2 Presentation title - edit in the Master slide
Emerging Europe
Civil Nuclear Opportunities
Jonathan Allen 27 January 2014, London
![Page 3: Nuclear in emerging europe ukti export showcase 2014](https://reader034.vdocuments.site/reader034/viewer/2022052619/5570c0cbd8b42a4f6e8b52f6/html5/thumbnails/3.jpg)
3
What is Emerging Europe? • Nine countries - stretching from Slovenia to Romania,
from Poland to Croatia
• All EU regulated, part of the EU’s Single Market • 110 million consumers
• A combined GDP of over £ 1 trillion • Potential to double exports by 2020
• Lower risk profile than other distant emerging markets
• Easy and low cost access – just 2-3 hours from the UK
• Proven market for UK businesses
![Page 4: Nuclear in emerging europe ukti export showcase 2014](https://reader034.vdocuments.site/reader034/viewer/2022052619/5570c0cbd8b42a4f6e8b52f6/html5/thumbnails/4.jpg)
4
Sustainable Medium-term Growth...
Average Annual GDP Growth Forecast (%)
2010-20 2020-30 2030-40
CEE Average 4.7 4.2 3.8
Dev. World 1.8 1.8 1.9
Asia 5.8 5.1 4.7
Latin America 4.9 4.5 4.1
...on a par with other emerging economies
Source: HSBC The World in 2050
![Page 5: Nuclear in emerging europe ukti export showcase 2014](https://reader034.vdocuments.site/reader034/viewer/2022052619/5570c0cbd8b42a4f6e8b52f6/html5/thumbnails/5.jpg)
5
Main Challenges
• Outdated perceptions of the region among UK businesses
• Bureaucracy • Transparency • Strong and increasing global
competition across the region
![Page 6: Nuclear in emerging europe ukti export showcase 2014](https://reader034.vdocuments.site/reader034/viewer/2022052619/5570c0cbd8b42a4f6e8b52f6/html5/thumbnails/6.jpg)
6
Civil nuclear opportunities across “Emerging Europe” Country New Build Life Extension Decommission Waste disposal
Bulgaria Kozloduy Unit 7 & Belene (x2)?
Kozloduy (5 & 6) Kozloduy (1-‐4) Radiana / NDF
Czech Rep. Temelin (x2) Dukovany -‐ -‐
Hungary Paks (x 2) Paks 1 -‐ LILW Repository
Poland New NNB (x2) -‐ -‐ -‐
Romania Chernovoda (Units 3 & 4)
Chernovoda (1 & 2)
-‐ Chernovoda WDF
Slovakia Mochovce (3 & 4) & Bohunice?
Bohunice V1 Jaslovské Bohunice
-‐
Slovenia Krsko (Unit 2) Krsko NNP -‐ LILW
UNCLASSIFIED
![Page 7: Nuclear in emerging europe ukti export showcase 2014](https://reader034.vdocuments.site/reader034/viewer/2022052619/5570c0cbd8b42a4f6e8b52f6/html5/thumbnails/7.jpg)
7 7
New Build –7 countries, over £66 bn
• Poland: 2 x new 3GW (each) power plants in 2024 & 2030 (£1 bn AUKV)
• Bulgaria: New Westinghouse AP1000 reactor at Kozloduy NPP – early 2020s (£800m)
• Czech Republic: New reactor at Temelin NPP in 2024 (£500m)
• Romania: 2 x CANDU 6 reactors at Cernavodă in 2022 (£400m)
![Page 8: Nuclear in emerging europe ukti export showcase 2014](https://reader034.vdocuments.site/reader034/viewer/2022052619/5570c0cbd8b42a4f6e8b52f6/html5/thumbnails/8.jpg)
8 8
Life Extension in 4 countries, over £2.1 bn
• Bulgaria: 20 year life extension, 2 VVER units, from 2014, £40m AUKV
• Romania: Replacing fuel channels in CANDU reactors, Cernavoda,£120m AUKV from 2018
• Slovenia: Life extension of Westinghouse PWR operating life in Krško, £15m AUKV
![Page 9: Nuclear in emerging europe ukti export showcase 2014](https://reader034.vdocuments.site/reader034/viewer/2022052619/5570c0cbd8b42a4f6e8b52f6/html5/thumbnails/9.jpg)
9 9
Decommissioning & Waste Management £3.5 bn across 5 markets
• Bulgaria: On-going decommissioning (4 units) and waste programme with UK firm (Nuvia Ltd) co-managing, £40m AUKV
• Romania: New waste repository project, starting 2015, £40m AUKV
• Slovakia: Ongoing tendering for decommissioning 2 units, £100m AUKV
![Page 10: Nuclear in emerging europe ukti export showcase 2014](https://reader034.vdocuments.site/reader034/viewer/2022052619/5570c0cbd8b42a4f6e8b52f6/html5/thumbnails/10.jpg)
10 It’s not just about world-class Civil Engineering....
UK Nuclear supply chain….
![Page 11: Nuclear in emerging europe ukti export showcase 2014](https://reader034.vdocuments.site/reader034/viewer/2022052619/5570c0cbd8b42a4f6e8b52f6/html5/thumbnails/11.jpg)
11
![Page 12: Nuclear in emerging europe ukti export showcase 2014](https://reader034.vdocuments.site/reader034/viewer/2022052619/5570c0cbd8b42a4f6e8b52f6/html5/thumbnails/12.jpg)
12
Our not-so-secret weapon!
![Page 13: Nuclear in emerging europe ukti export showcase 2014](https://reader034.vdocuments.site/reader034/viewer/2022052619/5570c0cbd8b42a4f6e8b52f6/html5/thumbnails/13.jpg)
13
Czech Republic: Bretislav Nitka • New Build (£17 bn AUKV)
• 2 companies (Westinghouse AP1000 and Rosatom VVER) under evaluation
• The winner should be announced in Q1 2015
![Page 14: Nuclear in emerging europe ukti export showcase 2014](https://reader034.vdocuments.site/reader034/viewer/2022052619/5570c0cbd8b42a4f6e8b52f6/html5/thumbnails/14.jpg)
14
Romania: Daniella Lulache • Building of 2 CANDU 6 reactors at Cernavoda
• Legal and consulting services - construction of 3rd & 4th reactors, Cernavoda
• LIL waste repository
![Page 15: Nuclear in emerging europe ukti export showcase 2014](https://reader034.vdocuments.site/reader034/viewer/2022052619/5570c0cbd8b42a4f6e8b52f6/html5/thumbnails/15.jpg)
15
Poland: Marzena Piszczek
• 2 x new 3 GW nuclear power plants in 2024 and 2030 (cca. £12 bln total cost)
• Owner’s Engineer tender (3 UK companies involved) – winner to be announced in Q1 2014
• Integrated Reactor tender to be issued in Q4 2014
![Page 16: Nuclear in emerging europe ukti export showcase 2014](https://reader034.vdocuments.site/reader034/viewer/2022052619/5570c0cbd8b42a4f6e8b52f6/html5/thumbnails/16.jpg)
16
Slovakia: Peter Liska • New NPP - Jaslovské Bohunice
• Decommissioning the two units of V1 - Jaslovské Bohunice NPP
• V1’s two reactors to be decommissioned in 2025
![Page 17: Nuclear in emerging europe ukti export showcase 2014](https://reader034.vdocuments.site/reader034/viewer/2022052619/5570c0cbd8b42a4f6e8b52f6/html5/thumbnails/17.jpg)
17
Bulgaria: Sashka Evtimova • 20 year life extension - Kozloduy Unit 5 & 6
• New Build - AP1000 reactor at Kozloduy
• Decommissioning - VVER reactors at Kozloduy site
![Page 18: Nuclear in emerging europe ukti export showcase 2014](https://reader034.vdocuments.site/reader034/viewer/2022052619/5570c0cbd8b42a4f6e8b52f6/html5/thumbnails/18.jpg)
18
Hungary: Csilla Toth • 2 new VVER nuclear power plants (Paks NNP)
• Ongoing project for 20 year life extension of 4 existing blocks (VVER-440)
• Final disposal facility for low- and intermediate-level wastes
![Page 19: Nuclear in emerging europe ukti export showcase 2014](https://reader034.vdocuments.site/reader034/viewer/2022052619/5570c0cbd8b42a4f6e8b52f6/html5/thumbnails/19.jpg)
19
Slovenia: Ales Bursic • Considering building 2nd nuclear reactor at Krško (~1.2 GW)
• Extension of operating life of Krško
• Decommissioning & Waste Management opportunities .
![Page 20: Nuclear in emerging europe ukti export showcase 2014](https://reader034.vdocuments.site/reader034/viewer/2022052619/5570c0cbd8b42a4f6e8b52f6/html5/thumbnails/20.jpg)
20
Croatia: Zeljko Tomsic • Hrvatska Elektroprivreda - co-owner of 696 MWe NPP Krško
in Slovenia
• Croatia has not yet reached the decision on the construction of NNB
• Preliminary activities – not carried out yet
![Page 21: Nuclear in emerging europe ukti export showcase 2014](https://reader034.vdocuments.site/reader034/viewer/2022052619/5570c0cbd8b42a4f6e8b52f6/html5/thumbnails/21.jpg)
21 Presentation title - edit in the Master slide
Follow up:
27 January 2014, London