Not Your Father’s CommissioningCommissioning Changes & Requirements for LEED v4
Presenters:TIM McELROY, COMMISSIONING AUTHORITYCertified Energy Manager, Qualified Commissioning Provider, LEED_AP
KEITH G. PEHL, PRESIDENT of OPTIMA ENGINEERINGProfessional Engineer, LEED AP
CHRISTINE M. QUIGLEY, PRINCIPALProfessional Engineer, Registered Roof Consultant, LEED AP
Everything Changes… All the Time
PrerequisiteFundamental
Commissioning and Verification
• Credit title renamed from “Fundamental Commissioning of Building Energy Systems”.• Modified intent to ensure project meets the owner’s projects requirements related to energy, water, indoor environmental quality and durability.• Added requirement for preparing an Operations andMaintenance Plan.• Added requirement to engage a Commissioning Authority by the end of the design development phase.• Clarified language for who can be the commissioning authority.• Included requirements for a design review of the enclosure.
CreditEnhancedCommissioning
•Added options for monitoring based commissioning and envelope commissioning.• Added requirements to prepare the building operators for the intended operation of building systems• Clarified language for who can be the commissioning authority.
• Requirement for preparing an Operating and Maintenance Plan• Requirement to engage Cx Agent by the end of the Design Development phase• Requirement for design review of enclosure
LEED 2009 LEED v4
Fundamental Commissioning
EnhancedCommissioning
FundamentalCx & Verification
Option 1 Option 2
EnhancedCommissioning
Path 1 Enhanced Commissioning (3 points)
Path 2 Enhanced and Monitoring Based Cx (1 point)
Envelope Cx (2 points)
Predesign, SD, DDLEED 2009
EAp1 Fund Cx EAc3 Enhanced Cx
Owner documents Owner’s Project Requirements (OPR) same as EAp1
Design Team develops Basis of Design (BOD) document
same as EAp1
LEED v4
EAp1 Fund Cx & Verification
EAc1 Enhanced Cx
OPR with envelope requirements Same as EAp1
BOD document including envelope Same as EAp1
Prior to start of CDs Owner designates CxA Same as EAp1
Commissioning Authority provides Cx Plan
Option 1(Choose either Path 1 or both
Paths)Option 2
Path 1:Same as EAp1
Path 2:AND ADD
development of monitoring-based procedures and
identify points to be measured and
evaluated to assess performance of
energy- and water-consuming systems
Same as EAp1 AND include envelope
Construction DocumentsLEED 2009
EAp1 Fund Cx
EAc3 Enhanced Cx EAp1 Fund Cx & Verification EAc1 Enhanced Cx
Option 1Option 2
Path 1 Path 2
N/A Prior to 50% CDs Owner designates CxA - - - --
N/A Prior to 50% CDs CxA provides Cx Plan - - - -
N/A Prior to 50% CDs CxA conducts Cx drawing design review
Prior to 50% CDs CxA conducts Cx drawing design review (includes envelope) Same as EAp1 Same as
Path1Same as EAp1
N/A Prior to 50% CDs CxA reviews OPR Prior to 50% CDs CxA reviews OPR Same as EAp1 Same as Path1
Same as EAp1
N/A Prior to 50% CDs CxA reviews BOD Prior to 50% CDs CxA reviews BOD Same as EAp1 Same as Path1
Same as EAp1
Project team incorporates Cx reqirements into
CDs
Same as EAp1 Project team incorporates Cx reqirements into CDs
Same as EAp1 PLUS
incorporates systems manual
requirements and operator and occupant
training requirements
Same as Path1
Same as EAc1 Path
1 PLUS Envelope
and training
requirements
N/A CxA performs back-check of all reviewed documents CxA performs back-check of all reviewed documents Same as EAp1 Same as
Path1Same as EAp1
LEED v4
BiddingLEED 2009 LEED v4
EAp1 Fund Cx EAc3 Enhanced Cx EAp1 Fund Cx & Verification
EAc1 Enhanced Cx
Option 1
Option 2
Path 1 Path 2
Owner designates CxA prior to installation. CxA presents
Cx Plan
CxA reviews contractor submittals for applicable systems
N/A
CxA reviews contractor
submittals for applicable systems
Same as Path 1
Same as EAc1 Path 1 PLUS envelope component submittals
ConstructionLEED 2009
EAp1 Fund Cx EAc3 Enhanced Cx EAp1 Fund Cx & Verification EAc1 Enhanced Cx
Option 1Option 2
Path 1 Path 2
CxA verifies installation and performance of Cx'd
sytemsSame as EAp1
CxA verifies installation and performance of Cx'd sytems
(envelope excluded)
Same as EAp1
Same as Path 1
Same as EAp1 AND include
envelope
CxA performs systems functional performance
testingSame as EAp1
CxA performs systems functional performance testing (envelope
excluded)
Same as EAp1
Same as Path 1
Same as EAp1 AND include
envelope
N/AO&M and Systems Manual for the Cx'd systems developed and
verified
Systems Manual for the Cx'd systems developed and verified
Same as EAp1
Same as Path 1
Same as EAp1 AND include
envelope
Facilities Requirements and O&M plan for the HVAC and lighting systems developed and verified
Same as EAp1
Same as Path 1
Same as EAp1 AND include
envelope
LEED v4
EAp1 requirements: a sequence of operations for the building; the building occupancy schedule; equipment run-time schedules; setpoints for all HVAC equipment; set lighting levels throughout the building; minimum outside air requirements; any changes in schedules or setpoints for different seasons, days of the week, and times of day; a systems narrative describing the mechanical and electrical systems and equipment; a preventive maintenance plan for building equipment described in the systems narrative; and a commissioning program that includes periodic commissioning requirements, ongoing commissioning tasks, and continuous tasks for critical facilities.
Post ConstructionLEED 2009
EAp1 Fund Cx
EAc3 Enhanced Cx EAp1 Fund Cx & Verification
EAc1 Enhanced Cx
Option 1Option 2
Path 1 Path 2
N/A CxA verifies that operator and occupant training are complete
N/A
CxA verifies that operator and occupant training are complete AND effective
Same as Path 1
Same as EAc1 Path 1 PLUS envelope
components
CxA develops a Cx Report
Same as EAp1 CxA develops a Cx Report
Same as EAp1 PLUS develop an on-going commissioning plan
Same as Path 1
Same as EAc1 Path 1 PLUS envelope
components
N/A
Verify delivery of updated Facilities
requirements, O&M plan and Systems
Manual
Same as Path 1 AND include
needed changes in
settings found during
monitoring with reasonfor changes
Same as EAc1 Path 1 PLUS envelope
components
LEED v4
OccupancyLEED 2009
EAp1 Fund Cx
EAc3 Enhanced Cx EAp1 Fund Cx & Verification
EAc1 Enhanced Cx
Option 1Option 2
Path 1 Path 2
N/ACxA reviews building operation within 10 months after substantial completion
N/A
CxA reviews building operation within 10
months after substantial completion
Same as Path 1
Same as EAc1 Path 1 PLUS envelope
components
N/AVerify seasonal
testingSame as Path 1
Same as EAc1 Path 1 PLUS envelope
components
LEED v4
CxA RestrictionsLEED 2009
EAp1 Fund Cx EAc3 Enhanced Cx EAp1 Fund Cx & Verification
EAc1 Enhanced Cx
Option 1Option 2
Path 1 Path 2
<50,000 gsf: CxA can be from design or
construction team in addition to below
Any gsf: CxA is a 3rd party contracted by owner, architect or
engineer. Also owner's rep or employee
<20,000 gsf: CxA can be from design or construction team in
addition to below
Any gsf: CxA is a 3rd party contracted by owner, architect or engineer. Also owner's
rep or employee
Applies to ALL paths & options
>50,000 gsf: CxA can be 3rd party, Owner's Rep or employee. Can be from
design firm or construction company but only responsibility is Cx
>20,000 gsf: CxA can be 3rd party, Owner's Rep or employee.
Can be from design firm or construction company but only
responsibility is Cx
Any gsf: Reviewer of envelope design can be performed by a
member of design or construction team
LEED v4
CxA QualificationsLEED 2009
EAp1 Fund Cx EAc3 Enhanced Cx EAp1 Fund Cx & Verification
EAc1 Enhanced Cx
Option 1
Option 2
Path 1 Path 2
(2) buildings similar in type and scope (2) buildings similar in type and scope; early design through 10 month occupancy
LEED v4
Systems Required to be in Scope of CxALEED 2009
EAp1 Fund Cx EAc3 Enhanced Cx
EAp1 Fund Cx & Verification EAc1 Enhanced Cx
Option 1Option 2
Path 1 Path 2
HVAC Same as EAp1 HVAC and controls Same as EAp1
Same as EAp1 PLUS
monitoring equipment
Same as EAp1
Domestic Hot Water Same as EAp1 Domestic hot water including pumps and controls Same as EAp1 Same as EAp1 Same as EAp1
Lighting & Daylighting Controls
Same as EAp1Service and distribution, lighting system, lighting
and daylighting controlsSame as EAp1
Same as EAp1 PLUS
monitoring equipment
Same as EAp1
Renewable Energy Same as EAp1 Renewable Energy
Building Envelope (design phase only) Same as EAp1 Same as EAp1
Same as EAp1 PLUS
construction phase and occupancy
LEED v4
Building Enclosure Commissioning (BECx) is a quality-focused process involving evaluation, verification, and documentation that a building’s envelope design, construction and operation meet defined performance expectations established during
project initiation in the Owner’s Project Requirements (OPR).
Building Enclosure Commissioning
Building Enclosure Systems• Foundations• Below Grade Walls• Plaza Decks and Planters• Exterior Cladding• Curtain walls and Storefronts• Windows and Doors• Sealant, Expansion Joints and Flashings• Air Barriers• Roofs • Skylights
Why BECx?• BE Function & Performance Expectations
• Thermal Performance• Air/Moisture/Light Control• Fire Resistance• Acoustical Performance• Indoor Comfort• Structural Integrity• Security• Aesthetics• Maintainability/Sustainability• Economically Viable
Why BECx?• LEED 2009 EA Prerequisite 1: “The building envelope is an important component of
a facility that impacts energy consumption, occupant comfort and indoor air quality. While this prerequisite does not require building envelope commissioning, an owner can achieve significant financial savings and reduce risk of poor indoor air quality by including it in the commissioning process.”
• Energy Savings• 2005 NIST Study concluded that “…
continuous air barrier systems can reduce air leakage by up to 83%...”
• ASHRAE Journal, March 2005: “Uncontrolled air leakage in buildings increases the heating and cooling energy consumption by up to 40%.”
Why BECx?
• Building and MEP System Performance Dependent upon Building Enclosures• Well-recognized MEP Cx Benefits• MEP systems rely on properly designed and installed
Building Enclosure Systems• Without air/moisture/thermal control, HVAC systems
utilized to achieve thermal comfort and quality of indoor air will be unnecessarily expensive to install, operate and maintain
Why BECx?
• Underperforming Buildings• March 2008 New Buildings Institute Study: 25% of LEED
buildings are extremely less energy efficient than forecasted• LEED Gold Project Twin Lakes Green Building Complex
(Sarasota County, FL): Evacuated for mold• LEED Platinum Project (Wake Forest, NC): Costly water
intrusion investigation and flashing repair project
Why BECx?
• Small Percentage But Big Consequences • “Transitions between building envelope components or
assemblies generally total less than 1% of the building envelope area but can account for 90% of envelope failures and leakage.” - (NIBS Annex U, 2006)
• “Errors and omissions in design and construction process are primary (and most frequently overlooked) source of uncontrolled rainwater penetration through the Building Envelope and represent 80% of all construction-related claims in the US.” – (Real Estate Issues. 33.3, 2008)
Why BECx?
• Small Percentage But Big Consequences • BE Design Flaws/Construction Defects result
in:• Uncontrolled air/water intrusion• Premature failures/deterioration• Biological growth• Increased energy costs• Costly investigations/repairs• Decreased occupant productivity/tenant
retention
Why BECx?
BECx Approach• Follow Industry Standards:
• ASHRAE Guideline 0-2005• NIBS Guideline 3-2012• ASTM E2813-12
BECx Approach
BECx Process• Pre-Design Phase• Design Phase• Construction Phase• Occupancy and Operations Phase
Pre-Design Phase Services
• Attend project kick-off meeting• Establish communication plan• Review project requirements • Discuss influencing factors
• Develop/document preliminary BE Owner’s Project Requirements (OPR)
• Identify Scope and Budget for BECx• Develop preliminary BECx Plan
Owner’s Project Requirements
• OPR Example: Exterior Enclosure Curtain Wall• Thermal Performance Criteria: Minimum R or U values• Structural Performance Criteria: Minimum live, snow,
wind loads, maximum deflection and drift • Fire Resistance Criteria: Fire rating• Air Leakage Criteria: Maximum CFM/s.f. at specified
pressure (psf) measured by specified standard• Water Leakage Criteria: No uncontrolled leaks at a static
for specified pressure (psf) measured by specified standard• Condensation Control: Minimum Condensation Resistance
Factor• Others: Acoustical Performance, Glare Control
BECx Plan
• BECx Plan Outlines:• BECx process• Roles and responsibilities of BECxA
and other project team members• Methodology to verify and document
compliance of as-built construction with contract documents and OPR• Clear, unambiguous definitions of
failure and quantifiable threshold of performance to validate OPR and BOD
Relative Humidity Comparison
40
50
60
70
80
90
100
7/26/1012:00 PM
7/27/1012:00 AM
7/27/1012:00 PM
7/28/1012:00 AM
7/28/1012:00 PM
7/29/1012:00 AM
7/29/1012:00 PM
7/30/1012:00 AM
7/30/1012:00 PM
Time, day/hr
Re
lati
ve
Hu
mid
ity,
%
Beam Cavity RH%
Occupied Area RH%
Exterior RH%
Design Phase Services• 3rd Party Independent design review during Schematic
Design, Design Development and Construction Document Phases
• Attend design review meetings• Deliver BECx Specification Section 019115• Develop and maintain Basis of Design (BOD)• Update OPR and BECx Plan
Design Reviews• BE Drawings/Details Address:
• Drainage Plane/Flashing Details• Air/Vapor Barrier System Details• Thermal Barrier Details
• BE Reviews Verify:• Continuous/Constructible Control Layers• Material Compatibility and Product
Appropriateness• Compliance with OPR, Building Code and
Manufacturer’s Requirements• Drawing Continuity: Identification of Missing
or Conflicting Details
Pre-Construction Phase Services
• Attend Pre-Bid Conference• Review BE Information in Bids• Review BE Submittals and Shop Drawings • Coordinate BECx activities with Contractor• Update and Document OPR, BOD, BECx Plan
Construction Phase Services• Attend pre-construction, mock-ups installations and
construction progress meetings• Perform on-site inspections and report observations
• Assist with QA/QC reviews• Develop and maintain BE-related punch list reports of
outstanding or defective items
• Develop/distribute BECx close-out documents• Maintain/Update OPR, BOD and BECx Plan• Observe or Conduct Performance Verification Testing
Inspection Services
Performance Verification Testing• Air Leakage• Static and Dynamic Pressure Water Penetration• Adhesion Strength Testing• Anchor strength• Sound
Performance Verification Testing• Infrared Imaging• IR/Nuclear Roof Surveys• Flood testing• Dynamic Pressure Water Penetration • Wind Uplift Testing
Occupancy and Operations Phase Services
• Attend Occupancy and Operations planning meeting• Provide Final BECx Report
• Summary of BE systems tested and results• Tabulation of BE system warranties• Maintenance Manual
• Perform limited survey and testing (nondestructive) of BE systems at milestone intervals
• Assist with LEED Certification• University of Florida: Innovation in Design credit for BECx• LEED V4: BECx still not part of prerequisite Cx but BE Design
Review required
Systems optional in scope of CxA (must pursue EAc3 / EAp1 to apply for ID credit)
LEED 2009
EAp1 Fund Cx EAc3 Enhanced Cx EAp1 Fund Cx & Verification
EAc1 Enhanced Cx
N/A Envelope N/A Envelope Cx during & after construction
N/A Fire & Life Safety N/A Fire & Life Safety
N/A Water Collection systems N/A Water Collection systems
N/A Stormwater Management N/A Stormwater Management
N/A Water Treatment N/A Water Treatment
N/A IT Systems N/A IT Systems
N/A Irrigation N/A Irrigation
LEED v4
Referenced Standards
LEED 2009
EAp1 Fund Cx EAc3 Enhanced Cx EAp1 Fund Cx & Verification
EAc1 Enhanced Cx
Option 1Option 2
Path 1 Path 2
NONE NONEASHRAE Guidelines 0-2005 and 1.1-2007; NIBS Guideline 3-
2012
LEED v4
•ASHRAE Guidelines 0-2005 - GENERAL •ASHRAE 1.1-2007 – HVAC Systems• NIBS Guideline 3-2012 – BUILDING ENVELOPE
Envelope Requirements
LEED 2009
EAp1 Fund Cx EAc3 Enhanced Cx EAp1 Fund Cx & Verification
EAc1 Enhanced Cx
Option 1Option 2
Path 1 Path 2
NONE NONEInclude in OPR, BOD and
review of OPR, BOD and design documents
NONE NONE
same as EAp1 PLUS envelope inspection and performance
testing
LEED v4
Documents required to be uploaded to LEED OnlineLEED 2009
EAp1 Fund Cx
EAc3 Enhanced Cx EAp1 Fund Cx & Verification
EAc1 Enhanced Cx
Option 1Option 2
Path1 Path 2
Summary of the Cx Report
Cx Plan TOCTraining
PlanMeasurements
Points
Evidence of envelope
performance testing
(1) completed FTOngoing
Commissioning Plan
Current Facilities Requirements (CFR) and O&M plan and TOC
Summary of the Cx Report
LEED v4
Bottomline Changes to v4 from v2009Fundamental Cx & Verification
• Includes envelope design review
• 50k sf lowered to 20k sf• CxA designated prior to CDs• Added review and back-check
of OPR, BOD and design documents
• Added systems manual and facilities requirements documentation
• Additional documentation uploaded to LEED Online
Enhanced Cx:
Option 1/Path 1• Added ongoing Cx plan• Added systems manual requirements and
operator and occupant training requirements to CDs
• Verifying delivery of Facilities requirements, O&M plan and Systems Manual
• Verify seasonal testing occurredOption 1/Path 2• M&V
Option 2• Envelope inspection and performance
testing
QUESTIONS?