nstx-u fwp 2015 budget planning meeting-nstx upgrade status- ron strykowsky – 4/10/2013 1 nstx...

19
NSTX-U NSTX-U FWP 2015 Budget Planning Meeting-NSTX Upgrade Status- Ron Strykowsky – 4/10/2013 1 NSTX Upgrade NSTX Upgrade Progress Overview Progress Overview Ron Strykowsky Erik Perry, Tim Stevenson, Larry Dudek, Steve Langish, Tom Egebo, Mike Williams and the NSTXU Project Team FWP FY2015 Budget Planning Meeting April 10, 2013 NSTX-U NSTX-U Supported by Culham Sci Ctr York U Chubu U Fukui U Hiroshima U Hyogo U Kyoto U Kyushu U Kyushu Tokai U NIFS Niigata U U Tokyo JAEA Inst for Nucl Res, Kiev Ioffe Inst TRINITI Chonbuk Natl U NFRI KAIST POSTECH Seoul Natl U ASIPP CIEMAT FOM Inst DIFFER ENEA, Frascati CEA, Cadarache IPP, Jülich IPP, Garching ASCR, Czech Rep Coll of Wm & Mary Columbia U CompX General Atomics FIU INL Johns Hopkins U LANL LLNL Lodestar MIT Lehigh U Nova Photonics Old Dominion ORNL PPPL Princeton U Purdue U SNL Think Tank, Inc. UC Davis UC Irvine UCLA UCSD U Colorado U Illinois U Maryland U Rochester U Tennessee U Tulsa U Washington U Wisconsin X Science LLC

Upload: mitchell-wheeler

Post on 30-Dec-2015

221 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: NSTX-U FWP 2015 Budget Planning Meeting-NSTX Upgrade Status- Ron Strykowsky – 4/10/2013 1 NSTX Upgrade Progress Overview Ron Strykowsky Erik Perry, Tim

NSTX-UNSTX-U FWP 2015 Budget Planning Meeting-NSTX Upgrade Status- Ron Strykowsky – 4/10/2013 1

NSTX UpgradeNSTX UpgradeProgress OverviewProgress Overview

Ron StrykowskyErik Perry, Tim Stevenson, Larry Dudek, Steve Langish, Tom

Egebo, Mike Williamsand the NSTXU Project Team

FWP FY2015 Budget Planning Meeting April 10, 2013

NSTX-UNSTX-U Supported by

Culham Sci CtrYork U

Chubu UFukui U

Hiroshima UHyogo UKyoto U

Kyushu UKyushu Tokai U

NIFSNiigata UU Tokyo

JAEAInst for Nucl Res, Kiev

Ioffe InstTRINITI

Chonbuk Natl UNFRI

KAISTPOSTECH

Seoul Natl UASIPP

CIEMATFOM Inst DIFFER

ENEA, FrascatiCEA, Cadarache

IPP, JülichIPP, Garching

ASCR, Czech Rep

Coll of Wm & MaryColumbia UCompXGeneral AtomicsFIUINLJohns Hopkins ULANLLLNLLodestarMITLehigh UNova PhotonicsOld DominionORNLPPPLPrinceton UPurdue USNLThink Tank, Inc.UC DavisUC IrvineUCLAUCSDU ColoradoU IllinoisU MarylandU RochesterU TennesseeU TulsaU WashingtonU WisconsinX Science LLC

Page 2: NSTX-U FWP 2015 Budget Planning Meeting-NSTX Upgrade Status- Ron Strykowsky – 4/10/2013 1 NSTX Upgrade Progress Overview Ron Strykowsky Erik Perry, Tim

NSTX-UNSTX-U FWP 2015 Budget Planning Meeting-NSTX Upgrade Status- Ron Strykowsky – 4/10/2013 2

• Technical Progress

• Cost, schedule, risks

Outline

Page 3: NSTX-U FWP 2015 Budget Planning Meeting-NSTX Upgrade Status- Ron Strykowsky – 4/10/2013 1 NSTX Upgrade Progress Overview Ron Strykowsky Erik Perry, Tim

NSTX-UNSTX-U FWP 2015 Budget Planning Meeting-NSTX Upgrade Status- Ron Strykowsky – 4/10/2013 3

• Excellent safety record• On schedule and cost

Significant progress in the last year• Excellent safety record• On schedule and cost

Page 4: NSTX-U FWP 2015 Budget Planning Meeting-NSTX Upgrade Status- Ron Strykowsky – 4/10/2013 1 NSTX Upgrade Progress Overview Ron Strykowsky Erik Perry, Tim

NSTX-UNSTX-U FWP 2015 Budget Planning Meeting-NSTX Upgrade Status- Ron Strykowsky – 4/10/2013 4

Neutral beam installation ahead of schedule

TIV valve installed on the front of the Neutral Beam

40 ton Neutral Beam move into the NSTX TC

New vacuum vessel port installed

Neutral Beam in final position

Ready for connecting

duct

Page 5: NSTX-U FWP 2015 Budget Planning Meeting-NSTX Upgrade Status- Ron Strykowsky – 4/10/2013 1 NSTX Upgrade Progress Overview Ron Strykowsky Erik Perry, Tim

NSTX-UNSTX-U FWP 2015 Budget Planning Meeting-NSTX Upgrade Status- Ron Strykowsky – 4/10/2013 5

Center Stack Fabrication & Assembly Proceeding WellCooling tube soldered into inner

TF conductor (completed )

Conductor being wrapped with fiberglass insulation

Insulated conductor being placed into mold

Assembled TF mold ready for Vacuum Pressure Impregnation (VPI)

First Quadrant successfully VPI !

Page 6: NSTX-U FWP 2015 Budget Planning Meeting-NSTX Upgrade Status- Ron Strykowsky – 4/10/2013 1 NSTX Upgrade Progress Overview Ron Strykowsky Erik Perry, Tim

NSTX-UNSTX-U FWP 2015 Budget Planning Meeting-NSTX Upgrade Status- Ron Strykowsky – 4/10/2013 6

Centerstack casing delivered

• Forms the inner part of the vacuum vessel and houses the inner TF/OH magnet.

• 500 Inconel studs will added to the outside surfaces.

• 696 Tiles with diagnostics will then be mounted.

Page 7: NSTX-U FWP 2015 Budget Planning Meeting-NSTX Upgrade Status- Ron Strykowsky – 4/10/2013 1 NSTX Upgrade Progress Overview Ron Strykowsky Erik Perry, Tim

NSTX-UNSTX-U FWP 2015 Budget Planning Meeting-NSTX Upgrade Status- Ron Strykowsky – 4/10/2013 7

Plans Forward for Centerstack Components• Components & Hardware

– Flex connectors delivered– PF 1b,a,c coils- Awarded. Delivery July, August, October

– PFC Tiles-delivered and being machined– Casing delivered

• Inner TF Bundle– VPI first Quadrant- Completed– VPI Full Bundle- July 2013

• OH Solenoid– OH Conductor delivered– Begin winding OH solenoid- September 2013– OH Mold Award. Delivery August– VPI OH – December 2013

• Centerstack Assembly- – Delivery to NSTX TC April 2014

Page 8: NSTX-U FWP 2015 Budget Planning Meeting-NSTX Upgrade Status- Ron Strykowsky – 4/10/2013 1 NSTX Upgrade Progress Overview Ron Strykowsky Erik Perry, Tim

NSTX-UNSTX-U FWP 2015 Budget Planning Meeting-NSTX Upgrade Status- Ron Strykowsky – 4/10/2013 8

New CS Installation one year away!

• Completed center-stack assembly being lifted into the vacuum vessel

• Planned for April 2014

Page 9: NSTX-U FWP 2015 Budget Planning Meeting-NSTX Upgrade Status- Ron Strykowsky – 4/10/2013 1 NSTX Upgrade Progress Overview Ron Strykowsky Erik Perry, Tim

NSTX-UNSTX-U FWP 2015 Budget Planning Meeting-NSTX Upgrade Status- Ron Strykowsky – 4/10/2013 9

Machine modifications making good progress

Umbrella Legs and Arch Reinforcement

TF Outer Leg Supports

Umbrella/TF Reinforcements

Page 10: NSTX-U FWP 2015 Budget Planning Meeting-NSTX Upgrade Status- Ron Strykowsky – 4/10/2013 1 NSTX Upgrade Progress Overview Ron Strykowsky Erik Perry, Tim

NSTX-UNSTX-U FWP 2015 Budget Planning Meeting-NSTX Upgrade Status- Ron Strykowsky – 4/10/2013 10

TF Coil Flag Replacement

Machine modifications continued

Neutral Beam Bay J/K Port Cap MPTS Bay L Port

Page 11: NSTX-U FWP 2015 Budget Planning Meeting-NSTX Upgrade Status- Ron Strykowsky – 4/10/2013 1 NSTX Upgrade Progress Overview Ron Strykowsky Erik Perry, Tim

NSTX-UNSTX-U FWP 2015 Budget Planning Meeting-NSTX Upgrade Status- Ron Strykowsky – 4/10/2013 11

Other Field work progressing well

• Davis-Bacon Services and Electrical work being bid• NB High Voltage Enclosures (HVE’s) being prepared for transport to the Test Cell• Cable tray installations on the north wall and labyrinth underway.• Fabrication and leak checking of NB LHe cryo lines underway.• Installation of new gas injection ports underway• Fabrication of NB/TVPS duct components underway.

Re-installation of cable trays and racks underway

2 New Outer TF Coils being fabricated

Conductor

Mold

Page 12: NSTX-U FWP 2015 Budget Planning Meeting-NSTX Upgrade Status- Ron Strykowsky – 4/10/2013 1 NSTX Upgrade Progress Overview Ron Strykowsky Erik Perry, Tim

NSTX-UNSTX-U FWP 2015 Budget Planning Meeting-NSTX Upgrade Status- Ron Strykowsky – 4/10/2013 12

• Cost – CPI = 0.99

• Schedule– SPI = 1.00 – Total float = 1 week to early finish PLUS 12 months to late finish CD-4

• Completion– Forecast = September 22, 2014– CD-4 Project Baseline (Early Finish) = September 30, 2014– CD-4 DOE Milestone (Late Finish) = September 2015

• BAC =$83.5 EAC= $ 84.8 TPC =94.3M

• Cost to date = $50.9 M 60% complete

• Contingency balance = 30% ($10.0M remaining) (27% at CD-2)

Performance metrics good (1)

(1) Through February 2013

Page 13: NSTX-U FWP 2015 Budget Planning Meeting-NSTX Upgrade Status- Ron Strykowsky – 4/10/2013 1 NSTX Upgrade Progress Overview Ron Strykowsky Erik Perry, Tim

NSTX-UNSTX-U FWP 2015 Budget Planning Meeting-NSTX Upgrade Status- Ron Strykowsky – 4/10/2013 13

Project Budget Consistent with CD-2 Plans and EAC

$0

$5,000

$10,000

$15,000

$20,000

$25,000

$30,000

$35,000

$40,000

$45,000

$50,000

$55,000

$60,000

$65,000

$70,000

$75,000

$80,000

$85,000

$90,000

$95,000

$100,000

$105,000

$0

$500

$1,000

$1,500

$2,000

$2,500

$3,000

$3,500

JAN

FY

09F

EB

FY

09M

AR

FY

09A

PR

FY

09M

AY

FY

09JU

NF

Y09

JUL

FY

09A

UG

FY

09S

EP

FY

09O

CT

FY

10N

OV

FY

10D

EC

FY

10JA

NF

Y10

FE

BF

Y10

MA

RF

Y10

AP

RF

Y10

MA

YF

Y10

JUN

FY

10JU

LF

Y10

AU

GF

Y10

SE

PF

Y10

OC

TF

Y11

NO

VF

Y11

DE

CF

Y11

JAN

FY

11F

EB

FY

11M

AR

FY

11A

PR

FY

11M

AY

FY

11JU

NF

Y11

JUL

FY

11A

UG

FY

11S

EP

FY

11O

CT

FY

12N

OV

FY

12D

EC

FY

12JA

NF

Y12

FE

BF

Y12

MA

RF

Y12

AP

RF

Y12

MA

YF

Y12

JUN

FY

12JU

LF

Y12

AU

GF

Y12

SE

PF

Y12

OC

TF

Y13

NO

VF

Y13

DE

CF

Y13

JAN

FY

13F

EB

FY

13M

AR

FY

13A

PR

FY

13M

AY

FY

13JU

NF

Y13

JUL

FY

13A

UG

FY

13S

EP

FY

13O

CT

FY

14N

OV

FY

14D

EC

FY

14JA

NF

Y14

FE

BF

Y14

MA

RF

Y14

AP

RF

Y14

MA

YF

Y14

JUN

FY

14JU

LF

Y14

AU

GF

Y14

SE

PF

Y14

OC

TF

Y15

NO

VF

Y15

DE

CF

Y15

JAN

FY

15F

EB

FY

15M

AR

FY

15

Plan

Budget Profile

Actual Cost

NSTX-U Cost and Budget

Plan (excl contingency)

FY 2009 | FY 2010 | FY 2011 | FY 2012 | FY 2013 | FY 2014 |FY 2015

($K) ($K)

Page 14: NSTX-U FWP 2015 Budget Planning Meeting-NSTX Upgrade Status- Ron Strykowsky – 4/10/2013 1 NSTX Upgrade Progress Overview Ron Strykowsky Erik Perry, Tim

NSTX-UNSTX-U FWP 2015 Budget Planning Meeting-NSTX Upgrade Status- Ron Strykowsky – 4/10/2013 14

Project on Track for September 2014 Completion

Page 15: NSTX-U FWP 2015 Budget Planning Meeting-NSTX Upgrade Status- Ron Strykowsky – 4/10/2013 1 NSTX Upgrade Progress Overview Ron Strykowsky Erik Perry, Tim

NSTX-UNSTX-U FWP 2015 Budget Planning Meeting-NSTX Upgrade Status- Ron Strykowsky – 4/10/2013 15

Transition into operations- Planning underway

Pre-operational test of subsystems (PTP’S)

Activity Certification Committee (ACC) review

DOE Readiness assessment (RA)

Integrated system test procedure (ISTP) (per OP-NSTX-02 rev 14)

Commence Operations and

run XP’s

CD-4 DemonstratedPerformance

NSTX-U ISTP, Commissioning, and Startup will follow the same process as NSTX initial commissioning and startup from February 1999.

Page 16: NSTX-U FWP 2015 Budget Planning Meeting-NSTX Upgrade Status- Ron Strykowsky – 4/10/2013 1 NSTX Upgrade Progress Overview Ron Strykowsky Erik Perry, Tim

NSTX-UNSTX-U FWP 2015 Budget Planning Meeting-NSTX Upgrade Status- Ron Strykowsky – 4/10/2013 16

Near Term Risks & UncertaintiesSCHEDULE – 1.Center Stack Assembly

• Planning workshop conducted. Increased fabrication times offset with 2 shift operations.

2.Vendor deliveries (e.g. Outer TF coils, PF 1 coils, OH mold)3.Funding uncertainties and impact of a potential reduction in force on project schedule.

TECHNICAL – 1.Centerstack VPI operations . First VPI successful! 5 more to follow.

Page 17: NSTX-U FWP 2015 Budget Planning Meeting-NSTX Upgrade Status- Ron Strykowsky – 4/10/2013 1 NSTX Upgrade Progress Overview Ron Strykowsky Erik Perry, Tim

NSTX-UNSTX-U FWP 2015 Budget Planning Meeting-NSTX Upgrade Status- Ron Strykowsky – 4/10/2013 17

NSTX Upgrade Summary

• Project risks identified and being worked

• The project continues to make good technical progress.

• The project is on schedule and cost.

• Planning for start-up underway

• Project risks identified and being worked

• The project continues to make good technical progress.

• The project is on schedule and cost.

• Planning for start-up underway

Page 18: NSTX-U FWP 2015 Budget Planning Meeting-NSTX Upgrade Status- Ron Strykowsky – 4/10/2013 1 NSTX Upgrade Progress Overview Ron Strykowsky Erik Perry, Tim

NSTX-UNSTX-U FWP 2015 Budget Planning Meeting-NSTX Upgrade Status- Ron Strykowsky – 4/10/2013 18

SUPPLEMENTAL MATERIAL

Page 19: NSTX-U FWP 2015 Budget Planning Meeting-NSTX Upgrade Status- Ron Strykowsky – 4/10/2013 1 NSTX Upgrade Progress Overview Ron Strykowsky Erik Perry, Tim

NSTX-UNSTX-U FWP 2015 Budget Planning Meeting-NSTX Upgrade Status- Ron Strykowsky – 4/10/2013 19

Level MilestoneDOE

Commitment Date

PMB (early finish) Baseline

Forecast Actual

Level I Receive CD-2 Approval Jan-11 Dec-10 Dec-10

Level II Project FDR Jun-11 Jun-11 Jun-11Level I Receive CD-3 Approval Jan-12 Sep-11 Dec-11

Level II Receive First Delivery Machined Inner Tf Conductor Jun-12 May-12 Apr-12

Level II Nstx Complete Operations Jul-12 Mar-12 Sep-11

Level II Begin Upgrade Outage Aug-12 Apr-12 Sep-11

Level II Award Neutral Beam (NB) Vessel Cap Jun-13 Oct-12 Feb-11

Level II Begin Inner Tf Quadrant Fab (Apply Turn Insul #1 Apr-13 Oct-12 Jun-12

Level II Complete Assy and Pot Of 4th Inner TF Quadrant Oct-13 Mar-13 Jun-13

Level II Complete Fabricate & Test Inner TF/OH Coil Assy Jun-14 Oct-13 Jan-14

Level II NB Cap Installed Oct-14 Jan-14 Jan-13

Level II Lift In New Centerstack Jan-15 Mar-14 Apr-14

Level II Complete ISTP Aug-15 Sep-14 Sep-14

Level II Resume Operations Sep-15 Sep-14 Sep-14

Level I CD-4 Sep-15 Sep-14 Sep-14

Project Milestones