nuclear regulatory united states …nuclear regulatory commission (nrc) of its plan to resume...

31
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 December 20, 2017 MEMORANDUM TO: Catherine Haney, Regional Administrator FROM: William B. Jones, Director Division of Construction Oversight SUBJECT: WATTS BAR UNIT 2 CONSTRUCTION LESSONS LEARNED REPORT The Watts Bar 2 Construction Oversight Lessons Learned Working Group has completed the Watts Bar Unit 2 Construction Lessons Learned Review Report. The report, which is enclosed, will be made available to the public via the U.S. Nuclear Regulatory Commission’s Agencywide Documents Access and Management System. Issuance of the report concludes the working group’s actions under its charter. Enclosure: Watts Bar Unit 2 Construction Lessons Learned Report cc: V. McCree, EDO L. Dudes, RII J. Munday, RIl B. Holian, NRR F. Brown, NRC CONTACT: Tomy Nazario, R2/DCO Phone: 240-701-4174

Upload: others

Post on 23-May-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: NUCLEAR REGULATORY UNITED STATES …Nuclear Regulatory Commission (NRC) of its plan to resume construction of WBN2. Shortly thereafter, the NRC staff submitted SECY-07-0096, Possible

UNITED STATESNUCLEAR REGULATORY COMMISSION

REGION II245 PEACHTREE CENTER AVENUE NE, SUITE 1200

ATLANTA, GEORGIA 30303-1257

December 20, 2017

MEMORANDUM TO: Catherine Haney, Regional Administrator

FROM: William B. Jones, DirectorDivision of Construction Oversight

SUBJECT: WATTS BAR UNIT 2 CONSTRUCTION LESSONS LEARNED REPORT

The Watts Bar 2 Construction Oversight Lessons Learned Working Group has completed theWatts Bar Unit 2 Construction Lessons Learned Review Report. The report, which is enclosed,will be made available to the public via the U.S. Nuclear Regulatory Commission’s AgencywideDocuments Access and Management System. Issuance of the report concludes the workinggroup’s actions under its charter.

Enclosure:Watts Bar Unit 2 Construction Lessons Learned Report

cc: V. McCree, EDOL. Dudes, RIIJ. Munday, RIlB. Holian, NRRF. Brown, NRC

CONTACT: Tomy Nazario, R2/DCOPhone: 240-701-4174

Page 2: NUCLEAR REGULATORY UNITED STATES …Nuclear Regulatory Commission (NRC) of its plan to resume construction of WBN2. Shortly thereafter, the NRC staff submitted SECY-07-0096, Possible

C. Haney 2

Memorandum to Catherine Haney from William B. Jones

SUBJECT: WATTS BAR UNIT 2 CONSTRUCTION LESSONS LEARNED REPORT

PUBLICLY AVAILABLE NON-PUBLICLY AVAILABLE 0 SENSITIVE NON-SENSITIVE

ADAMS APPLICABLE JSUNSI REVIEW COMPLETE ML#___________________

OFFICE tRIl: DCO/CIB3 RIl: DCC

SIGNATURE %i,;;g.NAME I T. Ntario WSJens

DATE rZ/2c/

Page 3: NUCLEAR REGULATORY UNITED STATES …Nuclear Regulatory Commission (NRC) of its plan to resume construction of WBN2. Shortly thereafter, the NRC staff submitted SECY-07-0096, Possible

U.S.NRCUnited States Nuclear Regulatory Cummisson

Protecting People and the Environment

WATTS BAR NUCLEAR PLANT UNIT 2CONSTRUCTION LESSONS LEARNED

October 31, 2017

Enclosure

Page 4: NUCLEAR REGULATORY UNITED STATES …Nuclear Regulatory Commission (NRC) of its plan to resume construction of WBN2. Shortly thereafter, the NRC staff submitted SECY-07-0096, Possible

Table of Contents

Executive Summary.iii

Acronyms iv

I. Background 1

II. Scope and Methodology 4

Ill. Lessons Learned 5

IV. Recommendations 12

V. Attachment A-i

Page 5: NUCLEAR REGULATORY UNITED STATES …Nuclear Regulatory Commission (NRC) of its plan to resume construction of WBN2. Shortly thereafter, the NRC staff submitted SECY-07-0096, Possible

Executive Summary

This report summarizes the Watts Bar Nuclear Plant Unit 2 (WBN2) Construction LessonsLearned project. The lessons learned project involved contributions from senior staff, interviewsof staff involved with the reactivation of WBN2, and review of previous lessons learned efforts.The lessons learned contained in this report highlight actions that contributed to theeffectiveness of program implementation and enhancements for future activities, consistent withthe U.S. Nuclear Regulatory Commission’s (NRC’s) Principles of Good Regulation(Independence, Openness, Efficiency, Clarity, and Reliability). This report also provides acomparison that will inform the development of prospective inspection programs and identifyareas for followup.

This report groups the lessons learned into the areas of (1) planning, scheduling, and reporting,(2) inspection program staffing, (3) communications, and (4) construction to operationstransition. Specific lessons and recommendations range from improvements to existinginspection program guidance to the use of tabletop exercises to identify potential gaps,strengths, and focus areas.

This report documents the following additional lessons and recommendations:

• The agency’s ability to adapt to change throughout all phases of a project is key to thesuccessful completion of inspection and licensing objectives.

• Early inspection program development by experienced and knowledgeable staff isvaluable to the inspection effort.

• Staff training and selections for first time and one-of-a-kind projects are an essentialelement to regulatory oversight effectiveness.

• Stakeholder engagement during all phases of a project assist with keeping everyoneinformed and serve as a platform for open communication.

Although this report refers to a number of lessons and the corresponding recommendations as“proposed,” several recommendations have been implemented and the associated actions havebeen completed. In other cases, the lesson or the recommendation may not apply, in whichcase a justification is provided.

In summary, this report captures noteworthy lessons learned from the reactivation of WBN2.The consideration and potential implementation of these lessons learned and recommendationswill serve as a principal component to the development of future NRC programs. Moreover,these lessons will continue to support the NRC’s commitment to continuous improvement.

III

Page 6: NUCLEAR REGULATORY UNITED STATES …Nuclear Regulatory Commission (NRC) of its plan to resume construction of WBN2. Shortly thereafter, the NRC staff submitted SECY-07-0096, Possible

ACRONYMS

CFR Code of Federal RegulationsADAMS Agencywide Documents Access and Management SystemCIPIMS Construction Inspection Program Information Management SystemDCO Division of Construction OversightIMC inspection manual chapterIP inspection procedureIP&S inspection plan and schedulingITAAC inspections, tests, analyses, and acceptance criteriaNGO nongovernmental organizationNRC U.S. Nuclear Regulatory CommissionNRO Office of New ReactorsNRR Office of Nuclear Reactor RegulationOEDO Office of the Executive Director for OperationsORAl Operational Readiness Assessment TeamRIl Region IIROP Reactor Oversight ProcessSRI senior resident inspectorTVA Tennessee Valley AuthorityWBN1 Watts Bar Nuclear Plant Unit 1WBN2 Watts Bat Nuclear Plant Unit 2WRAG WBN2 Review and Assessment Group

iv

Page 7: NUCLEAR REGULATORY UNITED STATES …Nuclear Regulatory Commission (NRC) of its plan to resume construction of WBN2. Shortly thereafter, the NRC staff submitted SECY-07-0096, Possible

I. BACKGROUND

The reactivation of Watts Bar Nuclear Plant Unit 2 (WBN2) has a unique licensing history andregulatory framework. The Watts Bar site consists of two Westinghouse-designedpressurized-water reactors, owned and operated by the Tennessee Valley Authority (TVA).TVA received a construction permit for Watts Bar Nuclear Plant Unit 1 (WBNJ) and WBN2 in1973 under Title 10 of the Code of Federal Regulations(l0 CFR) Part 50, ‘Domestic Licensingof Production and Utilization Facilities.” In 1985, TVA stopped construction on WBN1 andWBN2 because of multiple construction quality issues. TVA completed WBN1 in 1995, but ithas conducted very little work specific to WBN2 since 1985.

In 2007, TVA informed the U.S. Nuclear Regulatory Commission (NRC) of its plan to resumeconstruction of WBN2. Shortly thereafter, the NRC staff submitted SECY-07-0096, “PossibleReactivation of Construction and Licensing Activities for the Watts Bar Nuclear Plant Unit 2,”dated June 7, 2007 (Agencywide Documents Access and Management System (ADAMS)Accession No. ML071220492) to the NRC Commission. The SECY paper discussed the staff’sapproach for possible reactivation of licensing and construction inspection activities for WBN2.The Commission approved the staff’s recommendations for the licensing and inspection ofWBN2 in Staff Requirements Memorandum (SRM)-SECY-07-0096, dated July 25, 2007(ADAMS Accession No. ML072060688). In keeping with its approach, the NRC staff developeda site-specific inspection program contained within Inspection Manual Chapter (IMC) 2517,“WBN2 Construction Inspection Program.” This IMC delineates the policy for the conduct ofinspections at WBN2 during construction and startup under the following IMCs:

• IMC 2512, “Light Water Reactor Inspection Program—Construction Phase”

• IMC 2513, “Light Water Reactor Inspection Program—Preoperational Testing andOperational Preparedness Phase”

• IMC 2514, “Startup Testing Inspections”

IMC 2517 also defines the roles and responsibilities for Region II (RIl) and NRC Headquarters.

The NRC reviewed all historical documentation to determine the status of the IMC 2512inspection procedures (IPs) in effect at the time TVA stopped construction and to confirm that allissues and inspection requirements would be completed for WBN2. The NRC staff called thiseffort the reconstitution process. The staff documented the results of the reconstitution processin Inspection Report 05000391/2009602, dated April 30, 2009 (ADAMS AccessionNo. ML091210420), and used the results to identify areas that required additional inspections.

During the early stages of the NRC’s oversight of WBN2, RIl coordinated and workedextensively with the WBN2 Special Projects Branch in the NRC Office of Nuclear ReactorRegulation (NRR). This coordination resulted in the establishment of an oversight group knownas the WBN2 Review and Assessment Group (WRAG), which consisted of NRC seniormanagers from Rh and NRC Headquarters, the cognizant Rh branch chief, NRR senior projectmanager, and senior resident inspector. The senior managers in NRR and RIl constructionorganizations co-chaired the WRAG.

The WRAG proved to be a key process in integrating licensing and inspection activities with thelicensee’s schedule and focused the NRC’s management oversight on complying with the

1

Page 8: NUCLEAR REGULATORY UNITED STATES …Nuclear Regulatory Commission (NRC) of its plan to resume construction of WBN2. Shortly thereafter, the NRC staff submitted SECY-07-0096, Possible

Commission’s directions in SRM-SECY-07-0096. The WRAG ensured an effective integrationof licensing and inspection activities, which enabled NRC staff to be adequately prepared tosupport meetings and hearings.

To effectively manage the IMC 2517 inspection program, RIl developed a site-specificinspection plan and scheduling (IP&S) tool to complete the inspections required by IMC 2512,IMC 2513, and IMC 2514$ open temporary instructions (TIs); and open NRC genericcommunications such as generic letters and bulletins. The IP&S tool also facilitated theaccounting, tracking, and completion of items that resulted from the reconstitution of theinspection program. The tool assisted with and provided sufficient flexibility for reschedulinginspections to accommodate applicant schedule changes.

The NRC staff reviewed inspection activities, particularly near the completion of construction, ona nearly daily basis to establish when, where, and what type of inspection resources wereneeded. The NRC assigned additional resident inspectors to the site, and regional inspectorsremained on site for weeks to several months during construction, preoperational testing, andstartup testing. As an example, the agency used the former WBN1 senior resident inspector toassist in the development of other inspectors and with WBN2 operational knowledge transfer.This helped maintain project continuity and train other inspectors during the preoperational andstartup periods. Additionally, the continued use of rotational resident inspector positions helpedmaintain adequate levels of staffing at the site. The NRC regional offices, the NRC TechnicalTraining Center (TTC), and NRC Headquarters provided support during the construction periodand through startup testing. IMC 2517 governs the qualifications for individuals performingthese different types of inspections.

As the project neared completion, the WRAG provided frequent communication on the status ofWBN2 and eliminated the need for the generic readiness IP 94300, “Status of Plant Readinessfor an Operating License,” 90-day status report, and subsequent status report updates. TheNRC issued IP 94302, “Status of WBN2 Readiness for an Operating License,” specific toWBN2, which provided a list of open items to be tracked and resolved following issuance of theoperating license (ADAMS Accession No. ML15288A305). IP 94302 provided updatedguidance to support reporting the status of WBN2 readiness for an operating license. Thisguidance allowed for a detailed understanding of the outstanding and completed inspections,the type (discipline), and the inspectors needed to accomplish the remaining work. The NRCmade the list of open items available to the publicly (via ADAMS) and provided the basis forRIl’s assessment of WBN2 readiness for an operating license.

Consistent with the NRC’s value of openness, the agency held numerous public meetingsthrough standing weekly teleconferences, WRAG updates, end-of-cycle meetings,nongovernmental organization (NGO) interactions, and informational meetings. Thesemeetings took place in the NRC Headquarters and RIl offices and in the vicinity of Watts Bar.The NRC held an informational public meeting on March 26, 2015, at a high school in Athens,TN, as construction activities were ending. At the meeting, NRC senior management met withthe public, TVA, and other stakeholders concerning WBN2 and discussed the status of theWBN2 construction project, including major milestones and potential challenges that couldimpact the project schedule. During this meeting, the RIl Regional Administrator and the NRROffice Director addressed the operating license process. The NRC also held a meeting withNGOs earlier that same day.

The NRC developed a detailed transition plan (ADAMS Accession No. ML15096A204) inApril 2015 to support the transition of WBN2 from construction and testing under IMC 2517 to

2

Page 9: NUCLEAR REGULATORY UNITED STATES …Nuclear Regulatory Commission (NRC) of its plan to resume construction of WBN2. Shortly thereafter, the NRC staff submitted SECY-07-0096, Possible

the Reactor Oversight Process (ROP). This transition plan ensured the use of a deliberateapproach to transition each individual ROP cornerstone. It also assigned responsibilitiesresolving any relevant open issues to ensure that each cornerstone was ready for NRCmonitoring using the ROP before final transition (i.e., performance indicators and inspections).

The ROP and IMC 2517 provided the guidance for the inspection and assessment of thelicensee’s performance through preoperational and startup testing and into full-poweroperations. The RH construction organization continued to participate in WBN2 briefings untilthe followup items identified in the IP-94302 letter were closed. The Division of ReactorProjects assumed the lead oversight responsibility following issuance of the operating licenseand established a communication protocol that included a standardized form of upcomingactivities, challenges, and resource needs. The Division shared this communication protocolwithin Ru and with the cognizant headquarters offices, including the Office of the ExecutiveDirector for Operations fOEDO). OEDO also used this tool to update the Commission onongoing activities at WBN2.

On May 26, 2015, the Commission issued SRM-SECY-15-0068, “Watts Bar Nuclear Plant,Unit 2—Review Status and Authority of the Director of the Office of Nuclear Reactor Regulationfor Operating License Issuance” (ADAMS Accession No. ML15146A213). The Commissionapproved the staffs recommendation to grant the NRR Office Director the authority to issueWBN2 a full-power operating license. On October 22, 2015, the NRC issued the operatinglicense (ADAMS Accession No. ML1 525 1A587). After issuance of the operating license, theNRC disbanded the WRAG, and NRC oversight of WBN2 transitioned to the ROP for operatingreactors.

3

Page 10: NUCLEAR REGULATORY UNITED STATES …Nuclear Regulatory Commission (NRC) of its plan to resume construction of WBN2. Shortly thereafter, the NRC staff submitted SECY-07-0096, Possible

II. SCOPE AND METHODOLOGY

On March 8,2017, the NRC Rh staff conducted and documented an initial lessons learned effortin a memorandum from William B. Jones, Director, Division of Construction Oversight (DCO) inRH to Chris Miller, Director, Division of Inspection and Regional Support (DIRS) in NRR. Rhstaff issued the WBN2 lessons learned memorandum to capture the staff’s initial insights intothe implementation of the WBN2 oversight program. The staff identified four general areas intowhich the lessons were categorized: organization, construction inspection, testing, andtransition. The associated items provided an outline of the types of issues the staff andmanagement addressed to accomplish the inspection and assessment of WBN2 duringconstruction and transition to commercial operation. The attachment to this report includes thespecific items identified in the memorandum.

In June 2017, RIl established an interoffice working group made up of senior staff from NRRand the Rh inspection office to further assess the lessons learned from WBN2. The workinggroup transmitted its charter via memorandum dated June 26, 2017 (ADAMS AccessionNo. ML17192A031). The working group focused on aspects of the WBN2 reactivation, includingthe transition from construction to operations. The working group used the March 8, 2017,lessons learned memorandum as a basis for this report.

On August 9—10, 2017, the working group met to discuss WBN2 lessons learned. The groupreviewed several documents, combined lessons learned from previous efforts, and identifiedlessons learned that could be retained and disseminated in a manner that would maximize theirbenefits and usefulness to the staff. Section III of this report describes the following fourgeneral lesson learned areas:

• Lesson Area 1: Planning, Scheduling, and Reporting• Lesson Area 2: Inspection Program Staffing• Lesson Area 3: Communications• Lesson Area 4: Construction to Operations Transition

The working group developed specific lessons under each general lesson area. Some lessonshave overlapping themes. Section IV of this report further discusses the specificrecommendations and applicability to existing processes such as those covered under10 CFR Part 52, “Licenses, Certifications, and Approvals for Nuclear Power Plants.” This reportconsolidates all the lessons gathered through interviews and other similar efforts, including theMarch 8, 2017, memorandum.

The following individuals contributed to this Watts Bar Plant Unit 2 Construction LessonsLearned report:

• Tomy Nazario, NRC Rh• James Baptist, NRC RhI• Christopher Even, NRC RIl• Jason Eargle, NRC RII• Stephen Campbell, NRC NRR• Phil O’Bryan, NRC NRO

4

Page 11: NUCLEAR REGULATORY UNITED STATES …Nuclear Regulatory Commission (NRC) of its plan to resume construction of WBN2. Shortly thereafter, the NRC staff submitted SECY-07-0096, Possible

III. LESSONS LEARNED

Lesson Area 1: Planning, Scheduling, and Reporting

1 .a Because of the plant’s unique nature and licensing basis, the NRC developedproject-specific procedures and processes for WBN2. For example, the staff developedand issued IMC 2517, “WBN2 Construction Inspection Program,” and IP 37002,“Construction Refurbishment Process—Watts Bar Unit 2.” During the development ofthe IMC and IP, the program office engaged experienced regional inspectors to compileguidance that was mote directly applicable to and specifically designed for theinspectors.

The regional inspectors involved in the IMC and IP development had direct involvementin the restart of the Browns Ferry Nuclear Power Plant and Watts Bar during the 1 980sand 1990s. The authors of the WBN2-specific documents understood the unique historyof Watts Bar and had first-hand knowledge of the licensing basis, technology, and thematerial condition of the plant. They also had an indepth understanding of theinspection program used for WBN1 and how to develop a program that supported theCommission’s approach that employed “the current licensing basis for Unit 1 as thereference basis for the review and licensing of Unit 2,” as stated in SRM-SECY-07-0096.In summary, the participation of experts and knowledgeable staff in the development ofthe inspection program proved valuable, as evidenced by site-specific tailored guidanceand procedures that required minimal future revisions.

Lesson: For first-of-a-kind or unique projects, the engagement of experiencedexperts and knowledgeable staff during the development of guidance documentsproved valuable and resulted in final guidance that was tailored to the uniquelicensing basis of Wafts Bar.

1 .b During the early stages of the WBN2 project, the regional construction organization wasinitially set up to mirror the current operating reactor oversight organizational structure,which distributed the responsibilities to a project management division (Division ofReactor Projects) and an inspection support division (Division of Reactor Safety). Thisdivision of responsibilities introduced additional approval layers and independenttracking of open items. It also resulted in inspection planning, scheduling, and reportingchallenges. Initially, there were varied methods of coordinating inspections becauseinspection assignments were independently assigned, scheduled, and tracked amongdifferent work groups. This inspection planning methodology required resident andproject staff to routinely validate project schedule information to ensure that inspectionswere scheduled accordingly. Moreover, the documentation and reporting of inspectionsvaried, requiring added review efforts by the project managers.

A centralized project management approach was instituted with a single managementchain of command at the project level to address some of the unique inspection planningchallenges. This approach assigned all inspection items to the project managementbranch responsible for project oversight, so that a single point of contact collectivelyassigned, scheduled, and tracked inspection items instead of multiple sources and workgroups. In summary, this approach resulted in a “one stop shop” for inspectionassignments, which contributed to a more structured environment, improved statusupdates, and provided a consistent quality of inspection reports.

5

Page 12: NUCLEAR REGULATORY UNITED STATES …Nuclear Regulatory Commission (NRC) of its plan to resume construction of WBN2. Shortly thereafter, the NRC staff submitted SECY-07-0096, Possible

The centralized project management approach instituted an environment of clearexpectations and development of detailed roles and responsibilities with sufficientauthority, all of which contributed to project success.

Lesson: A centralized project management structure with single managementchain of command, institution of clear expectations, and development of detailedroles and responsibilities with sufficient authority were key to project success.

1 .c As discussed in Section I of this report, the NRC initiated a review of all historicaldocumentation to determine the status of all open items and confirm that all issues hadbeen addressed and inspection requirements would be completed for WBN2. This effortwas known as the reconstitution effort. During the reconstitution effort (2008—2009) forWBN2, the retention of applicable documentation (in accordance with agency guidance)for open items was important to establishing a comprehensive basis for the resumptionof discontinued projects. These open items included legacy items, genericcommunications, allegations, corrective action programs, special programs, andunresolved items. In some cases, the thorough and detailed documentation of thesehistorical open items provided the staff a comprehensive basis during the reconstitutioneffort.

Lesson: Retention of thorough and detailed documentation associated with openitems was important to establishing a comprehensive basis for the resumption ofdiscontinued projects.

I .d In addition to reviewing the documentation of open items during the reconstitution effort,the staff reviewed IFs to determine whether inspection objectives had been satisfied.The staff reviewed historical inspection reports (pre-2008) to determine whether IPsamples had been completed. If inspection sample information was limited orincomplete, the staff made conservative decisions and determined those to beincomplete samples that required further inspection. Examples of such limited orincomplete information included (1) a specific unit identifier for components was notlisted, (2) sufficient detail to provide the basis for completion of IF steps and substepswas lacking, (3) the intent of the top level steps could not be satisfied as documented inthe historical inspection reports, and (4) only partial inspections of WBN2 wereperformed for some systems common to or shared with WBN1.

As the staff developed the WBN2 inspection program (post-2008), the staff implementeda detailed recording and accounting of IP steps and substeps in publicly availableinspection reports. This effort proved beneficial and valuable because of the ability toaccurately track inspection completion in spite of project delays.

Lesson: Progress of the inspection program (including IP samples) should bethoroughly documented and accounted for to ensure completion. Thedocumentation and status of top-level and lower level inspection steps shouldcontain sufficient detail such that they can be reconstituted if the need arises.

1 .e Typically, large-scale construction projects rely on complex schedules. The NRC projectmanagement staff and resident inspectors initiated several compensatory measures togather real-time site activity information and validate schedule information. Thisinformation was then matched up with inspection objectives and schedule site visits. Itwas recognized early on that remotely synchronizing inspection schedules with

6

Page 13: NUCLEAR REGULATORY UNITED STATES …Nuclear Regulatory Commission (NRC) of its plan to resume construction of WBN2. Shortly thereafter, the NRC staff submitted SECY-07-0096, Possible

construction schedules required additional onsite corroboration because the higher levelconstruction schedules did not reflect specific field work inspection activities. Theresident staff was routinely relied upon to validate and corroborate schedule information,causing additional administrative burden on the inspectors. It is important to note thatwhile the NRC was and continues to be focused on the nuclear safety of constructionprojects versus construction schedules, efficiently managing and planning inspectionresources is consistent with one of the five Principles of Good Regulation (Efficiency).For WBN2, onsite NRC representatives continuously evaluated, monitored,corroborated, and modified inspection schedule changes that could affect NRCresources.

Lesson: Use onsite NRC project management to continuously evaluate, monitor,corroborate, and modify inspection schedules in order to minimize impacts toNRC resources and support the agency’s oversight responsibilities.

Lesson Area 2: Inspection Program Staffing

2.a A main component of inspection program implementation was the continuity of staffingon the project and the use of experienced personnel. During the development of theinspection program, the NRC used experienced individuals who participated inconstruction inspection programs in the 1980s and 1990s. Experiences and insightsprovided by these team members greatly contributed to the establishment of a viableprogram and to the completion of the inspection program. The ability to retain key,experienced personnel during different phases of the project provided continuity andstability to the oversight of WBN2 construction.

It is important to note that during the WBN2 project, the NRC underwent severalchanges and transitions in staffing at the management level both in Rh and NRCHeadquarters. Consequently, a contributor to the successful completion of theinspection program was that key staff remained on the project as attrition or staffingchanges took place.

Throughout the WBN2 project, a number of individuals supported inspections on arotational basis, which allowed the agency to develop and train staff who would later beassigned to 10 CFR Part 52 (Advanced Passive (AP) 1000) projects. Given thecomplexity and duration of large-scale projects, it is important to develop and conductdetailed tabletop exercises for project staffing strategies. These strategies shouldinclude the use of individuals with extensive relevant experience, the evaluation oftraining programs, and the involvement of stakeholders.

Lesson: Project staffing within the organization should be commensurate withthe level of activity at the site to provide flexibility, continuity, and assurance thatthe NRC is equipped to handle attrition and transition events, such as projectdelays, turnover of personnel, or reprioritization of agency activities.

2.b During the WBN2 project, some targeted work activities for inspection occurred outsideof normal working hours (dayshift Monday through Friday). Because of the largenumber of construction and testing activities during different phases of the project, bothregional and resident inspectors exercised a large degree of flexibility to successfullycover and inspect around-the-clock work activities. Typically, resident inspectors wereexpected to covet backshift and weekend work activities, as stated in Regional Office

7

Page 14: NUCLEAR REGULATORY UNITED STATES …Nuclear Regulatory Commission (NRC) of its plan to resume construction of WBN2. Shortly thereafter, the NRC staff submitted SECY-07-0096, Possible

Instruction 2251, “Staff Guidance for the Division of Reactor Projects,” and IMC 2515,“Light Water Reactor Inspection Program-Operations Phase.” However, residentguidance and expectations on how to provide backshift and weekend coverage did notinclude or apply to inspectors who were not part of the resident program.

Lesson: Clearly establish and manage expectations and guidance for onsiteinspection presence during construction and testing such that resources areevenly distributed and equitably assigned during backshift and weekend hours.

2.c Resident offices at operating sites and construction sites are composed of a seniorresident inspector (SRI) who performs supervisory duties, resident inspector(s), and anadministrative assistant. Historically, SRIs are solicited for informal input during theselection of their staff; however, they are not directly involved in the selection process.Inspection staff turnover at Watts Bar and specific inspection skill needs changedthroughout the project. The NRC recruited high-performing individuals in an effort tomeet short-term and long-term staffing needs. During the selection process, keypersonnel, including the SRI, were consulted and asked for their input on specific skillneeds. The regional inspection organization found it to be beneficial to engage sitesupervisory staff (i.e., the SRI) and RIl leadership during the selection of candidates forprojects such as WBN2 that required unique skill sets and experience.

Lesson: Engage site supervisory staff (i.e., the SRI) and regional leadershipduring the selection of candidates for projects that require unique skill sets andexperience.

2.d The NRC trained and qualified inspectors to perform WBN2-specific inspections insupport of the WBN2 project. IMC 2517 governs the qualifications for individualsperforming inspections at WBN2, including testing activities, whereas IMC 1252,“Construction Inspector Training and Qualification Program,” dated April 25, 2011(ADAMS Accession No. ML1 10470606), governs the construction inspector qualificationprogram for AP1000 sites under construction (10 CFR Part 52). It is important to notethat IMC 2517 contains qualification guidance for inspections of testing, and IMC 1252also requires the Preoperational and Startup Testing Inspection course (with a focus oninspections, tests, analyses, and acceptance criteria (ITAAC)); however, theIMC 1252-specific course was never developed and IMC 1252 was superseded inAugust 2017 by IMC 1245, “Qualification Program for New and Operating ReactorPrograms,” Appendix C-i 5, “Construction Inspector Technical Proficiency Training andQualification Journal.”

Given the industry’s proposals to build numerous plants with new reactor designs, theagency trained and qualified most construction inspectors under IMC 1252 during thesame time the WBN2 project was taking place. The inspection needs at that timeresulted in a limited number of qualified and experienced individuals available to inspecttesting activities at WBN2. Even though the regional inspection office started out with alimited number of qualified testing inspectors, the efforts to conduct just-in-time trainingand increase the number of qualified testing inspectors contributed to the successfulcompletion of key and targeted testing inspections.

Lesson: Proactive regional training enhancements during the testing phases ofWBN2 contributed to the successful completion of key and targeted testinginspections.

8

Page 15: NUCLEAR REGULATORY UNITED STATES …Nuclear Regulatory Commission (NRC) of its plan to resume construction of WBN2. Shortly thereafter, the NRC staff submitted SECY-07-0096, Possible

Lesson Area 3: Communications

3.a Effective communications during the project were important because of the uniquenature and complex licensing history of WBN2. Stakeholder involvement at all levelsincluded NRC Headquarters, Rh, the public, other government agency representatives,NGOs, the Commission, and the licensee’s organization.

During the early stages of the project, an oversight group (the WRAG) consisting ofsenior personnel from Rh and NRC Headquarters was established. The WRAG’s scopeof activities included the following:

• oversight for overall project planning among the NRC offices

• communication of licensing and technical issues to stakeholders

• conduct of periodic meetings with the applicant to discuss progress of thereactivation effort and identify ways to enhance NRC oversight of the project

• oversight for the established WBN2 Reactivation Communication Plan to ensurethat key stakeholders were informed of the review status

• coordination and oversight of the applicant’s preoperational and startup testing

As the WRAG increased its oversight role, added benefits were noted throughout theproject, such as the WRAG’s ability to coordinate and prioritize resources. The WRAGcontinuously evaluated the project for change, including redirection and curtailment ofspecific inspection and licensing activities as a result of changes in project scope,schedule, and objectives. The WRAG also contributed to periodic internal and externalmeetings, the development of the communication plan, and effective communicationsthrough different phases of the project.

Lesson: The WRAG proved to be a key component of the WBN2 oversight effort.The WRAG closely integrated project priorities and focused the NRC’smanagement oversight.

3.b The NRC held numerous public meetings through recurring weekly teleconferences,WRAG updates, end-of-cycle meetings, NGO interactions, and informational meetings.These meetings took place at the NRC Headquarters office and the RIl office and in thevicinity of Watts Bar. Between 2015 and 2016, the NRC developed an internalcommunications plan for the transition of the plant from construction to operations. Thetransition communication plan outlined the NRC’s criteria for determining readiness forWBN2 to startup. The plan also contained key messages and specific actions during thephases of the transition. The NRC developed another communication plan in 2010 onthe Notice of Violation associated with molded case circuit breakers. Even thoughmultiple communication plans existed throughout the project, one integrated andcomprehensive communication plan may have been easier to update and maintain.Also, the development of a communications plan during the early stages of the projectmay have further enhanced communications at all levels.

Lesson: The use of several detailed communication plans for WBN2 provedvaluable; however, the development of one integrated and comprehensive

9

Page 16: NUCLEAR REGULATORY UNITED STATES …Nuclear Regulatory Commission (NRC) of its plan to resume construction of WBN2. Shortly thereafter, the NRC staff submitted SECY-07-0096, Possible

communication plan would be easier to update and enhance communications atall levels.

Lesson Area 4: Construction to Operations Transition

4.a NRC inspectors witness, first hand, equipment assembly and subsequent testing duringconstruction and component testing of the plant. This afforded inspectors theopportunity to gain unique insights into the equipment history of targeted safety-relatedcomponents, such as safety injection pumps. Construction IPs for WBN2 providedlimited guidance on how to inspect component testing activities. IMC 2517 governspreoperational and startup testing inspections; however, the guidance did notincorporate component testing.

Lesson: Inspections of construction component testing should be incorporatedinto the inspection program and should be used to inform preoperational andstartup testing inspections.

4.b The NRC staff performed an Operational Readiness Assessment Team (ORAT)inspection in accordance with IMC 2514. Before issuance of the operating license atWBN2, IMC 2514 identified the requirement to perform the ORAT inspection inaccordance with IP 93806, “Operational Readiness Assessment Team Inspections,” toassist the NRC’s determination for plant startup readiness.

In June 2015, WA informed the NRC of its “Declaration of Readiness for WBN2Operational Readiness Assessment Team Inspection” (ADAMS AccessionNo. ML15156A848). WA’s letter briefly described the manner in which it had or willfulfill ORAT inspection-specific prerequisites. ORAT inspections typically coincided withthe construction window after system completion and turnover to operations but beforeplant startup. This allowed inspectors to sample safety-related systems with issuedoperational procedures and, in some cases, partial or full implementation of thoseprocedures.

Both IMC 2514 and IP 93806 allowed for the ORAT inspections to be tailored to theindividual plant circumstances. The NRC staff performed the ORAT inspection with anumber of safety-related systems incomplete and still within the custody of the project’sconstruction organization. Because of the timing of the inspection and the limited timebetween construction completion and turnover of all systems, several site procedureswere not fully issued or implemented.

On July 27, 2015, the NRC staff completed the ORAT inspection and concluded thatTVA adequately demonstrated the readiness of the facility and staff to safely start upand conduct power operations at WBN2. The staff performed a number of inspections tosupport plant operations, after the turnover of the safety-related systems to theoperations organization but before the systems were relied upon. This approachsupported the NRC’s determination for plant startup readiness and allowed the NRC toinspect the implementation of safety-significant activities.

Lesson: Perform a detailed assessment of the licensee’s readiness for an ORATinspection immediately before the inspection to validate that the licensee’soperational programs and safety-related systems have met the ORATprerequisites.

10

Page 17: NUCLEAR REGULATORY UNITED STATES …Nuclear Regulatory Commission (NRC) of its plan to resume construction of WBN2. Shortly thereafter, the NRC staff submitted SECY-07-0096, Possible

4.c Following the issuance of the operating license on October 22, 2015 (ADAMS AccessionNo. ML15251A587), WBN2 transitioned into the ROP. The NRC monitored plantperformance by focusing on seven cornerstones as part of the ROP. Thesecornerstones were assessed by a combination of objective performance indicatorsreported by the licensee and the NRC inspectors’ findings. ROP cornerstones becamemonitorable and transitioned from the NRC’s WBN2 construction assessment process(IMC 2517) to the ROP (IMC 0305, “Operating Reactor Assessment Program,” andIMC 0609, “Significance Determination Process”), as construction activities finalized andthe plant’s operations organizations took operational control.

The NRC developed IMC 2517 (as discussed above in Section I) and used thetraditional enforcement process to assess findings identified throughout the constructionphase because of the unique nature of WBN2. During the transition of cornerstonesfrom construction to operations, the inspectors noted that the assessment guidance fordispositioning findings differed under the construction assessment process and theROP. In some cases under IMC 2517, assessment guidance was limited and did notfully address findings associated with operational programs, whereas the ROP may havebeen more applicable to disposition these types of findings. Nonetheless, inspectorsused the applicable guidance and successfully evaluated findings during the transitionprocess.

Lesson: Phase the transition from construction to operations inspections andassessment programs (including enforcement) to reflect the licensee’soperational transition and ensure applicable NRC processes are being used.

11

Page 18: NUCLEAR REGULATORY UNITED STATES …Nuclear Regulatory Commission (NRC) of its plan to resume construction of WBN2. Shortly thereafter, the NRC staff submitted SECY-07-0096, Possible

IV

.R

EC

OM

ME

ND

AT

IO

NS

Rec

om

men

dat

ions

are

prim

arily

bas

edon

how

the

less

ons

lear

ned

may

appl

yto

curr

ent

and

futu

re10

CF

RP

art

52re

acto

rco

nstr

ucti

onpr

ojec

ts.

The

NR

Cco

nsid

ered

plan

tsto

beco

nstr

ucte

d,re

star

ted,

orli

cens

edun

der

10C

FR

Par

t50

aspa

rtof

the

less

on

sle

arne

dev

alua

tion

.T

hes

ele

ssons

lear

ned

may

also

beap

plic

able

tofu

ture

NR

C-r

egul

ated

cons

truc

tion

proj

ects

ofdi

ffer

ent

type

s.

WB

N2

Les

son

Lea

rned

Ap

pli

cab

ilit

yto

10C

FR

Par

t50

and

Rec

om

men

dat

ions

10C

FR

Par

t52

1.P

lan

nin

g,

Sch

eduli

ng,

and

Rep

ort

ing

1.a

For

firs

t-of

-a-k

ind

orun

ique

10C

FR

Par

t50

:C

onti

nue

tou

segu

idan

ceco

ntai

ned

inpr

ojec

ts,

the

eng

agem

ent

ofF

utur

eJO

CF

RP

art

50pr

ojec

tsw

ould

IMC

0040

,sp

ecif

ical

ly,

Sec

tion

s06

.04,

exp

erie

nce

dex

pert

san

dha

veto

beev

alua

ted

ona

case

-by-c

ase

“Reg

iona

lan

dO

ffic

eC

omm

ents

,”an

d06

.05,

know

ledg

eabl

est

aff

duri

ngth

ebas

isto

dete

rmin

ew

heth

erth

isle

sson

and

“Com

men

tR

esol

utio

n.”

deve

lopm

ent

ofgu

idan

cere

com

men

dati

onco

uld

beap

plie

d.docu

men

tspr

oved

valu

able

and

Exi

stin

ggu

idan

ce(i

.e.,

IMC

0040

,It

isim

port

ant

tono

teth

atIM

C00

40ou

tlin

esre

sult

edin

fina

lgu

idan

ceth

atw

asP

repa

ring

,R

evis

ing

and

Issu

ing

regi

onal

com

men

tpa

rtic

ipat

ion

duri

ngth

edr

aft

tail

ored

toth

eun

ique

lice

nsin

gD

ocum

ents

for

the

NR

CIn

spec

tion

pro

cess

.T

his

guid

ance

serv

esw

ell

for

the

bas

isof

Wat

tsB

ar.

Man

ual”

)m

aybe

appl

icab

leto

futu

rere

visi

onof

exis

ting

insp

ecti

onm

anua

lpr

ojec

tsan

dth

usgo

vern

corr

espo

ndin

gdo

cum

ents

;ho

wev

er,

for

uniq

ueor

insp

ecti

onpr

ogra

ms.

firs

t-of

-a-k

ind

proj

ects

,th

ew

orki

nggr

oup

reco

mm

ends

that

expe

rien

ced

and

10C

FR

Par

t52

:kn

owle

dgea

ble

pers

onne

l(i

nclu

ding

tho

sein

Dur

ing

the

earl

yde

velo

pmen

tof

the

the

regi

on)

beco

me

invo

lved

atth

eea

rlie

st10

CF

RP

art

52in

spec

tion

prog

ram

,st

ages

ofgu

idan

cede

velo

pmen

t.ex

peri

ence

dan

dkn

owle

dgea

ble

staf

f(i

nclu

ding

regi

onal

insp

ecto

rs)

part

icip

ated

Als

o,fo

run

ique

orfi

rst-

of-a

-kin

def

fort

s,u

sein

the

deve

lopm

ent

ofth

epr

ogra

mth

roug

hta

blet

opex

erci

ses

inw

hich

key

pers

onne

lw

orki

nggr

oups

and

revi

ewan

ddis

cuss

sim

ulat

edsc

enar

ios.

The

tabl

etop

conc

urre

nce

ofdr

aft

docu

men

ts.

exer

cise

sca

nbe

used

toas

sess

insp

ecti

onpr

ogra

mgu

idan

cedo

cum

ents

and

proc

edur

esbe

fore

issu

ance

.1.

bA

cent

rali

zed

proj

ect

JOC

FR

Par

t50

:E

valu

ate

cons

olid

atio

nof

reso

urc

esan

dm

anag

emen

tst

ruct

ure

with

sing

leF

utur

e10

CF

RP

art

50pr

ojec

tsw

ould

sim

plif

ied

man

agem

ent

repo

rtin

gst

ruct

ure

man

agem

ent

chai

nof

com

man

d,ha

veto

beev

alua

ted

ona

case

-by-c

ase

(one

divi

sion

repo

rtin

gst

ruct

ure

vs.

inst

itut

ion

ofcl

ear

expe

ctat

ions

,bas

isto

dete

rmin

ew

heth

erth

isle

sson

and

12

Page 19: NUCLEAR REGULATORY UNITED STATES …Nuclear Regulatory Commission (NRC) of its plan to resume construction of WBN2. Shortly thereafter, the NRC staff submitted SECY-07-0096, Possible

and

deve

lopm

ent

ofde

tail

edro

les

and

resp

onsi

bili

ties

with

suff

icie

ntau

thor

ity

wer

eke

yto

proj

ect

succ

ess.

reco

mm

enda

tion

coul

dbe

appl

ied.

Org

aniz

atio

nal

stru

ctur

ean

dm

anag

emen

tst

ruct

ure

may

bedep

enden

tup

onav

aila

ble

reso

urc

esat

the

tim

e.

10C

FR

Par

t52

:T

heN

RC

has

impl

emen

ted

asp

ects

ofth

isre

com

men

dati

onfo

rth

e10

CF

RP

art

52in

spec

tion

prog

ram

.

Exa

mpl

esin

clud

eth

efo

llow

ing:

•R

eorg

aniz

edth

eco

nstr

ucti

ondi

visi

ons

inR

u,w

hich

mer

ged

two

divi

sion

sin

toon

edi

visi

on,

also

know

nas

the

DC

Cm

erge

r(t

his

intr

oduc

eda

sing

lem

anag

emen

tch

ain

ofco

mm

and

for

the

proj

ect

over

sigh

tgr

oup

and

insp

ecti

ongr

oup)

.•

Des

igna

ted

ase

nior

cons

truc

tion

prog

ram

man

ager

with

suff

icie

ntsc

hedu

ling

auth

orit

yan

dre

spon

sibl

efo

rth

epl

anni

ng,

sche

duli

ng,

and

trac

king

ofin

spec

tion

assi

gnm

ents

.•

Dev

elop

eda

Con

stru

ctio

nIn

spec

tion

Pro

gram

Info

rmat

ion

Man

agem

ent

Sys

tem

(CIP

IMS

)w

ithth

eab

ility

topl

an,

sche

dule

,an

dgen

erat

eco

nsis

tent

insp

ecti

onre

port

s.•

Con

duct

edpe

riod

icin

tern

alm

eeti

nqs

tod

iscu

ssin

spec

tion

two

divi

sion

sal

read

yin

plac

evi

ath

eD

CO

mer

ger)

.

Est

abli

shcl

ear

role

san

dre

spon

sibi

liti

esth

atsu

ppor

tth

ein

spec

tion

prog

ram

and

ensu

rean

orga

niza

tion

alst

ruct

ure

that

allo

ws

for

wor

kas

signm

ents

tobe

equi

tabl

ydi

stri

bute

d.

Con

side

rce

ntra

lizi

ngpr

ojec

tm

anag

emen

tre

spon

sibi

liti

esan

dcl

earl

yde

fini

ngpr

ojec

tm

anag

emen

tro

les

and

resp

onsi

bili

ties

atth

ebe

ginn

ing

ofa

proj

ect.

WB

N2

Les

son

Lea

rned

App

lica

bili

tyto

10C

FRP

art

50an

dR

ecom

men

dat

ions

10C

FR_P

art_

52

13

Page 20: NUCLEAR REGULATORY UNITED STATES …Nuclear Regulatory Commission (NRC) of its plan to resume construction of WBN2. Shortly thereafter, the NRC staff submitted SECY-07-0096, Possible

WB

N2

Lesso

nL

earn

ed

Ap

plicab

ility

to

10

CF

RP

art

50

and

Recom

mendations

10

CF

R_

Part_

52

plan

ning

,pr

ojec

tas

sess

men

t,an

dex

pect

atio

ns.

1.c

Ret

enti

onof

thor

ough

and

Ens

ure

rete

ntio

nof

insp

ecti

onop

enit

ems

Eva

luat

eth

ene

edfo

rre

tent

ion

ofdo

cum

ents

deta

iled

docu

men

tati

onas

soci

ated

and

alle

gati

on-r

elat

edm

ater

ial

for

asso

ciat

edw

ithpr

ojec

tsth

atha

vece

ased

with

open

item

sw

asim

port

ant

todi

scon

tinu

edco

nstr

ucti

onpr

ojec

ts,

asco

nstr

ucti

on,

cons

iste

ntw

ithre

cord

rete

ntio

nes

tabl

ishi

nga

com

preh

ensi

veap

plic

able

and

consi

sten

tw

ithag

ency

poli

cies

.b

asis

for

the

resu

mpt

ion

ofgu

idan

ce.

disc

onti

nued

proj

ects

.A

spec

tsof

this

reco

mm

enda

tion

have

been

impl

emen

ted

for

10C

FR

Par

t52

insp

ecti

onpr

ogra

m;

CIP

IMS

has

the

abili

tyto

reco

rdin

spec

tion

s.1 .

dP

rog

ress

ofth

ein

spec

tion

10C

FR

Par

t50

:E

valu

ate

the

need

for

deta

iled

IPsa

mpl

epr

ogra

m(i

nclu

ding

lPsa

mple

s)T

his

less

ondi

rect

lyap

plie

sto

both

docu

men

ting

and

acco

unti

ng.

As

lear

ned

shou

ldbe

thor

ough

lydo

cum

ente

d10

CF

RP

art

50an

d10

CF

RP

art

52th

roug

hout

the

WB

N2

proj

ect,

thor

ough

and

and

acco

unte

dfo

rto

ensu

repr

ojec

ts.

deta

iled

acco

unti

ngof

insp

ecti

onob

ject

ives

com

plet

ion.

The

docu

men

tati

onpr

oved

valu

able

bec

ause

ofpr

ojec

tde

lays

.It

isan

dst

atu

sof

top-

leve

lan

dlo

wer

Par

t10

CF

R52

:im

port

ant

tono

teth

atso

me

lPs

may

take

leve

lin

spec

tion

step

ssh

ould

The

NR

Ch

asim

plem

ente

das

pec

tsof

this

seve

ral

yea

rsto

com

plet

ean

dth

eref

ore

rely

onco

ntai

nsu

ffic

ient

deta

ilsu

chth

atre

com

men

dati

onin

part

for

the

acu

mul

ativ

esa

mpl

ean

dsa

tisf

acti

onof

they

can

bere

cons

titu

ted

ifth

e10

CF

RP

art

52in

spec

tion

prog

ram

.in

spec

tion

obje

ctiv

es.

need

aris

es.

For

10C

FR

Par

t52

,C

IPIM

Spr

ovid

esth

eab

ility

totr

ack

IPco

mpl

etio

nto

the

desi

red

leve

l;ho

wev

er,

atth

isti

me

itis

uncl

ear

how

tode

term

ine

whe

ther

the

inte

ntof

the

IPst

eps

have

bee

nm

et.

Eve

nth

ough

IPsa

mple

sar

ere

cord

edat

the

top-

leve

lst

eps,

consi

sten

tw

ithIM

C25

06,

“Con

stru

ctio

nR

eact

orO

vers

ight

Pro

cess

Gen

eral

Gui

danc

ean

dB

asis

Doc

umen

t,”da

ted

Feb

ruar

y20

,20

17(A

DA

MS

Acc

essi

onN

o.M

L163

15A

349)

,de

tail

edre

cord

ing

may

bew

arra

nted

toen

sure

that

14

Page 21: NUCLEAR REGULATORY UNITED STATES …Nuclear Regulatory Commission (NRC) of its plan to resume construction of WBN2. Shortly thereafter, the NRC staff submitted SECY-07-0096, Possible

WB

N2

Les

son

Lea

rned

Ap

pli

cab

ilit

yto

10C

FR

Par

t50

and

Rec

om

men

dat

ions

10C

FR

_Par

t_52

the

inte

ntof

IPs

and

supp

orti

ngob

ject

ives

have

been

sati

sfie

d.1.

eU

seon

site

NR

Cpr

ojec

t10

CF

RP

art

50:

Eva

luat

ere

sult

sfr

omth

epi

lot

for

effi

cien

cies

man

agem

ent

toco

ntin

uous

lyT

his

less

ondi

rect

lyap

plie

sto

both

and

aspec

tstr

ansf

erra

ble

tocu

rren

tev

alua

te,

mon

itor

,co

rrob

orat

e,an

d10

CF

RP

art

50an

d10

CF

RP

art

52co

nstr

ucti

onpr

ojec

tm

anag

er(C

PM)

acti

viti

es,

mod

ify

insp

ecti

onsc

hed

ule

sin

proj

ects

.in

clud

ing

cond

uct

ofC

PMac

tivi

ties

onsi

te.

orde

rto

min

imiz

eim

pact

sto

NR

Cre

sou

rces

and

supp

ort

the

10C

FR

Par

t52

:ag

ency

’sov

ersi

ght

resp

onsi

bili

ties

.T

heN

RC

rece

ntly

pilo

ted

asp

ects

ofth

isre

com

men

dati

onat

Virg

ilC

.S

umm

erN

ucle

arS

tati

on,

Uni

ts2

and

3.

2.M

ainta

inin

gan

Adeq

uat

eIn

spec

tion

Sta

ff2.

aP

roje

ctst

affi

ngw

ithin

the

10C

FR

Par

t50

:D

evel

opea

rly

proj

ect

staf

fing

stra

teg

ies

thro

ugh

orga

niza

tion

shou

ldbe

Thi

sle

sson

dire

ctly

appl

ies

tobo

thth

eu

seof

deta

iled

tabl

etop

exer

cise

s.T

hes

eco

mm

ensu

rate

with

the

leve

lof

10C

FR

Par

t50

and

10C

FR

Par

t52

stra

teg

ies

shou

ldin

clud

eth

eu

seof

indi

vidu

als

acti

vity

atth

esi

teto

prov

ide

proj

ects

.w

ithva

ryin

gte

chni

cal

expe

rtis

ean

dex

tens

ive

flex

ibili

ty,

cont

inui

ty,

and

expe

rien

ce,

the

eval

uati

onof

trai

ning

and

assu

rance

that

the

NR

Cis

10C

FR

Par

t52

:pr

ogra

ms,

and

the

invo

lvem

ent

ofst

akeh

olde

rs.

equi

pped

toha

ndle

attr

ition

and

The

NR

Ch

asdis

cuss

edas

pec

tsof

this

The

follo

win

gar

eco

nsid

erat

ions

for

the

tran

siti

onev

ents

,su

chas

proj

ect

reco

mm

enda

tion

aspa

rtof

the

tabl

etop

exer

cise

s:de

lays

,tu

rnov

erof

pers

onne

l,or

deve

lopm

ent

ofth

eco

nstr

ucti

onR

OP

repr

iori

tiza

tion

ofag

ency

acti

viti

es,

tran

siti

onpl

an.

•U

sero

tati

ons

and

incr

ease

dst

affi

ng,

asap

plic

able

,co

mm

ensu

rate

with

the

leve

lR

efer

toth

efo

llow

ing

docu

men

tsfo

rm

ore

ofac

tivity

.in

form

atio

n:•

Ass

ign

test

insp

ecto

rsto

faci

lita

tean

dre

spon

dto

test

ing

acti

viti

eson

shor

t•

Con

stru

ctio

nIn

spec

tion

Pro

gram

noti

ce.

Pub

lic

Mee

ting

,Ju

ly19

,20

16•

Use

adi

vers

ifie

dgr

oup

of(A

DA

MS

Acc

essi

onkn

owle

dgea

ble

and

expe

rien

ced

No.

ML

161

97A

125)

insp

ecto

rs(T

iger

team

)w

hoca

n.

SEC

Y-1

7-00

48,

Con

stru

ctio

nad

dre

ssta

rget

edpr

ojec

tn

eed

s.R

eact

orO

vers

ight

Pro

cess

Sel

f-•

Mai

ntai

nth

ep

rese

nce

ofan

onsi

teA

sses

smen

tfo

rC

alen

dar

Yea

rpr

ojec

tm

anag

er(s

eeL

esso

n1.

e).

15

Page 22: NUCLEAR REGULATORY UNITED STATES …Nuclear Regulatory Commission (NRC) of its plan to resume construction of WBN2. Shortly thereafter, the NRC staff submitted SECY-07-0096, Possible

WB

N2

Lesso

nL

earn

ed

Ap

plicab

ility

to

JO

CF

RP

art

50

and

Recom

mendations

JO

CF

RP

art

52

2016

,da

ted

Apr

il11

,20

17(A

DA

MS

•H

ave

am

ulti

disc

ipli

nary

and

tech

nica

lA

cces

sion

No.

ML

1704

7A69

4).

team

(pan

el)

coll

ecti

vely

revi

ewte

sts

for

tech

nica

lad

equa

cy.

2.b

Cle

arly

esta

blis

han

dm

anag

eT

his

less

ondi

rect

lyap

plie

sto

both

Eva

luat

eth

efo

llow

ing:

exp

ecta

tions

and

guid

ance

for

10C

FR

Par

t50

and

10C

FR

Par

t52

onsi

tein

spec

tion

pre

sen

cedu

ring

proj

ects

.•

Rev

ise

the

exis

ting

insp

ecti

onpr

ogra

mor

cons

truc

tion

and

test

ing

such

that

regi

onal

offi

cegu

idan

ceto

incl

ude

reso

urc

esar

eev

enly

dist

ribu

ted

expe

ctat

ions

for

onsi

tepre

sence

byan

deq

uita

bly

assi

gned

duri

ngno

nres

iden

tin

spec

tors

.ba

cksh

ift

and

wee

kend

hour

s.R

evis

epo

siti

onde

scri

ptio

nsan

dpe

rfor

man

ceel

emen

tsan

dst

andar

ds

toin

clud

eba

cksh

ift

and

wee

kend

cove

rage

for

nonr

esid

ent

insp

ecto

rs,

and

com

mun

icat

eth

ech

ang

eas

appr

opri

ate

2.c

En

gag

esi

tesu

perv

isor

yst

aff

10C

FR

Par

t50

:E

valu

ate

the

need

for

mod

ifyi

ngth

ese

lect

ion

(i.e

.,th

eS

RI)

and

regi

onal

Thi

sle

sson

dire

ctly

appl

ies

tobo

than

din

terv

iew

pro

cess

toin

clud

eth

efo

llow

ing:

lead

ersh

ipdu

ring

the

sele

ctio

nof

10C

FR

Par

t50

and

10C

FR

Par

t52

candid

ates

for

proj

ects

that

requ

ire

proj

ects

.•

onsi

tein

terv

iew

s,as

appl

icab

leun

ique

skill

sets

and

expe

rien

ce.

•in

volv

emen

tof

site

supe

rvis

ory

staf

f10

CF

RP

art

52:

(i.e

.,th

eS

RI)

duri

ngth

ein

terv

iew

and

The

NR

Cim

plem

ente

das

pec

tsof

this

sele

ctio

np

roce

ssre

com

men

dati

ondu

ring

the

sele

ctio

nof

•tr

aini

ngof

supe

rvis

ory

staf

fon

how

tore

side

ntin

spec

tor

deve

lopm

ent

prog

ram

inte

rvie

wca

nd

idat

esca

nd

idat

esfo

rA

Pi 0

00.

Dur

ing

the

inte

rvie

wpro

cess

,al

lre

side

ntin

spec

tor

deve

lopm

ent

prog

ram

can

did

ates

wer

ein

terv

iew

edon

site

tom

eet

with

the

site

supe

rvis

ory

staf

f(i

.e.,

the

SR

I)an

dbr

iefl

yex

per

ience

the

wor

ksi

te.

Incl

ude

the

SRI

inth

ere

side

ntin

spec

tor

sele

ctio

np

roce

ss,

incl

udin

gon

site

and

fiel

din

terv

iew

s.

16

Page 23: NUCLEAR REGULATORY UNITED STATES …Nuclear Regulatory Commission (NRC) of its plan to resume construction of WBN2. Shortly thereafter, the NRC staff submitted SECY-07-0096, Possible

WB

N2

Les

son

Lea

rned

Ap

pli

cab

ilit

yto

10C

FR

Par

t50

and

Rec

om

men

dat

ions

10C

FR

_Par

t_52

2.d

Pro

acti

vere

gion

altr

aini

ng10

CF

RP

art

50:

The

late

stre

visi

onof

IMC

1245

add

ress

esth

isen

han

cem

ents

duri

ngth

ete

stin

gT

his

less

ondi

rect

lyap

plie

sto

both

reco

mm

enda

tion

for

all

qual

ific

atio

ns.

phas

esof

WB

N2

cont

ribu

ted

toth

e10

CF

RP

art

50an

d10

CF

RP

art

52su

cces

sful

com

plet

ion

ofke

yan

dpr

ojec

ts.

As

cont

inue

dim

prov

emen

tsto

the

qual

ific

atio

nta

rget

edte

stin

gin

spec

tion

s,pr

ogra

mar

em

ade,

cons

ider

the

follo

win

g:10

CF

RP

art

52:

The

NR

Cad

dre

ssed

aspec

tsof

this

•ju

st-i

n-ti

me

trai

ning

for

test

ing

and

reco

mm

enda

tion

inth

ela

test

revi

sion

ofop

erat

iona

lpr

ogra

ms

IMC

1245

,“Q

uali

fica

tion

Pro

gram

for

New

•po

stqu

alif

icat

ion

men

tori

ngan

don

-the

-job

and

Ope

rati

ngR

eact

orP

rogr

ams,

”da

ted

trai

ning

Aug

ust

24,

2017

.IM

C12

45in

clud

esa

new

App

endi

x0-

15,

whi

chin

tegr

ates

the

diff

eren

tqu

alif

icat

ions

and

reco

gniz

esth

eex

per

ience

nee

ded

tope

rfor

mop

erat

iona

l)n

s.su

chas

____

__

__

__

__

__

__

__

__

__

IT

hT

3.E

ffec

tive

Com

munic

atio

ns

wit

hIn

tern

alan

dE

xte

rnal

Sta

keh

old

ers

3.a

The

WR

AG

prov

edto

bea

key

10C

FR

Par

t50

:E

valu

ate

the

need

for

and

cons

ider

the

com

po

nen

tof

the

WB

N2

over

sigh

tT

heN

RC

wou

ldha

veto

eval

uate

futu

rees

tabli

shm

ent

ofan

over

sigh

tgr

oup

for

plan

tsef

fort

.T

heW

RA

Gcl

osel

y10

CF

RP

art

50pr

ojec

tson

aca

se-b

y-c

ase

unde

rco

nstr

ucti

on.

inte

grat

edpr

ojec

tpr

iori

ties

and

basi

sto

dete

rmin

ew

heth

erth

isle

sson

and

focu

sed

the

NR

C’s

man

agem

ent

reco

mm

enda

tion

appl

y.ov

ersi

ght.

10C

FR

Par

t52

:T

heO

ffic

eof

New

Rea

ctor

san

dRh

cond

uct

over

sigh

tof

10C

FR

Par

t52

plan

ts.

The

use

ofC

IPIM

S,w

eekl

ypr

ojec

tm

eeti

ngs,

peri

odic

seni

orm

anag

emen

tm

eeti

ngs

with

the

lice

nsee

,an

dpe

riod

icag

ency

asse

ssm

ents

acco

mpl

ish

som

eof

the

obje

ctiv

essi

mil

arto

the

WR

AG

.H

owev

er,

the

staf

fsh

ould

cons

ider

the

bene

fits

ofa

proj

ect-

spec

ific

and

inte

grat

ed

17

Page 24: NUCLEAR REGULATORY UNITED STATES …Nuclear Regulatory Commission (NRC) of its plan to resume construction of WBN2. Shortly thereafter, the NRC staff submitted SECY-07-0096, Possible

WB

N2

Les

son

Lea

rned

Ap

pli

cab

ilit

yto

10C

FR

Par

t50

and

Rec

om

men

dat

ions

10C

FR

Par

t52

man

agem

ent

over

sigh

tgr

oup

for

10C

FR

Par

t52

plan

ts.

3.b

The

use

ofse

vera

lde

tail

edT

his

less

ondi

rect

lyap

plie

sto

both

Con

side

rea

rly

revi

ewan

dde

velo

pmen

t,as

com

mun

icat

ion

plan

sfo

rW

BN

210

CF

RP

art

50an

d10

CF

RP

art

52ap

plic

able

,of

anin

tegr

ated

,co

mpr

ehen

sive

,pr

oved

valu

able

;ho

wev

er,

the

proj

ects

.In

stea

dof

deve

lopi

ngm

ultip

lean

dpr

ojec

t-sp

ecif

icco

mm

unic

atio

npl

anth

atde

velo

pmen

tof

one

inte

grat

edan

dco

mm

unic

atio

nspl

ans

for

asi

ngle

proj

ect,

incl

udes

peri

odic

ity

ofco

mm

unic

atio

n,ro

les

com

pre

hen

sive

com

mun

icat

ion

cons

ider

deve

lopi

ngon

ein

tegr

ated

proj

ect

and

resp

onsi

bili

ties

,fr

eque

ntly

ask

edpl

anw

ould

beea

sier

toup

date

and

com

mun

icat

ions

plan

.qu

esti

ons,

use

ofso

cial

med

iafo

rpu

blic

enh

ance

com

mun

icat

ions

atal

lou

trea

ch,

and

part

neri

ngw

ithth

eO

ffic

eof

leve

ls.

Pub

lic

Aff

airs

.

4.C

onst

ruct

ion

toO

per

atio

ns

Tra

nsi

tion

Rea

din

ess

Rev

iew

4.a

Insp

ecti

ons

ofco

nstr

ucti

on10

CF

RP

art

50:

Thi

sre

com

men

dati

onha

sbe

enad

dre

ssed

for

com

po

nen

tte

stin

gsh

ould

beT

heN

RC

wou

ldha

veto

eval

uate

futu

re10

CF

RP

art

52in

the

late

stre

visi

onof

inco

rpor

ated

into

the

insp

ecti

on10

CF

RP

art

50pr

ojec

tson

aca

se-b

y-c

ase

IMC

2503

.pr

ogra

man

dsh

ould

beus

edto

basi

sto

dete

rmin

ew

heth

erth

isle

sson

and

info

rmpr

eope

rati

onal

and

star

tup

reco

mm

enda

tion

appl

y.C

onsi

dera

tion

shou

ldbe

give

nas

tow

heth

erte

stin

gin

spec

tion

s,co

mpo

nent

test

ing

insp

ecti

ons

shou

ldbe

JOC

FR

Par

t52

:in

corp

orat

edin

the

10C

FR

Par

t50

insp

ecti

onT

heN

RC

inco

rpor

ated

aspec

tsof

this

prog

ram

and

appl

icab

leIP

san

dpo

tent

ial

reco

mm

enda

tion

into

IMC

2503

,re

visi

ons

toIM

C12

52.

“Con

stru

ctio

nIn

spec

tion

Pro

gram

:IT

AA

CR

elat

edW

ork,

”da

ted

July

5,20

12.

4.b

Per

form

ade

tail

ed10

CF

RP

art

50:

The

NR

Cad

dre

ssed

this

reco

mm

enda

tion

for

asse

ssm

ent

ofth

eli

cens

ee’s

The

NR

Cw

ould

have

toev

alua

tefu

ture

10C

FR

Par

t52

thro

ugh

impl

emen

tati

onof

the

read

ines

sfo

ran

OR

AT

insp

ecti

on10

CF

RP

art

50pr

ojec

tson

aca

se-b

y-c

ase

com

bine

dli

cens

ep

roce

ssan

dIM

C25

04.

imm

edia

tely

befo

reth

ein

spec

tion

bas

isto

dete

rmin

eho

wth

isle

sson

and

tova

lida

teth

atth

eli

cens

ee’s

reco

mm

enda

tion

coul

dbe

appl

ied.

For

futu

re10

CF

RP

art

50pr

ojec

ts,

cons

ider

oper

atio

nal

prog

ram

san

dw

heth

erde

tail

edas

sess

men

tsof

the

lice

nsee

’ssa

fety

-rel

ated

syst

ems

have

met

10C

FR

Par

t52

:re

adin

ess

for

anO

RA

Tin

spec

tion

shou

ldbe

the

OR

AT

prer

equi

site

s.T

his

less

ondoes

not

dire

ctly

appl

yto

perf

orm

edim

med

iate

lybe

fore

the

insp

ecti

on.

10C

FR

Par

t52

plan

tsbec

ause

oper

atio

nal

read

ines

sw

asin

corp

orat

edin

toth

eco

mbi

ned

lice

nse

pro

cess

and

18

Page 25: NUCLEAR REGULATORY UNITED STATES …Nuclear Regulatory Commission (NRC) of its plan to resume construction of WBN2. Shortly thereafter, the NRC staff submitted SECY-07-0096, Possible

WB

N2

Les

son

Lea

rned

Ap

pli

cab

ilit

yto

10C

FR

Par

t50

and

Rec

om

men

dat

ions

10C

FR

_Par

t_52

10C

FRP

art

52in

spec

tion

prog

ram

(I MC

2504

,“C

onst

ruct

ion

Insp

ecti

onP

rogr

am—

Insp

ecti

onof

Con

stru

ctio

nan

dO

pera

tion

alP

rogr

ams”

).F

or10

CF

RP

art

52pl

ants

,op

erat

iona

lre

adin

ess

isbas

edon

sati

sfac

tory

com

plet

ion

ofin

spec

tion

sof

ITA

AC

.C

ompl

etio

nof

targ

eted

ITA

AC

iscl

osel

ym

onit

ored

,in

spec

ted,

and

reco

rded

thro

ugh

the

use

ofC

IPIM

S.

Add

ition

ally

,IM

C25

04sp

ecif

ical

lydis

cuss

esth

eco

nfir

mat

ion

ofop

erat

iona

lpr

ogra

ms

and

the

NR

Cst

aff’

sro

lein

info

rmin

gth

eC

omm

issi

onof

the

stat

us

ofth

ese

prog

ram

sbe

fore

mak

ing

the

dete

rmin

atio

nth

atth

eli

cens

eeca

nlo

adfu

el(s

ee10

CF

R52

.103

(g))

.4.

cP

has

eth

etr

ansi

tion

from

Thi

sle

sson

dire

ctly

appl

ies

tobo

thE

valu

ate

the

need

for

ap

has

edap

proa

chfo

rco

nstr

ucti

onto

oper

atio

ns10

CF

RP

art

50an

d10

CF

RP

art

52th

etr

ansi

tion

ofR

OP

corn

erst

ones

.T

hein

spec

tion

san

das

sess

men

tpr

ojec

tssi

nce

both

prog

ram

str

ansi

tion

eval

uati

onsh

ould

addre

ssw

hich

pro

cess

prog

ram

s(i

nclu

ding

enfo

rcem

ent)

from

aco

nstr

ucti

onas

sess

men

tpr

ogra

m(c

onst

ruct

ion

orR

OP

)is

bett

ersu

ited

toas

sess

tore

flec

tth

eli

cens

ee’s

oper

atio

nal

toth

eR

OP

.fi

ndin

gsdu

ring

the

diff

eren

tst

ages

ofth

etr

ansi

tion

and

ensu

reap

plic

able

proj

ect

whe

reth

eco

rner

ston

em

ayno

tha

veye

tN

RC

pro

cess

esar

ebe

ing

used

.S

cen

ario

sm

ayex

ist

inth

efu

ture

whe

retr

ansi

tion

edto

the

RO

P.

test

ing

acti

viti

esas

soci

ated

with

oper

atio

nal

prog

ram

sm

aybe

taki

ngpl

ace

whi

leth

epl

ant

rem

ains

unde

rco

nstr

ucti

on,

yet

the

appl

icab

leco

rner

sto

nes

have

not

tran

siti

oned

toth

eR

OP

.

19

Page 26: NUCLEAR REGULATORY UNITED STATES …Nuclear Regulatory Commission (NRC) of its plan to resume construction of WBN2. Shortly thereafter, the NRC staff submitted SECY-07-0096, Possible

Attachment

Watts Bar 2 Construction Oversight Lessons Learned Working Group Charter

A-i

Page 27: NUCLEAR REGULATORY UNITED STATES …Nuclear Regulatory Commission (NRC) of its plan to resume construction of WBN2. Shortly thereafter, the NRC staff submitted SECY-07-0096, Possible

I

UNITED STATESNUCLEAR REGULATORY COMMISSION

REGION II245 PEACHTREE CENTER AVENUE NE, SUITE 1200

ATLANTA, GEORGIA 30303-1257

June 26, 2017

MEMORANDUM TO: William B. Jones, DirectorDivision of Construction Oversight

FROM: Laura A. Dudes, Deputy Regional Administrator for ConstructionOffice of the Regional Administrator IRN

SUBJECT: WATTS BAR UNIT 2 CONSTRUCTION INSPECTION ANDOVERSIGHT LESSONS-LEARNED

This memorandum transmits the enclosed Waifs Bar Unit 2 Construction Inspection and OversightLessons-Learned Working Group Charter. The Working Group (WG) is comprised of inter-officestaff that have broad knowledge of the construction inspection and assessment programs asimplemented under 10 CFR Part 50 and Part 52. The purpose of the Working Group is toassess the U.S. Nuclear Regulatory Commission’s (NRC’s) construction oversight and inspectionactMties at Watts Bar 2 and identify lessons learned from that project that can be used to further enhanceour construction oversight and inspection activities going forward for both 10 CFR Part 50 and 10 CFRPart 52 facilities.

As the lead for the assessment, you should ensure the WG focuses on the different aspects of theconstruction inspection programs, included in the Construction Reactor Oversight Process (cROP)through the transition to the Reactor Oversight Process (ROP). This will include development andimplementation of the IMC 2517, ‘Watts Bar Unit 2 Construction Inspection Program,” and thetransition to IMC 2515, “Light Water Inspection Program-Operations Phase”.

The lessons-learned should include, for example those attributes that made the development ofthe Inspection, Planning and Scheduling (IPS) for Watts Bar Unit 2 under IMC 2517 effectiveand areas to focus on to improve any future implementation. Addressing the different areas inthe March 9, 2017, staff’s Watts Bar Lessons Learned Memorandum (ML1 7067A458), in thiscontext should provide guidance for any future 10 CFR Part 50 new or reactivation activities.You are also to consider the ongoing 10 CFR Part 52 oversight and inspection activities andprovide a comparison to the lessons-learned from Watts Bar Unit 2 as a separate attachment forfollow up by the Region II Division of Construction Oversight and other divisions within the NRCas applicable.

In addition to the members in your group, Headquarters or Regional support will be provided toyou, as requested. The WG should provide a written report to the Region II, RegionalAdministrator, by August 25, 2017, which at a minimum documents the areas for improvement,their bases, and any WG recommendations.

CONTACT: Laura A. Dudes, ORA(404) 997-4472

Page 28: NUCLEAR REGULATORY UNITED STATES …Nuclear Regulatory Commission (NRC) of its plan to resume construction of WBN2. Shortly thereafter, the NRC staff submitted SECY-07-0096, Possible

W. Jones 2

Documentation of the recommendations should be completed in accordance with Exhibit 2,Effectiveness Review Report Template, of Management Directive 6.8 “Lessons-LearnedProgram”. Region II DCO will ensure that program office recommendations are submitted to theappropriate contact.

Enclosure:

1. Watts Bar Unit 2 Construction Inspection andOversight Lessons-Learned Working Group Charter

Page 29: NUCLEAR REGULATORY UNITED STATES …Nuclear Regulatory Commission (NRC) of its plan to resume construction of WBN2. Shortly thereafter, the NRC staff submitted SECY-07-0096, Possible

Watts Bar Unit 2 Construction Inspection and Oversight Lessons LearnedWorking Group Charter

PURPOSE

The purpose of this working group (WG) is to assess the U.S. Nuclear Regulatory Commission(NRC) Watts Bar Unit 2 construction inspection and assessment reactivation through poweroperation. Lessons learned through this initiative shall consider specific insights into the differentareas identified in the staff’s March 9, 2017, Watts Bar Lessons Learned Memorandum(ML1 7067A458) and to identify areas to emphasize. This lessons-learned review shouldevaluate the NRC’s construction inspection and oversight implementation for the effectiveness of theprograms and processes, highlight actions that contributed to the effectiveness of programimplementation and areas to specifically emphasize where improvements can be made inkeeping with the NRC’s Principles of Good Regulation (Independence, Openness, Efficiency,Clarity, and Reliability).

The WG’s review should also consider the inspection and oversight program implementation forthe AP-1000 plants as compared to the lessons-learned from Watts Bar Unit 2. Specific areasof focus will be provided as a separate attachment for follow up by the Region II Division ofConstruction Oversight.

WORKING GROUP MEMBERSHIP

The WG will be led by Mr. Jason Eargle, Senior Construction Inspector, Division ConstructionOversight (DCO). The other full time members are Mr. Phil O’Bryan, Division of ConstructionInspection and Operational Programs (DCIP), and Mr. Steven Campbell, Division of Inspection andRegional Support (DIRS).

SCOPE

The WG should focus on the different aspects of the Watts Bar Unit 2 construction programdevelopment, through the transition of program responsibilities to operating reactors. The staff’sMarch 9, 2017, Watts Bar Lessons Learned Memorandum provides insights into the programimplementation areas of Organization, Construction Inspection, Testing, and Transition. TheWG should utilize applicable inspection manual chapters (IMCs), including IMC 2517, ‘WattsBar Unit 2 Construction Inspection Program,” IMC 2515, “Light-Water Reactor InspectionProgram - Operations Phase,” and those related to the 10 CFR Part 52 Light Water ReactorInspection Program. This comparison will inform the lessons-learned, and identify areas for follow-upseparate to this WG’s activities.

PROCESS

The WG should remain focused on the implementation of the inspection and oversight programsat Watts Bar Unit 2. A comparison to the inspection and oversight program implementation atthe AP-1 000 facilities should be conducted to identify areas for consideration by Region II’sDCO and NRO as needed. Duplication of work already in process or completed as part of otherefforts should be avoided. This specific assessment may include vertical slice reviews of themajor inspection activities, planning processes and resource loading implemented at WB2 usingthe staff’s lessons-learned and other background information. Vertical slice reviews areexaminations of the portions of the requirements, policies, procedures or guidance applicable tothe specific actions considered significant within this assessment. WG observations that are

Enclosure

Page 30: NUCLEAR REGULATORY UNITED STATES …Nuclear Regulatory Commission (NRC) of its plan to resume construction of WBN2. Shortly thereafter, the NRC staff submitted SECY-07-0096, Possible

2

best suited for incorporation into other oversight programs such as the Reactor Oversight Self-Assessment or the Construction Reactor Oversight Process Self-Assessment, should becoordinated and submitted for such consideration.

DOCUMENTATION

The WG should provide a written report to the Region II, Regional Administrator, by August 25,2017, which at a minimum documents the WG recommendations. Documentation should becompleted in accordancewith Exhibit 2, Effectiveness Review Report Template, ofManagement Directive 6.8 “Lessons-Learned Program,” and submitted to the contact for thatprogram. The report will be made publically available.

Page 31: NUCLEAR REGULATORY UNITED STATES …Nuclear Regulatory Commission (NRC) of its plan to resume construction of WBN2. Shortly thereafter, the NRC staff submitted SECY-07-0096, Possible

Memorandum to Mr. William B. Jones from Ms. Laura A. Dudes

SUBJECT: WATTS BAR UNIT 2 CONSTRUCTION INSPECTION AND OVERSIGHTLESSONS-LEARN ED

DISTRIBUTION:Laura Dudes, RIlWilliam Jones, AllMichael Ernstes, RIlJamie Heisserer, RIlRandall Musser, RIlRebecca Nease, AllJason Eargle, AllPUBLIC

PUBLICLY AVAILABLE DNON-PUBLICLY AVAILABLE

ADAMS: No. ACCESSION NUMBER: ML17192A031

Q SENSITIVE NONSENSITIVE

SUNSI REVIEW COMPLETE FORM 665 ATTACHED

OFFICE RII:ORA

SIGNATURE LAD

NAME L. Dudes

DATE 06/26/2017

IIIIIIII

OFFICIAL RECORD COPY