NSTX Upgrade Test Cell Initial Schedule Vent vacuum vessel by 9/19 No vessel entry at this time Period of removals prior to start of outage: 9/19 – 10/14 Must complete by October 14th Machine Technicians will provide assistance Install new 118’ platform on west side by 10/14 Needed for racks being moved out of the way of NB2 Establish construction power by 10/14 Portable carts in 3 places in NTC Disconnect all power in NSTX Test Cell except construction power Will occur on 10/17 Assures all power has been removed from racks and equipment Marks the end of free access to the Test Cell 1 E. Perry 9/13/11

Upload: heather-gibson

Post on 18-Jan-2018

215 views

Category:

Documents


0 download

DESCRIPTION

NTC Layout at End of Upgrade 3E. Perry 9/13/11

TRANSCRIPT

Page 1: NSTX Upgrade Test Cell Initial Schedule Vent vacuum vessel by 9/19 No vessel entry at this time Period of removals prior to start of outage: 9/19 – 10/14

E. Perry 9/13/11 1

NSTX Upgrade Test Cell Initial Schedule

Vent vacuum vessel by 9/19No vessel entry at this time

Period of removals prior to start of outage: 9/19 – 10/14Must complete by October 14thMachine Technicians will provide assistance

Install new 118’ platform on west side by 10/14Needed for racks being moved out of the way of NB2

Establish construction power by 10/14Portable carts in 3 places in NTC

Disconnect all power in NSTX Test Cell except construction powerWill occur on 10/17Assures all power has been removed from racks and equipmentMarks the end of free access to the Test Cell

Page 2: NSTX Upgrade Test Cell Initial Schedule Vent vacuum vessel by 9/19 No vessel entry at this time Period of removals prior to start of outage: 9/19 – 10/14

E. Perry 9/13/11 2

NSTX Upgrade Test Cell Initial Schedule

Remove cable tray at top of machine start 10/18To provide access for structural modifications

Remove RF piping within 10’ of machine starts 10/18To provide access to the east side of the machine

Rack and equipment removals to make room for NB2 starts 10/18Removals by machine technicians working to written proceduresReviewed and coordinated by the Work Control Center

Removals of diagnostics from on/near vacuum vessel starts 10/18Start with Bays J, K, and LCoil up and protect cables, tubing and fibers

Structural modifications to umbrella and coil supports starts 1/2Grinding and welding involved in all bays – top, mid-plane and bottom

Page 3: NSTX Upgrade Test Cell Initial Schedule Vent vacuum vessel by 9/19 No vessel entry at this time Period of removals prior to start of outage: 9/19 – 10/14

E. Perry 9/13/11 3

NTC Layout at End of Upgrade

Page 4: NSTX Upgrade Test Cell Initial Schedule Vent vacuum vessel by 9/19 No vessel entry at this time Period of removals prior to start of outage: 9/19 – 10/14

E. Perry 9/13/11 4

NTC Layout at End of Upgrade

Page 5: NSTX Upgrade Test Cell Initial Schedule Vent vacuum vessel by 9/19 No vessel entry at this time Period of removals prior to start of outage: 9/19 – 10/14

E. Perry 9/13/11 5

NTC Layout at End of Upgrade