Nottingham UKBus Charging Project
Peter SaundersTransport Planner Nottingham City Council
13 BYD (Build Your Dreams) single decker
buses
12 BYD Charging Points
• £4M investment.
• Government Green
Bus grant 2016
• Remourban
• Nottingham’s
Workplace Parking
Levy
£945,000 Charging Infrastructure
Trench,
Cables
& bases
£437,000
Lease &
legal
£11,500
Civils &
Plinths
£102,500Substation
Charging
Points
Resurfacing/Fencing/Kerbing
£320,000
Painting/lining
Floodlights/Cameras
£35,000
Project Management £20,000
ChallengesFlood Risk
Solution: 396 kva Substation & Switch Room. Additional charging capacity on slip road
UK Distributor Network Organisation’s (DNO): differing standards/procedures/opinions Solution: UK Govt pressing DNOs to perform. New standardised process for grid connection applications
Supply Chain: Replacement parts e.g. windscreens
Solution: BYD joint venture with Alexander Dennis Ltd (leading UK bus builder). BYD chassis/battery. AD bodies
Upscaling/Advice
- Large footprint - queuing/charging /turning.
- Council owned land?
- EV’s expensive – Capital outlay
- Grant dependant
- Site capacity - electrical supply
- Operational advantages
- Strategic Air Quality Plans