Page 1: North Texas Municipal Water District · sale in April 2016 – Bond sale for ... • Manufacturing and delivery of pipes – Delivery of the pipes scheduled for last week of June

North Texas Municipal Water District“Regional Service Through Unity … 

Meeting our Region’s Needs Today and Tomorrow”

Water Committee MeetingMay 26, 2016

Page 2: North Texas Municipal Water District · sale in April 2016 – Bond sale for ... • Manufacturing and delivery of pipes – Delivery of the pipes scheduled for last week of June

I. CALL TO ORDER

II. ACTION ITEMS

A. Consider Approval of Water Committee Meeting Minutes – April 18, 2016B. TABLED ITEM: Consider Recommendation on Authorizing Execution of Contract

Amendment to the Construction Manager At-Risk Agreement and AuthorizingGuaranteed Maximum Price for Project No. 269, Trinity River Main Stem Pump Stationand Raw Water Pipeline

C. Consider Recommendation on Authorizing Implementation of Operational Scenariosto Reduce Evaporative Loss at the East Fork Raw Water Supply Project (Wetland)(Please refer to Administrative Memorandum No. 4656)

D. Consider Recommendation on Adoption of Resolution No. 16-26 Authorizing Filing ofWater Use Amendment Application Regarding Overdrafting Lake Lavon for the EastFork Wetland Project When Water Cannot Be Pumped to Lake Lavon(Please refer to Administrative Memorandum No. 4654)

E. Consider Recommendation on Adoption of Resolution No. 16-25 Authorizing Filing of Temporary Water Use Permit Application Regarding Overdrafting Lake Lavon for Three-Year Period (Please refer to Administrative Memorandum No. 4653)

Agenda

Page 3: North Texas Municipal Water District · sale in April 2016 – Bond sale for ... • Manufacturing and delivery of pipes – Delivery of the pipes scheduled for last week of June

F. Consider Recommendation on Adoption of Resolution No. 16-27 Authorizing Filing of Amendment to Water Right Regarding Overdrafting Lake Lavon in Lieu of Transporting Water from Lake Texoma or Chapman Lake (Please refer to Administrative Memorandum No. 4655)

G. Consider Authorizing Reallocation of Funding for Construction Manager At-Risk Construction Services on Project No. 269, Trinity River Main Stem Pump Station and Raw Water Pipeline(Please refer to Administrative Memorandum No. 4671)

III. DISCUSSION ITEMS

A. Update on Able Springs Emergency Connection authorized in October 2014B. Discuss Property Right Matters Related to the East Fork Raw Water Supply Project

(Wetland)C. Update on Alternatives for Main Stem Pump StationD. Update on Accessing Lake Fork Water Rights and Potential OptionsE. Update on Lower Bois d’Arc Creek Permitting and HGM ModelF. Update on Wylie Water Treatment Plan Regulatory MattersG. Opportunity for Committee Members to Request Potential Future Agenda Items

(No substantive discussion of items will take place at this time)

IV. ADJOURNMENT

Agenda

Page 4: North Texas Municipal Water District · sale in April 2016 – Bond sale for ... • Manufacturing and delivery of pipes – Delivery of the pipes scheduled for last week of June

II. ACTION ITEMS

A. Consider Approval of Water Committee Meeting Minutes – April 18, 2016 

Recommend Approval of Water Committee Meeting Minutes of April 18, 2016

Agenda

Page 5: North Texas Municipal Water District · sale in April 2016 – Bond sale for ... • Manufacturing and delivery of pipes – Delivery of the pipes scheduled for last week of June

II. ACTION ITEMS

B. TABLED ITEM: Consider Recommendation on Authorizing Execution of Contract Amendment to the Construction Manager At‐Risk Agreement and Authorizing Guaranteed Maximum Price for Project No. 269, Trinity River Main Stem Pump Station and Raw Water Pipeline

Recommend tabling until next Water Committee Meeting

Agenda

Page 6: North Texas Municipal Water District · sale in April 2016 – Bond sale for ... • Manufacturing and delivery of pipes – Delivery of the pipes scheduled for last week of June

II. ACTION ITEMS

C. Consider Recommendation on Authorizing Implementation of Operational Scenarios to Reduce Evaporative Loss at the East Fork Raw Water Supply Project (Wetland) (Please refer to Administrative Memorandum No. 4656)

Agenda

Page 7: North Texas Municipal Water District · sale in April 2016 – Bond sale for ... • Manufacturing and delivery of pipes – Delivery of the pipes scheduled for last week of June
Page 8: North Texas Municipal Water District · sale in April 2016 – Bond sale for ... • Manufacturing and delivery of pipes – Delivery of the pipes scheduled for last week of June

• Wetlands were Designed to Treat 91 mgd: Currently Treating Less than 35‐40 mgd on Average (East Fork Water) 

• Negotiations are Ongoing for Treating Additional Main Stem Water in Wetlands

• NTMWD Has Operational Flexibility

Executive Director and Staff Recommend authorizing Implementation of Operational Scenarios to Reduce Evaporative Loss at the East Fork Raw Water Supply Project (Wetland)

Wetlands Operation

Page 9: North Texas Municipal Water District · sale in April 2016 – Bond sale for ... • Manufacturing and delivery of pipes – Delivery of the pipes scheduled for last week of June

II. ACTION ITEMS

D. Consider Recommendation on Adoption of ResolutionNo. 16‐26 Authorizing Filing of Water Use AmendmentApplication Regarding Overdrafting Lake Lavon for theEast Fork Wetland Project When Water Cannot BePumped to Lake Lavon

(Please refer to Administrative Memorandum No. 4654)

Agenda

Page 10: North Texas Municipal Water District · sale in April 2016 – Bond sale for ... • Manufacturing and delivery of pipes – Delivery of the pipes scheduled for last week of June

• East Fork Water Rights Tied to Daily WWTP Discharges• USACE Operational Protocol for Lake Lavon Preclude Moving East Fork Water when Lavon in Flood Stage

• Water Right Application Seeks Rights to Account for Water Used Against East Fork Water Right when Lavon in Flood Pool (Above Elev. 492’)

• Staff and Consultants added sources after agenda was posted

East Fork Spill Credit

Page 11: North Texas Municipal Water District · sale in April 2016 – Bond sale for ... • Manufacturing and delivery of pipes – Delivery of the pipes scheduled for last week of June

“Recommend to the Board of Directors tabling the action included on today’s Board agenda (May 26, 2016) with:• Direction for staff to include additional water supplies in 

the water right amendment application, and • Recommend to the Board of Directors adopting a 

Resolution at the June 2016 Board Meeting, authorizing the filing of an application with the TCEQ to secure the right to overdraft Lake Lavon whenever:– the elevation of the Lake is above elevation 492’ mean sea level 

and water cannot be transported to Lake Lavon from the East Fork Wetland, or 

– from the District’s supplies in the Sabine River Basin or – supplies made available through the Main Stem Pump Station.”

East Fork Spill Credit

Page 12: North Texas Municipal Water District · sale in April 2016 – Bond sale for ... • Manufacturing and delivery of pipes – Delivery of the pipes scheduled for last week of June

II. ACTION ITEMS

E. Consider Recommendation on Adoption of Resolution No. 16‐25 Authorizing Filing of Temporary Water Use Permit Application Regarding Overdrafting Lake Lavon for Three‐Year Period

(Please refer to Administrative Memorandum No. 4653)

Agenda

Page 13: North Texas Municipal Water District · sale in April 2016 – Bond sale for ... • Manufacturing and delivery of pipes – Delivery of the pipes scheduled for last week of June

• New Water Supplies are Delayed for a Number of Reasons

• A Temporary Permit May be Granted to Assist with Water Rights

• 3 Years is the Maximum Term TCEQ May Grant• Similar Permit was Granted for Loss of Texoma

Executive Director and Staff Recommend Adoption of Resolution No. 16‐25 Authorizing Filing of Temporary Water Use Permit Application Regarding OverdraftingLake Lavon for Three‐Year Period

3‐Year Temporary Overdraft

Page 14: North Texas Municipal Water District · sale in April 2016 – Bond sale for ... • Manufacturing and delivery of pipes – Delivery of the pipes scheduled for last week of June

II. ACTION ITEMS

F. Consider Recommendation on Adoption of Resolution No. 16-27 Authorizing Filing of Amendment to Water Right Regarding Overdrafting Lake Lavon in Lieu of Transporting Water from Lake Texoma or Chapman Lake

(Please refer to Administrative MemorandumNo. 4655)

Agenda

Page 15: North Texas Municipal Water District · sale in April 2016 – Bond sale for ... • Manufacturing and delivery of pipes – Delivery of the pipes scheduled for last week of June

• NTMWD's Existing Water Rights Permit Overdraft Lavon Under Certain Conditions1) Lavon in Flood Pool & "Spilling“2) Ray Hubbard Above 435.5' & "Spilling"3) Downstream Flows

• USACE Does Not Always Release Flood Waters From Lavon• DWU Does Not Always Allow Water to Rise Above 435.5‘• Idea is to Permit the Claiming of "Spill Credit" on Lavon 

Water Elevation Only

Modify Existing Overdraft Rights

Page 16: North Texas Municipal Water District · sale in April 2016 – Bond sale for ... • Manufacturing and delivery of pipes – Delivery of the pipes scheduled for last week of June

Executive Director and Staff Recommend Adoption of Resolution No. 16-27 Authorizing Filing of Amendment to Water Right Regarding Overdrafting Lake Lavon in Lieu of Transporting Water from Lake Texoma or Chapman Lake

Modify Existing Overdraft Rights

Page 17: North Texas Municipal Water District · sale in April 2016 – Bond sale for ... • Manufacturing and delivery of pipes – Delivery of the pipes scheduled for last week of June

II. ACTION ITEMS

G. Consider Authorizing Reallocation of Funding for Construction Manager At‐Risk Construction Services on Project No. 269, Trinity River Main Stem Pump Station and Raw Water Pipeline

(Please refer to Administrative Memorandum No. 4671)

Agenda

Page 18: North Texas Municipal Water District · sale in April 2016 – Bond sale for ... • Manufacturing and delivery of pipes – Delivery of the pipes scheduled for last week of June

MSPS CMAR• April 2015 ‐ Board authorized an initial appropriation of $41 million to 

fund the project.

• June and October 2015 ‐ Board authorized execution of contract amendment(s) for procurement, construction packages, and CMAR construction services.

– Maximize use of the $40,120,541 funding available for the project– Purchase of approximately 18 miles of 72‐inch pipe– Construction of weir box within wetlands property

• Balance for the project to be funded upon approval of the GMP and bond sale in April 2016

– Bond sale for MSPS portion was $70,000,000– GMP of $103,500,000– Tabled by the Water Committee

Page 19: North Texas Municipal Water District · sale in April 2016 – Bond sale for ... • Manufacturing and delivery of pipes – Delivery of the pipes scheduled for last week of June

MSPS CMAR• Two major challenges facing the project team

– Manufacturing and delivery of pipes– Keeping CMAR team productive and intact

• Manufacturing and delivery of pipes– Delivery of the pipes scheduled for last week of June 2016– Stopping production can lead to extended delays and additional costs– Ad Memo No. 4671 to reallocate funds to facilitate delivery of pipes on project site– No additional funding required for the project

• Keeping CMAR team productive and intact– Allow the CMAR to construct a new weir box to improve metering – Work is required regardless of wetlands property issue outcome– Work coordinated between Lewis Isaacks and Rosewood Properties– Provides sufficient work for the CMAR team to keep intact

Page 20: North Texas Municipal Water District · sale in April 2016 – Bond sale for ... • Manufacturing and delivery of pipes – Delivery of the pipes scheduled for last week of June

Executive Director and Staff recommend authorizing reallocation of funding for Construction Manager at‐Risk Construction Services for Project No. 269, Trinity River Main Stem Pump Station and Raw Water Pipeline

MSPS CMAR 

Page 21: North Texas Municipal Water District · sale in April 2016 – Bond sale for ... • Manufacturing and delivery of pipes – Delivery of the pipes scheduled for last week of June

III. DISCUSSION ITEMS

A. Update on Able Springs Emergency Connection authorized in October 2014

Agenda

Page 22: North Texas Municipal Water District · sale in April 2016 – Bond sale for ... • Manufacturing and delivery of pipes – Delivery of the pipes scheduled for last week of June

• October 2014: Board Authorized an Emergency Interconnect through Able Springs for Private Water Supplier (Aqua Texas)

• Initial Term 6 mos. Additional 6 mos. Optional.  (12 mos. Total)

• Emergency Supply Contract Never Executed• April 2015: Aqua Texas Requested Connection Activation• New Well for Aqua Texas is Not Imminent

Able Springs

Page 23: North Texas Municipal Water District · sale in April 2016 – Bond sale for ... • Manufacturing and delivery of pipes – Delivery of the pipes scheduled for last week of June

III. DISCUSSION ITEMS

B. Discuss Property Right Matters Related to the East Fork Raw Water Supply Project (Wetland)

Agenda

Page 24: North Texas Municipal Water District · sale in April 2016 – Bond sale for ... • Manufacturing and delivery of pipes – Delivery of the pipes scheduled for last week of June
Page 25: North Texas Municipal Water District · sale in April 2016 – Bond sale for ... • Manufacturing and delivery of pipes – Delivery of the pipes scheduled for last week of June

III. DISCUSSION ITEMS

C. Update on Alternatives for Main Stem Pump Station

Agenda

Page 26: North Texas Municipal Water District · sale in April 2016 – Bond sale for ... • Manufacturing and delivery of pipes – Delivery of the pipes scheduled for last week of June

Cost / Schedule Summary

Alt Description Schedule Impact Cost Impact

1 Treatment at Main Stem PS (Join at Conveyance PS)

Spring 2019 $46,900,000 

2 Deliver to East Fork (Upstream from Wetlands)

Spring 2018 $6,460,000 

3 Deliver to Treatment Plant Along Conveyance PL (North of Seagoville Ranch)

Spring 2019 $89,900,000 

4 Treat after Water from Wetlands Joins Water from Main Stem

Spring 2019 $114,800,000 

26

Cost / Schedule Summary

Notes: These are additional costs for each option – the current cost for the Main Stem PS with no changes is $104,000,000. Completion is scheduled for Spring 2018.

Page 27: North Texas Municipal Water District · sale in April 2016 – Bond sale for ... • Manufacturing and delivery of pipes – Delivery of the pipes scheduled for last week of June

AlternativesOption 1 – Treatment at Main Stem PS (Join at Conveyance PS)

27

Costs:• MSPS Inlet Box Mods/ Low Lift Pumps ‐

$5,000,000• Chemical Treatment ‐ $9,600,000• MSPS Forebay Mods ‐ $5,000,000• 42 MG Storage at Conveyance PS ‐ $9,100,000• Other Construction ‐ $2,000,000• Contingencies (30%) ‐ $9,300,000• Design (15%) ‐ $6,000,000• Easements ‐ $900,000• Total: $46.9M

Notes: 1. Wetland or Chemical/Wetland Treatment 

would cost more.2. Chemical treatment will have substantial 

O&M costs (sludge and chemicals).

Page 28: North Texas Municipal Water District · sale in April 2016 – Bond sale for ... • Manufacturing and delivery of pipes – Delivery of the pipes scheduled for last week of June

AlternativesOption 2 – Deliver to East Fork Upstream from Wetlands

28

Costs:• Additional Pipeline ‐ $2,425,000• Discharge Structure ‐ $500,000• Bank Armoring ‐ $750,000• Other Construction ‐ $325,000• Contingencies (30%) ‐ $1,200,000• Design (15%) ‐ $800,000• Easements ‐ $460,000• Total: $6.46M

Page 29: North Texas Municipal Water District · sale in April 2016 – Bond sale for ... • Manufacturing and delivery of pipes – Delivery of the pipes scheduled for last week of June

AlternativesOption 3 – Deliver to Treatment Plant Along Conveyance PL (North of Seagoville Ranch)

29

Costs:• Chemical Treatment ‐ $10,900,000• 114 mgd booster PS ‐ $38,900,000• 28.5 MG Storage at PS ‐ $6,800,000• Other Construction ‐ $3,300,000• Contingencies (30%) ‐ $18,000,000• Design (15%) ‐ $11,700,000• Easements/Property ‐ $300,000• Total: $89.9M

Notes: 1. Wetland or Chemical/Wetland Treatment 

would cost more.2. Chemical treatment will have substantial 

O&M costs (sludge and chemicals).

Page 30: North Texas Municipal Water District · sale in April 2016 – Bond sale for ... • Manufacturing and delivery of pipes – Delivery of the pipes scheduled for last week of June

AlternativesOption 4 – Treat after Water from Wetlands Joins Water from Main Stem

30

Costs:• Low head pumps for Conveyance PS – $5,000,000• Chemical Treatment (150 mgd) ‐ $15,200,000• 150 mgd booster PS ‐ $43,600,000• 37.5 MG Storage at PS ‐ $8,300,000• Other Construction ‐ $4,400,000• Contingencies (30%) ‐ $23,000,000• Design (15%) ‐ $15,000,000• Easements/Property ‐ $300,000• Total: $114.8M

Notes: 1. Wetland or Chemical/Wetland Treatment would 

cost more.2. Chemical treatment will have substantial O&M 

costs (sludge and chemicals).

Page 31: North Texas Municipal Water District · sale in April 2016 – Bond sale for ... • Manufacturing and delivery of pipes – Delivery of the pipes scheduled for last week of June

III. DISCUSSION ITEMS

D. Update on Accessing Lake Fork Water Rights and Potential Options

Agenda

Page 32: North Texas Municipal Water District · sale in April 2016 – Bond sale for ... • Manufacturing and delivery of pipes – Delivery of the pipes scheduled for last week of June

• Temporary DWU Lake Fork Contract Expired May 2016– Staff Started Discussions with DWU in Fall 2015– Received a Draft Transport Contract in February 2016

• Water Rights are Adequate for 2016• Agreement is Currently on Hold• Pursuing:

– Additional Discussions with DWU– Reaching out to Sabine River Authority– Water Right Amendments

Accessing Lake Fork Water Rights

Page 33: North Texas Municipal Water District · sale in April 2016 – Bond sale for ... • Manufacturing and delivery of pipes – Delivery of the pipes scheduled for last week of June

III. DISCUSSION ITEMS

E. Update on Lower Bois d’Arc Creek Permitting and HGM Model

Agenda

Page 34: North Texas Municipal Water District · sale in April 2016 – Bond sale for ... • Manufacturing and delivery of pipes – Delivery of the pipes scheduled for last week of June

• HGM Workshop Held May 4th & 5th• Preliminary Findings Rolled Out at that Time• Results & Project Impacts Should be Ready in June 2016• Design Team is Moving Out to Minimize Delays

LBCR Update

Page 35: North Texas Municipal Water District · sale in April 2016 – Bond sale for ... • Manufacturing and delivery of pipes – Delivery of the pipes scheduled for last week of June

III. DISCUSSION ITEMS

F. Update on Wylie Water Treatment Plan Regulatory Matters

Agenda

Page 36: North Texas Municipal Water District · sale in April 2016 – Bond sale for ... • Manufacturing and delivery of pipes – Delivery of the pipes scheduled for last week of June

• Findings of Mandatory Comprehensive Performance Evaluation Pending

• May 10th, 11th & 16th: TCEQ Performed 3‐Year Routine Inspection of Wylie WTP

• Reported WTP III Chlorine Gas Release on April 28th• Release of Chloraminated Water in St. Paul on May 10th Due 

to Non‐NTMWD Contractor Boring Through Line– 328 Fish Killed– Est. 6.6 MG of Water Released– 24 hr. TCEQ Reporting Deadline Missed.  Reported One Week Later.

Regulatory Update

Page 37: North Texas Municipal Water District · sale in April 2016 – Bond sale for ... • Manufacturing and delivery of pipes – Delivery of the pipes scheduled for last week of June

III. DISCUSSION ITEMS

G. Opportunity for Committee Members to Request Potential Future Agenda Items(No substantive discussion of items will take place at this time)

Agenda

Page 38: North Texas Municipal Water District · sale in April 2016 – Bond sale for ... • Manufacturing and delivery of pipes – Delivery of the pipes scheduled for last week of June

IV. ADJOURNMENT

Agenda

Page 39: North Texas Municipal Water District · sale in April 2016 – Bond sale for ... • Manufacturing and delivery of pipes – Delivery of the pipes scheduled for last week of June

North Texas Municipal Water District“Regional Service Through Unity … 

Meeting our Region’s Needs Today and Tomorrow”

Water Committee MeetingMay 26, 2016