note: this is only part 5 of 5 of this report (appendices a and b). … · 2008-01-30 · note:...

26

Upload: others

Post on 12-Jul-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: NOTE: This is only Part 5 of 5 of this report (Appendices A and B). … · 2008-01-30 · NOTE: This is only Part 5 of 5 of this report (Appendices A and B). The other four parts
bomberger
Text Box
NOTE: This is only Part 5 of 5 of this report (Appendices A and B). The other four parts are, also, located on the Lake County Water Atlas and have the same title, Astor Flood Study – Phase 1 Final Report, only with a different part designation at the end of the main title.
Page 2: NOTE: This is only Part 5 of 5 of this report (Appendices A and B). … · 2008-01-30 · NOTE: This is only Part 5 of 5 of this report (Appendices A and B). The other four parts

A i

Contents

Executive Summary

Section 1 Introduction 1.1 Background ...............................................................................................................1-1 1.2 Study Area .................................................................................................................1-1 1.3 Project Objective .......................................................................................................1-1 1.3.1 Data Collection and Review......................................................................1-1 1.3.2 Stormwater System Inventory and Mapping .........................................1-1 1.3.3 Problem Area Identification and Conceptual Improvements ..............1-1 1.3.4 Water Quality Analyses.............................................................................1-2 1.3.5 Floodplain Review......................................................................................1-2 1.3.6 Alternative Development ..........................................................................1-2 1.3.7 Stormwater Needs Prioritization..............................................................1-2

1.3.8 Capital Improvement Project Recommendation....................................1-3 1.3.9 Stormwater Ordinance Review ................................................................1-3

Section 2 Existing Data Review and Evaluation for Flood Study 2.1 Introduction...............................................................................................................2-1 2.2 Hydrologic Data .......................................................................................................2-1 2.2.1 Rainfall .........................................................................................................2-1 2.2.2 St. Johns River Stages and Flow at Astor ................................................2-2 2.3 Topographic Data .....................................................................................................2-3 2.4 Soils.............................................................................................................................2-3 2.5 Land Use ....................................................................................................................2-4 2.6 Plans Review .............................................................................................................2-4 2.6.1 Subdivision and Roadway Plans...............................................................2-4 2.6.2 Building Permits ..........................................................................................2-4 2.6.3 Environmental Resource Permits..............................................................2-4 2.7 Floodplain Review....................................................................................................2-5 2.8 Stormwater System Inventory and Mapping .......................................................2-7 2.8.1 Description of Existing Drainage System................................................2-7 2.8.2 Open Channels and Swales.......................................................................2-8 2.8.3 Culverts ........................................................................................................2-8 2.8.4 Ponds ............................................................................................................2-9 2.8.5 Streets ...........................................................................................................2-9

Section 3 Identified Problems and Conceptual Improvements 3.1 Introduction...............................................................................................................3-1 3.2 Classification of Problem Areas..............................................................................3-1 3.3 Flooding Due to High Stages in the St. Johns River ............................................3-3

Page 3: NOTE: This is only Part 5 of 5 of this report (Appendices A and B). … · 2008-01-30 · NOTE: This is only Part 5 of 5 of this report (Appendices A and B). The other four parts

Table of Contents Lake County Astor Flood Study

A ii S:\41542\52768\Report\Table of Contents.doc

3.4 Localized Flooding ...................................................................................................3-4 3.5 Stormwater Infrastructure Damage .......................................................................3-4 3.6 Poor Conditions in the Finger Canals....................................................................3-5 3.7 Specific Problem Areas and Conceptual Improvements ....................................3-6 3.7.1 Problem Area No.1 – Bass, Indigo and Tyty Roads .............................3-6 3.7.1.1 Bass and Indigo Roads (11P1 & 10R) ....................................3-6 3.7.7.2 Tyty Road (7P2)........................................................................3-7 3.7.2 Problem Area No. 2 – Ward Street, West Lloyd Street and Alco Road ...........................................................................................................3-7 3.7.2.1 Ward Street (36P1, 37P1, 38P1, 39P1, 40P1 and 5P2)...........3-7 3.7.2.2 West Lloyd Street and Alco Road (41P1)..............................3-8 3.7.3 Problem Area No. 3 – James Street (19P1), Lisa Street (20P1) and Trespass Trail (27P1) .................................................................................3-9 3.7.4 Problem Area No. 4 – 3rd Street (26P1 and 31P1) ................................3-15 3.7.5 Problem Area No. 5 – Butler and Ann Streets.....................................3-17 3.7.5.1 Butler Street (1P2) ..................................................................3-17 3.7.5.2 Ann Street (11R) .....................................................................3-17 3.7.6 Problem Areas No. 6,7,8,9 and 10 .........................................................3-18 3.7.6.1 Problem Area No. 6 – Maple Road (32P1)..........................3-18 3.7.6.2 Problem Area No. 7 – Fox Road (10P2)...............................3-18 3.7.6.3 Problem Area No. 8 – Carrol Street (30P1) .........................3-18 3.7.6.4 Problem Area No. 9 – Veterans Drive (21P1).....................3-18 3.7.6.5 Problem Area No. 10 – Alco Road (1P1).............................3-18 3.8 Summary of Alternatives for Localized Flooding..............................................3-19 3.9 Flood Early Warning System ................................................................................3-19

Section 4 Water Quality and Pollutant Load Analysis 4.1 Introduction...............................................................................................................4-1 4.2 Water Quality............................................................................................................4-1 4.3 Pollutant Load Analysis ..........................................................................................4-1 4.3.1 Watershed Management Model (WMM) Background ........................4-2 4.3.1.1 Basins and Pollution Sources .................................................4-3 4.3.1.2 Rainfall/Runoff Relationships ...............................................4-3 4.3.1.3 Nonpoint Pollution Event Mean Concentrations................4-4 4.3.1.4 Nonpoint Pollution Loading Factors.....................................4-7 4.3.1.5 Failing Septic Tank Impacts....................................................4-9 4.3.1.6 Point Source Loadings...........................................................4-10 4.3.1.7 Model Limitations..................................................................4-11 4.4 WMM Data Analysis..............................................................................................4-11 4.4.1 Land Use ..................................................................................................4-11 4.4.2 BMP Identification and Pollution Removal Efficiencies ....................4-12 4.4.3 Event Mean Concentration Values .......................................................4-13

Page 4: NOTE: This is only Part 5 of 5 of this report (Appendices A and B). … · 2008-01-30 · NOTE: This is only Part 5 of 5 of this report (Appendices A and B). The other four parts

Table of Contents Lake County Astor Flood Study

A iii S:\41542\52768\Report\Table of Contents.doc

4.4.4 Rainfall Data.............................................................................................4-15 4.4.5 Septic Tank Usage ...................................................................................4-15 4.4.6 Point Source Discharges .........................................................................4-15 4.5 WMM Results..........................................................................................................4-15 4.5.1 Existing Land Use Condition Results...................................................4-16 4.5.2 Recommendations...................................................................................4-16 4.6 Conceptual Improvements to Address Water Quality .....................................4-17 4.6.1 Problem Area No. 11 – Fern, Bobcat, Palmetto and Deer Roads (9P2)...............................................................................................4-17 4.6.2 Problem Area No. 12 – Aqua Utilities Pond (8P2)..............................4-19 4.6.3 Problem Area No. 13 – Riverview Drive Pond (33P) .........................4-19 4.6.4 Finger Canals – Various Locations (8P1, 9P1, 2P2, 3P2, 4P2, 6P2, 8P2 and 2R .......................................................................................................4-20

Section 5 Problem Ranking and Prioritization 5.1 Introduction...............................................................................................................5-1 5.2 Estimated Alternative Costs....................................................................................5-1 5.3 Development of Ranking Criteria ..........................................................................5-2 5.4 Problem Area Ranking and Preliminary Capital Projects List...........................5-4 5.5 Stormwater Management Needs............................................................................5-4 5.6 Stormwater Management Needs Ranking............................................................5-6

Section 6 Stormwater Ordinance Review 6.1 Introduction...............................................................................................................6-1 6.2 Stormwater Management Performance Criteria ..................................................6-1 6.3 Water Quality Standards .........................................................................................6-2 6.4 Development in Special Flood Hazard Areas ......................................................6-3 6.5 Redevelopment Control Measures.........................................................................6-6 6.6 Stormwater System Maintenance...........................................................................6-7 6.7 Applicability to Astor...............................................................................................6-8

Section 7 Summary of Recommendations 7.1 Introduction...............................................................................................................7-1 7.2 Plan Implementation Guidelines............................................................................7-1

Appendices Appendix A Infrastructure Damage Appendix B Opinion of Probable Construction Cost

Page 5: NOTE: This is only Part 5 of 5 of this report (Appendices A and B). … · 2008-01-30 · NOTE: This is only Part 5 of 5 of this report (Appendices A and B). The other four parts

Appendix A

Page 6: NOTE: This is only Part 5 of 5 of this report (Appendices A and B). … · 2008-01-30 · NOTE: This is only Part 5 of 5 of this report (Appendices A and B). The other four parts

Damage D01Description - Cross drain pipe broken

Damage D02Description - Cross drain pipe broken

Damage D03Description - Washout next to the mitered end section

A

Appendix A-1Infrastructure Damage

D01, D02 & D03Astor Flood Study

D01

D02

D03

Page 7: NOTE: This is only Part 5 of 5 of this report (Appendices A and B). … · 2008-01-30 · NOTE: This is only Part 5 of 5 of this report (Appendices A and B). The other four parts

Damage D04Hole/washout at top of the mitered end section

Damage D05Hole/washout at side of the mitered end section

Damage D06Concrete on mitered end section broken and pulling away from culvert pipe

A

Appendix A-2Infrastructure Damage

D04, D05 & D06Astor Flood Study

D04

D05

D06

Page 8: NOTE: This is only Part 5 of 5 of this report (Appendices A and B). … · 2008-01-30 · NOTE: This is only Part 5 of 5 of this report (Appendices A and B). The other four parts

Damage D07RCP pipe is exposed

Damage D08CMP pipe is exposed at the mitered end section

Damage D09Washing out around the mitered end section

A

Appendix A-3Infrastructure Damage

D07, D08 & D09Astor Flood Study

D07

D08

D09

Page 9: NOTE: This is only Part 5 of 5 of this report (Appendices A and B). … · 2008-01-30 · NOTE: This is only Part 5 of 5 of this report (Appendices A and B). The other four parts

Damage D10Washout at the mitered end section

Damage D11Pipe bent and pulling away from the mitered end section

Damage D12Washout at the headwall

A

Appendix A-4Infrastructure Damage

D10, D11 & D12Astor Flood Study

D10

D11

D12

Page 10: NOTE: This is only Part 5 of 5 of this report (Appendices A and B). … · 2008-01-30 · NOTE: This is only Part 5 of 5 of this report (Appendices A and B). The other four parts

Damage D13Deep washout between River Road and ditch

Damage D14Pipe exposed and broken in dirt roadway

Damage D15Deep washout at the corner of Fern Road and River Rd

A

Appendix A-5Infrastructure Damage

D13, D14 & D15Astor Flood Study

D13

D14

D15

Page 11: NOTE: This is only Part 5 of 5 of this report (Appendices A and B). … · 2008-01-30 · NOTE: This is only Part 5 of 5 of this report (Appendices A and B). The other four parts

Damage D16Washout, pipe torn & concrete broken

Damage D17Severe washout & pipe damage

Damage D18RCP pipe exposed

A

Appendix A-6Infrastructure Damage

D16, D17 & D18Astor Flood Study

D16

D17

D18

Page 12: NOTE: This is only Part 5 of 5 of this report (Appendices A and B). … · 2008-01-30 · NOTE: This is only Part 5 of 5 of this report (Appendices A and B). The other four parts

Damage D19Washout causing collapse of the mitered end section

Damage D23Driveway culvert crushed in center

A

Appendix A-7Infrastructure Damage

D19 & D23Astor Flood Study

D19

D23

Page 13: NOTE: This is only Part 5 of 5 of this report (Appendices A and B). … · 2008-01-30 · NOTE: This is only Part 5 of 5 of this report (Appendices A and B). The other four parts

Damage D21Severe washout undermining roadway

Damage D22Severe washout undermining roadway

A

Appendix A-8Infrastructure Damage

D21 & D22Astor Flood Study

D21

D22

Page 14: NOTE: This is only Part 5 of 5 of this report (Appendices A and B). … · 2008-01-30 · NOTE: This is only Part 5 of 5 of this report (Appendices A and B). The other four parts

Damage D24Washout under flume

Damage D25Severe washout under flume

Damage D26Bank washed away & canal filled with sediment

A

Appendix A-9Infrastructure Damage

D24, D25 & D26Astor Flood Study

D24

D25

D26

Page 15: NOTE: This is only Part 5 of 5 of this report (Appendices A and B). … · 2008-01-30 · NOTE: This is only Part 5 of 5 of this report (Appendices A and B). The other four parts

Damage D27Washout beside the mited end section causing damage to structure

Damage D28Washout beside road exposing drainage pipe

Damage D29Road washing out into ditch

A

Appendix A-10Infrastructure Damage

D27, D28 & D29Astor Flood Study

D27

D28

D29

Page 16: NOTE: This is only Part 5 of 5 of this report (Appendices A and B). … · 2008-01-30 · NOTE: This is only Part 5 of 5 of this report (Appendices A and B). The other four parts

Damage D30Road washed out badly

Damage D34Severe washout - road could be washed out

Damage D35This area is lower than the surrounding area is flooded badly when raining

A

Appendix A-11Infrastructure Damage

D30, D34 & D35Astor Flood Study

D30

D34

D35

Page 17: NOTE: This is only Part 5 of 5 of this report (Appendices A and B). … · 2008-01-30 · NOTE: This is only Part 5 of 5 of this report (Appendices A and B). The other four parts

Damage D31Washout at top of the mitered end section, which could cause mitered end section to crack

Damage D32Severe washout at the edge of road, which could cause road to collapse

Damage D33Severe washout at the edge of riprap, which could cause riprap to collapse

A

Appendix A-12Infrastructure Damage

D31, D32 & D33Astor Flood Study

D31

D32

D33

Page 18: NOTE: This is only Part 5 of 5 of this report (Appendices A and B). … · 2008-01-30 · NOTE: This is only Part 5 of 5 of this report (Appendices A and B). The other four parts

Appendix B

Page 19: NOTE: This is only Part 5 of 5 of this report (Appendices A and B). … · 2008-01-30 · NOTE: This is only Part 5 of 5 of this report (Appendices A and B). The other four parts

Site DemolitionDemolish Concrete Driveways 55.56 CY $6,496 $3,479 $5,784 15,759$

Remove Existing Driveway Culverts 600 LF $3,408 $750 $8,376 $3,717 16,251$ Earthwork -$

Regrade Swale 2205 CY $7,662 $20,303 27,965$ Construct 1 acre Pond (with 835' of Berm, 20' W x 10'H) 9254 CY $88,401 $141,660 230,061$

Drainage & Containment -$ Driveway Culverts 30 EA $31,512 $27,693 $6,396 65,601$

End Structures 60 EA $6,300 $12,000 18,300$ Overflow Weir at Pond Outlet 1 EA $749 $2,380 $7 $1,907 5,043$

Site Improvements & Amenities -$ Sod @ Swale 52000 SF $30,680 30,680$

Sod @ Pond Slopes & Berm 28000 SF $16,520 16,520$ Concrete -$

Repave Concrete Driveways 55.56 CY $19,765 $15,634 $605 $830 $130 36,964$ Subtotal= 463,144$

Subtotal 1 (Nearest $1,000) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 463,000$

Indirect CostsSales tax (Material, Equipment, Other) (7%) $17,193

Builders Risk Insurance (1.5% total cost) $12,930General Liability Insurance (1% total cost) $8,620

General Construction Bonds (1.5 % total cost) $12,930Indirect Cost Subtotal 51,673$

Subtotal 2 (Nearest $1,000) 515,000$ Overhead and Profit

General Contractor Field General Conditions (7% of Subtotal 2) $36,050General Contractor Indirects, OH & Profit (10% of Subtotal 2) $51,500

Overhead & Profit Subtotal 87,550$

Subtotal 3 (Nearest $1,000) 603,000$ Contingency

Construction Contingency (35% of Subtotal 3) $211,050Contingency Subtotal 211,050$

Subtotal 4 (Nearest $1,000) 814,000$ Engineering Services

Engineering, Design & Permitting (30% of Subtotal 4) $244,200Engineering Subtotal 244,200$

EscalationEscalation to Mid Point Constr (6% (of Subtotal 4) per year) $48,840

Escalation Subtotal 48,840$

TOTAL COST 1,106,000$

NOTE:

Table B-1Opinion of Probable Construction CostProblem Area 1Astor Flood Study

ItemLabor

AmountMaterial Amount

Estimated Total Cost

Estimated Quantity Units

Subcontractor Amount

Equipment Amount

Other Amount

4. Cost does not include any potential hazardous material remediation or utilities adjustments cost.

1. The above probable construction cost does not include R/W acquisition, land acquisition or wetland mitigation cost.2. Construction cost is based on data from a customized database that is oriented toward the specific type of project designed and executed by CDM. The database, compiled from years of project-specific cost quotations and contractor schedules of values, contains information on process and specialty equipment, engineered materials, and labor and productivity factors in Construction Specifications Institute Inc. (CSI) format for environmental and infrastructure projects3. Excavation cost (CY) may vary significantly if the excavated material can not be used as common fill and may need to be disposed of by the contractor.

A

S:\41542\52768\Report\Appendix B.xls

Page 1 of 8

Page 20: NOTE: This is only Part 5 of 5 of this report (Appendices A and B). … · 2008-01-30 · NOTE: This is only Part 5 of 5 of this report (Appendices A and B). The other four parts

Site Demolition

Demolish Concrete Driveways 18.52 CY $2,165 $1,160 $1,928 5,253$

Remove Existing Driveway Culverts 200 LF $1,138 $250 $2,855 $1,243 5,486$

Earthwork -$

Regrade Swale 530 CY $2,120 $5,944 8,064$

Construct 6 acre Pond (with 2000' of Berm, 20'W x 10'H) 75366 CY $568,483 $996,059 1,564,542$

Drainage & Containment -$

Driveway Culverts 10 EA $10,504 $9,231 $2,132 21,867$

End Structures 20 EA $2,100 $4,000 6,100$

Overflow Weir at Pond Outlet 1 EA $749 $2,380 $7 $1,907 5,043$

Site Improvements & Amenities -$

Sod @ Swale 14000 SF $8,260 8,260$

Sod @ Pond Slopes & Berm 73000 SF $43,070 43,070$

Concrete -$

Repave Concrete Driveways 18.52 CY $6,589 $5,212 $202 $277 $43 12,323$

Subtotal= 1,680,008$

Subtotal 1 (Nearest $1,000) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1,680,000$

Indirect Costs

Sales tax (Material, Equipment, Other) (7%) $62,348

Builders Risk Insurance (1.5% total cost) $46,890

General Liability Insurance (1% total cost) $31,260

General Construction Bonds (1.5 % total cost) $46,890

Indirect Cost Subtotal 187,388$

Subtotal 2 (Nearest $1,000) 1,867,000$

Overhead and Profit

General Contractor Field General Conditions (7% of Subtotal 2) $130,690

General Contractor Indirects, OH & Profit (10% of Subtotal 2) $186,700

Overhead & Profit Subtotal 317,390$

Subtotal 3 (Nearest $1,000) 2,184,000$

Contingency

Construction Contingency (35% of Subtotal 3) $764,400

Contingency Subtotal 764,400$

Subtotal 4 (Nearest $1,000) 2,948,000$

Engineering Services

Engineering, Design & Permitting (30% of Subtotal 4) $884,400

Engineering Subtotal 884,400$

Escalation

Escalation to Mid Point Constr (6% per year) $176,880

Escalation Subtotal 176,880$

TOTAL COST 4,010,000$

NOTE:

4. Cost does not include any potential hazardous material remediation or utilities adjustments cost.

1. The above probable construction cost does not include R/W acquisition, land acquisition or wetland mitigation cost.

2. Construction cost is based on data from a customized database that is oriented toward the specific type of project designed and executed by CDM. The database, compiled from years of project-specific cost quotations and contractor schedules of values, contains information on process and specialty equipment, engineered materials, and labor and productivity factors in Construction Specifications Institute Inc. (CSI) format for environmental and infrastructure projects

3. Excavation cost (CY) may vary significantly if the excavated material can not be used as common fill and may need to be disposed of by the contractor.

ItemLabor

AmountMaterial Amount

Estimated Total Cost

Estimated Quantity Units

Subcontractor Amount

Equipment Amount

Other Amount

Table B-2Opinion of Probable Construction CostProblem Area 2Astor Flood Study

A

S:\41542\52768\Report\Appendix B.xls

Page 2 of 8

Page 21: NOTE: This is only Part 5 of 5 of this report (Appendices A and B). … · 2008-01-30 · NOTE: This is only Part 5 of 5 of this report (Appendices A and B). The other four parts

Site Demolition

Demolish Concrete Driveways 63.33 CY $7,365 $3,966 $6,560 17,891$

Remove Existing Driveway Culverts 680 LF $3,864 $850 $9,518 $4,214 18,446$

Remove RCP Cross Drain 39 LF $222 $49 $571 $243 1,085$

Remove CMPCross Drain 42 LF $272 $53 $26 $321 672$

Earthwork -$

Regrade Swale 1125 CY $4,089 $11,045 15,134$

Excavation for Baffle Box 70 CY $625 $186 $93 $729 1,633$

Drainage & Containment -$

Driveway Culverts 680 LF $35,744 $31,390 $7,291 74,425$

End Structures 68 EA $7,140 $13,600 20,740$

36" RCP 175 LF $10,351 $11,157 $0 $4,209 25,717$

Site Improvements & Amenities -$

Sod @ Swale 26520 SF $15,647 15,647$

Concrete -$

Repave Concrete Driveways 63.33 CY $22,532 $17,823 $690 $946 $148 42,139$

Baffle Box (10.80'W x 32.30'L x 7.50' H) 43.32 CY $20,215 $16,241 $602 $936 $101 38,095$

Subtotal= 271,624$

Subtotal 1 (Nearest $1,000) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 272,000$

Indirect Costs

Sales tax (Material, Equipment, Other) (7%) $10,092

Builders Risk Insurance (1.5% total cost) $7,590

General Liability Insurance (1% total cost) $5,060

General Construction Bonds (1.5 % total cost) $7,590

Indirect Cost Subtotal 30,332$

Subtotal 2 (Nearest $1,000) 302,000$

Overhead and Profit

General Contractor Field General Conditions (7% of Subtotal 2) $21,140

General Contractor Indirects, OH & Profit (10% of Subtotal 2) $30,200

Overhead & Profit Subtotal 51,340$

Subtotal 3 (Nearest $1,000) 353,000$

Contingency

Construction Contingency (35% of Subtotal 3) $123,550

Contingency Subtotal 123,550$

Subtotal 4 (Nearest $1,000) 477,000$

Engineering Services

Engineering, Design & Permitting (30% of Subtotal 4) $143,100

Engineering Subtotal 143,100$

Escalation

Escalation to Mid Point Constr (6% per year) $28,620

Escalation Subtotal 28,620$

TOTAL COST 649,000$

NOTE:

Table B-3Opinion of Probable Construction CostProblem Area 3Astor Flood Study

ItemLabor

AmountMaterial Amount

Estimated Total Cost

Estimated Quantity Units

Subcontractor Amount

Equipment Amount

Other Amount

4. Cost does not include any potential hazardous material remediation or utilities adjustments cost.

1. The above probable construction cost does not include R/W acquisition, land acquisition or wetland mitigation cost.2. Construction cost is based on data from a customized database that is oriented toward the specific type of project designed and executed by CDM. The database, compiled from years of project-specific cost quotations and contractor schedules of values, contains information on process and specialty equipment, engineered materials, and labor and productivity factors in Construction Specifications Institute Inc. (CSI) format for environmental and infrastructure projects

3. Excavation cost (CY) may vary significantly if the excavated material can not be used as common fill and may need to be disposed of by the contractor.

A

S:\41542\52768\Report\Appendix B.xls

Page 3 of 8

Page 22: NOTE: This is only Part 5 of 5 of this report (Appendices A and B). … · 2008-01-30 · NOTE: This is only Part 5 of 5 of this report (Appendices A and B). The other four parts

Site Demolition

Demolish RCP Cross Drain 102 LF $871 $735 $1,049 2,655$

Earthwork -$

Excavation for Baffle Box 3371 CY $17,593 $2,238 $1,119 $21,422 42,372$

Drainage & Containment -$

RCP Culvert Box (48"x84") 34 LF $2,843 $13,953 $87 $5,551 22,434$

Concrete -$

Baffle Box (39'W x 117'L x 27.20' H) 568 CY $226,570 $180,383 $7,894 $10,678 $1,329 426,854$

Subtotal= 494,315$

Subtotal 1 (Nearest $1,000) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 494,000$

Indirect Costs

Sales tax (Material, Equipment, Other) (7%) $18,329

Builders Risk Insurance (1.5% total cost) $13,785

General Liability Insurance (1% total cost) $9,190

General Construction Bonds (1.5 % total cost) $13,785

Indirect Cost Subtotal 55,089$

Subtotal 2 (Nearest $1,000) 549,000$

Overhead and Profit

General Contractor Field General Conditions (7% of Subtotal 2) $38,430

General Contractor Indirects, OH & Profit (10% of Subtotal 2) $54,900

Overhead & Profit Subtotal 93,330$

Subtotal 3 (Nearest $1,000) 642,000$

Contingency

Construction Contingency (35% of Subtotal 3) $224,700

Contingency Subtotal 224,700$

Subtotal 4 (Nearest $1,000) 867,000$

Engineering Services

Engineering, Design & Permitting (30% of Subtotal 4) $260,100

Engineering Subtotal 260,100$

Escalation

Escalation to Mid Point Constr (6% per year) $52,020

Escalation Subtotal 52,020$

TOTAL COST 1,179,000$ 1179120

NOTE:

4. Cost does not include any potential hazardous material remediation or utilities adjustments cost.

1. The above probable construction cost does not include R/W acquisition, land acquisition or wetland mitigation cost.2. Construction cost is based on data from a customized database that is oriented toward the specific type of project designed and executed by CDM. The database, compiled from years of project-specific cost quotations and contractor schedules of values, contains information on process and specialty equipment, engineered materials, and labor and productivity factors in Construction Specifications Institute Inc. (CSI) format for environmental and infrastructure projects

3. Excavation cost (CY) may vary significantly if the excavated material can not be used as common fill and may need to be disposed of by the contractor.

ItemLabor

AmountMaterial Amount

Estimated Total Cost

Estimated Quantity Units

Subcontractor Amount

Equipment Amount

Other Amount

Table B-4Opinion of Probable Construction CostProblem Area 4Astor Flood Study

A

S:\41542\52768\Report\Appendix B.xls

Page 4 of 8

Page 23: NOTE: This is only Part 5 of 5 of this report (Appendices A and B). … · 2008-01-30 · NOTE: This is only Part 5 of 5 of this report (Appendices A and B). The other four parts

Site Demolition

18" RCP Culvert 110 LF $4,751 $2,992 $631 8,374$

Drainage & Containment -$

18" Flap Gate 1 LS $1,717 $10,027 $26 11,770$

Subtotal= 20,144$

Subtotal 1 (Nearest $1,000) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20,000$

Indirect Costs

Sales tax (Material, Equipment, Other) (7%) $738

Builders Risk Insurance (1.5% total cost) $555

General Liability Insurance (1% total cost) $370

General Construction Bonds (1.5 % total cost) $555

Indirect Cost Subtotal 2,218$

Subtotal 2 (Nearest $1,000) 22,000$

Overhead and Profit

General Contractor Field General Conditions (7% of Subtotal 2) $1,540

General Contractor Indirects, OH & Profit (10% of Subtotal 2) $2,200

Overhead & Profit Subtotal 3,740$

Subtotal 3 (Nearest $1,000) 26,000$

Contingency

Construction Contingency (35% of Subtotal 3) $9,100

Contingency Subtotal 9,100$

Subtotal 4 (Nearest $1,000) 35,000$

Engineering Services

Engineering, Design & Permitting (30% of Subtotal 4) $10,500

Engineering Subtotal 10,500$

Escalation

Escalation to Mid Point Constr (6% per year) $2,100

Escalation Subtotal 2,100$

TOTAL COST 48,000$

NOTE:

Table B-5Opinion of Probable Construction CostProblem Area 6Astor Flood Study

ItemLabor

AmountMaterial Amount

Estimated Total Cost

Estimated Quantity Units

Subcontractor Amount

Equipment Amount

Other Amount

4. Cost does not include any potential hazardous material remediation or utilities adjustments cost.

1. The above probable construction cost does not include R/W acquisition, land acquisition or wetland mitigation cost.2. Construction cost is based on data from a customized database that is oriented toward the specific type of project designed and executed by CDM. The database, compiled from years of project-specific cost quotations and contractor schedules of values, contains information on process and specialty equipment, engineered materials, and labor and productivity factors in Construction Specifications Institute Inc. (CSI) format for environmental and infrastructure projects

3. Excavation cost (CY) may vary significantly if the excavated material can not be used as common fill and may need to be disposed of by the contractor.

A

S:\41542\52768\Report\Appendix B.xls

Page 5 of 8

Page 24: NOTE: This is only Part 5 of 5 of this report (Appendices A and B). … · 2008-01-30 · NOTE: This is only Part 5 of 5 of this report (Appendices A and B). The other four parts

Earthwork -$

Swale 40 CY $504 $1,755 2,259$

Site Improvements & Amenities -$

Sod @ Swale 1000 SF $590 590$

Subtotal= 2,849$

Subtotal 1 (Nearest $1,000) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3,000$

Indirect Costs

Sales tax (Material, Equipment, Other) (7%) $120

Builders Risk Insurance (1.5% total cost) $90

General Liability Insurance (1% total cost) $60

General Construction Bonds (1.5 % total cost) $90

Indirect Cost Subtotal 360$

Subtotal 2 (Nearest $1,000) 3,000$

Overhead and Profit

General Contractor Field General Conditions (7% of Subtotal 2) $210

General Contractor Indirects, OH & Profit (10% of Subtotal 2) $300

Overhead & Profit Subtotal 510$

Subtotal 3 (Nearest $1,000) 4,000$

Contingency

Construction Contingency (35% of Subtotal 3) $1,400

Contingency Subtotal 1,400$

Subtotal 4 (Nearest $1,000) 5,000$

Engineering Services

Engineering, Design & Permitting (30% of Subtotal 4) $1,500

Engineering Subtotal 1,500$

Escalation

Escalation to Mid Point Constr (6% per year) $300

Escalation Subtotal 300$

TOTAL COST 7,000$

NOTE:

4. Cost does not include any potential hazardous material remediation or utilities adjustments cost.

1. The above probable construction cost does not include R/W acquisition, land acquisition or wetland mitigation cost.

2. Construction cost is based on data from a customized database that is oriented toward the specific type of project designed and executed by CDM. The database, compiled from years of project-specific cost quotations and contractor schedules of values, contains information on process and specialty equipment, engineered materials, and labor and productivity factors in Construction Specifications Institute Inc. (CSI) format for environmental and infrastructure projects.

3. Excavation cost (CY) may vary significantly if the excavated material can not be used as common fill and may need to be disposed of by the contractor.

ItemLabor

AmountMaterial Amount

Estimated Total Cost

Estimated Quantity Units

Subcontractor Amount

Equipment Amount

Other Amount

Table B-6Opinion of Probable Construction CostProblem Area 8Astor Flood Study

A

S:\41542\52768\Report\Appendix B.xls

Page 6 of 8

Page 25: NOTE: This is only Part 5 of 5 of this report (Appendices A and B). … · 2008-01-30 · NOTE: This is only Part 5 of 5 of this report (Appendices A and B). The other four parts

Drainage & Containment

15" RCP Culverts 120 LF $4,829 $3,139 $488 8,456$

End Structures 6 EA $630 $1,200 1,830$

Control Structure at Pond Outlet 1 EA $749 $2,380 $7 $1,907 5,043$

Subtotal= 15,329$

Subtotal 1 (Nearest $1,000) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15,000$

Indirect Costs

Sales tax (Material, Equipment, Other) (7%) $558

Builders Risk Insurance (1.5% total cost) $420

General Liability Insurance (1% total cost) $280

General Construction Bonds (1.5 % total cost) $420

Indirect Cost Subtotal 1,678$

Subtotal 2 (Nearest $1,000) 17,000$

Overhead and Profit

General Contractor Field General Conditions (7% of Subtotal 2) $1,190

General Contractor Indirects, OH & Profit (10% of Subtotal 2) $1,700

Overhead & Profit Subtotal 2,890$

Subtotal 3 (Nearest $1,000) 20,000$

Contingency

Construction Contingency (35% of Subtotal 3) $7,000

Contingency Subtotal 7,000$

Subtotal 4 (Nearest $1,000) 27,000$

Engineering Services

Engineering, Design & Permitting (30% of Subtotal 4) $8,100

Engineering Subtotal 8,100$

Escalation

Escalation to Mid Point Constr (6% per year) $1,620

Escalation Subtotal 1,620$

TOTAL COST 37,000$

NOTE:

4. Cost does not include any potential hazardous material remediation or utilities adjustments cost.

1. The above probable construction cost does not include R/W acquisition, land acquisition or wetland mitigation cost.

2. Construction cost is based on data from a customized database that is oriented toward the specific type of project designed and executed by CDM. The database, compiled from years of project-specific cost quotations and contractor schedules of values, contains information on process and specialty equipment, engineered materials, and labor and productivity factors in Construction Specifications Institute Inc. (CSI) format for environmental and infrastructure projects.

3. Excavation cost (CY) may vary significantly if the excavated material can not be used as common fill and may need to be disposed of by the contractor.

ItemLabor

AmountMaterial Amount

Estimated Total Cost

Estimated Quantity Units

Subcontractor Amount

Equipment Amount

Other Amount

Table B-7Opinion of Probable Construction CostProblem Area 11Astor Flood Study

A

S:\41542\52768\Report\Appendix B.xls

Page 7 of 8

Page 26: NOTE: This is only Part 5 of 5 of this report (Appendices A and B). … · 2008-01-30 · NOTE: This is only Part 5 of 5 of this report (Appendices A and B). The other four parts

Earthwork -$

Regrade Swale 813 CY $3,079 $8,409 11,488$

Drainage & Containment -$

End Structures 50 EA $5,255 $10,000 15,255$

Manholes 4 EA $3,298 $12,697 $60 $2,569 $378 19,002$

Control Structure 1 EA $749 $2,380 $7 $1,907 5,043$

Inlets 2 EA $1,500 $12,496 $23 $3,803 17,822$

15" RCP Culverts 28 EA $54,862 $33,817 $5,691 94,370$

18" RCP Culverts 370 LF $14,739 $7,827 $2,123 24,689$

Site Improvements & Amenities -$

Sod @ Swale 20000 SF $11,800 11,800$

Subtotal= 199,469$

Subtotal 1 (Nearest $1,000) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 199,000$

Indirect Costs

Sales tax (Material, Equipment, Other) (7%) $7,380

Builders Risk Insurance (1.5% total cost) $5,550

General Liability Insurance (1% total cost) $3,700

General Construction Bonds (1.5 % total cost) $5,550

Indirect Cost Subtotal 22,180$

Subtotal 2 (Nearest $1,000) 221,000$

Overhead and Profit

General Contractor Field General Conditions (7% of Subtotal 2) $15,470

General Contractor Indirects, OH & Profit (10% of Subtotal 2) $22,100

Overhead & Profit Subtotal 37,570$

Subtotal 3 (Nearest $1,000) 259,000$

Contingency

Construction Contingency (35% of Subtotal 3) $90,650

Contingency Subtotal 90,650$

Subtotal 4 (Nearest $1,000) 350,000$

Engineering Services

Engineering, Design & Permitting (30% of Subtotal 4) $105,000

Engineering Subtotal 105,000$

Escalation

Escalation to Mid Point Constr (6% per year) $21,000

Escalation Subtotal 21,000$

TOTAL COST 475,000$

NOTE:

4. Cost does not include any potential hazardous material remediation or utilities adjustments cost.

1. The above probable construction cost does not include R/W acquisition, land acquisition or wetland mitigation cost.

2. Construction cost is based on data from a customized database that is oriented toward the specific type of project designed and executed by CDM. The database, compiled from years of project-specific cost quotations and contractor schedules of values, contains information on process and specialty equipment, engineered materials, and labor and productivity factors in Construction Specifications Institute Inc. (CSI) format for environmental and infrastructure projects.

3. Excavation cost (CY) may vary significantly if the excavated material can not be used as common fill and may need to be disposed of by the contractor.

ItemLabor

AmountMaterial Amount

Estimated Total Cost

Estimated Quantity Units

Subcontractor Amount

Equipment Amount

Other Amount

Table B-8Opinion of Probable Construction CostProblem Area 13Astor Flood Study

A

S:\41542\52768\Report\Appendix B.xls

Page 8 of 8