nsr enforcement cases · nsr reform rules and court challenges phase i of epa nsr reform: december...
TRANSCRIPT
NSR Enforcement Cases
David Rosskam David Rosskam
U.S. Dept. of JusticeU.S. Dept. of Justice
New Source ReviewNew Source Review
Applies to new “construction” which is defined to include certain “modifications” of existing sources
“Modification” is “any physical change in, or change in method of operation of, a stationary source which increases the amount of any air pollutant emitted by such source . . . .” Clean Air Act Section 111(a)(4), 42 U.S.C. § 7411(a)(4)
New Source Review (cont’d)New Source Review (cont’d)
Prevention of Significant Deterioration (PSD) - part of NSR - applying to areas designated as attaining National Ambient Air Quality Standards (NAAQS) or unclassified; analogous NSR provisions for non-attainment areas
Core PSD requirement: a preconstruction permit incorporating emissions limitations reflecting Best Available Control Technology (BACT).
New Source Review (cont’d)New Source Review (cont’d)For a “modified” existing source, this could mean
expensive retrofitting, e.g., FGDs (scrubbers) and selective catalytic reduction (SCR)
SIPs must contain NSR programs, 42 U.S.C. § 7410(a)(2)(C)
New Source Performance Standards (NSPS): technology-based performance standards based on best demonstrated emission reduction systems, also applicable to new and modified sources regardless of local air quality
New Source Review (cont’d)New Source Review (cont’d)Both PSD and NSPS programs have exclusion (from definition of physical or operational change) for “routine maintenance, repair, and replacement,” so “routine maintenance” is not a modification and does not trigger PSD or NSPS requirements
PSD and NSPS set forth different tests for “emissions increases” – PSD requires “significant net emissions increase” based on “actual emissions” measured in “tons per year,” 40 C.F.R. § 51.166(b)(2), (3), (21), whereas NSPS refers to emission rates measured in kilograms per hour, 40 C.F.R. § 60.14(b).
NSR Reform Rules and Court NSR Reform Rules and Court ChallengesChallengesPhase I of EPA NSR Reform: December 31, 2002 rules. Provisions for calculating emission levels before and after a facility change that make it less likely to trigger NSR; provisions to exempt certain other activities that would otherwise trigger NSR (“plant-wide applicability limit,” “pollution control project,” “clean unit”)
Phase I rules are being challenged by a group of Northeastern states and by environmental groups in Court of Appeals for the D.C. Circuit
NSR Reform Rules and Court NSR Reform Rules and Court Challenges (cont’d)Challenges (cont’d)
D.C. Circuit denied challengers’ request to stay the Phase I rules pending court review
Briefing is underway - decision could come in 2005
Industry generally supportive of Phase I with one major exception: Utility Air Regulatory Group (UARG) and other industry groups challenge PSD “emissions increase” methodology that does not require an increase in unit’s “capacity to emit”
NSR Reform Rules and Court NSR Reform Rules and Court Challenges (cont’d)Challenges (cont’d)
Phase II of EPA NSR Reform: October 27, 2003 “Equipment Replacement Provision” (ERP) rule
ERP would broaden exception for “routine maintenance, repair, and replacement” by exempting projects that cost up to 20% of unit’s replacement cost, subject to various conditions
ERP rule is being challenged by a group of Northeastern states and by environmental groups in Court of Appeals for the D.C. Circuit
NSR Reform Rules and Court NSR Reform Rules and Court Challenges (cont’d)Challenges (cont’d)
D.C. Circuit granted challengers’ request to stay the Phase II rules pending court review on December 24, 2003, so rule is not now in effect
Briefing is now on hold because EPA has reopened its rulemaking to consider and respond further to additional comments, a process that is still ongoing
Difficult to predict future course of this litigation
NSR Enforcement:NSR Enforcement:Coal Fired UtilitiesCoal Fired Utilities
Enforcement actions filed, decided, pending, and still in litigation
Settlements
Why did EPA examine the coalWhy did EPA examine the coal--fired utility sector?fired utility sector?
Increase in electric generating capacity
Increase in coal consumption
Aging of power plant fleet
Lack of permitting activity
Total U.S. 1999 SOTotal U.S. 1999 SO22 Emissions Emissions InventoryInventory
Total U.S. 1999 NOTotal U.S. 1999 NOXX Emissions Emissions InventoryInventory
Health ImpactsHealth Impacts
SO2
Affects breathing and may aggravate existing respiratory and cardiovascular disease; primary contributor to acid rain
Health ImpactsHealth Impacts
NOX
Health and environmental impacts include, ground-level ozone, acid rain, particulate matter, global warming, water quality deterioration, and visual impairment.
Health ImpactsHealth Impacts
Ozone and PMLinked with serious illnesses such as chronic bronchitis and heart attacks, and respiratory illnesses such as asthma exacerbations and, in the case of PM, premature death.
Enforcement HistoryApprox. 190 CAA 114 Information Requests issued to utilities11 Complaints Filed
American Electric Power (1999)Cinergy Corp. (1999)First Energy (1999)Illinois Power (1999)Southern Indiana Gas & Electric Company (1999)Southern Company (split into Alabama Power and Georgia Power)(1999)Tampa Electric Company (TECO) (1999)Tennessee Valley Authority (TVA) (administrative action) (1999)Duke Energy (2000)East Kentucky Power Cooperative (2004)
NSR Enforcement Status of CasesNSR Enforcement Status of Cases
EPA largely prevailed in administrative case against TVA, but its final administrative compliance order was ruled “legally inconsequential” by the Eleventh Circuit Court of Appeals on constitutional grounds. Supreme Court denied U.S. request for review.
Two cases went to trial on liability in 2003 – Ohio Edison and Illinois Power. U.S. prevailed in Ohio Edison; Illinois Power still pending. Ohio Edisonremedy trial scheduled for January 2005.
NSR Enforcement Status of CasesNSR Enforcement Status of Cases(cont’d)(cont’d)Two cases had significant pre-trial rulings that led to resolution without trial - SIGECO settled after rulings largely favorable to U.S. In Duke, parties agreed to judgment to allow for immediate appeal of rulings largely favorable to Duke.
Duke decision is on appeal to the Fourth Circuit Court of Appeals - a decision may well come in 2005.
NSR Enforcement Status of CasesNSR Enforcement Status of Cases(cont’d)(cont’d)AEP and Cinergy cases are in active litigation. AEP case is also in court-ordered mediation. Trial on liability is currently scheduled for mid-2005 in AEPand early 2006 in Cinergy.
Cases against Southern Company operating affiliates (Alabama Power, Georgia Power, Savannah Electric) were split by jurisdictional rulings, then stayed while TVA matter was on appeal. Alabama Power case has been returned to active docket this year. The court has asked for briefing on same issues that are on appeal in Duke; no trial schedule yet.
NSR Enforcement Status of CasesNSR Enforcement Status of Cases(cont’d)(cont’d)East Kentucky Power Cooperative case was filed in January 2004. The parties initially informed the court that they were exploring settlement. The court has scheduled trial for December 2005.
Excerpts from Court Rulings in NSR Enforcement Cases
Elements of Past NSR Utility Settlements
Settlements to DateSettlements to Date7 settlements, 23 facilities, 75 units
VEPCO, WEPCO, PSEG, TECO, SIGECO, Santee Cooper, ALCOA (industrial boiler)
SO2 estimated annual reductions of 446,000 tons
NOx estimated annual reductions of 214,000 tons
Civil penalties = $17.5 million
Environmental Projects = $60.4 million
Significant Reduction of PM Emissions
Settlements: Components for Settlements: Components for SystemSystem--Wide SettlementsWide Settlements
State-of-the-Art Pollution Controls on 70% of the System-Wide Coal-Fired Megawattage
90% NOx Reduction (i.e. Selective Catalytic Reduction); 95% SO2 Reduction (i.e. Scrubbers);Retirement; orRepowering
Declining System-Wide Tonnage Caps and Rates SO2 Allowances and NOX Trading Used Only Within System; Excess Allowances Surrendered as a General Matter
Components of Settlements (cont.)Components of Settlements (cont.)PM
Meet NSPS rate of 0.030 lb/mmBtu at all units or elect to undergo BACT-Lite process
Immediate optimization of PM pollution controls
PM CEMs (on 50% of units)
Timeframes
Hardware in place before December 31, 2012
NSR repose for future operations until 2015
Settlement FeaturesSettlement FeaturesGuaranteed court-order emission reductions to be incorporated into Federally enforceable operating permits
Year-round operation of technology (not required by trading programs)
Installation of proven state-of-the-art hardware
Upgrade of existing controls to state-of-the-art levels
SO2 allowance surrenders
NOx credits trading limitations
NONOxx Reductions from Final Reductions from Final SettlementsSettlements
2000 2005 2010 2015 2020Year
0
5
10
15
20
25
Thou
sand
sN
Ox
Em
issi
ons
(tons
)
Reduction of NOx Emissions from PSEG Agreement
2000 2005 2010 2015 2020Year
10
20
30
40
50
60
Thou
sand
sN
Ox
Em
issi
ons
(tons
)
Reduction of NOx Emissions from TECO Agreement
2000 2005 2010 2015 2020Year
30405060708090
100110
Thou
sand
sN
Ox
Em
issi
ons
(tons
)
Reduction of NOx Emissions from VEPCo Agreement
20022004
20062008
20102012
20142016
20182020
Year
101520253035404550
Thou
sand
s
Tons
of N
Ox
Anticipated Santee Cooper NOx Emission Reductions from Existing Units
NONOXX Reductions from Final Reductions from Final Settlements (cont.)Settlements (cont.)
SOSO22 Reductions from Final Reductions from Final SettlementsSettlements
2000 2005 2010 2015 2020Year
0
10
20
30
40
50
Thou
sand
sS
O2
Em
issi
ons
(tons
)
Reduction of SO2 Emissions From PSEG Agreement
2000 2005 2010 2015 2020Year
20
30
40
50
60
70
80
90
100
Thou
sand
sS
O2
Em
issi
ons
(tons
)
Reduction of SO2 Emissions From TECO Agreement
20022004
20062008
20102012
20142016
20182020
Year
40
50
60
70
80
90Th
ousa
nds
Tons
of S
O2
Anticipated Santee Cooper SO2 Emission Reductions from Existing Units
2000 2005 2010 2015 2020Year
50
100
150
200
250
300
Thou
sand
sSO
2 Em
issi
ons
(tons
)
Reduction of SO2 Emissions From VEPCo Agreement
SOSO22 Reductions from Final Reductions from Final Settlements (cont.)Settlements (cont.)
2001 2003 2005 2007 2009Year
0
2
4
6
8
10
12
Thou
sand
sS
O2
Em
issi
ons
(tons
)
Anticipated SIGECO Culley SO2 Emissions