numi transmission line (tl) review wbs 1.1.3 power supply system transmission line (tl) review nancy...

21
NUMI Transmission Line (TL) Review WBS 1.1.3 Power Supply System Transmission Line (TL) Review Nancy Grossman FNAL April 23, 2003

Upload: cornelius-ross

Post on 05-Jan-2016

225 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: NUMI Transmission Line (TL) Review WBS 1.1.3 Power Supply System Transmission Line (TL) Review Nancy Grossman FNAL April 23, 2003

NUMI

Transmission Line (TL) Review

WBS 1.1.3 Power Supply System

Transmission Line (TL) Review

Nancy Grossman

FNAL

April 23, 2003

Page 2: NUMI Transmission Line (TL) Review WBS 1.1.3 Power Supply System Transmission Line (TL) Review Nancy Grossman FNAL April 23, 2003

NUMI

Internal NuMI ReviewApril 23, 2003

Transmission Line ReviewPage 2Outline

Overview & Specifications (N. Grossman, 10’) Scope of review General Layout & Overall Specifications Schedule, Concerns

Response to Recommendations (2/26/02 review) (N. Grossman, 10’)

Testing at MI8 (J. Hylen, 15’) Remote clamp & joint testing so far Future plans

Ionization Calculations (J. Hylen, 10’)

Cooling Calculations (A. Stefanik, 10’)

TL through Block & Beyond Design/Status (B. Boettinger, 45’) Design (clamps, connection, supports) Heating/cooling (expansion) & Vibration Issues Service Considerations

Page 3: NUMI Transmission Line (TL) Review WBS 1.1.3 Power Supply System Transmission Line (TL) Review Nancy Grossman FNAL April 23, 2003

NUMI

Internal NuMI ReviewApril 23, 2003

Transmission Line ReviewPage 3

Scope and Conceptual Layout:Target Hall Transmission

Material: Aluminum, Dimensions: 12 inches wide by 3/8 inch thick Width: Stripline nominal width is 12 inches, reduce to 8” from below clamp to horns. Gap: Stripline nominal spacing between bars is 3/8 inch, can increase in flex region.

HORN 1 JOINT

HORN 2 JOINTREMOTE CLAMP

REMOTE CLAMP

ROCK WALL BETWEEN PS ROOM AND TARGET HALL- 23’

REMOVABLE Z-BAR

REMOVABLE Z-BAR

REMOVABLE 28’ SECTION

Page 4: NUMI Transmission Line (TL) Review WBS 1.1.3 Power Supply System Transmission Line (TL) Review Nancy Grossman FNAL April 23, 2003

NUMI

Internal NuMI ReviewApril 23, 2003

Transmission Line ReviewPage 4

Scope and Conceptual Layout:Target Hall Transmission

Page 5: NUMI Transmission Line (TL) Review WBS 1.1.3 Power Supply System Transmission Line (TL) Review Nancy Grossman FNAL April 23, 2003

NUMI

Internal NuMI ReviewApril 23, 2003

Transmission Line ReviewPage 5Scope/Charge to Group

Scope Includes: Transmission Line design from joint/remote clamp to connection at capacitor bank

Electrical Isolation Considerations Heating/cooling (thermal expansion) Vibration

Stands & support structures to hold transmission line in place Wedge clamps in the transmission line block Support stands in the target hall Three point support structure in 24” round penetration from hall to PS room

Service Considerations Removing the section through the wall Horn replacement

Cover to protect transmission line – to be designed, simple slanted sheet metal Charge:

Look at overall design. Consider QA, longevity, ESH issues. Comment back to [email protected] within a week.

Page 6: NUMI Transmission Line (TL) Review WBS 1.1.3 Power Supply System Transmission Line (TL) Review Nancy Grossman FNAL April 23, 2003

NUMI

Internal NuMI ReviewApril 23, 2003

Transmission Line ReviewPage 6

MI-8 Fingers, Remote Clamp

Remote clamp plugged in @ MI-8

Horn 1 joint/electrical plug @ MI-8

Routine pulsing of prototype horn 1, production horn 1 joint, remote clamp underway: ~370,000 pulses to date.

Goal is 1 million pulses, 1/2 offset/flexed

Page 7: NUMI Transmission Line (TL) Review WBS 1.1.3 Power Supply System Transmission Line (TL) Review Nancy Grossman FNAL April 23, 2003

NUMI

Internal NuMI ReviewApril 23, 2003

Transmission Line ReviewPage 7

Joints and Remote Clamp

Horn 2 joint in machine shop (now done)

Horn 1 joint, remote clamp at MI-8

Page 8: NUMI Transmission Line (TL) Review WBS 1.1.3 Power Supply System Transmission Line (TL) Review Nancy Grossman FNAL April 23, 2003

NUMI

Internal NuMI ReviewApril 23, 2003

Transmission Line ReviewPage 8

Overall Specifications/Concerns

1. Lifetime: Part of stripline connected to horn will be replaced each time a horn is

replaced, ~>1 year. Part of stripline within stripline block (includes clamp) does not have to be

replaced every time a horn is replaced, but we will most likely have a spare just in case.

Lifetime of NuMI ~ 10 years2. Radiation Environment such that ceramics must be used near the beam, but

not necessary above the module/T-blocks.

Ceramics spacers from horn to top of module/block G-10 spacers used beyond that as insulators

3. Vibration, keep to a minimum everywhere. Biggest horn vibration is from stripline (MI8 measurements) Not near horn natural frequencies (200 Hz), damping times short wrt rep-rate Clamp every 12” in target hall

Pulsed for about 9.5 millions pulses at MI-8 (non-joint portion of transmission line) with no problems – clamping every 12”

More on recent vibration measurements from Jim.

Page 9: NUMI Transmission Line (TL) Review WBS 1.1.3 Power Supply System Transmission Line (TL) Review Nancy Grossman FNAL April 23, 2003

NUMI

Internal NuMI ReviewApril 23, 2003

Transmission Line ReviewPage 9

Overall Specifications/Concerns

4. Cooling Target chase cooled by ~24,000 cfm flowing in the beam direction in the

horn region and back in the opposite direction between the top of the T-blocks and the concrete cap.

Beam heating: ~183 KW/m3 (transmission line near the beam) TL Electrical heating: ~27 KW/m3 (flex joint number) Assume air cooling from target chase is sufficient (A. Stefanik talk) Want air flow through TL shield block from top of module to horn (this air

flow cools stripline) Air dam is needed at the H-block cover between the module and the

stripline along the target hall wall (intended to contain air-borne radiation).

5. Service Considerations: Must not block survey holes in T-blocks just off module ends, need direct

vertical line of sight. Two removable sections to allow removal of section through the wall (28’). Removable “z-bar”s at top of module/block. Allows replacement of horns.

Page 10: NUMI Transmission Line (TL) Review WBS 1.1.3 Power Supply System Transmission Line (TL) Review Nancy Grossman FNAL April 23, 2003

NUMI

Internal NuMI ReviewApril 23, 2003

Transmission Line ReviewPage 10

Transmission Line: Through the Block

Page 11: NUMI Transmission Line (TL) Review WBS 1.1.3 Power Supply System Transmission Line (TL) Review Nancy Grossman FNAL April 23, 2003

NUMI

Internal NuMI ReviewApril 23, 2003

Transmission Line ReviewPage 11

Transmission Line: Through the Block

( figure slightly out of date )

Page 12: NUMI Transmission Line (TL) Review WBS 1.1.3 Power Supply System Transmission Line (TL) Review Nancy Grossman FNAL April 23, 2003

NUMI

Internal NuMI ReviewApril 23, 2003

Transmission Line ReviewPage 12

Transmission Line: Through the Block

Page 13: NUMI Transmission Line (TL) Review WBS 1.1.3 Power Supply System Transmission Line (TL) Review Nancy Grossman FNAL April 23, 2003

NUMI

Internal NuMI ReviewApril 23, 2003

Transmission Line ReviewPage 13

Transmission Line: Beyond the Shielding

Page 14: NUMI Transmission Line (TL) Review WBS 1.1.3 Power Supply System Transmission Line (TL) Review Nancy Grossman FNAL April 23, 2003

NUMI

Internal NuMI ReviewApril 23, 2003

Transmission Line ReviewPage 14

Transmission Line: Beyond the Shielding

Page 15: NUMI Transmission Line (TL) Review WBS 1.1.3 Power Supply System Transmission Line (TL) Review Nancy Grossman FNAL April 23, 2003

NUMI

Internal NuMI ReviewApril 23, 2003

Transmission Line ReviewPage 15

Transmission Line: Beyond the Shielding

Page 16: NUMI Transmission Line (TL) Review WBS 1.1.3 Power Supply System Transmission Line (TL) Review Nancy Grossman FNAL April 23, 2003

NUMI

Internal NuMI ReviewApril 23, 2003

Transmission Line ReviewPage 16

Transmission Line: Through the Rock Wall

Page 17: NUMI Transmission Line (TL) Review WBS 1.1.3 Power Supply System Transmission Line (TL) Review Nancy Grossman FNAL April 23, 2003

NUMI

Internal NuMI ReviewApril 23, 2003

Transmission Line ReviewPage 17

Transmission Line: Through the Rock Wall

Page 18: NUMI Transmission Line (TL) Review WBS 1.1.3 Power Supply System Transmission Line (TL) Review Nancy Grossman FNAL April 23, 2003

NUMI

Internal NuMI ReviewApril 23, 2003

Transmission Line ReviewPage 18

Response to Recommendations: Horn PS/TL Review (August 2001)

Consider using a dynamic type fastener (e.g., spiralock nut) in the clamp joints and stripline support brackets. This is being done, except in the block region where it is tack-welded to the

fasteners.

Consider measuring bolt preload in critical connections by measuring bolt stretch as opposed to bolt torque. Not sure how to implement this – ideas?

Consider longitudinal damping along the TL section along the Target Hall wall to damp out possible undamped vibrations from electrical pulsing. Using polyeruthane isolators and swinging end-links (see Bill’s talk).

Worry about scratching the silver-plating off the TL “fingers” when clamping/unclamping. Have seen no damage in the silver-plating on the TL fingers out at MI-8 and

they have been connected and disconnected a few times. (more from Jim)

Page 19: NUMI Transmission Line (TL) Review WBS 1.1.3 Power Supply System Transmission Line (TL) Review Nancy Grossman FNAL April 23, 2003

NUMI

Internal NuMI ReviewApril 23, 2003

Transmission Line ReviewPage 19

Response to Recommendations:TL, Remote Clamp, TL Block Review (Feb. 2002)

Flex Joint Comments (joint with slits) No longer using a joint with slits. ANSYS shows we can get sufficient

flexibility with the non-slitted design. Single strip force tests agree with the ANSYS analysis. Testing at MI-8 of the horn1 joint is going well. More from Jim – not specifically part of this review.

Suggest quantitative measurements be made at MI-8 (deflection at specific points, resonant frequencies, etc.) to compare to ANSYS calculations (and any other calculations) and thus support longevity estimates. We are making some quantitative measurements at MI-8 and will compare

measurements with predictions– Jim will talk about this. Concerns abut a tight testing schedule at MI-8 which might be hard to meet if

problems are encountered. Agree. We have encountered problems, testing is tight, and we hope to make it

(more from Jim). Can delay installation of horn PS & continue testing longer. Concerns with human resources – lack of.

This is a constant battle we continue to fight. Suggest pre-assemble entire setup (power supply to horns) at MI-8.

We will do this to the extent that we can.

Page 20: NUMI Transmission Line (TL) Review WBS 1.1.3 Power Supply System Transmission Line (TL) Review Nancy Grossman FNAL April 23, 2003

NUMI

Internal NuMI ReviewApril 23, 2003

Transmission Line ReviewPage 20

Schedule & Concerns

Schedule: MI-8 testing until Horn PS removed for installation.

Test pulsing of horn 1 and horn 2 on test stand.

Task Current ProjectionFNAL Baseline

Date (3/04 running)Complete Design & Drawings of TL 7/15/03 8/15/03

Complete Installation of Horn PS in PS Room (DOE MS L-2-17, 9/1/04) 10/6/03 2/16/04Receipt of all TL parts 11/25/03 3/19/04Start TL Installation 4/14/04 6/21/04Complete TL Intstallatoin 5/11/04 7/21/04Start Horn System Electrical Checkout 10/18/04 11/12/04

Page 21: NUMI Transmission Line (TL) Review WBS 1.1.3 Power Supply System Transmission Line (TL) Review Nancy Grossman FNAL April 23, 2003

NUMI

Internal NuMI ReviewApril 23, 2003

Transmission Line ReviewPage 21

Schedule & Concerns

Specific Concerns: Making sure all bolts on the TL clamps are tighten (and remain tightened)

Checkout checklist item Periodic checks in Target Hall?

QA that clamps are put together correctly If doesn’t look like it is going together well, stop and ask expert. Alignment rods at removable sections

General Concerns: Resources (manpower)

Engineering/drafting to get the design done and parts ordered/made Technicians to get it assembled and installed

Fitting it all in with the target hall shield block installation & Module installation Concerns about damaging the TL parts Final connections of the TL to the horns/PS are near the critical path

The transmission line (and joint) have always been underestimated in their complexity (cost, time to make, problems encountered in installation/testing).