nstx nstx team meeting –masa ono april 25, 2014 nstx-u team meeting april 25, 2014 culham sci ctr...
TRANSCRIPT
NSTXNSTX NSTX Team Meeting –Masa Ono April 25, 2014
NSTX-U Team Meeting
April 25, 2014
Culham Sci CtrU St. Andrews
York UChubu UFukui U
Hiroshima UHyogo UKyoto U
Kyushu UKyushu Tokai U
NIFSNiigata UU Tokyo
JAEAHebrew UIoffe Inst
RRC Kurchatov InstTRINITI
NFRIKAIST
POSTECHSeoul National U
ASIPPENEA, Frascati
CEA, CadaracheIPP, Jülich
IPP, GarchingASCR, Czech Rep
Columbia UCompXGeneral AtomicsFIUINLJohns Hopkins ULANLLLNLLodestarMITNova PhotonicsNew York UORNLPPPLPrinceton UPurdue USNLThink Tank, Inc.UC DavisUC IrvineUCLAUCSDU ColoradoU IllinoisU MarylandU RochesterU WashingtonU Wisconsin
NSTX-UNSTX-U Supported by
NSTXNSTX NSTX Team Meeting –Masa Ono April 25, 2014
Time: 1:30 ~ 3:00, April 25 (Friday), 2014
Place: LSB 318, PPPL
• General Items (15 minutes)
• Program Item (20 minutes)
• Upgrade Project (20 minutes)
• Facility Engineering Operations (15 minutes)
• Research Operations (20 minutes)
NSTX-U Team Meeting Agenda
2
NSTXNSTX NSTX Team Meeting –Masa Ono April 25, 2014
• ES&H Issues (J. Levine)
• NSTX-U operational preparation activity (e.g., diagnostic installation) is commencing and we need to be extra cautious regarding safety!
• With nice spring weather, the outdoor activities could bring hazards
- Proper protective clothing (e.g., long sleeve shirts and pants)
- Mindful of Ladder safety
- Gloves, mask, and eye protection
- Watch out for bees and other insects
Safely, Safely, Safely
3
NSTXNSTX NSTX Team Meeting –Masa Ono April 25, 2014
NSTX-U Department Activities in Q2 FY 14
• Significant collaboration research contributions are being made in diverse science areas by the NSTX-U research team.
• On-going active research collaboration particularly with DIII-D and EAST. Several activities resulted in IAEA synopses.
• A good set of IAEA synopses (~ 30) accepted by IAEA.• Favorable budget should enable preparation for the NSTX-U operation while
completing the Upgrade Project. Some resources maybe available to start the design work on high priority five year plan enhancements. – MG motor generator repair procurement should be concluded in the near future and
the work to start in May.
– Firing generators were installed. It is ready for test when the DCPS is avaiiable.
– HHFW antenna should be re-installed in early May along with the P-CHERs passive plates.
– In-vessel diagnostic installation/reinstallation work is in progress.
• NSTX-U OFES BPM visit / presentation took place on April 17, 2014.4
NSTXNSTX NSTX Team Meeting –Masa Ono April 25, 2014
Formulating Strategy for Successful Implementation of FY14 MilestonesMainly Through Data Analyses, Theory/Modeling, and Collaborations
NSTXNSTX NSTX Team Meeting –Masa Ono April 25, 2014
FY 14 NSTX-U PEMP Notable Outcomes
Goal 1.0 Mission Accomplishment
FES: Carry out scenario modeling and research planning to ensure a strong NSTX-U research program in FY 2015. (Objective 1.1) Part of the high priority NSTX-U research activities including enhanced modelling of NSTX-U current ramp-up by Francesca Poli (PPPL). Favorable budget helping this area of program activity.
FES: Analyze experimental data from FES major facilities to investigate and quantify plasma response to non-axisymmetric (3D) mangetic fields in tokamaks , in support of the FES joint research target. (Objective 1.1) NSTX-U researchers, Jong-kyu Park (PPPL) and John Canik (ORNL) are co-leading the effort at PPPL.
Goal 2.0 Design, Fabrication, Construction and Operation of Research Facilities
FES: Continue to maintain the NSTX-U project with 10% of cost and schedule. (Objective 2.2) The NSTX Upgrade project is supported at the highest priority from the NSTX Program side. The preparation for operation of the NSTX-U research facility has begun by the NSTX-U engineering and research operations team. Favorable budget is helping this area of program activity. Ron Hatcher’s recent passing has created special challenges in various areas including DCPS, CHI, and ISTP.
Goal 3.0 Program Management
FES: Expand engagement with university scientists to enhance the NSTX-U program. (Objective 3.2) C-Mod collaboration contract in place, but postponed at least 1 year due to C-Mod operations. . Favorable budget helping fund collaborators, also holding team-wide meetings to identify ways of expanding university engagement.
NSTXNSTX NSTX Team Meeting –Masa Ono April 25, 2014
NSTX-U diagnostics to be installed during first 2 yearsDiagnostics presently being installed prior to the center-stack installation
MHD/Magnetics/ReconstructionMagnetics for equilibrium reconstructionHalo current detectorsHigh-n and high-frequency Mirnov arraysLocked-mode detectorsRWM sensors
Profile DiagnosticsMPTS (42 ch, 60 Hz) T-CHERS: Ti(R), V(r), nC(R), nLi(R), (51 ch)P-CHERS: V(r) (71 ch)MSE-CIF (18 ch)MSE-LIF (20 ch)ME-SXR (40 ch)Midplane tangential bolometer array (16
ch)
Turbulence/Modes DiagnosticsPoloidal Microwave high-k scattering Beam Emission Spectroscopy (48 ch)Microwave Reflectometer, Microwave PolarimeterUltra-soft x-ray arrays – multi-color
Energetic Particle DiagnosticsFast Ion D profile measurement (perp +
tang)Solid-State neutral particle analyzerFast lost-ion probe (energy/pitch angle
resolving)Neutron measurements
Edge Divertor PhysicsGas-puff Imaging (500kHz)Langmuir probe array Edge Rotation Diagnostics (Ti, V, Vpol)1-D CCD H cameras (divertor, midplane)2-D divertor fast visible cameraMetal foil divertor bolometer AXUV-based Divertor BolometerIR cameras (30Hz) (3)Fast IR camera (two color)Tile temperature thermocouple arrayDivertor fast eroding thermocoupleDust detectorEdge Deposition MonitorsScrape-off layer reflectometerEdge neutral pressure gaugesMaterial Analysis and Particle ProbeDivertor VUV Spectrometer
Plasma MonitoringFIReTIP interferometer Fast visible camerasVisible bremsstrahlung radiometerVisible and UV survey spectrometersVUV transmission grating spectrometerVisible filterscopes (hydrogen & impurity
lines)Wall coupon analysisNew capability, Enhanced capability
7
NSTXNSTX NSTX Team Meeting –Masa Ono April 25, 2014
• The NSTX Upgrade Project Team is focused on CD-4 completion in December, 2014.
• The NSTX-U Research Team should focus on starting in March 2015.
• Complete as much research run preparation tasks as possible prior to CD-4 to minimize the period between CD4 and the research plasma operation.
• Assume the machine accessibility decreases as time goes on.
• Get your work done early!!
Schedule will Provide Exciting Research Operation in FY15 18 Run-Week commitment means we must start the run in mid-March
Res. Op
Nov. 2014 Dec. 2014 Jan. 2015 Feb. 2015 Mar. 2015
Bakeout ISTP/Comm
CD4
Research Run Prep
Research Preparation for FY 2015 Run
8
ISTP/Comm
Apr. 2014 May 2014 Jun. 2014 Sep. 2015Jul. 2014 Aug 2014 Oct. 2014
Pump down
InstallCS
OH VPI
OH Winding
Research Run Prep
NSTXNSTX NSTX Team Meeting –Masa Ono April 25, 2014
2014 2015 2016 2017 2018 2019 2020 2021 2022 2023
New center-stack
2nd NBI
Start-up and
Ramp-up
Scenarios and Control
Boundary Physics
Materials and PFCs
MHD
Transport & Turbulence
Waves and Energetic Particles
Liquid metals / lithium
Upgrade Outage
UpwardLiTERLi granule
injector
High-Z first-wall + lower OBD tiles
NCC SPA upgrade
Enhanced MHD sensors
Divertor Thomson
High-Z PFC
diagnostics
MGI disruption mitigation
High k
Partial NCC
4 coil AE antenna1 coil AE antenna
B polarimetry
1 MW ECH/EBW
up to 1 MA plasma gun
Lower divertor
cryo-pump
High-Z tile row on
lower OBD
Upgraded CHI for ~0.5MA
LLD using bakeable cryo-baffle
0.5-1 MA CHI
Metallic PFCs, 5s 10-20s
Extend NBI duration to 10-20s and/or implement 2-4 MW off-axis EBW H&CD
Hot high-Z FW PFCs using bake-out system
Flowing Li divertor or limiter module
Full toroidal flowing Li lower OBD
Full NCC
1.5 2 MA, 1s 5s
High-power AE antenna
HHFW straps to excite EHO
Charged fusion product, neutron-collimator
HHFW limiter upgrade
DBS, PCI, or other intermediate-k
All high-Z PFCs
Upper divertor
cryo-pump
Establish control of:
2 MW
Control integration, optimization with long-pulse and full metal wall
Control integration, optimizationRotation Divertor Prad
qminSnowflake ne
20 16 16 20 22 6 18 22 22Run Weeks:
Inform choice of
FNSF: aspect ratio,
divertor, and PFCs
9
Significant Near Term Upgrade Scopes Are HighlightedECH, Cryo-Pump and NCC system require resources starting in 2015