62-282-5070004 E-Mail:[email protected]:www.ysbs.or.id

    Narrative Project Report of Reforestation Nusakambangan Island -YSBS | 9

    The Foundation not only gave donations in the form of seeds and other farming material, but

    also a training, educational meeting, and discussion on finding solution on how to send their

    children to school for a better future than just farming in Nusakambangan Island. Therefore,the Foundation regularly has a meeting with the farmers.

    The following pictures show Father Charlie, OMI, is discussing with the farmers on the

    possibilities of their children going to schools managed by the Foundation with the

    scholarship from the Foundation. Two schools which are promising enough among others

    are: SMK (Vocational School) and Akademi Maritime Nusantara (Nusantara Maritime

    Academy). Both have proved to enable the graduates to get jobs quicker with a very well

    payment. In this case, they can help the parents in Nusakambangan Island.

    Pic 29. Father Charlie is discussing with the farmers about the education for their children.

    8) The Coordination Meeting with The Wardens of Batu Nusakambangan Prison.The Reforestation Project in Nusakambangan Island can only work well if the security is well

    guaranteed. Therefore, the existence of Warden Squad who work hand in hand with the

    Foto 29

  • 8/14/2019 Nusakambangan Reforestation Project Report english version.pdf

    10/12

    YAYASAN SOSIAL BINA SEJAHTERAGedungAMNLt.4, Jl. Kendeng307Sidanegara, Cilacap53223. JawaTengah INDONESIANPWPNo. 01-245-092.0-522.000 - KEPMENHUKUMDANHAMRI NO. AHU-3098AH.01.04.Tahun2011

    Tel.Fax. +62-282-5070004 E-Mail:[email protected]:www.ysbs.or.id

    Narrative Project Report of Reforestation Nusakambangan Island -YSBS | 10

    people in keeping the security is also urgent. The Foundation always makes coordination and

    regularly has a meeting with the squad to consolidate the forest security and the farmer safety

    in Nusakambangan Island.

    Pics 30-31 show the meeting between Father Charlie with the Batu Prison Squad discussing the coordination

    with the farmer to catch the timber thieves. One gang has been arrested and is waiting for the trial.

    9) The Committment for the FutureThe Foundation Reforestation Project, especially in Solok Jero area, has just been started.

    From the evaluation of the first period we can conclude that the Reforestation Project is

    showing a satisfying progress. Even some of the indigenous trees has grown more than 2

    (two) meters tall. On the other hand, due to the harvest of Palawija and fruit trees, the farmers

    become more enthusiastic to succeed the big Reforestation Project in Nusakambangan Island.

    Up to the moment, there are 7 hectares of the farmers land which still have not been planted

    with the indigenous plants (see the pic 32 below). This is because of the dry season which

    makes it unable to plant the indigenous trees. The planting will be done as soon as the wet

    season comes; the wet season is predicted to start in September.

    Foto 30-31

  • 8/14/2019 Nusakambangan Reforestation Project Report english version.pdf

    11/12

    YAYASAN SOSIAL BINA SEJAHTERAGedungAMNLt.4, Jl. Kendeng307Sidanegara, Cilacap53223. JawaTengah INDONESIANPWPNo. 01-245-092.0-522.000 - KEPMENHUKUMDANHAMRI NO. AHU-3098AH.01.04.Tahun2011

    Tel.Fax. +62-282-5070004 E-Mail:[email protected]:www.ysbs.or.id

    Narrative Project Report of Reforestation Nusakambangan Island -YSBS | 11

    Pic 32 shows the land which is ready to be planted with the indigenous plants..

    As committed from the beginning, the Foundation of the Bringing About of the Prosperity

    and Good Will still commits to give 1(one) million rupiahs to every farmer who succeeds to

    plant the indigenous plant and fruit trees in their land. Hopefully with that money they can

    cultivate more arid savanna to be planted with the indigenous plants and the fruit trees with

    the Tumpang Sari system so that the Reforestation widens. In that Reforestation area, it is

    forbidden to plant productive plants, but only the indigenous plants and fruit trees. The

    farmer/people are not allowed to cut or log the trees. They can only harvest the fruits from the

    trees.

    On Thursday, 4 August 2011, after the meeting on The Uncontrolled Forest Loggingespecially Albiso Trees in Nusakambangan Island, which was held in Cilacap Districts

    Meeting Room, we made a discussion with the Forest Police on working together to support

    the indigenous plants seedling in Solok Jero. The result of the discussion was the Forest

    Police was willing to guide the farmers to find the seed in the reservation forest and train the

    farmer on how to propagate the seedlings properly in such a way that it produces the high

    Foto 32

  • 8/14/2019 Nusakambangan Reforestation Project Report english version.pdf

    12/12

    YAYASAN SOSIAL BINA SEJAHTERAGedungAMNLt.4, Jl. Kendeng307Sidanegara, Cilacap53223. JawaTengah INDONESIANPWPNo. 01-245-092.0-522.000 - KEPMENHUKUMDANHAMRI NO. AHU-3098AH.01.04.Tahun2011

    Tel.Fax. +62-282-5070004 E-Mail:[email protected]:www.ysbs.or.id

    Narrative Project Report of Reforestation Nusakambangan Island -YSBS | 12

    quality indigenous trees. Based on our data, there are 170.000 indigenous seedlings in the

    pollybags which are ready to be planted in the wet season.

    CONCLUSION

    As the conclusion, we can inform that the Reforestation Project which is done together with

    the farmers in Solok Jero Nusakambangan has shown a very satisfying result. Regarding

    about the importance of Reforestation for human life, we are committed to keep on doing the

    Reforestation Project. We are grateful that the same commitment also happens to Central

    Java Province Law and Human Rights Department, Government and parties involved.

    This is the report that we can provide so far. We really appreciate and deeply thank for all thesupport and partnership that have been given so far and in the future (sm).