nuclear regulatory commission washington, d.c. … · notice of issuance will be included in the...

25
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 Mr. Thomas Joyce President and Chief Nuclear Officer PSEG Nuclear LLC P.O. Box 236, N09 Hancocks Bridge, NJ 08038 December 23, 2014 SUBJECT: HOPE CREEK GENERATING STATION AND SALEM NUCLEAR GENERATING STATION, UNIT NOS. 1 AND 2-ISSUANCE OF AMENDMENTS RE: REVISION TO CYBER SECURITY PLAN IMPLEMENTATION SCHEDULE AND CONDITIONS (TAC NOS. MF3384, MF3385, and MF3386) Dear Mr. Joyce: The U.S. Nuclear Regulatory Commission (NRC) has issued the enclosed Amendment No. 197 to Renewed Facility Operating License (FOL) No. NPF-57 for the Hope Creek Generating Station (Hope Creek) and Amendment Nos. 306 and 288 to Renewed FOL Nos. DPR-70 and DPR-75 for the Salem Nuclear Generating Station (Salem), Unit Nos. 1 and 2, respectively. These amendments consist of changes to the FOLs in response to your application dated December 24, 2013, as supplemented by letters dated June 23, 2014, and August 18, 2014. The amendments approve a revised schedule for implementation of the cyber security plan (CSP) Milestone 8 and revises paragraph 2.E for each of the three FOLs. The CSP and associated implementation schedule for Hope Creek and Salem, Unit Nos. 1 and 2, were previously approved by the NRC staff by letters dated July 28, 2011, and December 10, 2012. The NRC staff has determined that its documented safety evaluation does not contain Sensitive Security-Related information pursuant to Title 10 of the Code of Federal Regulations (1 0 CFR), Section 2.390, "Public inspections, exemptions, requests for withholding." By e-mail dated November 25, 2014, the NRC gave PSEG Nuclear LLC (PSEG) the opportunity to comment on any sensitive aspects of the safety evaluation. PSEG responded by e-mail dated December 2, 2014, agreeing with the NRC's assessment that the safety evaluation does not contain Sensitive Security-Related information pursuant to 10 CFR 2.390 and that the safety evaluation can be made available to the public.

Upload: others

Post on 03-Dec-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. … · Notice of Issuance will be included in the Commission's biweekly Federal Register notice. Docket Nos. 50-354, 50-272 and 50-311

UNITED STATES NUCLEAR REGULATORY COMMISSION

WASHINGTON, D.C. 20555-0001

Mr. Thomas Joyce President and Chief Nuclear Officer PSEG Nuclear LLC P.O. Box 236, N09 Hancocks Bridge, NJ 08038

December 23, 2014

SUBJECT: HOPE CREEK GENERATING STATION AND SALEM NUCLEAR GENERATING STATION, UNIT NOS. 1 AND 2-ISSUANCE OF AMENDMENTS RE: REVISION TO CYBER SECURITY PLAN IMPLEMENTATION SCHEDULE AND CONDITIONS (TAC NOS. MF3384, MF3385, and MF3386)

Dear Mr. Joyce:

The U.S. Nuclear Regulatory Commission (NRC) has issued the enclosed Amendment No. 197 to Renewed Facility Operating License (FOL) No. NPF-57 for the Hope Creek Generating Station (Hope Creek) and Amendment Nos. 306 and 288 to Renewed FOL Nos. DPR-70 and DPR-75 for the Salem Nuclear Generating Station (Salem), Unit Nos. 1 and 2, respectively. These amendments consist of changes to the FOLs in response to your application dated December 24, 2013, as supplemented by letters dated June 23, 2014, and August 18, 2014.

The amendments approve a revised schedule for implementation of the cyber security plan (CSP) Milestone 8 and revises paragraph 2.E for each of the three FOLs. The CSP and associated implementation schedule for Hope Creek and Salem, Unit Nos. 1 and 2, were previously approved by the NRC staff by letters dated July 28, 2011, and December 10, 2012.

The NRC staff has determined that its documented safety evaluation does not contain Sensitive Security-Related information pursuant to Title 10 of the Code of Federal Regulations (1 0 CFR), Section 2.390, "Public inspections, exemptions, requests for withholding." By e-mail dated November 25, 2014, the NRC gave PSEG Nuclear LLC (PSEG) the opportunity to comment on any sensitive aspects of the safety evaluation. PSEG responded by e-mail dated December 2, 2014, agreeing with the NRC's assessment that the safety evaluation does not contain Sensitive Security-Related information pursuant to 10 CFR 2.390 and that the safety evaluation can be made available to the public.

Page 2: NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. … · Notice of Issuance will be included in the Commission's biweekly Federal Register notice. Docket Nos. 50-354, 50-272 and 50-311

T. Joyce - 2 -

A copy of our safety evaluation is also enclosed. Notice of Issuance will be included in the Commission's biweekly Federal Register notice.

Docket Nos. 50-354, 50-272 and 50-311

Enclosures: 1. Amendment No. 197 to NPF-57 2. Amendment No. 306 to DPR-70 3. Amendment No. 288 to DPR-75 4. Safety Evaluation

cc w/encls: Distribution via Listserv

Sincerely,

~ ,v~ Carleen J. Parkir) Project Manager Plant Licensing~ nch 1-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation

Page 3: NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. … · Notice of Issuance will be included in the Commission's biweekly Federal Register notice. Docket Nos. 50-354, 50-272 and 50-311

UNITED STATES NUCLEAR REGULATORY COMMISSION

WASHINGTON, D.C. 20555-0001

PSEG NUCLEAR LLC

DOCKET NO. 50-354

HOPE CREEK GENERATING STATION

AMENDMENT TO FACILITY OPERATING LICENSE

Amendment No. 197 Renewed License No. NPF-57

1. The Nuclear Regulatory Commission (the Commission) has found that:

A. The application for amendment filed by PSEG Nuclear LLC dated December 24, 2013, as supplemented by letters dated June 23, 2014, and August 18, 2014, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Commission's rules and regulations set forth in 10 CFR Chapter I;

B. The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission;

C. There is reasonable assurance: (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commission's regulations;

D. The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and

E. The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commission's regulations and all applicable requirements have been satisfied.

2. Accordingly, the second paragraph of 2.E for Renewed Facility Operating License No. NPF-57 is hereby amended to read as follows:

PSEG Nuclear LLC shall fully implement and maintain in effect all provisions of the Commission-approved Cyber Security Plan (CSP), including changes made pursuant to the authority of 10 CFR 50.90 and 10 CFR 50.54(p). The Salem-Hope Creek CSP was approved by License Amendment No. 189 as supplemented by changes approved by License Amendment Nos. 192 and 197.

Enclosure 1

Page 4: NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. … · Notice of Issuance will be included in the Commission's biweekly Federal Register notice. Docket Nos. 50-354, 50-272 and 50-311

- 2-

3. The license amendment is effective as of its date of issuance and shall be implemented within 60 days. The implementation of the Cyber Security Plan (CSP), including the key intermediate milestone dates and the full implementation date, shall be in accordance with the implementation schedule, as submitted by the licensee by letter dated June 6, 2011, as revised by letters dated July 26, 2012, and December 24, 2013, and as approved by the NRC staff with this license amendment. All subsequent changes to the NRC-approved CSP implementation schedule will require prior NRC approval, pursuant to 10 CFR 50.90.

Attachment: Changes to the Renewed Facility

Operating License No. NPF-57

FOR THE NUCLEAR REGULATORY COMMISSION

Meena Khanna, Chief Plant Licensing Branch 1-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation

Date of Issuance: Decem1Jt·r 23, 2014

Page 5: NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. … · Notice of Issuance will be included in the Commission's biweekly Federal Register notice. Docket Nos. 50-354, 50-272 and 50-311

ATTACHMENT TO LICENSE AMENDMENT NO. 197

RENEWED FACILITY OPERATING LICENSE NO. NPF-57

DOCKET NO. 50-354

Replace the following page of the Renewed Facility Operating License with the revised page. The revised page is identified by amendment number and contains marginal lines indicating the area of change.

Remove

Page 16 Page 16

Page 6: NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. … · Notice of Issuance will be included in the Commission's biweekly Federal Register notice. Docket Nos. 50-354, 50-272 and 50-311

-16-

exempting Type C testing for instrument lines and lines containing excess flow check valves (Section 6.2.6 of SSER 5); and an exemption from Appendix J, exempting Type C testing of thermal relief valves (Section 6.2.6 of SSER 5). These exemptions are authorized by law, will not present an undue risk to the public health and safety, and are consistent with the common defense and security. These exemptions are hereby granted. The special circumstances regarding each exemption are identified in the referenced section of the safety evaluation report and the supplements thereto. These exemptions are granted pursuant to 10 CFR 50.12. With these exemptions, the facility will operate, to the extent authorized herein, in conformity with the application, as amended, the provisions of the Act, and the rules and regulations of the Commission.

E. The licensee shall fully implement and maintain in effect all provisions of the Commission-approved physical security, training and qualification, and safeguards contingency plans including amendments made pursuant to provisions of the Miscellaneous Amendments and Search Requirements revisions to 10 CFR 73.55 (51 FR 27817 and 27822) and to the authority of 10 CFR 50.90 and 10 CFR 50.54(p). The plans, submitted by letter dated May 19, 2006 are entitled: "Salem-Hope Creek Nuclear Generating Station Security Training and Qualification Plan," and "Salem-Hope Creek Nuclear Generating Station Security Contingency Plan." The plans contain Safeguards Information protected under 10 CFR 73.21.

PSEG Nuclear LLC shall fully implement and maintain in effect all provisions of the Commission-approved Cyber Security Plan (CSP), including changes made pursuant to the authority of 10 CFR 50.90 and 10 CFR 50.54(p). The Salem­Hope Creek CSP was approved by License Amendment No. 189 as supplemented by changes approved by License Amendment Nos. 192 and 197.

F. DELETED

G. The licensees shall have and maintain financial protection of such type and in such amounts as the Commission shall require in accordance with Section 170 of the Atomic Energy Act of 1954, as amended, to cover public liability claims.

Renewed License No. NPF-57 Amendment No. 197

Page 7: NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. … · Notice of Issuance will be included in the Commission's biweekly Federal Register notice. Docket Nos. 50-354, 50-272 and 50-311

UNITED STATES NUCLEAR REGULATORY COMMISSION

WASHINGTON, D.C. 20555-0001

PSEG NUCLEAR, LLC

EXELON GENERATION COMPANY, LLC

DOCKET NO. 50-272

SALEM NUCLEAR GENERATING STATION, UNIT NO. 1

AMENDMENT TO FACILITY OPERATING LICENSE

Amendment No. 306 Renewed License No. DPR-70

1. The Nuclear Regulatory Commission (the Commission) has found that:

A The application for amendment filed by PSEG Nuclear LLC, acting on behalf of itself and Exelon Generation Company, LLC (the licensees) dated December 24, 2013, as supplemented by letters dated June 23, 2014, and August 18, 2014, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Commission's rules and regulations set forth in Title 10 of the Code of Federal Regulations (1 0 CFR), Chapter I;

B. The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission;

C. There is reasonable assurance: (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commission's regulations;

D. The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and

E. The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commission's regulations and all applicable requirements have been satisfied.

2. Accordingly, the second paragraph of 2.E of Renewed Facility Operating License No. DPR-70 is hereby amended as follows:

PSEG Nuclear LLC shall fully implement and maintain in effect all provisions of the Commission-approved Cyber Security Plan (CSP), including changes made pursuant to the authority of 10 CFR 50.90 and 10 CFR 50.54(p). The Salem­Hope Creek CSP was approved by License Amendment No. 300 as supplemented by changes approved by License Amendment Nos. 302 and 306.

Enclosure 2

Page 8: NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. … · Notice of Issuance will be included in the Commission's biweekly Federal Register notice. Docket Nos. 50-354, 50-272 and 50-311

- 2 -

3. This license amendment is effective as of its date of issuance and shall be implemented within 60 days. The implementation of the Cyber Security Plan (CSP), including the key intermediate milestone dates and the full implementation date, shall be in accordance with the implementation schedule, as submitted by the licensee by letter dated June 6, 2011, as revised by letters dated July 26, 2012, and December 24, 2013, and as approved by the NRC staff with this license amendment. All subsequent changes to the NRC-approved CSP implementation schedule will require prior NRC approval, pursuant to 10 CFR 50.90.

Attachment: Changes to the Renewed Facility

Operating License No. DPR-70

Date of Issuance: December 23, 2014

FOR THE NUCLEAR REGULATORY COMMISSION

Meena K. Khanna, Chief Plant Licensing Branch 1-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation

Page 9: NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. … · Notice of Issuance will be included in the Commission's biweekly Federal Register notice. Docket Nos. 50-354, 50-272 and 50-311

ATTACHMENT TO LICENSE AMENDMENT NO. 306

RENEWED FACILITY OPERATING LICENSE NO. DPR-70

DOCKET NO. 50-272

Replace the following page of Renewed Facility Operating License No. DPR-70 with the attached revised page as indicated. The revised page is identified by amendment number and contains marginal lines indicating the areas of change.

Remove

Page 9 Page 9

Page 10: NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. … · Notice of Issuance will be included in the Commission's biweekly Federal Register notice. Docket Nos. 50-354, 50-272 and 50-311

- 9 -

evaluates such changes pursuant to the criteria set forth in 10 CFR 50.59 and otherwise complies with the requirements in that section.

(19) Appendix A of NUREG-2101, "Safety Evaluation Report Related to the License Renewal of Salem Nuclear Generating Station," dated June 2011, and PSEG Nuclear LLC UFSAR supplement submitted pursuant to 10 CFR 54.21(d), as revised on May 18, 2011, describe certain future programs and activities to be completed before the period of extended operation. PSEG Nuclear LLC shall complete these activities no later than August 13, 2016, and shall notify the NRC in writing when implementation of these activities is complete.

(20) All capsules in the reactor vessel that are removed and tested must meet the test procedures and reporting requirements of American Society for Testing and Materials (ASTM) E 185-82 to the extent practicable for the configuration of the specimens in the capsule. Any changes to the capsule withdrawal schedule, including spare capsules, must be approved by the NRC prior to implementation. All capsules placed in storage must be maintained for future insertion. Any changes to storage requirements must be approved by the NRC. Changes to the withdrawal schedule or storage requirements shall be submitted to the NRC as a report in accordance with 10 CFR 50.4.

(21) PSEG Nuclear LLC shall take one core sample in the Unit 1 spent fuel pool west wall, by the end of 2013, and one core sample in the east wall where there have been indications of borated water ingress through the concrete, by the end of 2015. The core samples (east and west walls) will expose the rebar, which will be examined for signs of corrosion. Any sample showing signs of concrete degradation and/or rebar corrosion will be entered into the licensee's corrective action program for further evaluation. PSEG Nuclear LLC shall submit a report in accordance with 10 CFR 50.4 no later than three months after each sample is taken on the results, recommendations, and any additional planned actions.

D. Paragraph 2.0. has been combined with paragraph 2.E. per Amendment No. 86, June 27, 1988.

E. The licensee shall fully implement and maintain in effect all provisions of the Commission-approved physical security, training and qualification, and safeguards contingency plans including amendments made pursuant to provisions of the Miscellaneous Amendments and Search Requirements revisions to 10 CFR 73.55 (51 FR 27817 and 27822) and to the authority of 10 CFR 50.90 and 10 CFR 50.54(p). The plans, submitted by letter dated May 19, 2006, are entitled: "Salem-Hope Creek Nuclear Generating Station Security Plan," "Salem-Hope Creek Nuclear Generating Station Security Training and Qualification Plan," and "Salem-Hope Creek Nuclear Generating Station Security Contingency Plan." The plans contain Safeguards Information protected under 10 CFR 73.21.

PSEG Nuclear LLC shall fully implement and maintain in effect all provisions of the Commission-approved Cyber Security Plan (CSP), including changes made pursuant to the authority of 10 CFR 50.90 and 10 CFR 50.54(p). The Salem-Hope Creek CSP was approved by License Amendment No. 300 as supplemented by changes approved by License Amendment Nos. 302 and 306.

Renewed License No. DPR-70 Amendment No. 306

Page 11: NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. … · Notice of Issuance will be included in the Commission's biweekly Federal Register notice. Docket Nos. 50-354, 50-272 and 50-311

UNITED STATES NUCLEAR REGULATORY COMMISSION

WASHINGTON, D.C. 20555-0001

PSEG NUCLEAR LLC

EXELON GENERATION COMPANY. LLC

DOCKET NO. 50-311

SALEM NUCLEAR GENERATING STATION. UNIT NO.2

AMENDMENT TO FACILITY OPERATING LICENSE

Amendment No. 288 Renewed License No. DPR-75

1. The Nuclear Regulatory Commission (the Commission) has found that:

A The application for amendment filed by PSEG Nuclear LLC, acting on behalf of itself and Exelon Generation Company, LLC (the licensees) dated December 24, 2013, as supplemented by letters dated June 23, 2014, and August 18, 2014, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Commission's rules and regulations set forth in Title 10 of the Code of Federal Regulations (1 0 CFR), Chapter I;

B. The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission;

C. There is reasonable assurance: (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commission's regulations;

D. The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and

E. The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commission's regulations and all applicable requirements have been satisfied.

2. Accordingly, the second paragraph of 2.E of Renewed Facility Operating License No. DPR-75 is hereby amended as follows:

PSEG Nuclear LLC shall fully implement and maintain in effect all provisions of the Commission-approved Cyber Security Plan (CSP), including changes made pursuant to the authority of 10 CFR 50.90 and 10 CFR 50.54(p). The Salem-Hope Creek CSP was approved by License Amendment No. 283 as supplemented by changes approved by License Amendment Nos. 285 and 288.

Enclosure 3

Page 12: NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. … · Notice of Issuance will be included in the Commission's biweekly Federal Register notice. Docket Nos. 50-354, 50-272 and 50-311

- 2-

3. This license amendment is effective as of its date of issuance and shall be implemented within 60 days. The implementation of the Cyber Security Plan (CSP), including the key intermediate milestone dates and the full implementation date, shall be in accordance with the implementation schedule, as submitted by the licensee by letter dated June 6, 2011, as revised by letters dated July 26, 2012, and December 24, 2013, and as approved by the NRC staff with this license amendment. All subsequent changes to the NRC-approved CSP implementation schedule will require prior NRC approval, pursuant to 10 CFR 50.90.

Attachment: Changes to the Renewed Facility

Operating License No. DPR-75

Date of Issuance: December 23, 2014

FOR THE NUCLEAR REGULATORY COMMISSION

Meena K. Khanna, Chief Plant Licensing Branch 1-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation

Page 13: NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. … · Notice of Issuance will be included in the Commission's biweekly Federal Register notice. Docket Nos. 50-354, 50-272 and 50-311

ATTACHMENT TO LICENSE AMENDMENT NO. 288

RENEWED FACILITY OPERATING LICENSE NO. DPR-75

DOCKET NO. 50-311

Replace the following page of Renewed Facility Operating License No. DPR-75 with the attached revised page as indicated. The revised page is identified by amendment number and contains marginal lines indicating the areas of change.

Remove

Page 11 Page 11

Page 14: NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. … · Notice of Issuance will be included in the Commission's biweekly Federal Register notice. Docket Nos. 50-354, 50-272 and 50-311

- 11 -

issuance of the License for Fuel-Loading and Low-Power Testing, dated April 18, 1980. The facility will operate, to the extent authorized herein, in conformity with the application as amended, the provisions of the Act, and the regulations of the Commission.

E. The licensee shall fully implement and maintain in effect all provisions of the Commission-approved physical security, training and qualification, and safeguards contingency plans including amendments made pursuant to provisions of the Miscellaneous Amendments and Search Requirements revisions to 10 CFR 73.55 (51 FR 27817 and 27822) and to the authority of 10 CFR 50.90 and 10 CFR 50.54 (p). The plans, submitted by letter dated May 19, 2006, are entitled: "Salem-Hope Creek Nuclear Generating Station Security Plan," "Salem-Hope Creek Nuclear Generating Station Security Training and Qualification Plan," and "Salem-Hope Creek Nuclear Generating Station Security Contingency Plan." The plans Contain Safeguards Information protected under 10 CFR 73.21.

PSEG Nuclear LLC shall fully implement and maintain in effect all provisions of the Commission-approved Cyber Security Plan (CSP), including changes made pursuant to the authority of 10 CFR 50.90 and 10 CFR 50.54(p). The Salem-Hope Creek CSP was approved by License Amendment No. 283 as supplemented by changes approved by License Amendment Nos. 285 and 288.

F. A temporary exemption from General Design Criterion 57 found in Appendix A to 10 CFR Part 50 is described in the Office of Nuclear Reactor Regulation's Safety Evaluation Report, Supplement No. 5, Section 6.2.3.1. This Exemption is authorized by law and will not endanger life or property or the common defense and security and is otherwise in the public interest. The exemption, therefore, is hereby granted and shall remain in effect through the first refueling outage as discussed in Section 6.2.3.1 of Supplement 5 to the Safety Evaluation Report. The granting of the exemption is authorized with the issuance of the Facility Operating License, dated May 20, 1981. The facility will operate, to the extent authorized herein, in conformity with the application as amended, the provisions of the Act, and the regulations of the Commission.

G. This renewed license is subject to the following additional condition for the protection of the environment:

Before engaging in additional construction or operational activities which may result in an environmental impact that was not evaluated by the Commission, PSEG Nuclear LLC shall prepare and record an environmental evaluation of such activity. When the evaluation indicates that such activity may result in a significant adverse environmental impact that was not evaluated, or that is significantly greater than that evaluated in the Final Environmental Statement or any addendum thereto, PSEG Nuclear LLC shall provide a written evaluation of such activities and obtain prior approval from the Director of Nuclear Reactor Regulation.

H. If PSEG Nuclear LLC plans to remove or to make significant changes in the normal operation of equipment that controls the amount of radioactivity in effluents from the Salem Nuclear Generation Station, the NRC shall be notified in writing regardless of whether the change affects the amount of radioactivity in effluents.

I. DELETED

Renewed License No. DPR-75 Amendment No. 288

Page 15: NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. … · Notice of Issuance will be included in the Commission's biweekly Federal Register notice. Docket Nos. 50-354, 50-272 and 50-311

UNITED STATES NUCLEAR REGULATORY COMMISSION

WASHINGTON, D.C. 20555-0001

SAFETY EVALUATION BY THE OFFICE OF NUCLEAR REACTOR REGULATION

RELATED TO AMENDMENT NOS. 197, 306 and 288

TO RENEWED FACILITY OPERATING LICENSE NO. NPF-57

PSEG NUCLEAR, LLC

HOPE CREEK GENERATING STATION

DOCKET NO. 50-354

AND TO RENEWED FACILITY OPERATING LICENSE NOS. DPR-70 AND DPR-75

PSEG NUCLEAR, LLC

EXELON GENERATION COMPANY, LLC

SALEM NUCLEAR GENERATING STATION, UNIT NOS. 1 AND 2

DOCKET NOS. 50-272 AND 50-311

1.0 INTRODUCTION

By letter dated December 24, 2013, as supplemented by letters dated June 23, 2014, and August 18, 2014 (Agencywide Document Access and Management System (ADAMS) Accession Nos. ML 14016A079, ML 14174B239, and ML 14231A048, respectively), PSEG Nuclear, LLC (PSEG, or the licensee) submitted license amendment requests for the Hope Creek Generating Station (Hope Creek or HCGS) and Salem Nuclear Generating Station (Salem), Unit Nos. 1 and 2. Portions of the letters dated December 24, 2013, and August 18, 2014, are withheld from public disclosure in accordance with Title 10 of the Code of Federal Regulations (10 CFR) Section 2.390(d)(1).

The proposed change would revise the Cyber Security Plan (CSP) Milestone 8 completion date. In addition, the amendments would revise the existing license condition in each of the three facility operating licenses which requires the licensee to fully implement and maintain in effect all provisions of the U.S. Nuclear Regulatory Commission (NRC or Commission)-approved CSP. Milestone 8 of the CSP implementation schedule concerns the full implementation of the CSP.

The CSP and associated implementation schedule for Hope Creek and Salem, Unit Nos. 1 and 2, were previously approved by the NRC staff by letters dated July 28, 2011 (ADAMS Accession No. ML 111861560), and December 10, 2012 (ADAMS Accession No. ML 12335A221 ).

Enclosure 4

Page 16: NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. … · Notice of Issuance will be included in the Commission's biweekly Federal Register notice. Docket Nos. 50-354, 50-272 and 50-311

- 2 -

The supplements dated June 23, 2014, and August 18, 2014, provided additional information that clarified the application, did not expand the scope of the application as originally noticed, and did not change the NRC staff's original proposed no significant hazards determination as published in the Federal Register on September 9, 2014 (79 FR 53461).

2.0 REGULATORY EVALUATION

The NRC staff reviewed and approved the licensee's CSP implementation schedule by License Amendment Nos. 189, 300, and 283, dated July 28, 2011, and incorporated the CSP into the facilities' current licensing basis. The NRC staff reviewed and approved the licensee's revised CSP by License Amendment Nos. 192, 302 and 285, dated December 10, 2012.

The revised amendments included the following statement:

The implementation of the Cyber Security Plan (CSP), including the key intermediate milestone dates and the full implementation date, shall be in accordance with the implementation schedule, as submitted by the licensee by letter dated June 6, 2011, as revised by letter dated July 26, 2012, and as approved by the NRC staff with this license amendment. All subsequent changes to the NRC-approved CSP implementation schedule will require prior NRC approval, pursuant to 10 CFR 50.90.

The NRC staff considered the following regulatory requirements and guidance in its review of the current license amendment request to modify the existing CSP implementation schedule:

• The regulations in 10 CFR 73.54, "Protection of digital computer and communication systems and networks," state, in part, that "[e]ach [CSP] submittal must include a proposed implementation schedule. Implementation of the licensee's cyber security program must be consistent with the approved schedule."

• The licensee's renewed FOLs include license condition 2.E, which requires the licensee to fully implement and maintain in effect all provisions of the Commission-approved CSP.

• Review criteria provided by the NRC staff in a memorandum dated October 24, 2013, "Review Criteria for Title 10 of The Code of Federal Regulations Part 73.54, Cyber Security Implementation Schedule Milestone 8 License Amendment Requests," (ADAMS Accession No. ML 13295A467), to be considered for evaluating licensees' requests to postpone their cyber security program implementation date (commonly known as Milestone 8).

The NRC staff does not regard the CSP milestone implementation dates as regulatory commitments that can be changed unilaterally by the licensee, particularly in light of the regulatory requirement at 10 CFR 73.54, that "[i]mplementation of the licensee's cyber security program must be consistent with the approved schedule." As the NRC staff explained in its letter to all operating reactor licensees dated May 9, 2011 (ADAMS Accession

Page 17: NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. … · Notice of Issuance will be included in the Commission's biweekly Federal Register notice. Docket Nos. 50-354, 50-272 and 50-311

- 3 -

No. ML 11 0980538), the implementation of the plan, including the key intermediate milestone dates and the full implementation date shall be in accordance with the implementation schedule submitted by the licensee and approved by the NRC. All subsequent changes to the NRC­approved CSP implementation schedule, thus, will require prior NRC approval as required by 10 CFR 50.90.

3.0 TECHNICAL EVALUATION

3.1 Background

Amendment Nos. 189, 300, and 283, were issued on July 28, 2011, to renewed FOLs for Hope Creek and Salem, Units 1 and 2, respectively. The NRC staff also approved the licensee's CSP implementation schedule, as discussed in the safety evaluation issued with the amendments. The implementation schedule was based on a template prepared by the Nuclear Energy Institute (NEI), which the NRC staff found acceptable for licensees to use to develop their CSP implementation schedules (ADAMS Accession No. ML 110600218). The licensee's proposed implementation schedule for the Cyber Security Program identified completion dates and bases for the following eight milestones:

1. Establish the Cyber Security Assessment Team (CSAT);

2. Identify Critical Systems (CSs) and Critical Digital Assets (CDAs);

3. Install a deterministic one-way device between lower level devices and higher level devices;

4. Implement the security control "Access Control For Portable And Mobile Devices;"

5. Implement observation and identification of obvious cyber-related tampering to existing insider mitigation rounds by incorporating the appropriate elements;

6. Identify, document, and implement technical cyber security controls in accordance with Mitigation of Vulnerabilities and Application of Cyber Security Controls for CDAs that could adversely impact the design function of physical security target set equipment;

7. Commence ongoing monitoring and assessment activities for those target set CDAs whose security controls have been implemented; and

8. Fully implement the CSP for all safety, security, and emergency preparedness functions (Milestone 8).

Amendment Nos. 192, 302, and 285, dated December 10, 2012, revised the scope of Milestone 6.

3.2 Licensee's Proposed Change

Currently, Milestone 8 of the licensee's CSP requires PSEG to fully implement the CSP by December 31, 2014. In its December 24, 2013, application, PSEG proposed to change the

Page 18: NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. … · Notice of Issuance will be included in the Commission's biweekly Federal Register notice. Docket Nos. 50-354, 50-272 and 50-311

- 4-

Milestone 8 completion date to June 30, 2017. The licensee stated that there is no change to the cyber security program, other than the change of the completion date.

3.3 NRC Staff Evaluation

The licensee's request dated December 24, 2013, is consistent with the October 24, 2013, NRC staff guidance, which was developed to evaluate requests to postpone Milestone 8 implementation dates. The intent of the cyber security implementation schedule was for licensees to demonstrate ongoing implementation of their CSP prior to full implementation, which is set for the date specified in Milestone 8. Activities include establishing a CSA T, identifying CSs and CDAs, installing deterministic one-way devices between defensive levels, implementing access control for portable and mobile devices, implementing methods to observe and identify obvious cyber related tampering, and conducting ongoing monitoring and assessment activities for target set CDAs. In their aggregate, the interim milestones demonstrate ongoing implementation of the CSP.

The criteria stated in the guidance document dated October 24, 2013, and addressed by the licensee as justification for its request are:

1. Identification of the specific requirement or requirements of the cyber security plan that the licensee needs additional time to implement.

2. Detailed justification that describes the reason the licensee requires additional time to implement the specific requirement or requirements identified.

3. A proposed completion date for Milestone 8 consistent with the remaining scope of work to be conducted and the resources available.

4. An evaluation of the impact that the additional time to implement the requirements will have on the effectiveness of the licensee's overall cyber security program in the context of milestones already completed.

5. A description of the licensee's methodology for prioritizing completion of work for critical digital assets associated with significant safety, security, or emergency preparedness consequences and with reactivity effects in the balance of plant.

6. A discussion of the licensee's cyber security program performance up to the date of the license amendment request.

7. A discussion of cyber security issues pending in the licensee's corrective action program.

8. A discussion of modifications completed to support the cyber security program and a discussion of pending cyber security modifications.

The NRC staff has evaluated the licensee's application based on the above review criteria.

Page 19: NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. … · Notice of Issuance will be included in the Commission's biweekly Federal Register notice. Docket Nos. 50-354, 50-272 and 50-311

- 5-

1. Identification of the specific requirement or requirements of the CSP that the licensee needs additional time to implement.

The licensee stated that the requirement of the CSP that it needs additional time to implement is CSP Section 3.1, "Analyzing Digital Computer Systems and Networks and Applying Cyber Security Controls." The licensee further noted that there are ongoing issues that need resolution prior to completing implementation of Section 3.1. These include NRC and industry discussions about CDA scope; regulatory guidance for addressing cyber security controls for various hardware and software platforms; CDA assessment rework; engineering and information technology design, planning and scheduling of remediation activities; change management; and training on new programs, processes and procedures.

2. Detailed justification that describes the reason the licensee requires additional time to implement the specific requirement or requirements identified.

The licensee stated it is experiencing challenges with full implementation of Milestone 8. These include the large number of CDAs (over 2000 between the three facilities) which has resulted in significant effort to complete tabletop reviews and validation testing required by Section 3.1.5. The licensee also stated "[t]he absence of guidance for addressing cyber security controls for the varied discrete, digital hardware and software platforms has impacted PSEG's ability to complete assessment work with consistent outcomes and in a way that provides reasonable assurance that assessment results and conclusions will not be subject to regulatory uncertainty." The licensee provided detailed justification for additional time to fully implement the CSP per Section 3.1, quoted below as follows:

a) Resolution of NEI/NRC discussion on CDA scope and security controls: • The anticipated resolution time frame does not align with the current

Salem and Hope Creek M8 [Milestone 8] date. • Resultant CDA/security controls scope changes will impact M8

completion. • Likely scope changes concerning CDA identification and security controls

will require significant rework such as: o Changes to newly issued procedures and updating existing

procedures; o Revision of training materials and delivery of training; o CDA Assessment Tool rework, programming, and validation; o Rework to revise completed CDA assessment work; and o Rework of the completed draft Security Controls Implementation

Strategy (SCIS), which is on-hold pending the outcome of NEI/NRC discussions concerning NEI 13-10, "Cyber Security Control Assessments," Revision 0

b) Attempts to define the cyber security controls in NEI 08-09, Revision 6, have been unsuccessful:

• NEI 10-09, "Addressing Cyber Security Controls for Nuclear Power Reactors," Revision 0, was not endorsed by the NRC.

Page 20: NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. … · Notice of Issuance will be included in the Commission's biweekly Federal Register notice. Docket Nos. 50-354, 50-272 and 50-311

- 6-

• NUREG/CR-7140 (cyber security controls interpretation guidelines) has not been distributed for industry review and comment.

• NEI 13-10, "Cyber Security Control Assessments," Revision 0 has not been endorsed by the NRC.

c) CDA Assessment work is resource intensive: • PSEG has over 2,000 CDAs for Salem, Hope Creek, and Common.

While some of these CDAs can be grouped to reduce assessment burden, completing assessments using the Section 3.1.6 methodology is resource intensive.

• Configuration of the assessment tool cannot be completed due to uncertainty surrounding interpretation of the security controls.

• Until the guidance is endorsed by the NRC, proceeding with CDA assessments would create the potential for significant rework that was not accounted for in the original project scope.

d) The technical bases for required remediation activities need to be well-defined and provide a clear security benefit:

• CDA security control modifications are new to both plant personnel and equipment suppliers.

• Plant modifications must be carefully implemented to ensure they do not impact plant safety and operation. PSEG has experienced challenges with cyber security equipment suppliers' understanding of their own products and their limitations. These challenges have resulted in delays in the implementation of the PSEG CSP. Additionally, suppliers are releasing products that have not been adequately documented and tested, which results in corrective action investigations and potential regulatory compliance challenges.

e) Challenges in incorporating Cyber Security Controls in plant processes: • Cyber security is challenging since it requires integration with daily plant

operations, maintenance, engineering, and procurement activities. • Integration of cyber security controls is taking longer than expected due to

impacts on the work control process and maintenance activities. • Cyber security for plant CDAs is new, and the security controls being

implemented on the plant CDAs are new to Maintenance, System Engineering, and Operations. Modifications must be implemented with careful planning to ensure safe reliable operation of plant equipment. Before modifications are implemented, significant verification analysis and testing must be performed to minimize potential impacts to plant equipment.

• Implementation of the many required recurring tasks of NEI 08-09, Revision 6 requires changes to planned maintenance routines based on assessment results and conclusions. New maintenance tasks must be created for each CDA to support implementing recurring tasks such as reviewing CDA accounts, changing passwords, scans for wireless and

Page 21: NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. … · Notice of Issuance will be included in the Commission's biweekly Federal Register notice. Docket Nos. 50-354, 50-272 and 50-311

- 7-

rogue connections, reviewing logs, security control functionality checks, etc.

• Many devices in production at PSEG do not support the NEI 08-09, Revision 6 security controls. Many simple, low-functionality CDAs cannot be procured with basic security control functionality such as identification, authentication, and accountability.

f) Training on new programs, processes, and procedures: • The site training needs and schedules are normally established up to a

year in advance and have to be presented to, and approved by, the PSEG Training Review Boards. Cyber security training adds a new burden on training resources that was not fully understood when the new cyber-related processes and procedures were first being developed. Cyber security training needs can be accommodated outside of normal training cycles, but adds an unanticipated burden on training resources.

3. A proposed completion date for Milestone 8 consistent with the remaining scope of work to be conducted and the resources available.

The licensee proposed a Milestone 8 completion date of June 30, 2017, and stated that the revised Milestone 8 date will encompass at least one additional refueling outage for each unit and will provide adequate time to plan and schedule the implementation of design changes. Additionally, the licensee noted the revised completion date will help to avoid rework that could result from ongoing discussions between NEI and NRC concerning the scope and application of security controls (CSP Section 3.1 ).

4. An evaluation of the impact that the additional time to implement the requirements will have on the effectiveness of the licensee's overall CSP in the context of milestones already completed.

In its letter dated December 24, 2013, the licensee stated, in part, that:

Based on cyber security implementation activities already completed, and completion of activities in progress, the Salem and Hope Creek plants are secure and will continue to ensure that the digital computer and communication systems and networks are adequately protected against cyber attacks during implementation of the remainder of the full program by the proposed [Milestone 8] date of June 30, 2017.

In addition, the licensee provided the details of the activities completed in each of the Milestones 1 through 7. The activities address significant cyber attack vectors.

5. A description of the licensee's methodology for prioritizing completion of work for critical digital assets associated with significant safety consequences and with reactivity effects in the balance of plant.

The licensee stated in its letter dated August 18, 2014, that CDAs will be logically grouped and assessments will be prioritized base on safety, important to safety (balance of plant),

Page 22: NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. … · Notice of Issuance will be included in the Commission's biweekly Federal Register notice. Docket Nos. 50-354, 50-272 and 50-311

- 8-

and security significance, to the extent practical. The methodology is based on defense-in­depth, installed configuration of the CDA and susceptibility to five commonly identified threat vectors.

6. A discussion of the licensee's CSP performance up to the date of the license amendment request.

In its letter dated December 24, 2013, the licensee stated that interim CSP Milestones 1 through 7 actions was successfully completed by December 31, 2012. The licensee stated that compliance of the HCGS and Salem Cyber Security programs with Milestones 1 through 7 was verified through a focused self-assessment with industry peers in May 2013. In addition, performance deficiencies and recommendations to close program performance gaps are entered in PSEG's corrective action program (CAP).

7. A discussion of cyber security issues pending in the licensee's CAP.

The licensee stated that the CAP database is used to document and track, from initiation through closure, all cyber security required corrective actions including issues identified during on-going program assessment activities cyber security issues. In addition, the licensee uses the CAP database to trend, correct, and improve the CSP and monitor and address adverse trends. The licensee provided the following examples of pending cyber security issues and activities in its CAP:

• Full Program (Milestone 8) implementation tracking

• Peer inspection findings and industry lessons learned

• July 1, 2013, Enforcement Discretion Memorandum

• Security Frequently Asked Question (SFAQs), and

• Issues documented for program improvements.

8. A discussion of modifications completed to support the cyber security program and a discussion of pending cyber security modifications.

In its letter dated December 24, 2013, the licensee provided a brief discussion of a completed modification and pending modifications.

The licensee indicated that completion of the activities associated with the CSP, as described in Milestones 1 through 7 and completed prior to December 31, 2012, provide significant protection against cyber attacks. The NRC staff finds that the licensee's site is much more secure after implementation of Milestones 1 through 7 because the activities the licensee completed mitigate significant cyber attack vectors. Therefore, the NRC has reasonable assurance that full implementation of the CSP by June 30, 2017, will provide adequate protection of the public health and safety and the common defense and security.

Page 23: NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. … · Notice of Issuance will be included in the Commission's biweekly Federal Register notice. Docket Nos. 50-354, 50-272 and 50-311

- 9-

The NRC staff finds that the actions the licensee noted as being required to implement CSP Section 3.1 are reasonable. The licensee stated that additional time is needed to conduct modifications and change management planning activities and execution. The staff recognizes that CDA assessment work is much more complex and resource intensive than originally anticipated, in part due to the NRC expanding the scope of the cyber security requirements to include balance of plant. As a result, the licensee has a large number of additional tasks not originally considered when developing its CSP implementation schedule. The staff finds that the licensee's request to delay final implementation of the CSP until June 30, 2017, is reasonable given the complexity and volume of the remaining unanticipated work.

The licensee proposed a Milestone 8 completion date of June 30, 2017. The licensee stated that changing the completion date of Milestone 8 will provide adequate time to plan and schedule implementation of design changes, as well as allowing time for at least one additional refueling outage for each unit. The licensee stated its methodology for prioritizing completion of cyber security activities and that the remaining Milestone 8 actions will be completed by June 30, 2017. The NRC staff finds that based on the large number of digital assets described above and the limited resources with the appropriate expertise to perform these activities, the licensee's methodology for prioritizing work on CDAs is appropriate. The staff further finds that the licensee's request to delay final implementation of the CSP until June 30, 2017, is reasonable given the complexity of the remaining unanticipated work.

3.4 Technical Evaluation Conclusion

The NRC staff concludes that the licensee's request to delay full implementation of its CSP until June 30, 2017, is reasonable for the following reasons: (i) the licensee's implementation of Milestones 1 through 7 provides mitigation for significant cyber attack vectors for the most significant CDAs as discussed in the staff evaluation above; (ii) the scope of the work required to come into full compliance with the CSP implementation schedule was much more complicated than anticipated and not reasonably foreseeable when the CSP implementation schedule was originally developed; and (iii) the licensee has reasonably prioritized and scheduled the work required to come to full compliance with its CSP implementation schedule.

3.5 Revision to License Condition

By letter dated December 24, 2013, the licensee proposed to modify the second paragraph of 2.E of each of the renewed FOLs, which provides license conditions to require the licensee to fully implement and maintain in effect all provisions of the NRC-approved CSP.

Based on the NRC staff's review, the license condition in the second paragraph of 2.E of Renewed FOL No. NPF-57 for HCGS is modified as follows:

PSEG Nuclear LLC shall fully implement and maintain in effect all provisions of the Commission-approved Cyber Security Plan (CSP), including changes made pursuant to the authority of 10 CFR 50.90 and 10 CFR 50.54(p). The Salem­Hope Creek CSP was approved by License Amendment No. 189 as supplemented by changes approved by License Amendment Nos. 192 and 197.

Page 24: NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. … · Notice of Issuance will be included in the Commission's biweekly Federal Register notice. Docket Nos. 50-354, 50-272 and 50-311

- 10-

Based on the NRC staff's review, the license condition in the second paragraph of 2.E of Renewed FOL No. DPR-70 for Salem Generating Station, Unit No. 1 is modified as follows:

PSEG Nuclear LLC shall fully implement and maintain in effect all provisions of the Commission-approved Cyber Security Plan (CSP), including changes made pursuant to the authority of 10 CFR 50.90 and 10 CFR 50.54(p). The Salem­Hope Creek CSP was approved by License Amendment No. 300 as supplemented by changes approved by License Amendment Nos. 302 and 306.

Based on the NRC staff's review, the license condition in the second paragraph of 2.E of Renewed FOL No. DPR-75 for Salem Generating Station, Unit No.2 is modified as follows:

PSEG Nuclear LLC shall fully implement and maintain in effect all provisions of the Commission-approved Cyber Security Plan (CSP), including changes made pursuant to the authority of 10 CFR 50.90 and 10 CFR 50.54(p). The Salem­Hope Creek CSP was approved by License Amendment No. 283 as supplemented by changes approved by License Amendment Nos. 285 and 288.

4.0 STATE CONSULTATION

In accordance with the Commission's regulations, the New Jersey State Official was notified of the proposed issuance of the amendment. The State official had no comments.

5.0 ENVIRONMENTAL CONSIDERATION

This amendment relates solely to safeguards matters and does not involve any significant construction impacts. This amendment is an administrative change to extend the date by which the licensee must have its cyber security plan fully implemented. Accordingly, the amendment meets the eligibility criteria for categorical exclusion set forth in 10 CFR 51.22(c)(12). Pursuant to 10 CFR 51.22(b), no environmental impact statement or environmental assessment need be prepared in connection with the issuance of the amendment.

6.0 CONCLUSION

The Commission has concluded, based on the considerations discussed above, that: (1) there is reasonable assurance that the health and safety of the public will not be endangered by operation in the proposed manner, (2) there is reasonable assurance that such activities will be conducted in compliance with the Commission's regulations, and (3) the issuance of the amendment will not be inimical to the common defense and security or to the health and safety of the public.

Principal Contributor: J. Rycyna, NSIR/CSD

Date: December 23, 2014

Page 25: NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. … · Notice of Issuance will be included in the Commission's biweekly Federal Register notice. Docket Nos. 50-354, 50-272 and 50-311

T. Joyce - 2-

A copy of our safety evaluation is also enclosed. Notice of Issuance will be included in the Commission's biweekly Federal Register notice.

Sincerely,

IRA/

Carleen J. Parker, Project Manager Plant Licensing Branch 1-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation

Docket Nos. 50-354, 50-272 and 50-311

Enclosures: 1. Amendment No. 197 to NPF-57 2. Amendment No. 306 to DPR-70 3. Amendment No. 288 to DPR-75 4. Safety Evaluation

cc w/encls: Distribution via Listserv

DISTRIBUTION: PUBLIC RidsAcrsAcnw_MaiiCTR Resource RidsNrrDoriDpr Resource RidsNs:rCsdResource RidsNrrLAABaxter Resource RidsRgn1 MaiiCenter Resource

LPLI-2 R/F RidsNrrDirsltsb Resource RidsNrrDorllpl1-2 Resource RidsNrrPMHopeCreek Resource RidsNrrPMSalem Resource J. Rycyna, NSIR

ADAMS Accession No.: ML 14323A974 *email dated OFFICE NRR/LPLI-2PM NRR/LPLI-2/LA NSIR/CSD/DD*

NAME CParker ABaxter (MHenderson for) RFelts

DATE 12/01/14 11/24/14 11/06/14

OFFICE OGC NRR/LPLI-2/BC NRR/LPLI-2PM

NAME SCI ark MKhanna CParker

DATE 12/18/14 12/23/14 12/23/14

OFFICIAL RECORD COPY