· non-operation and plcc mal- operation. the trippings due to gds, gis, auto-reclosure failure/...
TRANSCRIPT
Minutes of the 49th
PCSC Meeting held on 30-11-2015 Page 1
SOUTHERN REGIONAL POWER COMMITTEE BENGALURU
Minutes of the 49th Meeting of Protection Coordination Sub-Committee
(PCSC – 49) of SRPC held on 30.11.2015
1. Introduction The 49th meeting of Protection Coordination Sub-Committee (PCSC-49) was held on 30th November, 2015 in Mangalore, Karnataka. The list of participants is enclosed at Annexure-I.
Sh. R.C. Bhat, Station Head, UPCL extended warm welcome to Sh. S.R. Bhat, Member Secretary (MS), SRPC, Sh. P. Raghuram, Executive Director (ED), SRLDC, and other Officials from State & Private Power Utilities, SRLDC & SRPC. He thanked MS, SRPC for giving them the opportunity to host PCSC meeting, and added that ‘Team UPCL’ had put in all efforts to ensure a comfortable and enjoyable stay for all participating members. Then, a presentation was given by UPCL team highlighting the achievements and road-map of Adani Group with specific focus on Power Sector. Sh. S.R.Bhat, Member Secretary (MS), SRPC thanked Adani UPCL management for the excellent hospitality, and all the due care they have taken in making arrangements for the smooth conduct of the meeting. He then welcomed the Members and Participants to the meeting and briefed them on the following points:
Briefed the members on the proceedings of the third Grid Study Committee meeting held
on 18th November, 2015, wherein the Draft Report on Task-1 activities (Review of
implementation of Enquiry Committee recommendations given consequent to Grid
Disturbance in July, 2012) prepared by the Consultant (M/s Tractebel Engg.) was
discussed. As the performance of the Southern Region according to the report was not
very satisfactory, it was high-time Constituents make concerted efforts to resolve/
complete long-pending issues from their respective sides. The draft report was also
circulated all SR-Constituents for comments, however PGCIL (SR-II), KPTCL and KSEB only
responded.
Informed the members that the Task-2 data (relating to 15 Stations identified from SR for
audit-check by the Consultant) furnished by the respective Constituents had been
forwarded to the Consultant through NLDC for scrutiny and analysis, and the actual audit
of the Stations would commence shortly. In this regard, a meeting was also held (via VC)
with NLDC and the Consultant on 24th December, 2015 to discuss the modalities of
protection audit, wherein it was decided that the concerned Constituent-owner of the
Station would provide extracted relay settings (in pdf. format), if not already given to the
Consultant, and the Consultant would in turn provide their recommended relay settings
(based on the data already made available to them for each of the 15 stations) to the
concerned Constituent-owner of the Station well before the actual protection audit is
Minutes of the 49th
PCSC Meeting held on 30-11-2015 Page 2
undertaken for that particular Station. It was reasoned that by doing so, not only do the
concerned Constituent/ Station personnel get an opportunity to peruse the to-be-revised
settings, and prepare themselves for the protection audit, but it would also facilitate in
finalizing the settings during actual protection audit. To start with, NLC TPS-II of NLC
(Audit schedule: 4th , 5th & 7th December, 2015) and Alamathy S/S of TANTRANSCO (Audit
schedule: 9th , 10th & 11th December, 2015) would be audited in the first round and the
schedule for the other Stations would be intimated soon. He requested Constituents’
active cooperation in completing Task-2 activities to the satisfaction of all parties involved.
Informed the members that the issue of implementation of Power-Swing protection
philosophy as recommended by the Rama Krishna Committee would be discussed in the
forthcoming meeting of National Power Committee (NPC), and requested to present their
views when the issue is taken up for discussion later in the meeting.
Reminded members of nearing dead-lines of time-extensions given to SR-Constituents by
Hon’ble CERC for completion of their respective Protection Audit Remarks (PAR). KPCL,
KPTCL, TSTRANSCO were requested to approach CERC for extension of time-lines with
proper facts.
In this regard, KPTCL representative informed that their R&U proposal was approved
during Appraisal Committee meeting held on 17.11.2015 and sent to CERC for further
processing of the scheme as per PSDF disbursement procedure. Early sanctioning of PSDF
grants from Monitoring Committee was awaited and thereafter LOI would be issued to the
successful bidder M/s Alstom. The execution time finalized for completion of
works related to 93 substations is 15 months from the date of award, since sub stations
are scattered throughout the state and many works require planned outages. 26 numbers
of audited substations are planned to take up in the first phase.
However, as CERC, after hearing the petition filed by KSEB, TamilNadu in its Order dated
18.08.2015, has reiterated the deadline for completion of the R&U project by KPTCL
as 15.01.2016 which was requested by KPTCL in the affidavit filed during September 2014
and has also confirmed that no request for further extension of time would be considered,
a decision has been taken at KPTCL management level to file a petition before CERC with
all facts requesting for extension of time for execution of the project.
Brought to members’ attention the obligation of fulfilling their requirements under
Regulation 5.2 (r) of IEGC, as per which all Users, STU/ SLDC, and CTU are required to
furnish for analysis purpose the relevant information relating to tripping events in their
system along with Disturbance Recorder (DR) and Event Logger (EL) to SRLDC/ SRPC within
24-hrs of occurrence of the same. Though this issue was regularly brought to Constituents’
attention vide various SRLDC & SRPC (fort-nightly) letters, still data w.r.t. all events was
either not being furnished or being made available with unacceptable delay of few weeks.
Constituents were urged to strictly comply with Regulation 5.2 (r) of IEGC, and furnish the
data in time.
Minutes of the 49th
PCSC Meeting held on 30-11-2015 Page 3
Stressed upon the need to furnish remedial measures taken by the Constituents for the
forced outage of the transmission elements incident to their respective systems in time as
the same was also being monitored by the Office of Member (GO&D), CEA.
Finally requested members’ active participation in the ensuing discussions so as to raise
the quality standards to a new bar commensurate with the amazing ambience of
Mangalore city as orchestrated by Adani UPCL Team.
22. Confirmation of the Minutes of the 48th PCSC meeting held on 29.10.2015
SE (Protection), SRPC stated that the Minutes of the 48th meeting of the PCSC had been circulated vide SRPC letter No. SRPC/SE-III/ PCSC-48/ 2015/ 8412 - 44 dated 19.11.2015. As no comments had been received from any of the Constituents, the Minutes of the 48th meeting of PCSC were confirmed.
3. Details of Grid Disturbances (GD’s), Grid Incidents (GI’s), Line Trippings due to Auto-Reclose
non-operation and PLCC mal- operation. The trippings due to GD’s, GI’s, Auto-Reclosure failure/ non-operation, and PLCC mal-operation
that had occurred during the period October-November, 2015 were discussed in the Meeting. The deliberations and recommendations of the PCSC-forum are enclosed at Annexure–II. In the meeting ED,SRLDC informed that SRLDC would be approaching Hon’ble CERC for all the Grid Occurrences (GD’s and GI’s) which occurred due to abnormal delayed clearance.
4. Status of pending PCSC recommendations The status of implementation of pending PCSC recommendations was discussed in the meeting.
The Constituents had been requested to kindly submit the status of their compliance latest by 25-12-2015. The updated status of the same as on 14-12-2015 is enclosed at Annexure–III.
5. Remedial measures/ Action taken for the tripping incidents of the transmission elements
under forced outage The tripping incidents of the transmission elements under forced outage for which the remedial
measures/ actions taken still awaited were discussed in the meeting. The Constituents had regularly been kept apprised of the tripping events incident to their respective systems vide various SRPC mails. However, no replies have been received from APGENCO, TSTRANSCO during the period 29.10.2015 to 29.11.2015:
The Constituents have been requested to kindly furnish the remedial measures/ action taken in
time so as to forward the same to Central Electricity Authority. The updated list of the same as on 14.12.2015 is enclosed at Annexure-IV.
Minutes of the 49th
PCSC Meeting held on 30-11-2015 Page 4
6. Certificate for Healthiness of Batteries
As per the MoP/ CEA direction given in pursuant to recommendations of the Enquiry Committee (NEW grid disturbance on 30th & 31st July, 2012), RPC’s are required to obtain from their respective Constituents the monthly certificate for healthiness of batteries, installed at 220 KV and above voltage level Substations (for power supply to Relays, RTUs and PLCC equipment) and furnish the same to CEA/ MoP.
With reference to above, the Constituents have been requested to submit the certificate on healthiness of batteries on monthly basis (i.e. status for a month may be sent by the 7th day of the following month) to SRPC.
The sought status for the month of October, 2015 has not been received from the following SR-Constituents:
APTRANSCO, TSGENCO (Hydro), PED, MAPS, SEL, CEPL, TPCIL
7. NPCIL Agenda Items (i) Frequent tripping of 230 kV KKNPP-Tuticorin S/c line: 230 kV switchyard of KKNPP is connected to TN STU network through 2 circuits of 230 kV
(one S/C each to Tuticorin and Nagercoil). These circuits are meant to provide "Off Site Power" to KKNPP. It has been observed that 230 kV KKNPP-TTPS line has been tripping very frequently on Zone-2 protection. As frequent tripping of the line degrades the reliability of "Grid supply" and loss of the same at 230 kV may affect the stability of nuclear units, TANTRANSCO has been requested to present action taken to ensure requisite stability.
In this regard, Action Taken Report furnished by TANTRANSCO vide their letter dated
28.11.2015 (copy enclosed at Annexure-V) was discussed and noted that requisite action has been initiated/ taken by TANTRNSCO to address the concerns raised by KKNPP.
(ii) Outage of Units -1&2 at MAPS due to the loss of evacuation lines on 9th November, 2015 On 9-11-2015, MAPS Unit -1&2 were generating 215 MW and 172 MW respectively with
three 230 kV lines in service (D/C to SP Koil Station and S/C to Acharapakkam Station). 230 kV MAPS- Arni line had tripped on previous day at 18:35 hrs. On next day (09-11-2015) starting from 08:22 hrs to 09:33 hrs, the cascade tripping of these 3 lines resulted in the outage of both the units.
The issue was discussed in the meeting. The deliberations and recommendations of PCSC
forum are given at Grid Disturbance I.5 in Annexure-II.
8. Power Swing Protection Philosophy
The Power swing protection philosophy as recommended by the Ramakrishna Committee (Task Force on Power System Analysis under Contingencies) [copy given at Annexure-VI] was discussed in the meeting. It is observed that while PGCIL, NTPC, NPCIL, NLC, and State Utilities of Karnataka, Kerala are in line with Task force recommendations in so far as unblocking it Zone-1 and blocking it in other zones, the State Utilities of Andhra Pradesh (AP), Telangana (TS), and TamilNadu (TN) are found to be blocking it in all Zones.
Minutes of the 49th
PCSC Meeting held on 30-11-2015 Page 5
In this regard, it was agreed in the meeting that the matter would be favorably looked into by the above Constituents (of AP, TS & TN) and they would revert with their views after discussing with their respective managements.
9. Network configuration changes
As per the information furnished by SR-Constituents to the OCC forum in their 113th meeting
held on 06.11.2015 (Minutes circulated on 30.11.2015), the following network configuration changes (additions/ deletions/ modifications of transmission elements) took place in the southern grid during the month of October, 2015.
COD 220 kV Appayyadorapalem (ADR Palem) in Vizianagaram district was commissioned
on 15.10.2015 by APTRANSCO 220/132 kV Miyapur S/s of 1x160 MVA Transformer Capacity was augmented to 2x160
MVA Transformer Capacity on 07.09.2015 by TSTRANSCO. 220 KV D/C XLPE UG Cable from 220 kV Moulali SS to 220 KV GIS at Osmania University in
Hyderabad of ckm 17.926 was commissioned on 14.10.2015 by TSTRANSCO. 220 KV line on Narrow Based Multi Circuit Towers with 4 Circuits for LILO of both Circuits
of Dindi - Chandrayangutta 220 KV D/C Line to the proposed 220 kV SS, Bonguloor of ckm 2 was Commissioned on 31.10.2015 by TSTRANSCO.
LILO of 220kV Ramagundam- Mandamarry circuit-I to 220/6.6kV LI SS Murmur in Karimnagar district of 3.9 ckm was commissioned on 21.10.2015 by TSTRANSCO.
220 KV 2nd ckt stringing from 220 KV RSS 220 KV Mandamarry (34 KM) in Karimnagar of 34 ckm was commissioned by 20.10.2015 by TSTRANSCO.
LILO of 220kV Ogulapur- Durshed to 220/6.6kV LI SS Bommakal in Karimnagar district of 0.108 ckm was commissioned on 27.10.2015 by TSTRANSCO.
220/132 KV GIS Osmania University in Chilakalaguda, Hyderabad was commissioned on 14.10.2015 by TSTRANSCO.
220/6.6KV Murmur LI substation in Karimnagar district was commissioned on 21.10.2015 by TSTRANSCO.
220/6.6KV Bommakal LI substation in Karimnagar district was commissioned on 27.10.2015 by TSTRANSCO.
220/6.6KV Mallaram LI substation in Medak district was commissioned on 31.10.2015 by TSTRANSCO.
220/132 KVSS Bonguluru in Ranga Reddy Dist. (originally charged with 1x100MVA) was commissioned on 31.10.2015 by TSTRANSCO.
PGCIL vide their letter dated 16.10.2015 informed that consequent to the successful completion of Trial Operation, Transmission system associated with Kaiga 3 & 4 (2x235 MW) Project (Mysore-Kozhikode 400 D/C line along with new 400/220 kV S/S with 2x315 MVA ICTs and 2x50 MVAR switchable line reactors at Kozhikode and associated bay equipment at Mysore Substation) had been put under COD w.e.f 00:00 hours of 16th October 2015 in terms of Clause 4 of CERC(Terms and Conditions of Tariff) Regulations 2014.
Minutes of the 49th
PCSC Meeting held on 30-11-2015 Page 6
10. Instances of SPS Operations Based on the information furnished by SRLDC, it is informed that there were no instances of SPS operations in SR during the period 29.10.2015 - 29.11.2015.
11. Compliance of Hon’ble CERC Orders 11.1 Petition No. 146/MP/2013 with I.A. 36/2013: Order dated 20.02.2014
Compliance of Regulations 5.2 (r) of the Grid Code: Issue regarding non-furnishing of FIR / Trip Analysis Report, EL, DR, etc. was also highlighted. It is pointed out that the above reports are to be submitted / uploaded on SRLDC web application within 24 hours as mandated under IEGC / CEA Regulations.
Implementation of Phase-I and Phase-II of Protection Audit Recommendations: All the constituents are requested to submit the updated status of the compliance (those who have not completed recommendations mentioned in the Phase I and Phase II) to SRPC Secretariat at the earliest.
Compliance of Regulations 5.2 (e) & 5.2 (l) of the Grid Code and Regulation 3(1)(e) of CEA Grid Standards: The constituents are requested to strictly comply with these provisions by ensuring standard protections systems having the reliability, selectivity, speed and sensitivity to isolate the faulty equipment and protect all components from any type of faults, within the specified fault clearance time and providing protection coordination
Ensuring proper maintenance of transmission lines and adopting best O&M practices: The constituents are requested to conduct line patrolling regularly as per the SRPC transmission line patrolling guidelines (available under the menu item "All Uploads Operation Miscellaneous Transmission Line Patrolling Protocol / Guidelines for Southern Region" on SRPC website). (http://www.srpc.kar.nic.in/website/2014/operation/patrolling.pdf).
11.2 Petition No. 167/Suo- Motu/2012: Order dated 22.02.2014
The Constituents are requested to follow approved protection philosophy ISTS licensees are requested to submit details of updated distance protection relay
setting of all inter-regional lines to POSOCO & RPCs.
All SLDCs are requested to install/activate sound recording system in their control rooms within three months from the date of issue of this order.
The Constituents are requested to submit the progress of implementation to SRPC and SRLDC as specified in the Hon'ble CERC Order.
11.3 Petition No. 263/MP/2012: Order dated 19.12.2013
Constituents are requested to implement the quantum of relief by AUFR and df/dt relays by identifying additional feeders and keep them functional within one month of issuing this order.
SLDCs are also requested to map these relays on their respective SCADA system within three months of issuance of this order.
The Constituents are requested to submit the progress of implementation to SRPC and SRLDC as specified in the Hon'ble CERC Order.
11.4 APTRANSCO’s Petition No.95/MP/2015: Date of hearing 09-04-2015
Minutes of the 49th
PCSC Meeting held on 30-11-2015 Page 7
It was noted in the Analysis and Decision part of the Order that:
“8. Noting the submissions of the petitioner, SRPC and SRLDC and activities initiated by the petitioner for procurement of materials required for implementation of the remarks of protecting audit, we allow time to the petitioner till 31.12.2015 for completion of our directions in Order dated 19.12.2013 in Petition No. 146/MP/2013.”
“9. SRPC is directed to monitor the status of completion of works relating to protection audit remarks in respect of 7 nos 400 kV sub-stations and 11 nos 220 kV sub-stations of APTRANSCO, protection audit remarks in Protection Coordination Sub-Committee (PCSC) meetings and coordinate the periodic protection audit to be carried out in Southern Region after deliberation in SRPC and submit bi-monthly report to the Commission.”
11.5 TSTRANSCO’s Petition No.83/MP/2015: Order dated 14-05-2015
It was noted in the Order that:
“12. Noting the submission of the petitioner, SRLDC and SRPC and considering the actions already initiated by the petitioner for implementation of works relating to protection audit, we allow time till 31.10.2015 and 31.8.2016 for implementation of Phase-I and Phase -II works respectively. The petitioner is directed to submit affidavit confirming the completion of Phase I of protection audit remarks by 31.10.2015 and Phase-II of protection audit remarks by 31.8.2016.
13. SRPC is directed to monitor the status of completion of remarks in these substations vis-à-vis protection audit remarks in Protection Coordination Sub Committee (PCSC) meetings. SRPC is further directed to coordinate the periodic protection audit to be carried out in Southern Region after deliberation in SRPC.”
11.6 Order in Petition No. 86/MP/2014 and 374/MP/2014: Order dated 18-08-2015
The time-lines given to the various SR-Constituents for completion of Phase-I and Phase-II activities of Protection Audit Recommendations vide above Order are given below: (A) KSEBL: 18. Noting the submission of KSEBL, SRLDC and SRPC and considering the actions already initiated by KSEBL for implementation of remarks of protection audit, we allow time till 31.12.2015 and 31.3.2016 for implementation of Phase-II works and R&M works at Idduki HEP respectively. (B) TANTRANSCO: 21. After considering the submissions of TANTRANSCO, SRLDC and SRPC, it is noted that
TANTRANSCO`s request for time till 31.5.2015 for implementation of Phase–I activities of providing numerical relays for feeder protection and Auto transformer protection is already over. We allow time till 30.6.2016 for other Phase-I activities such as provision of line VT, 5 core CT, Time synchronizing with GPS, Disturbance recorder & event logger and Phase-II activities. According to SRLDC, total implementation period is 15 to 16 months for items which involve major procurement, design changes with major site modification/civil activities. Accordingly, we allow 16 months time i.e up to 30.11.2016,
Minutes of the 49th
PCSC Meeting held on 30-11-2015 Page 8
for Renovation and Modernization of Singarpet, Singaperumalkoil, Salem and Tondiarpet 230 kV sub-stations from the issue of the order.
(C) NLC: 22. NLC has sought time upto 31.12.2014 and 31.3.2015 for completion of Phase-I work of
Numerical Relay Retrofitting and for Phase-II works of providing second battery bank of PLCC respectively. It is noted that the completion dates for Phase-I and Phase-II of protection audit remarks as requested by NLC are already over. Therefore, no direction is required in this regard. However, we direct NLC to file a confirmation report regarding completion of protection audit works for Phase-I and Phase-II.
(D) KPTCL: 23. … … Considering the submission of KPTCL and SRLDC, we allow time to KPTCL time till
15.01.2016 for completion of Phase-I and Phase-II of protection audit remarks. No further extension shall be granted in this regard.
(E) KPCL: 24. … … Considering the submission of KPCL and SRLDC, we allow time to KPCL till 31.10.2015
and 31.12.2015 for completion of Phase-I for Phase-II of protection audit remarks respectively. No further extension shall be granted in this regard.
26. We direct SRPC to (a) submit status of protection audit remarks in respect of
APGENCO, NTPC (SR), Talcher, Puducherry, PGCIL (SRTS I & II), MAPS and TANGEDCO, (b) monitor the status of completion of remarks of protection audit in respect of all constituents of Southern Region in Protection Coordination Sub-Committee (PCSC) meetings, and (c) to coordinate periodic protection audit to be carried out in Southern Region after deliberation in SRPC. All the constituents of Southern Region are directed to file their status with SRPC on regular basis to facilitate proper monitoring in PCSC meetings. SRPC is directed to submit bi-annually status report to the Commission confirming the completion of Phase-I, Phase-II and R&M works of protection audit remarks of the constituents of Southern Region.
12. Nomenclature for naming various files uploaded in Web based Tripping Monitoring System of
SRLDC Portal
The nomenclature to be followed by the Constituents in naming various files (FIR, DR, EL, TR) corresponding to a tripping incident was brought out in the SRPC letter No. SRPC/ SE-III/ PCSC-45/ 4609 – 649 dated 26.06.2015 and in the minutes of PCSC-45 issued vide SRPC letter No. SRPC/SE-III/ PCSC-45/ 2015/ 5422-455 dated 21.07.2015. As illustrated therein, the format to be followed for the user entered part-name is given below:
Transmission Element File name to be given by the user
Transmission line SSN_DSN_line#_FT
Minutes of the 49th
PCSC Meeting held on 30-11-2015 Page 9
Inter-connecting Transformer SSN_ICT#_FT
Generating Transformer SSN_GT#_FT
Generating Unit SSN_Unit#_FT
Where, SSN = Source Station Name/ From end Station Name/ Sending end Station Name
DSN = Destination Station Name/ To end Station Name/ Receiving end Station Name
FT = File Type (FIR/ DR/ EL/ TR)
All SR-Constituents are requested to kindly intimate the above file naming nomenclature to all the concerned and ensure that it is followed at all stations in their control area so that tripping analysis can be done systematically.
13. Date & Venue of the next Meeting
It is informed that the 50th PCSC meeting will be held on 29.12.2015 (Tuesday) at 10:30 hrs in the Conference Hall of SRPC, Bengaluru.
14. Vote of Thanks
Member Secretary, SRPC thanked the members and other participants for their active contribution in the deliberations.
Sh. Uday Trivedi, AVP, UPCL thanked all the Members for their cooperation.
*****
Annexure-I
Annexure-I
Annexure-I
Annexure-I
Grid Occurrences discussed during 49th
PCSC Meeting on 30-11-2015 1/29
Grid Occurrences 1. Details of Grid Disturbances (GD’s):
1 Complete outage of 220kV Chikodi substation of KPTCL (GD-1)
(i) Date and Time of Event 13.10.2015 at 00:30 hrs
(ii) Location 230kV Chikkodi Substation
(iii) Reported Disturbance /
Fault
Tripped due of failure of 220kV Bus-2 PT at Chikkodi substation.
Lines tripped on zone-2 from Talandage and Mudshingi on
operation of Zone-2 protection. Bus bar protection is not
available at 220kV Chikodi substation
(iv) Load Loss
(v) Category GD-1
SLD:
As per FIR of KPTCL:
Annexure-II
Grid Occurrences discussed during 49th
PCSC Meeting on 30-11-2015 2/29
KPTCL:
Pre fault: Entire Chikkodi and Belgaum sub station loads were fed from Maharashtra system. At Chikkodi, both the buses were tied through bus coupler.220kV Gataprabha 1 &2 lines were kept open at Chikkodi as Gataprabha SS was on Karnataka system.
At Chikkodi, normally Talandage and Mudshingi lines are generally kept on different buses, however due to some metering arrangement constraint (PT input) both lines were brought on to same bus, viz., Bus-B.
At 00:30hrs, R phase PT of 220kV Bus A failed and the incoming lines tripped at Talandage and Mudashinge Zone-2. This resulted in bus shut down at Chikkodi.
At Chikkodi, there was no bus-bar protection. Further as Bus Coupler’s O/C operating time is more than that of Zone-2, the lines got opened from remote ends in Zone-2.
During the incident, Load Loss: 143 MW for about 1 Hr 15 minutes. Energy unserved is 0.179 MU
Remedial Action: When enquired about provision of A/R on these inter-state lines, KPTCL representative informed that
control panels had already been replaced, but due to problem with output cards of REL-511, the matter was taken up with M/s ABB (OEM), and the relays would be soon replaced by REL-760, and the work is likely to be completed by December, 2015.
Regarding provision of bus-bar protection, it was informed that the same would be provided as part of their R& U proposal covering 96 SS in Karnataka, for which funding was sought from PSDF. It was also informed their proposal was approved during Appraisal Committee meeting held on 17.11.2015 and sent to CERC for further processing of the scheme as per PSDF disbursement procedure. Early sanctioning of PSDF grants from Monitoring Committee was awaited and thereafter LOA would be issued to the successful bidder M/s Alstom.
SRLDC/SRPC:
PMU plot shows the occurrence of two successive faults; while the first fault got cleared within 320ms, the second fault got cleared in 360ms.
After the breaker got opened upon first fault, reasons for the second fault need to be investigated. Whether this could be correlated with the burning of R-ph Wave-Trap at Talandage end on 220 kV Chikkodi – Talandage line as mentioned in the FIR may be seen by KPTCL.
2 Complete outage of IL&FS power station (GD-1)
(i) Date and Time of Event 27.10.2015 at 19:43 hrs
(ii) Location 400kV IL&FS Station
(iii) Reported Disturbance /
Fault
Complete outage occurred at IL&FS due to tripping of evacuating
lines i.e. 400kV IL&FS-Nagapatinam line-1&2. Both lines tripped
due to mal-operation of Bus-1 and Bus-2 bus bar protection
(iv) Generation Loss 400 MW
(v) Category GD-1
SLD: 404, 405, 406 are in one dia with ILFS-1 line connected between 405 & 406;
407, 408, 409 are in one dia with ILFS-2 line connected between 408 & 409;
Annexure-II
Grid Occurrences discussed during 49th
PCSC Meeting on 30-11-2015 3/29
Pre-Fault:
Post-Fault:
400 kV Nagapattinam – ILFS line-1: Nagapattinam (PGCIL-SR2) end:
As per FIR/ TR, line tripped at 19:44 hrs due to BBP operation caused due to mal-operation of CB-406 & CB-407’s Gas Density Monitor on 3rd Stage. (But from DR, only CB-406 got opened. Tie-CB 405 observed to be in OPEN condition prior to occurrence of this fault).
As per DR/ EL, the lines tripped at 19:44:46.362 hrs due to BBP (96A) operation. IL&FS end:
As per FIR/DR/EL/TR, the line tripped at 19:35:02.383 hrs due to DT receipt from Nagapattinam PS. From EL, it is observed that DT has been received several times starting from 19:35:02 hrs. to 19:44:46 hrs. The resolution in EL was limited to seconds only. 400 kV Nagapattinam – ILFS line-2: Nagapattinam (PGCIL-SR2) end:
As per FIR/ TR line tripped at 19:44 hrs due to BBP operation caused by mal-operation of CB-406 & CB-407’s Gas Density Monitor on 3rd Stage.(But from DR, only CB-409 got opened. Tie-CB 408 observed to be in OPEN condition prior to occurrence of this fault)
As per DR/ EL, the lines tripped at 19:44:46.362 hrs due to BBP (96A) operation. IL&FS end:
As per FIR/DR/EL/TR, the line tripped at 19:44:46.405 hrs due to DT receipt from Nagapattinam PS. The resolution in EL was limited to seconds only.
Annexure-II
Grid Occurrences discussed during 49th
PCSC Meeting on 30-11-2015 4/29
PGCIL-SR2:
Gas Density Monitor (GDM) operation consist of three stages as given below: Normal stage SF6 Pressure:0.67Mpa
Stage1: <=0.64Mpa, Stage2:<=0.62Mpa , Stage3:<=0.60Mpa. It’s third stage operation causes BBP operation of the bus to which the concerned CB is connected.
In the instant case, first CB-407’s GDM operation in third stage caused BBP operation for Bus Bar -1 (top bus in the diagram). Then after 9 sec, CB-406’s GDM operation in third stage also caused BBP operation for Bus Bar – 2 (Bottom bus in the diagram). However as all Tie-CBs remained in service, the lines NLCTPS-Exp1 & NLC TPS 2 and , Trichy-1 & Trichy-2 got connected through Tie-CB 411 and Tie-CB 414 respectively.
On Examination at site, the pressure in 406-CB and 407-CB is found normal and tripping occurred due to mal-operation of gas density monitoring associated circuit.
The moisture entry in the associated circuit of gas density 3rd stage, caused mal-operation due to some contact problem with the miniature relays, and resulted in bus bar protection operation.
It was also found that the space heaters which keep LCC panels dry got accidentally got switched off
On this point, KKNPP representative informed that in their GIS, space heaters associated with GDM were not provided separately, but came as a built-in feature of GDM. Then, it was opined that could be due to design difference as PGCIL’s GDM is of China-make, and that of KKNPP is of Russian-make.
Remedial action: The Gas leakage detector healthiness checked. Precautions to avoid moisture entry in the panels have been taken to ensure no repetition of such
occurrences takes place. SRLDC/SRPC: As the Tie-CB’s 405 and 408 were found to be OPEN condition prior to occurrence of BBP operation from the
DR’s furnished, PGCIL (SR-II) needs to substantiate their statement by providing all the relevant EL’s.
At IL&FS end, the time-scale resolution in EL’s should be configured for msec. Time-sync for DR and EL needs to be ensured at IL&FS.
3 Complete outage of 220kV Ambewadi Substation of KPTCL (GD-1)
(i) Date and Time of Event 29.10.2015 at 14:34 hrs
(ii) Location 220 kV Ambewadi Substation
(iii) Reported Disturbance /
Fault
220kV Nagjheri-Ambewadi line-1 tripped at 13:33 hrs due to B
phase to earth fault. Ambewadi was radially fed from Nagjheri
power station through 220kV Nagjheri-Ambewadi line-2. Tripping
of this line caused 220kV Bus shut down at Ambewadi and
remaining lines and transformers were hand tripped
(iv) Load Loss Karnataka: 14 MW and Goa: 97 MW
(v) Category GD-1
Annexure-II
Grid Occurrences discussed during 49th
PCSC Meeting on 30-11-2015 5/29
SLD:
As per TR of KPTCL:
Ambewadi (KPTCL) end:
Prefault conditions: 220kV Ambewadi-Narendra 1 & 2 lines are under LC due to failure of insulator strings. Supa generation - Nil; Goa load on Ambewadi @ 14.00Hrs- 97MW; Karnataka load (11kV load of Ambewadi & 110kV loads) - 14MW
At 13:33hrs, Ambewadi-Nagjheri line-1 tripped on distance protection due to line fault and declared faulty. Line Clear was availed by TLI staff.
At 14:36 hrs, 220kV Ambewadi-Nagjheri line-2 tripped at Nagzari end on DPR in Zone-2(BN, 25km). This resulted in loss of supply to Ambewadi station as only source to Ambewadi was 220kV Nagjheri line-2.
220kV Ambewadi-Ponda line-1& 2 were hand tripped.
Load loss - Karnataka load : 14MW; Goa load:97MW and energy unserved was 0.0685 MU Restoration: 220kV Bus was restored by charging 220kV Nagjheri Ambewadi line- 2 at 14:50 hrs and 220kV
Ambewadi-Ponda line-1 was charged at 15:13hrs.
Line-1
Line-2
Line-1
Z2
NK
20 MVA
No Generation
XELDOM
55 MVA 100 MVA
Out of service
(Maintenance)
Hand trip
Z1 Z2
Line-2
AMBEWADI-
220kVAMBEWADI- 220kV
Annexure-II
Grid Occurrences discussed during 49th
PCSC Meeting on 30-11-2015 6/29
KPTCL also informed that Ambewadi – Narendra D/C line which were taken on outage replace insulator strings would be put into service by mid-December, 2015.
KPCL
Presently A/R & Carrier protection is not present on Nagjheri – Ambewadi lines due to absence of CVT’s at Nagjheri. However, as the material was already received (in third week of November, 2015), carrier protection and A/R will be provided in 3-month period.
To this, SRLDC insisted KPCL for providing the same in one month time, to which KPTCL also conveyed their preparedness.
Recommendations:
KPCL to provide A/R on all 220 kV lines emanating from Nagjheri PH. KPTCL to provide A/R on all 220 kV lines emanating from Ambewadi SS.
4 Complete outage of 220kV Ambewadi Substation of KPTCL (GD-1)
(i) Date and Time of Event 31.10.2015 at 16:54 hrs
(ii) Location 220 kV Ambewadi Substation
(iii) Reported Disturbance /
Fault
220kV Nagjheri-Ambewadi line-1 & 2 tripped at ambewadi end
only on operation of DEFR. This resulted in loss of supply to
Ambewadi station. Fault had occurred in 220kV Nagjheri-Hubli
line-2
(iv) Load Loss 4 MW
(v) Category GD-1
SLD:
220kV Ambewadi SS end: Prefault Conditions: 220kV Ambewadi-Narendra 1 & 2 lines were under LC due to failure of insulator strings. Supa generation : Nil Goa load on Ambewadi @ 16.00Hrs- 103MW Karnataka load (11kV load of Ambewadi & 110kV loads) - 12MW
Line-2
Line-1
Line-2
Line-1
PONDAP
ONDA
NARENDRA
SUPA HPS
(2X50 MW)
SUPA HPS
(2X50 MW)
NAGJHERI
NAGJHERI
AMBEWADI-
220kVAMBEWADI- 220kV
NK
20 MVA
110 kV
No Generation
XELDOM
55 MVA 100 MVA
Out of service
(Maintenance)
Hand trip
F (B-N)
DEFR
HUBLI
DEFR
DEFR Z2
Annexure-II
Grid Occurrences discussed during 49th
PCSC Meeting on 30-11-2015 7/29
As per TR of KPTCL:
At 16.54 hrs, 220kV Ambwadi – Nagheri lines - 1 &2 tripped at Ambewadi end on DEFR. Due to this 220kV Bus got de-energized and the remaining lines and transformers were hand tripped.
Restoration: 110kV bus restored at 17.17 hrs by charging 110kV NK-2 line (220kV Sirsi source). 11kV Load of Ambewadi for about 4 MW was restored immediately. 220kV bus restored at 17.45 Hrs and 220kV Ponda -1 line restored at 17.50 Hrs.
Load loss : 11kv load of 4 MW for 20 minutes ( Karnataka) Goa load of 103MW for 53 minutes.
Energy Unserved in MU: 0.0923 MU. KPTCL:
Details of trippings occurred at Nagjheri were collected and it was observed that 220kV Ambewadi- 1 & 2 lines were not tripped at Nagzari end during the instance. However 220kV NPH-Hubli-2 line was tripped during the instance with following relay indications: At Nagjheri : 220kV Hubli-2 line tripped on DPR, Zone-2,CN, 88.5km, 3.1kA; At Hubli: NPH-2 tripped on DEFR. Suspected transient fault in the line. This line was restored at 18.24Hrs on
31.10.2015.
During this time, there was reversal of power flow on the Nagjheri - Ambewadi lines 1 & 2, i.e. from Ambewadi to Nagjheri on account of acting of tertiary winding of the transformers at Ambewadi in shunt to the fault (thus contributing to the fault point) even though there was no source at Ambewadi.
Remedial Action: As NPH- Hubli, NPH-Ambewadi lines are passing through dense forest, these lines are prone to high
resistance faults. Hence resistive reaches of distance relays of NPH connected lines at remote end sub stations i. e. at Hubli, Bidnal and Ambewadi have been revised to 75 ohms (primary).
DEFR time-lever has also been increased to 0.225.
Upon enquiry by SRLDC regarding non-furnishing of DR for the tripping event, KPTCL informed that presently DEFR operation was not configured for triggering DR. So it was recommended that KPTCL configure DEFR output also for triggering DR at Ambewadi SS.
5 Complete outage of S.P.Koil station of TANTRANSCO and generation loss at Madras Atomic Power station(MAPS) (GD-1)
(i) Date and Time of Event 09-11-2015at 9:33hrs
(ii) Location 230 kV MAPS Station and 230kV S.P.Koil Substation
(iii) Reported Disturbance /
Fault
Fault had occurred in 230kV MAPS-S.P.Koil feeder-1. LBB
protection got operated as breaker of this feeder was under
lockout and resulted in tripping of 230kV bus at S.P.Koil. Unit-
1&2 at MAPS due to loss of evacuating feeders i.e. 230kV MAPS-
S.P.Koil feeder-1&2
(iv) Generation Loss 250 MW
(v) Load Loss 150 MW
(vi) Category GD-1
Annexure-II
Grid Occurrences discussed during 49th
PCSC Meeting on 30-11-2015 8/29
SLD:
Annexure-II
Grid Occurrences discussed during 49th
PCSC Meeting on 30-11-2015 9/29
Annexure-II
Grid Occurrences discussed during 49th
PCSC Meeting on 30-11-2015 10/29
MAPS is connected to four 230 kV lines, viz., SPKoil lines – 1 & 2 (L1 & L2); Acharapakkam line (L4); and Arni line (L3).
As per the Report dated 11.11.2015 furnished by MAPS:
230 kV Kalapakkam – Arani line (L3) was tripped on 08.11.15 first at 18:35 hrs, and then again at 19:06 hrs due to snapping of conductor between B-ph Wall Bushing & First Tower from MAPS. Strain insulator in the B-ph of first tower (towards switchyard) was also observed to have been damaged.
230 kV Kalapakkam – Acharapakkam line (L-4) was tripped on 09.11.2015 at 08:21 hrs due to snapping of Y-ph & B-ph conductors from First Tower to Second Tower from MAPS.
230 kV Kalapakkam – SP Koil line-2 (L-2) tripped on 09.11.15 at 09:02 hrs due to B-ph fault; and the line could not be normalised due to breaker problem at SP Koil end.
230 kV Kalapakkam – SP Koil line-1 (L-1) tripped on 09.11.15 at 09:33 hrs due to line fault.
As a result of losing of all four evacuating lines, both Units of MAPS tripped on Turbine Over Frequency protection.
No FIR/ DR/ EL furnished relating to tripping of Kalpakkam – SP Koil D/C lines and both Units of MAPS by NPCIL (MAPS).
As per the Report dated 27.11.2015 furnished by TANTRANSCO:
Annexure-II
Grid Occurrences discussed during 49th
PCSC Meeting on 30-11-2015 11/29
230 kV Kalapakkam – SP Koil line-2 (L-2): SP Koil (TANTRANSCO) end:
As per FIR/ TR, the line tripped at 9:06 hrs on B-E fault due to DPR, Z2 operation. It was stated that A/R was in locked-out condition.
From DR, the line got tripped on B-E fault at 08:39:30.102 hrs. (Digital inputs were not shown) EL furnished was not proper (It does not show SOE). Time sync of DR & EL needs to be checked. From synchro-phasor data, the fault seemed to have got cleared in 160 msec. This means that the fault got
cleared due to DPR, Z1 operation from MAPS end. 230 kV Kalapakkam – SP Koil line-1 (L-1): SP Koil (TANTRANSCO) end:
As per FIR/ TR, On 09.11.2015 at 06:00 hrs., the CB at SP Koil end on SP Koil – MAPS line-1 was under lock-out due to Compressor’s low SF6 pressure.
Subsequently at 09:32hrs., line fault occurred in the above feeder, but due to lockout condition the breaker had not tripped; as a result, LBB relay acted and tripped all the 230kV feeders & all the 4 Auto transformers.
EL furnished does not show events after time 9:03:36:416 hrs. (After this, only following two events were shown:
Monday 09 November 2015 09:24:03.677 : Any Pole Dead OFF Monday 09 November 2015 09:24:03.672 : All Pole Dead OFF)
From DR, the line trip happened at 08:32:55.174 hrs on Y-E fault due to DPR, Z1 operation. But due to A/R’s lock-out condition, 3-ph trip was given. However, only R-ph and B-ph currents only became zero. It is observed that Y-ph current became zero only after 560 msec. (It was also observed that similar operation, viz., R-ph and B-ph currents becoming zero, and the y-ph current becoming zero only after 560 msec. was also observed in the DR furnished for SP Koil end on SP Koil – Kalavindapattuu 230 kV S/C line). Hence, whether this happened because of sluggish operation of LBB relay or PD relay needs to be found out).
From Synchrophasor data, fault clearing time was observed to be 560ms. Hence, the operation of LBB protection needs to be validated.
Time sync of DR & EL also needs to be checked. TANTRANSCO:
On the tripping day, there was heavy rain and thunderstorms around SP Koil area due to which operators could not attend to the low air pressure of compressor in time which resulted in locked-out condition of A/R relay. This resulted in tripping of the SP Koil – MAPS lines on line faults subsequently.
MAPS:
MAPS being a Nuclear Power Station, the evacuating lines from MAPS need proper line maintenance by TANTRANSCO. Further, when it was already known that MAPS was operating under depleted network conditions due to tripping of MAPS – Arani line the previous day, more vigilance should have been exercised by SLDC so that MAPS remained in grid mode of operation.
As such incidents happened in the past also, SRPC is requested to form a sub-committee to look into all protection & operational issues concerning MAPS, and suggest suitable corrective measures.
SRLDC:
The breaker of 230kV SP.Koil-MAPS feeder-1 was under lockout due to SF6 gas pressure low from 6:00 AM of 09-11-2015 and no actions were taken by TANTRANSCO to rectify the same till teh occurrence of the fault at 9:33 AM.
Apart from the line maintenance related issues, the proposed sub-Committee may look into the following issues concerning MAPS: Connectivity of MAPS from Bhavini for increasing the reliability of secure grid-operation of MAPS. Carrier –Communication & PLCC related issues; Modalities to bring down generation at MAPS in case of tripping of few evacuating lines from MAPS may
also deliberated by the proposed sub-Committee.
Annexure-II
Grid Occurrences discussed during 49th
PCSC Meeting on 30-11-2015 12/29
SRPC:
A sub-Committee consisting of Officals from SRPC, SRLDC, PGCIL (SR-II), TANTRANSCO & MAPS would conduct a Protection System Analysis Group (PSAG-14) meeting at MAPS, Kalapakkam and deliberate on all protection & operational issues concerning MAPS.
Recommendations: TANTRANSCO to ensure correctness of operation of LBB relays at SP Koil. TANTRANSCO & MAPS to furnish their respective compliance report of the recommendations of to-be-
conducted PSAG-14 meeting at MAPS, Kalapakkam.
2. Details of Grid incidents (GI’s):
Sl. No.
क्र.स.ं घटनाकावििरण /
Details of Event
तारीख/ Date &
समय /Time कारण / Reason
शे्रणी/
Category
1 Multiple tripping at Nagjheri Hydro power station of KPCL
09-10-2015 at 11:43 hrs
220kV Nagjheri- Bidnal line tripped on operation of Directional earth fault protection due to suspected high resistance fault in line. Running Units -1&2 at Nagjheri power station tripped on operation of high set of back-up earth fault protection of Generator transformer protection. Remaining feeders at Nagjheri, i.e., Ambewadi-1, 2 and Hubli- 1 & 2 were not affected. Hubli-3 feeder was under shutdown
GI-1
SLD:
Nagjheri Capacity: 885 (5x150 + 1x 135) MW. Pre-fault conditions:
o Nagjheri – Kodasalli lines 1 & 2 were kept open. o Nagjheri – Hubli line -3 was under LC. (Check this because Nagjheri – Kubli is a D/C line only) o Units in service at Nagjheri: Unit-1 & Unit-4
220 kV Nagjheri – Bidnal line: Bidnal (KPTCL) end:
As per FIR, line tripped at 11:44 hrs on B-E fault due to OCR operation. No DR/EL furnished. Nagjheri (KPCL) end: As per DR/EL/ TR, the line tripped at 11:43:21.509 hrs on B-E fault due to operation of DEF (67N) protection.
In DR, no digital inputs (signals) were shown. In DR & EL the events/ signals or which protection operated to open the line were not shown.
It was stated that other 220 kV lines had not tripped.
Annexure-II
Grid Occurrences discussed during 49th
PCSC Meeting on 30-11-2015 13/29
Nagjheri Units -1 &4 tripping:
As per TR, the Units tripped due to operation of (High Set of) GT OC & E/F protection. (Time not mentioned, Instantaneously?).
DR & EL were not furnished for any of the Units. SRLDC:
Delayed clearance of the fault on Nagjheri –Bidnal line-1 was observed from PMU plot. The fault was observed to have sustained from 11:42:54.480 hrs to 11:42:55.600 hrs to 11:42:55.760 hrs 1.120 sec & 160 msec.
All trippings with delayed fault clearance (more than 1 sec) would be informed to CERC. When asked about operation of SPS, KPCL replied that SPS at NPH was provided for Units- 3 & 6 only which
were not in service during the tripping event. KPCL:
Remedial action: Settings of Instantaneous elements of Generator Transformer back up protection would be reviewed. The IDMT relay responsible for delayed fault clearance would soon be replaced. KPTCL also informed that resistive reaches of distance relays of NPH connected lines at remote end sub
stations i. e. at Hubli, Bidnal and Ambewadi had been taken up for review and revised to 75 ohms (Primary).
2 Tripping of 765kV Kurnool-Tiruvalam line-2
12-10-2015 at 11:18 hrs
Buchholz-2 of B-ph line reactor at Kurnool mal-operated and caused tripping of Line. Direct Trip was received at Thiruvelam end.
GI-2
Tiruvalam (PGCIL-SR2) end:
As per FIR/ DR/ El/ TR, the line tripped at 11:18:19.714 hrs due to DT receipt from Kurnool end. Kurnool (PGCIL-SR1) end:
As per FIR/ DR/ EL/ TR, the line tripped at 11:17:12.399 hrs due to mal-operation of Buchholtz-2 of B-ph Line Reactor.
PGCIL (SR-I):
It is a typical case of mal-operarion as the Buchholtz relay contacts were latched without any pressure variation.
Remedial Action: In fact, in all the newly commissioned 765 kV lines, they have been experiencing problems with
WTI and Buchholtz relays, and the issue has been taken up with OEM. All the Buchholz / PRD WTI / OTI Relays supplied under package are being replaced by OEM.
Already WTI relay was replaced at Kurnool; Buchholtz would also be replaced shortly.
When enquired by SRLDC regarding time-frame of completion of above work, he informed that the work would be completed in 3 months time.
When asked about spare transformers’ WTI and Buchholtz relays, it was informed that they were also being replaced.
3 Tripping of 220kV Edamon-Tirunelveli line-1&2
12-10-2015 at 21:30 hrs
220kV Edamon-Tirunelveli lines -1&2 got tripped due to operation of Bus Bar protection which was due to human error
GI-1
220 kV Edamon – Tirunelveli line-1: Edamon (KSEB) end: As per DR, the line tripped at21:47:38.549 hrs due to BBP operation.
EL not furnished (Uploaded EL was same as FIR) Tirunelveli (PGCIL-SR2) end:
Annexure-II
Grid Occurrences discussed during 49th
PCSC Meeting on 30-11-2015 14/29
As per FIR, the line was holding from their end. 220 kV Edamon – Tirunelveli line-2: Edamon (KSEB) end:
As per DR, the line tripped at 21:35:57.274 hrs due to BBP operation. EL not furnished (Uploaded EL was same as FIR) Tirunelveli (PGCIL-SR2) end:
As per FIR, the line was holding from their end.
Time sync between DR’s of both lines at Edamon end needs to be ensured. As per KSEB letter dated 27.11.2015:
SRLDC:
Had the tripping been due to accidental pressing of TEST LBB button of LBB, DT should have been sent to the remote end. But as this did not happen, KSEB should investigate the same.
Recommendations: KSEB to furnish reasons for DT not being sent to the remote end during the tripping event along with
remedial measures taken to PCSC forum.
4 Tripping of 400kV Gooty-NPS line-1
13-10-2015at 10:15 hrs
Direct Trip was sent to NPS end of line-1 during opening of Main CB of Gooty-NPS line-2 at Gooty end. This resulted in tripping of line-1 at NPS and line was holding from Gooty. Over voltage protection got operated at NPS end and resulted in tripping of line
GI-2
SLD:
Annexure-II
Grid Occurrences discussed during 49th
PCSC Meeting on 30-11-2015 15/29
400 kV Gooty – NPS line-1: Gooty (PGCIL-SR1) end:
As per FIR, the line tripped at 10:15 hrs due to DT receipt from NPS end. From EL, DT receipt was observed at 10:09:31.750 hrs from NPS end. [Prior to this, it was observed that both
Tie-CB 2952 and NPS-II Main-CB 2852 were in OPEN position]
DR (trigger time = 10:12:23.417 hrs) furnished was not readable. Also the cause of trip was not clear (as no relevant digital signals were shown)
As per TR, while manually tripping Tie-CB (2952) and Main-CB (2852) of NPS-II, DT was sent to NPS end. Subsequently on receipt of DT from NPS end, the line tripped at Gooty end. It was stated that at the time of hand tripping of Main-CB of NPS-II, DT was sent to NPS-I end wrongly. Due to this, 400 kV Gooty-NPS line-1 tripped at NPS end. Subsequently, OVR, Stage-I protection operated at NPS end, and sent DT to Gooty end, due to which Gooty-NPS line-1 tripped at Gooty end.
However, there was no evidence for OVR, Stage-I operation at NPS end.
Time sync of DR, EL needs to be ensured. NPS (PGCIL-SR1) end:
As per FIR/ TR, the line tripped at 10:15 hrs due to DT receipt from Gooty end. As per EL, DT receipt ALARM (NOT TRIP) only was observed at 10:15:33 hrs. Further, Time-Stamp was not
configured to show events at msec level. The events corresponding to OVR, Stage-I operation were not recorded.
As per DR, the line tripped at 10:15:33.053 hrs due to DT receipt from Gooty end. Time-sync of NPS and Gooty with GPS needs to be ensured. PGCIL (SR-I):
Prior to tripping event, 400kV Gooty-NPS Line-2 was out of service. Line Reactor (LR) at Gooty end for line-2 was being used as bus reactor.
Line-2 was to be taken into service. For opening LR, Main & Tie breakers of line-2 were opened at Gooty end.
However due to wiring problem (during commissioning stage), DT was sent to line-1 at NPS end which resulted in tripping of line-1 CB’s at NPS end. Line-1 was holding from Gooty end. The DT-sent was also a spurious operation due to latching of CB auxiliary contacts.
Then, Over voltage, Stage-I protection got operated at NPS end and resulted in tripping of line-2.
Remedial action: Problem with wiring connections got rectified. Latched CB auxiliary contacts were also replaced.
Recommendations:
PGCIL (SR-I) to configure time scale resolution in Event Logger to msec. at Nelllore PS (NPS) and furnish DR
corresponding to OVR, Stag-I operation at NPS end during the tripping event. PGCIL (SR-I) to ensure time-sync of DR’s and EL’s with GPS at Gooty and NPS.
5 Tripping of Gazuwaka Pole-2
13.10.2015 at 12:28 hrs
HVDC Pole-2 win-2 breaker tripped on operation of differential protection of Bus-2 of east side. Loss of East Bus-2 voltage led to tripping of Pole-2
SLD:
Annexure-II
Grid Occurrences discussed during 49th
PCSC Meeting on 30-11-2015 16/29
Pre-Conditions:
System Normal with Jeypore-Gazuwaka Line – I & II along with Line Reactors are in service Total Power Flow: 600MW E→S Pole - 1: 250 MW E→S Pole - 2: 350 MW E→S
Pole-2 East side WA2.W1.Q1 CB, connected to East Bus-1 was under shutdown condition for identification of SF6 Leakage points vide CPCC Code-CP/10/389 from 09:35 onwards.
Pole-2 East Bus voltage extended through WA2.W1.Q3 CB, connected to East Bus-2. Description of Fault:
At 12:28:06 Hrs on 13/10/2015, Voltage dip in the East Side was observed and HVDC POLE-2, East Bus-2 connected Breakers i.e WA2.W1.Q3 & WIN2.Q1 breaker tripped due to operation of “WIN2 Differential Current Phase L3 Trip” of East Bus-2.
Since East Bus Voltage was extended only through WA2.W1.Q3 Breaker i.e East Bus-2 as WA2.W1.Q1 CB (connected to East Bus-1) was under shutdown condition and tripping of WA2.W1.Q3 CB & WIN2.Q1 CB on above protection caused Loss to East Bus Voltage thereby tripping HVDC Pole-2 on “LOW DC VOLTAGE TRIP”.
Analysis:
DR Prints revealed current ZERO in Phase L3 (B-Phase) of WA2.W1.T3 CT connected to WA2.W1.Q3 Bay at the time of tripping, whereas the other two phases are showing healthy conditions i.e 182-Amps causing operation of “WIN2 Differential Protection” of East Bus-2 and loss of East Bus Voltage for HVDC Pole-2, thereby tripping the Pole on “Low DC Voltage Trip”
On detailed investigation it was found that the Core-4 B-Phase cable coming from WA2.W1.T3 CT Junction Box to Pole-1 Control room RTI-A System for East Bus Differential Protection had failed/earthed. The failure of particular core was confirmed through Continuity Check and Insulation Resistance measurement.
Remedial action: The trip was initiated by differential protection of RTI-A System. The protection in RTI-A system was
disabled and the same protection was made ACTIVE in redundant RTI-B system. The faulty CT cable from WA2.W1.T3 CT Junction box to Pole-1 Control room of length 1.5 km was
pleaced by spare, and PO for new cable ad already been placed. Normalization: At 14:06 Hrs, Pole-2 was Deblocked vide codes CPCC-414, NLDC- 433, SR-445, ER-351.
Annexure-II
Grid Occurrences discussed during 49th
PCSC Meeting on 30-11-2015 17/29
UPCL:
Since, the said cable is of 1.5 km length, line differential protection may be provided for protecting the same.
Provision of CT supervision may also be explored.
6
Tripping at 220kV Nunna Substation of APTRANSCO. 400/220kV ICT-2 at Vijayawada substation also got tripped.
15.10.2015 at 16:14 hrs
220kV bus bar protection operated at 220 kV Nunna APTRANSCO substation due to fault. All elements connected to 220kV bus-2 got tripped
GI-I
As per FIR/TR of Nunna (PGCIL-SR1), ICT-2 tripped at 16:14 hrs due to BBP operation of 220 kV Bus of APTRANSCO.
As per DR of Nunna (PGCIL-SR1), ICT-2 tripped at 16:14:51.802 hrs (the causing digital signal was not shown)
As per DR of Nunna (APTRANSCO), BBP of 220 kV Bus-2 operated at 15:12:12.264 hrs due to Y-ph bus fault. Time sync of Nunna (APTRANSCO) SS. Remedial Action: APTRANSCO informed that Aluminium wire had fallen on the 220KV BUS-2 and created the bus fault. Bus
bar protection operated and cleared the fault by tripping the Bus -2 connected Feeders, ICTs/PTRs. Protection was in order.
When enquired about time sync of Nunna-AP SS, APTRANSCO representative informed that GPS is not available at Nunna. However, they have planned to provide the same in a phased manner.
7 Tripping of 765/400kV ICT-2 at Kurnool Substation
15-10-2015 at 17:10 hrs
ICT tripped due to mal-operation of B-phase HV WTI trip
GI-2
As per FIR/ TR, ICT-2 tripped at 17:10:12 hrs due to mal-operation of HV B-ph WTI Trip. As per DR/ EL, ICT-2 tripped at 17:10:13 hrs due to mal-operation of HV B-ph WTI Trip. EL resolution was not configured to show events at msec level. Remedial action: This problem which was being experienced in all the newly commissioned 765 kV lines was
taken up with OEM and all the Buchholz / PRD WTI / OTI Relays supplied under package would be replaced by OEM.
At Kurnool, WTI relays were replaced by availing shut down on 17th and 18th Nov, 2015.
8
Tripping of 400kV Vemagiri-Sattenapalli line and 400kV Vemagiri-Kalpakka line
25-10-2015at 10:56hrs
B-phase to earth fault had occurred in line. From Vemagiri end D.R, three phase trip and Tie-CB LBB operated was observed. Sattenapalli end had auto-reclosed, however breaker at Satenapalli tripped 8 sec after A/R on receipt of DT from Vemagiri as observed from EL of Satenapalli station. For 400k Vemagiri-Kalpakka line at Vemagiri end, Tie LBB operation and Grp-A/B trip was observed and direct trip was sent to Kalpakka end
GI-2
400 kV Vemagiri – Sattenapalli line: Vemagiri (APTRANSCO) end:
As per DR/EL, line tripped at 10:55:39.487 hrs on B-E fault due to A/R operation. During A/R dead time, T-LBB operated at 10:55:39.559 hrs to result in 3-ph trip.
Annexure-II
Grid Occurrences discussed during 49th
PCSC Meeting on 30-11-2015 18/29
Sattenapalli (APTRANSCO) end:
As per EL, the line tripped at 10:56:19.203 hrs on B-E fault due to A/R operation, and successfully auto-reclosed after one second. But it again tripped at tripped at 10:56:29.457 hrs due to DT receipt from Vemagiri.
DR furnished was for second event (DT receipt) only. DR for the first event (for A/R operation) was not furnished.
If this DT receipt was due to T-LBB operation at Vemagiri end, then this time delay of 10 sec is inadmissible.
400 kV Vemagiri – Kalpakka line-1: Vemagiri (APTRANSCO) end:
As per DR/EL, the line tripped at 10:55:39.572 hrs due to operation of Tie-CB LBB protection. Kalpakka (APTRANSCO) end:
As per EL , the line tripped at 10:53:01.704 hrs due to DT receipt from Vemagiri
As per DR , the line tripped at 10:57:19.324 hrs due to DT receipt from Vemagiri Time sync of DR & EL needs to be ensured. APTRANSCO:
Vemagiri – Sattenapalli line and Vemagiri – Kalpakka line-1 are in the same dia. In the above dia at Vemagiri , Tie-CB has two auxiliary relays;
o One is for tripping its corresponding Main-CB and sending DT to Kalpakka and o The other is for tripping corresponding Main-CB sending DT to Satenapalli and.
On Tie LBB operation at Vemagiri end, Kalapkka line got tripped at Kalpakka end on DT receipt. On B-phase to earth fault, Satenapalli line auto-reclosed successfully. But after 8 seconds, Satenapalli line
tripped on OVR, Stage-I operation at Vemagiri.
Remedial Action: APTRANSCO representative informed that Tie-CB LBB auxiliary trip relay mal-operated. It was replaced
with spare relay, and feeders taken into service. SRPC:
The tripping of Vemagiri – Sattenapalli line due to T-LBB / OVR, Stage I operation could not be conclusively established from the DR & EL furnished in this regard.
Recommendations:
APTRANSCO to furnish a report on the tripping of 400 kV Vemagiri – Sattenapalli line along with relevant DR & EL showing clearly the successful operation of A/R followed by T-LBB/ OVR, Stage-I operation.
9
Tripping of 400/220 kV ICT-3 at Thrissur substation
25-10-2015at 11:04 hrs
Tie LBB protection of CB 405 resulted in tripping of breakers connected to 400kV Bus-1 along with main breaker of ICT-3. This in turn resulted in tripping of ICT-3 at Thrissur.
GI-2
KSEB:
Annexure-II
Grid Occurrences discussed during 49th
PCSC Meeting on 30-11-2015 19/29
Remedial action: Grading capacitor across CB-401 was replaced. The CBF relay was sent for repair works.
Annexure-II
Grid Occurrences discussed during 49th
PCSC Meeting on 30-11-2015 20/29
10 Tripping of 400kV Gooty - NPS line-1
26-10-2015 at 14:30 hrs
Line tripped on operation of REF protection at Gooty end and Direct Trip was sent to NPS end.
GI-2
Gooty (PGCIL-SR1) end:
As per FIR/TR, the line tripped due to operation of Reactor’s REF protection (64R). DT was also sent to NPS-1 end.
As per EL, the line tripped at 14:28:06.211 hrs due to Grp A & B trip relay operation. As per DR, the line tripped at 14:29:30.842 hrs. NPS (PGCIL-SR1) end:
As per FIR/DR/EL/TR, the line tripped at 14:30:46.290 hrs due to DT receipt from Gooty end. PGCIL (SR-I):
There was a problem with NGR-CT polarity, due to which its REF protection operated accidentally. Subsequently, it was rectified.
11
Tripping of 400/220 kV ICT-2 at Kurnool Substation and 400kV Kurnool-Srisailam line
26-10-2015 at 14:31 hrs
400kV Kurnool-Srisailam line - distance protection zone-2 had operated at Srisailam end. However from DR, R-phase to earth fault and zone-2 start were observed. Breakers at Kurnool end tripped on direct trip receive from Srisailam end. ICT-2 Main-CB tripped due to operation of bus bar protection, and Tie-CB tripped due to DT receipt from Srisailam
GI-2
SLD:
The SLD of 400/220 kV Kurnool SS as provided by APTRANSCO is attached at the end for reference. At 400 kV Kurnool SS, ICT-2 and Srisailam line are in the same dia. 400 kV Kurnool – Srisailam line: Kurnool (APTRANSCO) end:
As per FIR/ TR, the line tripped at 14:31 hrs due to DT receipt from Srisailam end DR, EL were not furnished to verify above operation. Srisailam end:
As per FIR, the line tripped at 14:31 hrs on R-E fault due to DPR, Z2 operation. As per DR/ EL, the line tripped at 14:29:44.489 hrs. But only Z2 Start (at 14:29:44.442 hrs) and DEF Start (at
14:29:44.449 hrs) were seen. Tripping of ICT-2 at Kurnool SS of APTRANSCO: As per FIR, ICT-2 Main-CB tripped at 14:31 hrs due to operation of BBP; Tie-CB tripped on receipt of DT signal
from Srisailam end. DR, EL not furnished. APTRANSCO:
ICT-1 Main-CB was availed Shutdown due to isolator problem. During maintenance, isolator of its earth switch got closed accidently which created a bus fault. Due to this , ICT-2 Main-CB got tripped.
The Tie-CB tripped along with Main-CB of Srisailam line due to DT receipt from Srisailam end. In the past also, APTRANSCO lines’s connected to Srisailam LB received DT in case of any kind of fault
occurring at Srisailam LB or on lines emanating from Srisailam LB.
Annexure-II
Grid Occurrences discussed during 49th
PCSC Meeting on 30-11-2015 21/29
TSGENCO:
At Srisailam end, newly commissioned relays (numerical) appeared to have configuration problems due to which DT is being sent to remote ends wrongly.
Remedial action: The matter had already been taken up with their OEM, and hope to resolve it at the earliest.
Recommendations: TSGENCO in coordination with APTRANSCO to carry out end-to-end testing of PLCC channels by 15.12.2015
on 400 kV Srisailam – Kurnool S/C line and 400 kV Srisailam – Sattenapalli D/C line. TSGENCO and APTRANSCO to make A/R functional on 400 kV Srisailam – Kurnool line. TSGENCO to resolve configuration problems with the newly commissioned relays at Srisailam LB so that
unwarranted DT sending to remote ends is addressed.
12 Tripping of 400/220kV ICT-2 at Chittoor substation
26-10-2015at 17:00hrs
ICT-2 at Chittoor tripped due to suspected mal-operation of Buchholtz relay.
GI-2
As per FIR, ICT-2 tripped at 16:59 hrs due to operation of Buchholtz relay.
From DR, ICT-2 tripped at 16:59:40.433 hrs due to operation of Buchholtz relay. The causing event was not recorded in the EL furnished. Remedial action: APTRANSCO representative informed that the line tripped due to mal-operation of ABB-make Buchholtz
relay. As a remedial measure, it was replaced with another relay of Areva make.
13
Tripping of running Units 1 & 3 at Rayalaseema TPS of APGENCO
31-10-2015 at 03:30 hrs
While synchronizing Unit-5 with grid, Bus bar protection of 220kV Bus-1 operated which resulted in de-energization of 220kV Bus-1. This resulted in tripping of running Unit-1&Unit-3, 220kV lines Pulivedula-1, Yeralaguntla-1, Chinakampalli-1, Timmapura
GI-1
SLD:
** Above is a part-SLD showing Unit-IV and Unit-V. Complete SLD is enclosed at the end.
Annexure-II
Grid Occurrences discussed during 49th
PCSC Meeting on 30-11-2015 22/29
Tripping of Units – 1 & 3 of Rayalaseema TPS of APGENCO:
As per FIR/ TR of APGENCO, Unit-5 of Rayalaseema TPP got tripped at 01:24 hrs on Flame Failure. In the process of taking Unit-5 back, TG set was kept 3000 RPM. During building-up of Generator Voltage, GT-5 LBB operated resulting in actuation of BBP of 220KV Bus-1. As a result, all out going feeders, GT-1, GT3, ST-1 &ST-5 on Bus-1 got tripped at 03:30 hrs.
From DR of Unit-5, it was observed that at 03:30:26.903 hrs that voltage was absent in R-phase. Also Dead-Machine condition and Class-A trip were observed 80 msec. subsequent to that.
From PMU data, dip in R-phase voltage was observed for 320ms. APGENCO:
While synchronizing Unit-5 manually, as the voltage build-up of generator reached around 10.5 kV, GCB got closed accidentally, and resulted in shorting/ burning of control cables. Due to this, closing pulse from the CB was not received by the main-relay, and dead-machine condition prevailed. This led to Class-A trip of Unit-5 generator protection. However, as the breaker failed to open, it resulted in BBP operation of 220 kV Bus-1.
Remedial action: The GCB Closing circuit was thoroughly checked in the presence of M/S. BHEL engineer from EDN
Bengaluru. 25CX (sync check relay) and k3-02 (GCB closing command) NO contacts have been incorporated in the
negative path of the GCB closing circuit along with the existing positive side. In the closing circuit of GCB, the Auto synchronising path and DEAD BUS closing path were completely
removed. Only manual closing path is kept after verifying thoroughly. New cables were laid for 220 Volts DC supply to GCB marshalling box for closing and tripping circuits. Close & open feedbacks of GCB poles are hooked up in protection relay disturbance record. The closing command output at GCB local panel was monitored by introducing an auxiliary relay. A NO
contact of this relay was connected to disturbance record of RET-670 relay. In the DVR auto channel soft start time was increased to 45seconds from 12 seconds in order to build up
the generator voltage in slow ramp to avoid inrush current. In manual channel Ifo (NO LOAD FIELD CURRENT), setting S885 was changed to position ‘0’ from position
‘A’. It will help in building up of generator voltage in slow ramp so that inrush current due to generator transformer charging shall be avoided.
After all the above checks the closing and protection tripping of GCB was checked and found OK
As regards keeping synchronization facility in auto-mode, it was informed that in the past with sync-facility in auto-mode, a fire accident took place in the cable gallery in which several control cables got burnt. Also they generally experienced abrupt changes in voltages and currents with auto-mode. As such, they have kept it in manual mode. The matter was referred to their OEM, M/s BHEL who had suggested to keep it under observation in mode for some time.
NLC:
Auto synchronization should be enabled where 25Ax relay is available, for it not only monitors the pre-conditions for synchronising, but also activates on-line correction signals, if necessary, to satisfy the conditions for synchronising, and ensures proper closing at right time. This is in place at NLC stations.
UPCL:
For CB closing circuit, negative breaking system, in which the sync-pulse will be transmitted from (-)ve, may be employed to secure operation of primary switching. (In this regard, a paper presented by Sh. Sanjay Bhatt,
UPCL is enclosed at Reference-I for kind perusal). Recommendations:
In view of the availability of 25AX, APGENCO shall keep synchronizing facility in auto-mode after getting it’s operation verified by its OEM, M/s BHEL.
Annexure-II
Grid Occurrences discussed during 49th
PCSC Meeting on 30-11-2015 23/29
14 Tripping of 220kV Ambewadi-Ponda line-1
31-10-2015at 11:51hrs
Line tripped on operation of directional earth fault protection, and distance protection had not sensed the fault.
GI-1
As per FIR, the line tripped on operation of DEF (67N) protection, and distance protection had not sensed the fault. The Currents recorded were Ia-284.2A, Ib-309.5A, Ic-566.9A.
The DR (with trigger time = 10:51:47.715 hrs) furnished may not be related to this tripping event, as while Ia, Ib became zero, Ic did not. Also no digital signals were shown.
In the EL furnished, no events relating to present tripping were observed between 10:00 hrs to 12:00 hrs. KPTCL:
The fault was well beyond the resistive reach of the distance relay. Remedial measures: The resistive reaches of distance relays of NPH connected lines at remote end sub stations i. e. at Hubli,
Bidnal and Ambewadi were taken up for review and revised to 75 ohms (Primary). DEFR time lever was also modified to 225ms.
15 Trippings at Raichur TPS
12-11-2015 at 00:30 hrs
Running Unit-4, 5 and Unit-8 and 400kV RTPS-Yeramaras TPS feeder got tripped due to de-energization of both 400kV Bus-1&2 at Raichur TPS
GI-2
RTPS Configuration: 400 kV – 1090 (4x210 MW + 1x250 ) MW 220 kV – 630 MW (3x210) MW SLD:
As per TR of RTPS of KPCL:
Running Units - 4, 5 & 8 and 400kV RTPS-Yeramaras TPS feeder got tripped due to de-energization of both 400kV Buses - 1&2 at Raichur TPS. Remaining 400kV lines, Units at 220kV level (Unit1,2 &3) and 400/220kV ICT-1&2 were not affected during the incident.
Unit-6 is under planned shutdown for annual overhaul from 28-10-2015. Unit-7 was tripped on auxiliary supply failure on 07-11-2015. Generation loss was 460 MW due to tripping of Units - 4, 5 & 8. Triggering incident: While building up voltage in Unit-7, (around 10kV) Unit-7 got tripped on operation of GT
neutral over-current protection. Simultaneously Main and Tie CB’s LBB of Unit-7 got operated. As a result, Main breakers connected to 400kV Buses - 1&2 got tripped (there was no other element in dia of Unit-7). 400kV Raichur line-1 got connected to ICT-2 through Tie-CB Mahboobnagar line got connected to Munirabad line through Tie-CB. Units - 4, 5 & 8 got tripped as the Main and Tie breaker are connected to Bus-1 & Bus-2 respectively
(there was no second element in the respective dia’s). As Unit-6 was already under planned shutdown, Yeramarus feeder got tripped on tripping of Main
breaker connected to 400kV Bus-2.
Annexure-II
Grid Occurrences discussed during 49th
PCSC Meeting on 30-11-2015 24/29
It was stated that as bus bar protection was electromechanical, DR & EL were not available for the incident. What about Stand-alone EL?
Reasons for operation of GT neutral over-current protection, and subsequent LBB-operation of Main-CB and Tie-CB of Unit-7.
SRLDC:
From PMU plots, three faults were observed, which got cleared with a delay of 320 ms, 400 ms, and 120 ms. Reasons for 3 successive faults and their delayed clearance.
SOE of RTPS was not recorded at SLDC SCADA and same needs to be checked. Reasons for why the fault went undetected by GT’s primary protection (Differential or REF) need to be seen. KPCL: On 12.11.2015 at 00:30hrs, during voltage build up of Unit-7 around 10KV, Unit-7 tripped on operation of GT
neutral over current protection (51NGT) due to surface conduction over the Main & Tie breakers. LBB relays of Main & Tie breakers got operated leading to Bus-1 & 2 bus bar relay operation.
Observation: As informed by the shift staff that, heavy sound & arcing observed near Unit-7 Main & Tie breakers. On
detailed inspection it is observed that, B-pole (RYB) of Unit-7 Tie breaker interrupter got ruptured. Due to this 51 NGT of Unit-7 operated and initiated class-A & LBB. Since, the surface current was persisting more than 200 milli seconds leading to tripping breakers connected to bus-2.
Due to surface conduction over the Unit-7 main breaker, (Bus-1) LBB relay of main breaker also operated simultaneously, leading to tripping breakers connected to bus-1.
Reason : The reason for surface current is due to deposition of ash, heavy mist & humidity. The Unit-7 bay is very
near to the cooling towers.
When enquired about hot-line washing, it was informed that an accident happened while carrying out hot-line washing of RTPS connected lines some time ago, subsequent to which it was temporarily put on hold.
To this, SRLDC stated that hot-line washing is essential to avoid fog-trippings and other unwarranted trippings due to deposition of dust on insulators.
UPCL:
Under the circumstances as above, a dedicated breaker-flashover protection comes in handy. Breaker failure schemes are specifically employed to provide backup protection in the event that a circuit breaker fails to operate properly during fault clearing. (In this regard, a write-up on Breaker flask-over protection, and a paper presented by Sh. Sanjay Bhat, UPCL on “Adaptive Logic for Breaker Flashover protection” are enclosed
at Reference-II and Reference-III for kind perusal). Recommendations:
KPCL to carry out hot-line washing of RTPS-connected lines regularly to avoid trippings due to fog and dust. KPCL may see the feasibility of providing breaker flashover protection at RTPS, and implement the same if
possible.
3. Failure/ Non-operation of Auto-reclose during transient fault
Sl. No. Element Date & Time Reason
1
Tripping of 220kV Sabarigiri-Theni line
09-10-2015 at 16:56 hrs
Line tripped on a R-phase to earth fault. At Sabarigiri, relay gave a 3 phase trip after 220ms. From Theni end D.R, auto reclose block was observed.
Theni (TANTRANSCO) end:
As per FIR/ TR, the line tripped at 16:56 hrs on R-E fault due to carrier-aided trip.
Annexure-II
Grid Occurrences discussed during 49th
PCSC Meeting on 30-11-2015 25/29
From DR, the line tripped in R-ph at 16:49:44.002 hrs on R-E fault due to carrier-aided trip. However, within 100 msec, A/R block was observed;
EL not furnished (Furnished EL was the last part of DR) Sabarigiri (KSEB) end:
As per FIR/ TR, the line tripped at 16:56 hrs on R-E fault due to DPR, Z1 operation (Distance 52.8 km). From DR/ EL, R-E fault got detected at 17:02:21.749 hrs; however, as the A/R status was not ready, it gave a
3-ph trip and sent carrier to the other end at (17:02:21.749 hrs + 241 ms). It was also observed that EF trip was blocked.
The delay in fault clearance for DPR, Z1 operation needs to be explained. KSEB:
The fault was of high resistance type due to arcing to tree branches in the forest. It was suspected that the fault could have been first picked up by DERF (this explains A/R not ready status),
and it slowly developed into a Zone-1 fault, due to which line tripped sending carrier to the remote end. Recommendations:
KSEB to furnish a report on the tripping incident along with the remedial measures taken to PCSC forum.
2 Tripping of 220kV Gummidipoondi-Sullurupeta line
14-10-2015 at 23:22 hrs
As per FIR, line tripped on a Y-phase to earth fault. Line did not auto-reclose.
Gummidipoondi (TANTRANSCO) end:
As per FIR/DR/EL/TR, line tripped at 11:20:12.971 hrs on Y-E fault due to DPR, Z1 operation (Distance = 36.96 km). As A/R provision was not present, the line tripped in 3-ph.
Remedial Action: Temporary fault; Feeder charged from Sullurpeta end at 23:38 hrs and tied at Gummudipoondi end
23:40 hrs. Sullurupeta (APTRANSCO) end:
As per FIR, the line tripped at 23:17 hrs on Y-E fault due to DPR, Z1 operation. As per DR/EL, the line tripped at 11:17:52.516 hrs on Y-E fault due to DPR, Z1 operation. As A/R provision
was not present, the line tripped in 3-ph. Status of Provision of A/R:
TANTRANSCO and APTRANSCO informed that A/R would be made functional on Gummidipoondi – Sullurupeta line by the last week of December, 2015.
As regards providing A/R on 400 kV Chittoor – Tiruvalam D/C line, material procurement it was informed that material procurement is under progress, and A/R would be made functional in one to two months time.
3 Tripping of 220kV Ambewadi-Ponda line-1.
17-10-2015at 14:01 hrs
line tripped on a B-phase to earth fault. There is no provision for auto-reclose for line
Ambewadi (KPTCL) end:
As per FIR, the line tripped on B-E fault (fault current = 6.87 kA, fault distance = 3.498 km) due to DEFR and DPR, Z1 operation.
From DR/EL (trigger time = 13:58:09.455 hrs), the fault current seemed to have sustained for 750 msec, after which only “Any Trip” acted.
KPTCL:
As per the information available from the field people, it was definitely a Zone-1 fault. However, the reasons for delayed fault clearance would be analysed and furnished to PCSC forum.
The A/R for this line was covered under KPTCL’s U&R proposal for their 93 SS, and would be provided under those works.
Annexure-II
Grid Occurrences discussed during 49th
PCSC Meeting on 30-11-2015 26/29
4
Tripping of 400kV Krishnapatnam-Chittoor line-1
19-10-2015 at 07:49 hrs
R-phase to earth fault had occurred in line. Chittoor end tried for auto-reclose. However, due to persistent fault, breaker at Chittoor end tripped. Krishnapatnam end relay did not try for auto-reclose and gave a 3 phase trip as observed from D.R
Krishnapatnam TPS (APGENCO) end:
As per FIR/ DR/ EL, the line tripped at 07:49:44.182 hrs on R-E fault due to DPR, Z1 operation (fault distance = 58.1 km).
The line did not try for A/R, and simply gave a 3-ph trip. Why? (In DR, addition signals - TEF1_STFW, ZCOM_CS – were observed)
Chittoor (APTRANSCO) end:
As per FIR/ DR/ EL, the line tripped at 07:49:44.182 hrs on R-E fault due to DPR, Z1 operation.
The line tried for A/R, but gave 3-ph trip due to persistent fault. APGENCO:
A/R was kept out of service at the time occurrence of tripping as there were only two evacuating lines [SDSTPS – Chittoor & SDSTPS – Nellore (AP)] then. Now with the commissioning of second circuit of both the lines in November, 2015, APGENCO agreed to put A/R into service. To this, SRLDC requested to keep A/R functional on all lines emanating from Krishnapatnam TPS by 10th December, 2015.
Recommendations: APGENCO to make A/R functional on all lines emanating from Krishnapatnam TPS by 10th December, 2015.
5 Tripping of 400kV Kaniyambeta-Kadakola line
28-10-2015at 12:08 hrs
Line tripped on a Y-phase to earth fault. There is no provision for auto-reclose
Kaniyampeta (KSEB) end:
As per FIR/ DR, the line tripped at 12:08:39.106 hrs on Y-E fault due to DPR, Z1 operation (FD = 30.47 km; FC = 1643 A)
No EL furnished. In DR, various Voltages & Currents should be shown separately (instead of superimposing); Time scale was
also very restrictive (configured to show only 300 msec).
Remedial Action: As per the information from field, after line patrolling, no fault or permanent tree touching found in the
Kerala area. A semi permanent fault is suspected to be in the maintenance area of Kadakola. (The fault location is around 35km).
Kadakola (KPTCL) end:
As per FIR/ DR. the line tripped at 12:02:00.776 hrs on Y-E fault due to DPR, Z1 operation (FD = 69.5 km; FC = 8 p.u.).
No EL furnished.
3-ph trip happened due to absence of A/R Remedial action: Transient fault; stood OK after test charging.
SRLDC:
KPTCL should provide 1-ph A/R from Kadakola end, as in case of transient faults supply can be restored within one second.
Recommendations:
KPTCL to provide A/R on Kadakola – Kaniyampeta line at Kadakola end.
Annexure-II
Grid Occurrences discussed during 49th
PCSC Meeting on 30-11-2015 27/29
4. Lines tripping due to tripping at one end/PLCC mal-operation
Sl. No.
क्र.स.ं घटनाकावििरण /
Details of Event
तारीख/ Date &
समय /Time
कारण / Reason
1 Tripping of 400 kV Mysore-Kozhikode line-2
31-10-2015at 16:19 hrs
Line tripped at Mysore end only on Direct trip receipt.
Kozhikode (PGCIL-SR2) end:
As per FIR, the line was kept holding. Mysore (PGCIL-SR2) end:
As per FIR/ DR/ EL/ TR, the line tripped at 16:19:57.294 hrs due to DT receipt from Kozhikode end. Remedial Action: Tripped at Mysore end only on receipt of DT from Kozhikode end. Suspected DC earth fault at Kozhikode.
The DC earth fault was rectified. SRPC/ SRLDC:
PGCIL (SR-II) may carry out PLCC end-to-end testing for this line to ensure carrier communication is intact.
2 Tripping of 400 kV JSW-BTPS line
10-10-2015 at 12:14 hrs
Line tripped at BTPS end only and was holding from JSW. R-phase CVT fuse fail had caused tripping at BTPS end
JSWEL end:
As per FIR/ TR, the line was kept holding. BTPS (KPCL) end:
As per FIR/ DR/ TR, the line tripped at 12:12:21.351 hrs due to External Trip caused due to R-ph fuse failure of CVT
Remedial Action: KPCL: Trip occurred due to CVT "R" Phase fuse failure. CVT Fuse replaced. Tested and found OK.
SRLDC:
In case of VT/ CVT fuse failure, the relay should block tripping. However, during such block if a fault occurs (this can be detected from neutral current), the block should be released.
Annexure-II
Grid Occurrences discussed during 49th
PCSC Meeting on 30-11-2015 28/29
SLD of Rayalaseema TPS (Courtesy: APGENCO)
Annexure-II
Meeting
No /
Index
Details of
Event
Date Reason PCSC Recommendations Utility
Responsible
for
implementat
ion
Status of Recommendations
as on 14-12-2015
Remarks
45/II/14 Tripping of
400/220 kV
ICT-1&2 at
Gooty
substation
31-05-2015at
06:37 hrs
As per FIR, ICT-1&2 tripped on
operation of directional overcurrent
and earth fault protection. It was
reported that there was fault in
220kV APTRANSCO system
1. APTRANSCO to check resistive reach of the
distance relays on 220 kV Gooty SS – Gooty
RS line
2. APTRANSCO to check time coordination of
distance relay on Gooty SS – Gooty RS line at
Gooty SS with Gooty ICT’s (1 & 2) back-up
protection.
APTRANSC
O
Yet to be informed Pending
APTRANSC
O
APTRANSCO to furnish a report on the
tripping of 400 kV Vemagiri – Sattenapalli line
along with relevant DR & EL showing clearly
the successful operation of A/R followed by T-
LBB/ OVR, Stage-I operation.
Pending Implementation of PCSC Recommendations (30th to 49th)
Andhra Pradesh42/II/3 Outage at
Regulapadu
station of
APTRANSC
O
21-02-2015
at
00:49 hrs
Y-Ph Metering PT failed at 220KV
Ragulapadu Substation. Fault got
cleared
by tripping of lines from remote
ends.
APTRANSCO to furnish the remedial
measures taken in consequent to the tripping
incident along with the status of bus bar
protection and bus coupler at Regulapadu S/s.
A/R feature to be enabled on Regulapadu –
Alipuira 220 kV inter-state line.
APTRANSC
O
Mail recieved on 22-08-2015:
APTRANSCOhas planned to commission ABB make ETL-41 type
PLCC terminal along with NSD-50 type protection coupler at
Ragulapadu end towards Alipura. vide our Ltr Dt 23-07-2015, it is
requested KPTCL to arrange ABB make ETL-41 cabinet with NSD-
50 type protection coupler for establishing PLC communication
between Alipura- Ragulapadu.
Pending
B-phase to earth fault had occurred
in line. From Vemagiri end D.R,
three phase trip and Tie-CB LBB
operated was observed.
Sattenapalli end had auto-reclosed,
however breaker at Satenapalli
tripped 8 sec after A/R on receipt
of DT from Vemagiri as observed
from EL of Satenapalli station.
For 400k Vemagiri-Kalpakka line
at Vemagiri end, Tie LBB
operation and Grp-A/B trip was
observed and direct trip was sent to
Kalpakka end
25-10-2015
at 10:56 hrs
Tripping of
400kV
Vemagiri-
Sattenapalli
line and
400kV
Vemagiri-
Kalpakka line
49/II/8 PendingYet to be informed
Annexure-III
Page 1 of 24
49/II/13 Tripping of
running Units
1 & 3 at
Rayalaseema
TPS of
APGENCO
31-10-2015
at 03:30 hrs
While synchronizing Unit-5 with
grid, BBP of 220kV Bus-1
operated which resulted in de-
energization of 220kV Bus-1. This
resulted in tripping of running Unit-
1&Unit-3, 220kV lines Pulivedula-
1, Yeralaguntla-1, Chinakampalli-
1, Timmapura
In view of the availability of 25AX,
APGENCO shall keep synchronizing facility in
auto-mode after getting it’s operation verified
by its OEM, M/s BHEL.
APGENCO Yet to be informed Pending
49/III/4 Tripping of
400kV
Krishnapatna
m-Chittoor
line-1
19-10-2015
at 07:49 hrs
R-phase to earth fault had occurred
in line. Chittoor end tried for auto-
reclose. However, due to persistent
fault, breaker at Chittoor end
tripped. Krishnapatnam end relay
did not try for auto-reclose and
gave a 3 phase trip as observed
from D.R
• APGENCO to make A/R functional on all
lines emanating from Krishnapatnam TPS by
10th December, 2015.
APGENCO Yet to be informed Pending
44/III/2 Tripping of
400kV
Ghanapur-
Mamidapalli
line
15-04-2015
at 2:03 hrs
Line tripped at Mamidapalli end
only and was holding at Ghanapur.
Overvoltage protection had
operated at Mamidapalli
TSTRANSCO to make DR
functional at Mamidipalli
TSTRANSC
O
TSTRANSCO informed vide their mail dated 24.06.15 that the
existing relays would be replaced with numerical relays in DPR
works.
Pending
Telangana
Annexure-III
Page 2 of 24
48/II/5 Tripping of
400kV
Nagarjunsaga
r-
Mahboobnaga
r line
07-09-2015
at 2:58 hrs
Line tripped on operation of OV
protection at Mahboobnagar and
DT received at N’sagar station. DT
receive was observed in DR and
EL of N’sagar station. D.R/EL of
Mahboobnagar was not furnished
to validate the overvoltage tripping
TSTRANSCO to furnish a detailed report on
the tripping event along with remedial
measures taken to PCSC forum.
TSTRANSC
O
Yet to be informed Pending
48/III/4 Tripping of
220kV
Gajwel-
Shankarapally
line
20-09-2015
at 2:24 hrs
line tripped at Gajwel end on R-
Phase to ground fault. Reason for
non-auto reclose could be
established as DR and EL of both
ends were not furnished
• TSTRANSCO to furnish a detailed report on
the tripping event along with remedial
measures taken to PCSC forum.
TSTRANSC
O
Yet to be informed Pending
47/I/1
(GD)
Disturbance
in Srisailam
left bank
power station
18-08-2015
at 15:25 hrs
PendingYet to be informedTSGENCO1. TSGENCO to check the reclaim time of A/R
and set it at 25 sec at KTPS.
2. TSGENCO to carry out PLCC end-to-end
testing in coordination with PGCIL (SR-I) for
KTPS – Khammam
line-2; retrofitting of Protection Coupler may
be carried out based on the test results.
Y-phase to earth fault had occurred
in line. From Khammam end DR it
was observed that the relay after
dead time tried for auto-reclose.
The fault was persisting and relay
gave a single phase
trip instead of a 3 phase trip after
1.25sec. R& B pole voltage dip
after 2 sec possibly due to
operation of pole discrepancy.
Auto-reclose close command
observed after 2.5 seconds
and all poles got closed.
30-07-2015
at 6:08 hrs
PendingYet to be informedTSGENCO1. TSGENCO to disable sensitive earth fault
protection provided as supplementary to static
bus-bar
protection at Srisailam LB (GIS).
2. TSGENCO to set the current setting for
phase-to-ground faults for numerical bus-bar
protection at a suitable value so that the
prominent high-resistance earth faults
occurring within the bus-zone are
covered at Srisailam LB (GIS).
Tripping of
400kV
Khammam-
KTPS line-2
400kV Srisailam-Mamidapalli line-
2, 400kV Srisailam- Satenapalli
line-2 and 400 kV Srisailam-
Kurnool line tripped during
multiple tripping at Srisailam
power station. 400kV Srisailam-
Mamidapalli-1 and 400kv
Srisailam-Satenapalli-1
was kept out of service due
over-voltage conditions. There was
no generation at Srisailam left bank
power station. Triggering incident
was failure of CT in 400kV
Srisailam- Satenapalli line-2 at
Srisailam end.
47/II/6
Annexure-III
Page 3 of 24
34/III/1 400kV
Raichur-
BTPS line
26-06-2014 Transient fault in R-phase.
Line did not auto reclose
A/R at BTPS end to be made operational
within one month
KPCL 1. A/R for 220kV lines enabled already.
2. Shut down of lines availed to commission the auto reclosing schme
for 400 kV line at BTPS.
Mail recieved on 21-10-2015:
Timer relays have been received at site. A letter has been addressed to
M/s Alstom to complete the work on priority basis.
Mail recieved on 23-11-2015:
Commissioning of Autorecloser planned on 14, 15 & 16th of Dec-
2015 subject to availability of LC.
Pending
Karnataka30/I/A RTPS
Tripping
incidents and
the Spl
meeting held
at RTPS on
13th and 14th
March 2014
Mar-14 Spl meeting held at RTPS on 13th
and 14th
March 2014
The PCSC forum recommended for
replacement of existing electromechanical
relays with Numerical relays.
KPCL Mail recieved on 21-10-2015 and 23-11-2015:
1) Replacement of Old electromagnetic relays with Numerical relays
has been completed for RTPS-BTPS line & commissioned on
18.03.2014.
Raichur-PG1 & Raichur-PG2 lines have already retrofitted with
numerical relays.
2. Job order placed on 26.06.2015 on M/s Alstom T&D India Ltd.
Chennai for retrofitting of relays for all 220kV lines at RTPS.
3. Retrofit of existing bus bar(CAG-34) with numerical version–
Budgetary offers obtained and is under process.
38/GD/3.
5
GD-1 at
Kadra and
Kodasalli
hydro power
station
13-11-2014
at 19:31hrs
A fault had occurred in 220 kV
Kadra and
Kodasalli. As A result, de-
energization of
220kV bus occurred at Kadra and
Kodasalli.
1. The PCSC forum requested KPCL to speed
up the installation of Numerical Distance
Protection relay in Kadra –Kaiga and
Kodasalli –Kaiga.
2. The PCSC forum requested KPCL to submit
the implementation status of PSAG-10
recommendations within a week’s time.
KPCL Mail recieved on 21-10-2015:
NIT floated on 5.5.15 through e-portal. Bid evaluation completed.
LOA's issued to M/s Schneider Electric Infrastructure Ltd. on
08.10.2015.
Mail recieved on 23-11-2015:
LOA's issued to M/s Schneider Electric Infrastructure Ltd. on
08.10.2015. Engineering work is in progress.
Pending
Pending
Annexure-III
Page 4 of 24
38/GD/3.
2
GD-1 at
Guttur
Substation of
KPTCL
05-11-2014
at 11:42 hrs
Circuit breaker of 400kV Guttur-
Hiriyur
line-1 failed at Guttur end while
availing
shutdown for replacement of CVT.
The
failure of breaker caused bus fault
at Guttur.
KPTCL was requested to expedite the early
implementation of pending recommendations
of:
1. Protection Audit (Phase-I & Phase-II)
2. PSAG-4, PSAG-5, and PSAG-8
KPTCL Mail received on 27-05-2015 & 29-07-2015:
Latest satus of implementatin of Phase-1 &2 recommendations,
PSAG 4,5 and 8 is being obtained from field. The Status will be
updated witin a weeks time.
Pending
39/I/5 Tripping of
400/220kV
ICT-2 at
Hoody
substation of
KPTCL
01-12-2014 Suspected mal-operation of 220kV
side Rphase
over current relay
1. PCSC forum recommended KPTCL to
replace the relay with a different make.
2. KPTCL was also requested to train the
O&M personnel adequately before performing
any maintenance works to avoid such unwanted
trippings.
KPTCL Mail received on 27-05-2015 & 29-07-2015:
C&R panels of 500MVA ICT 1&2 will be replaced under
scheduled R&M works. O&M personnel are instructed to take
sufficient care in order to avoid unwarrented trippings.
Pending
34/I/6 400/220 kV
ICT-1 & 2 at
MUNIRABA
D
16-07-2014 As reported directional over
current relay of ICT’s operated
due to snapping of line jumper
in 220kV Lingapur line.
1. Bus bar protection shall be provided by
asset owner ( i.e KPTCL).
2. Settings for main distance protection &
Overcurrent protection shall be examined and
reviewed.
3. Time synchronization of the Substation
shall be ensured.
4. Correct DR shall be submitted to the SRLDC
for trip analysis.
KPTCL Mail recieved on 27-05-2015 (KPTCL):
1. KPTCL has taken action to provide bus bar protection to 220kV
buses.
2. Over current relay Settings of ICTs to be reviewed by PGCIL.
Mail received on 29-07-2015 (KPTCL):
Initial Tendering stage
Pending
38/GD/3.
1
GD-1 at
Mahalingapur
a Substation
of KPTCL
25-10-2014 Fault had occurred in 220kV
Mahalingapura-Narendra line-2.
Due to the
failure of relay operation at
Mahalingapura,
breakers at remote end tripped
which
resulted in bus dead condition.
1. PCSC forum recommended KPTCL to
replace the old static distance protection
relays with numerical relays.
2. PCSC forum also requested KPTCL to
provide a broken conductor alarm indication in
Control Room.
3. Standing instruction needed to be given to
the all substation personnel for not changing
the relay settings without approval of RT/MRT
wing.
KPTCL Mail received on 27-05-2015 (KPTCL) & 29-07-2015:
1.Existing Back up relays will be replaced by numerical type
distance relays.Procurement is in tendering stage. Remaining
observations were attended.
Pending
Annexure-III
Page 5 of 24
40/IV/1 220kV Sedam-
Tandur line
20-12-2014
at 22:20 hrs
Line tripped on Yphase to earth
fault from both the ends
KPTCL was requested to explore the
possibility of providing A/R feature to this
line and submit the remedial measures to the
PCSC forum.
KPTCL Mail recieved on 29-07-2015:
Carrier protection is being restored for 220kV Sedam-Tandoor line at
Sedam end. After restoring the carrier protection , AR will be
enabled.
Pending
40/I/1 GD-1 at
220kV
Ambewadi
Station of
KPTCL
22-12-2014
at 21:22 hrs
Triggering incident was B-phase to
earth fault in 220kV Ambewadi-
Nagzari line-1. B-pole of breaker
did not open at Ambewadi end.
LBB protection not available at
Ambewadi end. All elements
tripped on Zone-2 from remote
ends.
1. Till the completion of R&M works for bus
bar and LBB protection, KPTCL shall explore
the possibility of having split bus operation
at Ambewadi and submit the details of the
same to PCSC forum.
2. KPTCL shall provide the details of the
tripping of Supa hydro station connected
downstream from 110 kV bus.
KPTCL Mail recieved on 29-07-2015:
Action is being taken by KPTCL for operating Ambewadi in split bus
mode. Problem in bus coupler breaker is attended.Isolator
overhaulling work is completed.PTs are already provided to 220kV
Bus-II. After commissioning of Bus-II PTs, Ambewadi can be
operated in split bus mode. Pending works will be completed within a
months time.
Pending
Mail received on 28-05-2015:
1. Main-2 relays already installed and commissioned.
2. DC fuses are intact. Till date no such incidence occurred.
3. Possibility of DC-1 & DC-2 arrangement and splitting of DC will
be reviewed.
Mail received on 07-07-2015 , 21-10-2015 and 23-11-2015:
1. Completed.
2. Completed.
3. Possibility of DC-1 & DC-2 arrangement and splitting of DC will
be reviewed.
Pending41/I/1 GD-1 at
220kV Kadra
power Station
of KPCL
16-02-2015
at 12:56 hrs
Triggering incident was B-phase to
earth fault had occurred in 220kV
Kadra-Kodasalli line. Line tripped
from Kodasalli end only. 220kV
Kaiga-Kadra tripped in Zone-3
from Kaiga end. Tripping of
evacuating lines caused bus shut
down at Kadra hydro station.
1. KPCL to make functional the Main2
(EPAC) relay with the help of KPTCL at the
earliest.
2. KPCL to investigate the reason for DC
fuse fail during transient fault in 220kV Kadra-
Kodasalli line including the testing/ checking
of DC supply cables, breaker control cables,
and trip coils.
3. KPCL to ensure supply for Main-1& Main-
2 protections, Trip Coils (TC1, TC2) from
separate battery banks.
KPCL
PendingMail received on 29-07-2015:
1. Procurement of Bus bar and LBB protection is in the final
tendering stage.
2. Action is being taken to restore the carrier protection for 220kV
Sedam-Tandoor line. AR will be enabled after restoration of PLCC.
KPTCL 1. KPTCL to provide Bus bar and LBB
protections for 220 kV bus at Sedam S/s.
2. KPTCL to implement A/R feature on 220
kV Sedam-Tandur inter-state line.
R-Phase to ground fault occurred
on 220kV Sedam-Shahpur line.
Fault not cleared from Sedam end
due to stuck-breaker condition.
While the Sedam- Sahapur line
tripped from Shahapur end in Zone-
1, the other 220 kv lines from
Sedam tripped at remote ends in
Zone-2. This caused complete
outage of 220kV Sedam substation.
27-01-2015
at 8.00 hrs
Complete
outage at
220kV Sedam
Substation of
KPTCL (GD-
1)
41/I/4
Annexure-III
Page 6 of 24
42/I/1
(GD)
Complete
outage of
220kV Sedam
substation of
KPTCL
15-02-2015
at 14:24 hrs
Fault occurred in 220kV Sedam-
Shahpur line
1. KPTCL to provide Bus Bar protection and
LBB protection at Sedam S/s and furnish
the status of their implementation to PCSC
forum.
2. KPTCL to implement A/R feature on 220 kV
Sedam-Tandur inter-state line.
KPTCL Mail received on 29-07-2015:
1. Procurement of Bus bar and LBB protection is in the final
tendering stage.
2. Action is being taken to restore the carrier protection for 220kV
Sedam-Tandoor line. AR will be enabled after restoration of PLCC.
Pending
42/I/2
(GD)
Complete
outage of
220kV
Ambewadi
substation of
KPTCL
12-03-2015
at 7:51 hrs
Fault in 220kV Ambewadi-
Nagjheri line-2
1. KPTCL shall provide A/R feature on
Ambewadi – Ponda 220 kV D/C inter-state
line.
2. Till the completion of R&M works for bus
bar and LBB protection, KPTCL shall explore
the possibility of having split bus operation at
Ambewadi and submit the details of the same
to PCSC forum.
KPTCL Mail received on 29-07-2015:
1. Procurement of Bus bar and LBB protection is in the final
tendering stage.
2. Action is being taken to restore the carrier protection for 220kV
Sedam-Tandoor line. AR will be enabled after restoration of PLCC.
Pending
42/II/2 Tripping of
220kV
Chikodi-
Talandage
and
Mudshingi
line
20-02-2015
at
06:40 hrs
Lines tripped during test charging
220kV
Chikodi-Belgaum line-2 from
Chikodi
end.
1. KPTCL to provide A/R feature on the 220
kV Chikkodi – Talandage, and 220 kV
Chikkodi –Mudashinge inter-state lines.
2. KPTCL to carry out E/F relay coordination
for Chikkodi - Talandage and Chikkodi –
Mudashinge lines in coordination with
Maharashtra.
KPTCL Mail received on 29-07-2015:
Action is taken for enabling AR for Mudashinge and Talandage lines.
Work is scheduled during first week of August 2015.
Pending
PendingMail received on 29-07-2015:
1. Procurement of Bus bar and LBB protection is in the final
tendering stage.
2. Action is being taken to restore the carrier protection for 220kV
Sedam-Tandoor line. AR will be enabled after restoration of PLCC.
KPTCL 1. KPTCL to provide Bus bar and LBB
protections for 220 kV bus at Sedam S/s.
2. KPTCL to implement A/R feature on 220
kV Sedam-Tandur inter-state line.
R-Phase to ground fault occurred
on 220kV Sedam-Shahpur line.
Fault not cleared from Sedam end
due to stuck-breaker condition.
While the Sedam- Sahapur line
tripped from Shahapur end in Zone-
1, the other 220 kv lines from
Sedam tripped at remote ends in
Zone-2. This caused complete
outage of 220kV Sedam substation.
27-01-2015
at 8.00 hrs
Complete
outage at
220kV Sedam
Substation of
KPTCL (GD-
1)
41/I/4
Annexure-III
Page 7 of 24
43/II/14 Tripping of
400/220kV
ICT-1 at
BTPS
14-01-2015
at 1:09
hrs
ICT tripped due to operation of
Over current and Earth fault relay
KPCL to check the possibility of providing line
differential protection between RTPS and
Yermarus stations.
KPCL Mail received on 07-09-2015 , 21-10-2015 and 23-11-2015:
Revised relay settings are awaited from KPTCL.
Revised relay settings furnished by KPTCL will be incorporated in co-
ordination with KPTCL shortly.
Pending
45/III/12 Tripping of
400kV
Raichur-
BTPS line
01-06-2015
at 01:02 hrs
line tripped on R-phase to earth
fault. Line did not auto-reclose
KPCL to make A/R operational on 400 kV
RTPS – BTPS S/C line at both ends.
KPCL Mail recieved on 23-11-2015:
Completed at RTPS end.
Pending
44/II/3 Tripping of
220kV
Kaiga-
Kodasalli
and 220kV
Kodasalli-
Nagjheri line-
1
22-04-2015
at
20:28 hrs
220kV Kodasalli-Nagjheri line-1
tripped from Kodasalli end on
operation of distance protection,
zone-2.
220kV Kodasalli-Nagjheri line-
1&2 is kept opened from Nagjheri
end, hence fault
could not be cleared with carrier
aided protection. Backup earth
fault relay at Kaiga end got
operated during the event and
resulted in tripping of 220kV
Kaiga- Kodasalli line from Kaiga
end.
1. KPCL to check the possibility of
implementing Permissive Over Reach (POR)
with Echo feature at Kodasally end.
2. If the above is not possible, KPCL shall
check the possibility of keeping the 220kV
Kodasalli-Nagjheri lines OPEN at Kodasalli
end and idle-charged at Nagjheri end, and
implement the same.
KPCL Mail received on 07.07.2015:
The matter had been discussed with KPTCL. KPTCL recommended
to keep Zone-2 time lever to zero. If this is acceptable, then the same
shall be incorporated immediately.
Mail received on 07-09-2015 , 21-10-2015 and 23-11-2015:
The matter has been discussed with KPTCL. KPTCL recommended to
keep Zone-2 time lever to zero.
If this is acceptable to SRLDC, then the same shall be incorporated
immediately.Reply from SRLDC is awaited.
Pending
PendingMail recieved on 23-11-2015:
1) Completed
3) Two bus operation for 220kV buses : In place of existing CT
switching relays, High speed manual heavy duty change over switch
of sufficient current capacity will be retrofitted to all feeders at 220kV
station and same will be operated manually during changeover of
feeder by one bus to the other and this arrangement may facilitate to
put both buses in service. Time required for this retrofit is around
90days . However, this work will be taken up only after retrofitting of
electromagnetic relays with numerical relays for Main-2 protection of
all 220kV lines, for which work is in progress.
KPCL1. KPCL to check the operation of anti-
pumping relay on 220 kV side and keep it in
healthy condition.
2. KPCL to provide manual reset to the 220 kV
side master trip relay.
3. KPCL to use both the 220 kV buses as main
buses under normal operation, and should go
for single bus operation only during
emergencies.
07-06-2015
at 01:35 hrs
Trippings at
220kV
Raichur TPS
46/II/21
Annexure-III
Page 8 of 24
47/III/8 Tripping of
220kV
Ambewadi-
Ponda line-2
02-08-2015
at 13:20 hrs
Line tripped on a transient fault in
B-phase. There is no
provision for auto reclose.
47/III/10 Tripping of
220kV
Ambewadi-
Ponda line-1
08-08-2015
at 10:51
hrs and 09-
08-2015 at
11:15 hrs
Line tripped on a B-phase to earth
fault. Line tripped as there is no
provision for auto-reclose
47/III/12 Tripping of
220kV
Ambewadi-
Ponda line-1
17-08-2015
at 13:20 hrs
Line tripped on a transient fault .
There is no provision for Auto
reclose.
Complete
outage of
220kV
Peenya
Substation in
Karnataka
48/I/2
(GD)
PendingYet to be informedKPTCL KPTCL to revise distance relay settings at
Nelamangala end for 220 kV Nelamangala –
Hebbal - Peenya line – 1 for the effective line
length of 17 km. These new settings can be
appropriately reviewed as and when the tie-
arrangement at Hebbal is done away with.
All connected 220kV lines and
transformers were taken on 220kV
North bus as South bus was under
shut down for conversion of strung
bus to rigid bus and isolator
replacement under R&M works.
Failure of HV side Y phase CT of
150MVA Transformer-3 occurred
at Peenya Substation which
resulted in operation of Differential
and HV REF protection. The
failure of CT also resulted in a
220kV bus fault in North Bus.
27-09-2015
at 4:23:17
hrs
PendingYet to be informedKPTCLKPTCL to activate non-directional Over
Current protection with a time delay of 600-
800 msec for Fuse
failure condition at Lingasugur.
Till A/R is put into service on Ambewadi-
Ponda line-1, KPTCL to reduce Zone-2 time
setting to zero sec. at Ambewadi end.
KPTCL Yet to be informed Pending
220kV RTPS-Lingasugur line-2
tripped at TPS end on operation of
distance protection zone-1.
400/220kV ICT-2 got tripped on
operation of earth fault protection.
220kV RTPS-Lingasugur line-
1&3 tripped on distance protection
zone-2 and zone-3 respectively.
Due to
tripping of ICT-2, the running units
got overloaded and it was
mentioned that under frequency
occurred as units are on load
control. The Units got tripped
on under frequency.
06-08-2015
at 4:51 hrs
Tripping of
Unit-1&2
along with
400/220kV
ICT-2 at
Raichur TPS
47/II/13
Annexure-III
Page 9 of 24
48/I/3
(GD)
Outage of
220kV
Ambewadi
station in
Karnataka
30-09-2015
at 10:41 hrs
220kV Ambewadi-Nagjheri line-2
tripped on B-phase to earth fault.
This resulted in loss of supply to
220kV Ambewadi bus. 220kV
Ambewadi-Ponda line-1&2 were
hand tripped after deenergization
of bus at Ambewadi.
KPTCL to fast-track providing A/R on all 220
kV lines emanating from Ambewadi SS to
prevent Station shut-down on temporary faults.
KPTCL Yet to be informed Pending
48/I/4
(GD)
Complete
outage of 220
kV HSR
substation of
Karnataka
06-10-2015
at 16:32 hrs
All connected 220kV lines at
220kV HSR substation i.e.
Somanahalli, EPIP, Hoody and
Nagnathapura tripped during the
incident. Triggering incident was
fault in 220kV HSR-EPIP line
KPTCL to review distance relay settings at
Naganathpura SS in view of LILO arrangement
at HSR Lay-out.
KPTCL Yet to be informed Pending
49/II/15 Trippings at
Raichur TPS
12-11-2015
at 00:30 hrs
Running Unit-4, 5 and Unit-8 and
400kV RTPS-Yeramaras TPS
feeder got tripped due to de-
energization of both 400kV Bus-
1&2 at Raichur TPS
1. KPCL to carry out hot-line washing of RTPS-
connected lines regularly to avoid trippings due
to fog and dust.
2. KPCL may see the feasibility of providing
breaker flashover protection at RTPS, and
implement the same if possible.
KPCL Yet to be informed Pending
49/III/5 Tripping of
400kV
Kaniyambeta-
Kadakola line
28-10-2015at
12:08 hrs
Line tripped on a Y-phase to earth
fault. There is no provision for auto-
reclose
• KPTCL to provide A/R on Kadakola –
Kaniyampeta line at Kadakola end.
KPCL Yet to be informed Pending
Pending1. KPCL to provide A/R on all 220 kV lines
emanating from Nagjheri PH.
2. KPTCL to provide A/R on all 220 kV lines
emanating from Ambewadi SS.
220kV Nagjheri-Ambewadi line-1
tripped at 13:33 hrs due to B phase
to earth fault. Ambewadi was
radially fed from Nagjheri power
station through 220kV Nagjheri-
Ambewadi line-2. Tripping of this
line caused 220kV Bus shut down
at Ambewadi and remaining lines
and transformers were hand tripped
29.10.2015
at 14:34 hrs
Complete
outage of
220kV
Ambewadi
Substation of
KPTCL
49/I/1.3
(GD)
Yet to be informedKPTCL
Annexure-III
Page 10 of 24
45/II/12 Multiple
tripping at
400/230kV
Alamathy
substation
25-05-2015at
09:08hrs
As per FIR, failure of R-phase CT
of 230kV Alamathy-Manali feeder
occurred at Alamathy end. Hence
230KV BBP Zone 1 & 2 Operated
at Alamathy substation. All the
230KV feeders, 230KV BC, ICT-3,
4 & 5 LV breakers got tripped.
TANTRANSCO to furnish a detailed tripping
report including reasons for delayed clearance
of fault at Almathy.
TANTRANS
CO
Mail received on 03-09-2015:
The faults were cleared with out time delay at Alamathy SS. Detailed
Tripping report sent vide Lr.No.CE/P&C/SE/D/
EPC4/AEE3/F.SRPC/ D.21/15, dated 14.07.2015.
The reasons for the delayed clearance of the third fault not
furnished.
Pending
48/I/1
(GD)
Disturbance
in 220kV
Tamilnadu
system
05-09-2015
at 14:04 hrs
Complete outage of 230kV
Palladam, 230 kV
Othakalmandapam S/s, 230 kV
Coimbatore S/s, 230 kV Thudialur
and 230 kV Sadayapalayam S/s
TANTRANSCO to take suitable measures like
installing more stub-towers along 230 kV OK
Mandapam – Myvady line to avoid excessive
sag due to over-loading.
TANTRANS
CO
Yet to be informed Pending
48/II/6 Tripping of
400/220kV
Alamathy
ICT-3,4&5
07-09-2015
at 04:24hrs
Triggering incident was failure of
Y & B phase CT failure in 230kV
Korattur feeder
1. TANTRANSCO to furnish a detailed report
on the tripping event covering the sequence of
events, and the remedial measures taken to
PCSC forum.
2. TANTRANSCO to configure Bus-Bar
protection at Alamathy for instantaneous
operation.
TANTRANS
CO
Yet to be informed Pending
PendingTANTRANSCO vide their mail dated 24.06.15 informed that
different relays in Main-I & Main-II would be ensured at the earliest.
Mail recieved on 24-07-2015:
Different relays in Main-I & Main-II will be ensured.
TANTRANS
CO
TANTRANSCO was requested to swap the
relays between two stations, so that
Main-1 and Main-2 will be of different make at
each station.
Line-2 tripped on R-phase to earth
fault.
Line autoreclosed at SVChatram
end and failed to reclose at
Alamathy end. Bphase to earth
fault in line-1. Line tried for A/r
but due to permanent fault line did
not reclose. ICT tripped on
operation of over flux protection.
29-03-2015
at
15:29 hrs
Tripping of
400kV
Alamathy-
SVChatram
line-1&2
and
400/230kV
ICT
at
S.V.Chatram
43/II/5
Tamil Nadu
Annexure-III
Page 11 of 24
49/II/3 Tripping of
220kV
Edamon-
Tirunelveli
line-1&2
12-10-2015
at 21:30 hrs
220kV Edamon-Tirunelveli lines -
1&2 got tripped due to operation of
Bus Bar protection which was due
to human error
KSEB to furnish reasons for DT not being
sent to the remote end during the tripping event
along with remedial measures taken to PCSC
forum.
KSEB Yet to be informed Pending
49/III/1 Tripping of
220kV
Sabarigiri-
Theni line
09-10-2015
at 16:56 hrs
Line tripped on a R-phase to earth
fault. At Sabarigiri, relay gave a 3
phase trip after 220ms. From Theni
end D.R, auto reclose block was
observed.
KSEB to furnish a report on the tripping
incident along with the remedial measures
taken to PCSC forum.
KSEB Yet to be informed Pending
PendingYet to be informedTANTRANS
CO
1. TANTRANSCO to ensure correctness of
operation of LBB relays at SP Koil.
2. TANTRANSCO & MAPS to furnish their
respective compliance report of the
recommendations of to-be-conducted PSAG-14
meeting at MAPS, Kalapakkam.
Fault had occurred in 230kV
MAPS-S.P.Koil feeder-1. LBB
protection got operated as breaker
of this feeder was under lockout
and resulted in tripping of 230kV
bus at S.P.Koil. Unit-1&2 at
MAPS due to loss of evacuating
feeders i.e. 230kV MAPS-S.P.Koil
feeder-1&2
09-11-2015at
09:33 hrs
Complete
outage of
S.P.Koil
station of
TANTRANS
CO and
generation
loss at
Madras
Atomic
Power
station(MAP
S)
49/I/1.5
(GD)
KeralaMail recieved on 30-10-2015:
1. Purchase procedures is still in progress.
2. Replaced.
3. PLCC equipment Tested and found OK.
Pending
(Recomm
endation
No.1)
44/I/1
(GD)
Complete
outage of
Idukki Hydro
Power Station
(GD-1)
28-04-2015
at 12:30 Hrs
220 kV breaker of unit-3 at Idukki
Power
house flashed and bus differential
protection
acted. All Generators (6Nos.) along
with all
220 kV feeders tripped during the
incident.
1. KSEB to reduce sensitivity of REF
protection appropriately at Idukki PH.
2. KSEB to replace/ repair the faulty breaker.
3. KSEB to check the PLCC equipment at New
Pallam and inform the remedial measures taken
to PCSC forum.
KSEB
Annexure-III
Page 12 of 24
41/III/2 Tripping of
400kV
Udumalpet-
Palakad line-
1& 400
Udumalpet-
Arasur line-2
09-02-2015
at 9:50hrs
PLCC of Udumalpet-Arasur-2 mal-
operated
• PGCIL to furnish remedial measures taken.
• PGCIL to properly tune PLCC panels.
PGCIL Mail received on 25-11-2015:
The issue was referred to BPL and OEM suggested to upgrade the
panels with design modifications. LOA has been placed on BPL for
the same. Work is expected to be completed by Nov'15 end.
Pending
42/II/22 Tripping of
HVDC pole-
1&2
at Gazuwaka
and 400kV
Jeypore
Gajuwaka
line -1
14-03-2015
at
17:12 hrs
HVDC Pole-1 at Gazuwaka tripped
due to
tripping of filter banks and Pole-2
tripped due to operation of
differential protection.
400kV Jeypore-Gazuwaka line-1
tripped on over-voltage from
Gazuwaka end.
PGCIL (SR-I) to furnish the reasons for
Converter Transformer differential protection
operation for Pole-2 along with the remedial
measures taken.
PGCIL Reply received during 46th PCSC meeting:
Operation is in-order as per OEM manual (ABB HVDC)
Pending
PGCIL34/I/7 HVDC
BHADRAV
ATHI POLE
2
18-07-2014 As reported pole-2 tripped due on
5th harmonic alarm.
1. Complete analysis of the faults and
rectification/remedial action taken to avert
similar occurrence in the HVDC Back to Back
station shall be submitted.
2. The PCSC forum recommended PGCIL,
SRTS-I take up the issue with WRTS to submit
the report as per IEGC guidelines.
3. SRLDC is also requested to send a letter to
WRLDC to submit the reports to SR also.
4. Based on the SRTS/SRLDC
correspondences, SRPC would take it up with
WR and PGCIL if the issue is not getting
resolved.
PGCIL Reply received during 46th PCSC meeting:
Being pursued with POWERGRID, WR-1
Pending
Pending42/II/7 Yet to be informedPGCILPGCIL (SR-II) to submit the report of M/s
ABB’s on preventing supply card failures.
HVDC pole-1 got tripped due to
failure
of 4 no. power supply card. HVDC
pole-2 tripped on DC low voltage
trip.
400kV Jeypore-Gazuwaka line-
1&2
tripped due to operation of Over
voltage
protection at Gazuwaka end.
23-02-2015
at
13:34 hrs
Tripping of
400kV
Jeypore-
Gazuwaka
line-
1&2 and
tripping of
HVDC back
to back pole-
1&2 at
Gazuwaka
Annexure-III
Page 13 of 24
42/II/23 Tripping of
HVDC
Bhadravathi
Pole-1
18-03-2015
at
13:55 hrs
Pole tripped due to failure of
auxiliary supply
PGCIL (SR-I) to submit the compliance report
on PSAG-11 recommendations to PCSC
forum.
PGCIL Reply received during 46th PCSC meeting:
Tertiary Transformer charged and auxiliary power for HVDC is being
availed from tertiary widings of ICT.
Pending
Annexure-III
Page 14 of 24
44/I/3
(GD)
765 kV
Raichur-
Sholapur line
1 &
2 tripped
24-05-2015
at 19:19 hrs
Tripped on Overload. 1. PGCIL to provide the status of healthiness of
SPS contact logic in SRLDC’s SCADA.
2. PGCIL to furnish the details of the
implemented SPS-7 scheme including logic
diagram to PCSC forum.
PGCIL Yet to be informed Pending
43/II/2 Multiple
tripping
at 400/230kV
Hosur
substation
of Powergrid
26-03-2015
at 15:40 hrs
230kV Bus-2 at Hosur (PG) got
tripped as spurious initiation got
extended to LBB relay of 230kV
Hosur-Hosur(PG) line at
Hosur(PG) end due to shorting of
contacts in lockout relay.
400/230kV ICT-2, ICT-3, 230kV
Hosur-Vinnamangalam,
230kV Hosur(PG)-Hosur which
were connected to Bus-2 got
tripped along with bus coupler
breaker
PGCIL (SR-II) to check the possibility of
providing re-trip feature in LBB relay.
PGCIL Mail received on 02-09-2015:
The scheme was tested thoroughly found normal.
Pending
PendingYet to be informedPGCILPGCIL (SR-I) to check healthiness of PLCC
panels at Hyderabad SS, and repair/ replace
them, if necessary.
400kV Ramagundam-Hyderabad
line-3 at
ramagundam end only due to DT
receive.
400kV Hyderabad-Malkaram line-
1
tripped at Hyderbad end only and
was
holding from Malkaram end.
400kV Bus-1 at Hyderabad due to
operation of bus
bar protection.
23-04-2015
at
15:11 hrs
Tripping of
400kV
Ramagundam-
Hyderabad
line-3,
400kV
Hyderabad-
Malkaram
line-1 and
400kV Bus-1
at Hyderabad
44/II/4
Multiple
tripping at
Vemagiri
substation of
APTRANSC
O
44/II/6 PendingYet to be informedPGCIL1. PGCIL (SR-I) to enable Auto reclosure
feature at Vijayawada end.
2. PGCIL (SR-I) to check distance relay
settings for Vijayawada – Vemagiri line 3, and
furnish a compliance report to PCSC forum.
400kV Vemagiri-Vijayawada line-
1&3, 400kV Vemagiri-Goutami
line-2, 400kV Vemagiri-
Konaseema line-2 and 400/220kV
ICT-2 at Vemagiri tripped
during the incident. Triggering
incident
was failure of B-phase L.A in
400kV
Vijayawada-Vemagiri line-1 at
Vemagiri end.
25-04-2015
at 10:04
hrs
Annexure-III
Page 15 of 24
44/II/7 Tripping of
765kV
Kurnool-
Tiruvalam
line-1
and 765kV
Kurnool-
NPS-1
25-04-2015
at
18:10 hrs
REF protection of Line reactor of
Nellore-1&2 and Tiruvalam line-1
maloperated
due to DC earth fault
1. PGCIL (SR-I) to submit the action taken
report on the measures suggested by their
OEM.
2. PGCIL (SR-I) to check for the availability of
Chatter Disable feature in P141 and
configure it appropriately to block operation of
REF protection on DC fluctuations.
PGCIL Yet to be informed Pending
44/II/8 Tripping of
400kV
Gooty-NPS
line-2
26-04-2015
at 13:16
hrs
R-phase to earth fault had occurred
in
line. Lines auto-reclosed at gooty
end
and later tripped due to DT receive
from
NPS end.
PGCIL (SR-I) to coordinate STUB protection
settings with the distance protection time
settings at NPS.
PGCIL Yet to be informed Pending
45/II/21 Tripping of
400/220kV
ICT-1 at
Gooty
Substation
03-06-2015
at 12:30 hrs
ICT tripped due to mal-operation
of differential relay
1. PGCIL to follow IS and CEA regulations
while carrying out maintenance work.
2. PGCIL to furnish a report on what caused
the ICT-1 tripping including remedial
measures.
PGCIL Yet to be informed Pending
PendingYet to be informedPGCILTo avoid tripping of transmission lines on
transient faults, PGCIL is recommended to
carry out periodic patrolling of lines, and
ensure their proper maintenance by carrying
out jungle/ bushing clearance and trimming of
tree branches within the RoW of transmission
lines as per the SRPC transmission line
patrolling guidelines (available under the menu
item "All Uploads Operation
Miscellaneous Transmission Line Patrolling
Protocol / Guidelines for Southern Region" on
SRPC website).
Lines tripped on transient fault.
Auto reclose was un-successful. SR
&NEW grid separated due to
tripping of 765kV lines
03-05-2015
at 4:13 hrs
Tripping of
765kV
Raichur-
Solapur line-
1&2
45/II/15
Annexure-III
Page 16 of 24
46/II/1 Tripping of
400/220kV
ICT-2 at
Nagarjunsaga
r Station
16-06-2015
at 18:12
hrs& 19:18
hrs
ICT-2 tripped due to mal-operation
of 86B relay due to suspected DC
earth fault.
PGCIL (SR-I) to furnish a detailed report on
ICT-2& Bus II outage at 19.18 hrs on
16.06.2015 along with the remedial measures
taken.
PGCIL Yet to be informed Pending
46/II/4 Tripping of
400/220kV
ICT-2 at
Gooty
substation
22-06-2015
at 13:06 hrs
At 220kV Gooty Switching
Station, 220KV Gooty Receiving
Station feeder line side Y-Phase
jumper connected between line
isolator to boom resulting in a
220kV Bus fault. This resulted in
tripping of ICT-2 and 220kV
feeders connected to 220KV BUS-
II
PGCIL (SR-I) to furnish a detailed report as to
what caused LBB operation at 400 kV Gooty
SS along with the remedial measures taken.
PGCIL Yet to be informed Pending
Tripping of
HVDC
Talcher-Kolar
Pole-2.
45/II/29
PendingYet to be informedPGCIL1. PGCIL (SR-I) to furnish a report detailing
the sequence of events including the remedial
measures taken to PCSC forum.
2. PGCIL (SR-I) to verify and ensure time-
synchronizationof DR& EL with GPS at both
Gooty and NPS.
3. PGCIL (SR-I) to check and resolve,in co-
ordination with APTRANSCO, the professed
Phase-Discrepancy that is found to be
occurring between 400 kV Gooty (PG) SS and
the surrounding 220 kV network of
APTRANSCO in the event of a fault.
Breaker at NPS end tripped on
Direct Trip receipt from NPS end.
After 4 seconds, over voltage
protection operated at NPS end as
observed from EL, and direct trip
was sent to Gooty.
01-07-2015
at 09:59 hrs
Tripping of
400kV Gooty-
NPS line-1
46/II/13
PendingMail received on 25-11-2015:
Major Shut Down of HVDC Bi-pole line for replacement of insulators
in Polluted Streched is planned from 07th 11th January-16 scheduled.
PGCILTo avoid tripping due to transient faults,
PGCIL (SR-I) is recommended to carry out
periodic patrolling of lines, and ensure proper
maintenance of transmission lines by carrying
out jungle/ bushing clearance and trimming of
tree branches within the RoW of transmission
lines as per the ‘SRPC transmission line
patrolling guidelines’ (available under the
menu item "All Uploads Operation
Miscellaneous Transmission Line Patrolling
Protocol / Guidelines for Southern Region" on
SRPC website).
DC line fault26-05-2015
at 17.55 hrs
Annexure-III
Page 17 of 24
47/II/11 Tripping of
HVDC
Bhadrawati
Pole-1
05-08-2015
at 10:53 hrs
Main pump-2 of valve cooling got
tripped during dip in 33kV
auxiliary bus
voltage. Valve cooling flow got
reduced
due to tripping of pump and
resulting in
tripping of pole-1
PGCIL (SR-I) to furnish compliance report on
PSAG-11 recommendations without further
delay to PCSC
forum.
PGCIL Yet to be informed Pending
765 kV
RAICHUR -
SHOLAPUR
1 and 2
04-09-2015
at
19:25 hrs
Sholapur -1 and 2 Feeder got
tripped at Raichur end on operation
of over current
protection in Main-1 distance relay
and holding from Solapur end on
04.09.2015 at
19:24:42 Hrs
765 KV
RAICHUR –
KURNOOL 2
04-09-2015
at
19:25 hrs
Kurnool -II Feeder got tripped on B-
N fault and holding from Kurnool
end (successfully auto-reclosed at
Kurnool end) subsequently tripped
at other end on operation of OV stg-
1 protection at Raichur end on
04.09.2015 at 19:24 Hrs
49/II/4 Tripping of
400kV Gooty-
NPS line-1
13-10-2015at
10:15 hrs
DT was sent to NPS end of line-1
during opening of Main CB of
Gooty-NPS line-2 at Gooty end.
This resulted in tripping of line-1
at NPS and line was holding from
Gooty. OV protection got operated
at NPS end and resulted in tripping
of line
1. PGCIL (SR-I) to configure time scale
resolution in Event Logger to msec. at Nelllore
PS (NPS) and furnish DR corresponding to
OVR, Stag-I operation at NPS end during the
tripping event.
2. PGCIL (SR-I) to ensure time-sync of DR’s
and EL’s with GPS at Gooty & NPS.
PGCIL Yet to be informed Pending
47/II/18 1. PGCIL (SR-I) to check the A/R scheme
implemented through BCU’s at all its GIS/
SAS substations for correct
operation.
2. PGCIL (SR-I) to ensure time-
synchronization of DR & EL of 765 kV
Kurnool SS with GPS.
3. PGCIL (SR-I) to sort out the LEGEND
ISSUE related to tripping of the lines in the
Event Logger of Raichur.
4. PGCIL (SR-I) to check & ensure the
functionality & healthiness of synchronization
facility at Raichur end at
the earliest opportune time.
PGCIL Yet to be informed Pending
46/II/22 PendingYet to be informedPGCIL1. PGCIL (SR-I) to obtain from PGCIL (WR-l)
the reasons for DT receipt from Sholapur end
and furnish thesame along with the remedial
measures taken to PCSC forum.
2. PGClL (SR-I) to verify the logic
implemented of SPS-1 and SPS-7 for the 76S
kV Raichur - Sholapur link byavailing the line
shutdown at the earliest opportune time.
3. PGCIL (SR-I) to furnishthe details of the
implemented SPS-1 and SPS-7 schemes
including their logicdiagrams to PCSC forum.
28-07-2015
at 11.52.22
hrs.
Separation of
SR-grid and
NEW-grid
Annexure-III
Page 18 of 24
41/II/12 Tripping of
400KV
Coastal-
NTPL line
13-02-2015
at 22:54 hrs
Line tripped B-phase to earth fault
and later tripped on R-Y phase
fault. From Coastal end D.R, Y &
B poles of breaker opened first and
R-pole appears to be opened on
Pole discrepancy.
CEPL to check A/R scheme at their end. CEPL Yet to be informed Pending
41/IV/2 400kV
Tuticorin PS-
NTPL line
09-02-2015
at 03:17 hrs
Y-phase to earth fault had occurred
in line. Line auto reclosed at
Tuticorin PS end and failed to
reclose at NTPL end.
NTPL to check A/R scheme at their end. NTPL Yet to be informed Pending
44/III/4 Tripping of
400kV
Coastal
(CEPL)-
Tuticorin
pooling
station
20-04-2015
at 12:35 hrs
Line tripped at Coastal energen end
only and was holding from
TTRNPS
CEPL to furnish a detailed report on this trip
event to PCSC forum.
CEPL Yet to be informed Pending
46/II/3 Tripping of
400kV
Ramagundam-
Dichipalli
line
21-06-2015
at 03:27 hrs
Line tripped on operation of
overvoltage protection at
Ramagundam end and direct trip
was received at Dichipalli. Over-
voltage operation could not be
established with D.R & E.L
submitted by Ramagundam station.
1. NTPC, Ramagundam to investigate the
reasons for OV alongside checking the drop off-
to- pick-up ratio of the OV relay.
2. The tripping is not as per the grading
adopted for OV, Stage-I protection (Grading is
C2: 110% and 6 sec time delay) at
Ramagundam. NTPC, Ramagundam to check
up the same.
NTPC Yet to be informed Pending
47/III/2 Tripping of
400kV
Vemagiri –
GVK (JPD)
line-2
16-07-2015
at 17:02 hrs
R-phase to earth fault had occurred
in line. Line auto reclosed at
Vemagiri end and failed to reclose
at GVK end.
GVK to put A/R into service at GVK
Jegurupadu end on 400 kV GVK (Jegurupadu)
– Vemagiri line-2.
GVK Yet to be informed Pending
48/II/16 Tripping of
400 kV
Hassan -
Udupi line-1
05-10-2015
at 13:33
Line tripped due to B-E fault in Z2.
Main 1 relay tripped in Z2. 3 phase
trip operated at Hassan. AR
successful at other end and line
was charging from other end. Then
OV stage 1 picked up in Main2
relay and operated in OV after the
time delay
UPCL to furnish reasons for delayed operation
of distance relay in Zone-1 at their end, and the
remedial measures taken, if any.
UPCL Mail recieved on 19-11-2015 (UPCL):
The fault was of resistive nature, was sensed from Hassan end in Zone-
2 reach. The DR from UPCL indicates resistive high current prior to
operation of Zone-1 in C Phase. This is seen as development of Zero
sequence voltage and current prior to Zone -1 operation.
The operation of single phase Z1 from UPCL end was correct
followed by successful AR operation.
Pending
Others
Annexure-III
Page 19 of 24
36/II/8 400kV
Raichur-
Munirabad
line
07-09-2014 B-phase to earth fault had occurred
in line.
Line auto reclosed at Munirabad
end and failed to reclose at Raichur
end.
KPTCL:
PD (pole discrepancy) time delay would be
changed.
PGCIL /
KPTCL
Yet to be informed Pending
38/II/5 400kV
Ramagundam-
Hyderabad
line-4
27-10-2014 Line tripped on Bphase
to earth fault.
Line did not auto
reclose at Hyderabad
end due to
PLCCmal-operation.
Planned to replace the PLCC system within a
week's time at both the ends during the
shutdown.
NTPC/
PGCIL
Yet to be informed. Pending
Miscellaneous
39/I/2 Tripping of
400Kv
Ghanapur-
Mamidipally
line
22-12-14
at 10:52 hrs,
24-12-14 at
11:32
hrs,
24-12-14 at
16:16 hrs
Due to PLCC Mal-operation at
HYD S/S end, DT received at
MMPLY end and line got tripped.
PGCIL is requested check up with the
manufacturer to resolve the issue and submit
remedial measures to PCSC forum.
PGCIL/
TSTRANSC
O
Mail received on 26-05-2015 from TSTRANSCO:
On 27-12-2014 PGCIL requested to arrange services of
OEM(Manufacturer)for identifying the problem. TSTRANSCO
arranged the same on 06-01-2015 and the manufacturer testing and
concluded that the problem in not in the newly erected digital
protection coupler at both ends and the issue is related to relay panel
at Ghanapur. [OEM minutes enclosed]
Pending
Annexure-III
Page 20 of 24
40/II/3 Tripping of
400
kV
TALAGUPP
A
– HASSAN
line
01-01-2015
at
13:38 hrs
On account of R-phase to earth
fault, line tripped at Hassan end
due to operation of distance Zone-2
and non-receipt of
carrier. From D.R of Talaguppa
end it is observed that fault had
occurred in Yphase.
1. PGCIL and KPTCL to ascertain the reason
for the phase discrepancy in the relay
operation and take suitable remedial measures.
2. KPTCL to check the PLCC operation at
Talaguppa end and submit the report to the
PCSC forum.
PGCIL/
KPTCL
Mail received on 27-05-2015 (KPTCL) & 29-07-2015:
End to end testing of PLCC has been done and problem in the PLCC
is atttended. Phase
discripancy in the relay operation is to be checked jointly.
Mail recieved on 02-09-2015:
Problem is in identification of phases at Talguppa end. To be rectified
by M/s KPTCL.
Pending
41/I/2 Complete
outage at
220kV
Bahoor
Substation of
Pondicherry
(GD-1)
15-02-2015
at 11:20 hrs
Bus fault occurred in 110kV bus at
230/110kV Bahoor substation due
to failure of Y-phase main bus
strain insulator. 220kV lines
connected to Bahoor (viz., Bahoor-
NLC TPS II and Bahoor – Pondy)
tripped from remote end on
operation of B/U protection.
1. PED to investigate the cause of non-
operation of ICT’s protection system
(differential protection, back-up protection)
and review the relay settings suitably.
2. PGCIL to check the settings of distance
relay and back-up relays for correctness of
operation.
PED/PGCIL Mail received on 02-09-2015 and 25-11-2015:
All the relay settings were checked and found ok
Pending
with
PED.
42/II/1 Tripping of
400kV
Coastal-
Tuticorin PS
line
19-02-2015
at
16:37 hrs
Line tripped at Coastal end only
due to suspected PLCC
maloperation
and was holding from
Tuticorin PS end. Running Unit at
Coastal energen also got tripped
during the event.
PLCC end-to-end testing shall be carried out by
CEPL and Tuticorin PS (PGCIL-SR II) by
06.04.2015.
CEPL/
PGCIL(SR-
II)
Mail received on 02-09-2015 and 25-11-2015:
On 11.06.2015 PLCC testing carried out by M/s ABB Engineer. ABB
suspects that the problem is with frequency interference related issue,
and suggested to change to new frequecies.
Pending
with
CEPL
Annexure-III
Page 21 of 24
43/II/12 Multiple
tripping at
400kV
Raichur(PG)
and RTPS of
KPCL
11-04-2015at
18:04 hrs
400kV Raichur(PG)-Gooty line-2,
400kV Raichur TPS-Raichur(PG)
line-1&2, 400kV Raichur-
Mahboobnagar, Unit#5 at RTPS
tripped during the incident
KPCL, KPTCL and PGCIL (SR-I) to furnish
the action taken report on the
recommendations given by PSAG members
held at Raichur on 22-04-2015 and
23-04-2015.
KPCL/KPTC
L/ PGCIL(SR-
I)
Yet to be informed Pending
Tripping of
Unit 1 at
NCTPS
24-05-2015
at 19:13 hrs
ID Fan trip
Tripping of
Unit 1 at
MEPL
24-05-2015
at 19:13 hrs
Coal Mill tripped
Tripping of
Unit 1 at
Krishnapatna
m
24-05-2015
at 19:17 hrs
Generator Protection operated
Tripping of
Unit-8 at
RTPS
24-05-2015
at 19:19 hrs
Tripped on Overvoltage.
Mail received on 26-05-2015 from TSTRANSCO:
It is found that the main-2 ABB make REL316 type distance relay
was defective and same was replaced with MICOM P444 by
M/s.PGCIL on 23.04-2015. After replacement of main-II, DR can be
extracted from this relay. For EL in to service, some field winding is
pending which is being taken up in this month.
Pending
44/I/3
(GD)
1. All Tripped units, viz., Krishnapatinam,
MEPL, Raichur, NCTPS to submit a detailed
report
on this event including the remedial measures
taken to PCSC forum.
2. KPCL to check the excitation system of Unit
8 of RTPS, and submit the remedial measures
taken to PCSC forum.
KPCL/
MEPL/
APGENCO/
TNEB
TANGEDCO vide their mail dated 07.07.2015 informed that as per
the discussion and recommendation of 44th meeting of PCSC held on
28.05.2015, a time delay of 2 Sec had been introduced for the above
tripping for all the ID fans at NCTPS-II.
MEPL vide their mail dated 14.09.2015 informed that they have
implemented 2 seconds delay for under voltage tripping of all Drag
Chain Feeder Conveyors. And this has been done for both the Units.
Pending
with
KPCL,
APGEN
CO
42/II/18 Multiple
tripping at
Raichur
thermal
power station
of
KPCL
09-03-2015
at
06:36 hrs
400kV Raichur TPS-Raichur(PG)
line-
1&2, 400kV Raichur-
Mahboobnagar,
Unit#7 and ICT-2 at RTPS tripped
during the incident. B phase to
earth
fault had occurred in 400kV
Raichur
TPS-Raichur line-1
1. KPCL to review REF setting (DMT or
IDMTL) for unit-7 by first week of April, 2015
and
inform the same to PCSC forum.
2. TSTRANSCO to furnish Mehaboobnagar’s
DR and EL and the reasons for distance relay
operation at their end within a week’s time.
3. PGCIL (SR-I) to rectify the issues relating to
A/R operation, relay reach (Z2), reverse reach
(Z4) and SOTF auxiliary contacts within a
week’s time, and submit the actions taken to
PCSC forum.
KPCL/TSTR
ANSCO/PGC
IL (SR-I)
Annexure-III
Page 22 of 24
Complete
outage of
Krishnapatna
m TPS
47/I/2
(GD)
PendingMEPL vide their mail dated 14.09.2015: informed the following
1. Tan Delta Testing of winding and DGA of Insulating Oil for all
CTs was carried out and normal.
2. Could not find any problem during internal checks hence we are in
touch with ABB for rectification work. Will be done by the end of
15th Oct'15
3. End to end testing of Carrier signals was carried out and found
them healthy.
MEPL/
PGCIL(SR-
I)/ SEL
1. MEPL to ensure healthiness of all CT’s by
carrying out Tan Delta and DGA tests wherever
necessary.
2. MEPL to take suitable action to correct the
operation of tie-CB Bay Control Unit that
caused LBB/ BBP operation.
3. PGCIL (SR-1) to carry out end-to-end
PLCC testing in coordination with MEPL and
ensure that carrier-aided protection on MEPL –
NPS line is in healthy condition.
4. SEL to properly time-coordinate their Over
Current phase and Earth fault relays in
consultation with MEPL.
Y phase CT failure at MEPL led to
tripping of 400kV NPS-MEPL,
400kV SEPL-MEPL line and Unit-
2 at MEPL. Uni-1 was not in
service at the time of tripping
20-05-2015
at 20:38 hrs
Complete
outage of
MEPL power
station
45/I/2
(GD)
Tripping of
220kV Kadra-
Karwar line-
1&2 and
220kV
Kaiga-Kadra
line
47/II/7 PendingYet to be informedKPTCL/
KPCL/
NPCIL
1. KPTCL/ KPCL to see the possibility of
implementing Weak Infeed logic with Echo
feature enabled by Under
Voltage (27) element on Kadra-Karwar lines 1
&2, and implement the same if feasible.
2. NPCIL to time-coordinate Kaiga’s DEFR
settings with (i) Zone-2 settings at Kaiga, and
(ii) primary protections of the lines emanating
from Kadra and Kodasalli.
3. KPCL to ensure time-sync of EL’s, and
healthiness of the Fault Locators at Kadra.
220kV KAdra-Karwar lines-1&2
tripped on earth fault in B-phase in
zone-2.
Kaiga-Kadra line tripped at Kaiga
end only on operation of
directional eath
fault protection.
31-07-2015
at
11:44 hrs
PendingYet to be informedAPGENCO/
PGCIL (SR-
I)
1. APGENCO to furnish to PCSC forum (i) A3-
size SLD of SDSTPS, and (ii) the sequence of
events with time stamp showing the protection
that opened Tie-CB (405) at SDSTPS.
2. APGENCO to review STUB/TEED
protection in all dias at SDSTPS and ensure
that they are configured for instantaneous
operation.
3. APGENCO to properly configure the STATE
of the tripping events so that they get recorded
appropriately like TRIP/ OPERATED in their
corresponding EL.
4. APGENCO to ensure time sync of all DR’s
and EL’s at SDSTPS.
5. PGCIL (SR-I) to provide line differential
protection for 400 kV NPS –Nellore-PG lines 1
& 2.
As per FIR submitted, CT damage
observed in Chitoor-Main bay
(404). Main breakers connected to
bus-1 (401, 404, 407, 410) got
tripped on operation of bus bar
protection. Unit-1 tripped on
operation of MFT. Unit-2 was not
in service
08-09-2015
at 18:20 hrs
Annexure-III
Page 23 of 24
48/III/11 Tripping of
400 kV
Kurnool –
Srisailam line
03-10-2015
at 04:40 hrs
on
Tripped at both ends on Y-Phase to
ground zone-1fault. Attempt for
auto-reclose could not be
established.
TSGENCO/ APTRANSCO to carry-out PLCC
end-to-end testing in co-ordination with
APTRANSCO/ TSGENCO to sort out
reception of signals on 400 kV Kurnool –
Srisailam line.
TSGENCO/
APTRANSC
O
Yet to be informed Pending
49/II/11 Tripping of
400/220 kV
ICT-2 at
Kurnool
Substation
and 400kV
Kurnool-
Srisailam line
26-10-2015
at 14:31 hrs
400kV Kurnool-Srisailam line -
distance protection zone-2 had
operated at Srisailam end.
However from DR, R-phase to
earth fault and zone-2 start were
observed. Breakers at Kurnool end
tripped on direct trip receive from
Srisailam end.
ICT-2 Main-CB tripped due to
operation of bus bar protection,
and Tie-CB tripped due to DT
receipt from Srisailam
1.TSGENCO in coordination with
APTRANSCO to carry out end-to-end testing
of PLCC channels by 15.12.2015 on 400 kV
Srisailam – Kurnool S/C line and 400 kV
Srisailam – Sattenapalli D/C line.
2. TSGENCO and APTRANSCO to make A/R
functional on 400 kV Srisailam – Kurnool line.
3. TSGENCO to resolve configuration
problems with the newly commissioned relays
at Srisailam LB so that unwarranted DT
sending to remote ends is addressed.
TSGENCO/
APTRANSC
O
Yet to be informed Pending
Tripping of
220kV Kadra-
Karwar line-
1&2 and
220kV
Kaiga-Kadra
line
47/II/7
PendingYet to be informedNTPL/ CEPL1. NTPL to ensure (i) proper DATE settings,
and (ii) time-sync with GPS for DR and EL at
NTPL.
2. CEPL to furnish remedial measures taken
regarding PLCC channel failure.
R-phase to earth fault had occurred
in 400kV Coastal NTPL line. Line
autoreclosed
at NTPL end and failed to
reclose at Coatal end. Auto reclose
block was persisting due to PLCC
channel fail. Also running Units-
1&2 at NTPL tripped on operation
of GT
differential protection.
Tripping of
400kV
Coastal-
NTPL line
and running
units
at NTPL
47/II/9 03-08-2015
at
15:43 hrs
PendingYet to be informedKPTCL/
KPCL/
NPCIL
1. KPTCL/ KPCL to see the possibility of
implementing Weak Infeed logic with Echo
feature enabled by Under
Voltage (27) element on Kadra-Karwar lines 1
&2, and implement the same if feasible.
2. NPCIL to time-coordinate Kaiga’s DEFR
settings with (i) Zone-2 settings at Kaiga, and
(ii) primary protections of the lines emanating
from Kadra and Kodasalli.
3. KPCL to ensure time-sync of EL’s, and
healthiness of the Fault Locators at Kadra.
220kV KAdra-Karwar lines-1&2
tripped on earth fault in B-phase in
zone-2.
Kaiga-Kadra line tripped at Kaiga
end only on operation of
directional eath
fault protection.
31-07-2015
at
11:44 hrs
Annexure-III
Page 24 of 24
Sl.No. Element NameOutage
date/time
Revival
date/time
Reason for
OutageSender/ Receiver
Remedial Measures/ Actions
taken
1400 Kv KRISHNAPATNAM -
NELLORE
20-07-
2015/11:27:00
20-07-
2015/12:00:00
BUS -1
TRIPPED :
REASON
AWAITED
APGENCO/
APTRANSCO
APGENCO: BUS-1 was tripped
at Power Grid Sub-
Station(PGCIL), Nellore during
the operation of the Isolators,
which is not pertaining to
APGENCO.
APTRANSCO: Line tripped at
Krishnapatnam end only.Line is
in service from Nellore-AP.
PGCIL (SR-I):
2 220 kV AMBEWADI - PONDA 127-09-
2015/15:53:00
27-09-
2015/16:38:00
DUE TO BUS
DEAD AT
AMBAWADI
STATION
KPTCL/ GOA To-be-discussed
3 220 kV AMBEWADI - PONDA 227-09-
2015/15:53:00
27-09-
2015/18:43:00
DUE TO BUS
DEAD AT
AMBAWADI
STATION
KPTCL/ GOA To-be-discussed
Pending Remedial Measures/ Actions taken
for the Critical Tripping Incidents (as on 14-12-2015)
Annexure-IV
Page 1 of 8
4 400 Kv NCTPS - SVCTM-I05-10-
2015/14:31:00
05-10-
2015/15:44:00
TRIPPED ON R-
PH FAULT
TANGEDCO/
TANTRANSCO
TANTRANSCO: Temporary
fault. AR lockout at both ends.
Feeder normalised at 15:43 hrs. on
05.10.2015.
TANGEDCO:
5 400 Kv VTPS - MALKARAM 112-10-
2015/11:40:00
12-10-
2015/16:01:00
TRIPPED ON B-
PH FAULT
APGENCO/
TSTRANSCOTo-be-discussed
6 400 Kv VTPS - MALKARAM 113-10-
2015/12:55:00B-N FAULT
APGENCO/
TSTRANSCOTo-be-discussed
7 400/220 kV ICT-1 AT BTPS30-10-
2015/21:02:00
30-10-
2015/22:42:00TRIPPED KPCL To-be-discussed
8400 Kv GAJWEL - SHANKARPALLY
1
02-11-
2015/11:33:00
02-11-
2015/11:59:00R-N FAULT TSTRANSCO To-be-discussed
9400 Kv GAJWEL - SHANKARPALLY
1
02-11-
2015/12:22:00
02-11-
2015/14:40:00R - N FAULT TSTRANSCO To-be-discussed
10 400/220 kV ICT-2 AT KAIGA03-11-
2015/08:26:00
03-11-
2015/09:49:00
TRIPPED ON
DIFFERENTIA
L
PROTECTION
KAPS To-be-discussed
11 400/110 kV ICT-3 AT SALEM10-11-
2015/03:49:00
10-11-
2015/05:04:00
DUE TO OVER
FLUX RELAY
ACTED
TANTRANSCO
TANTRANSCO:
Due to raise in 400 KV grid
voltage, Over fluxing relay
operated. The Frequency variation
from 49.90 Hz to 50.09 Hz was
recorded during the tripping of all
ICTs.
Annexure-IV
Page 2 of 8
12 400/230 kV ICT-1 AT SALEM10-11-
2015/03:53:00
10-11-
2015/04:49:00
DUE TO OVER
FLUX RELAY
ACTED
TANTRANSCO
TANTRANSCO:
Due to raise in 400 KV grid
voltage, Over fluxing relay
operated. The Frequency variation
from 49.90 Hz to 50.09 Hz was
recorded during the tripping of all
ICTs.
13 400/230 kV ICT-2 AT SALEM10-11-
2015/03:51:00
10-11-
2015/04:57:00
DUE TO OVER
FLUX RELAY
ACTED
PGCIL (SR-II)/
TANTRANSCO
TANTRANSCO:
Due to raise in 400 KV grid
voltage, Over fluxing relay
operated. The Frequency variation
from 49.90 Hz to 50.09 Hz was
recorded during the tripping of all
ICTs.
PGCIL (SR-II):
14 400/110 kV ICT-4 AT SALEM10-11-
2015/02:29:00
10-11-
2015/07:17:00
TRIPPED DUE
TO OVER
FLUX
TANTRANSCO
TANTRANSCO:
Due to raise in 400 KV grid
voltage, Over fluxing relay
operated. The Frequency variation
from 49.90 Hz to 50.09 Hz was
recorded during the tripping of all
ICTs.
15 400/230 kV ICT-4 AT SALEM11-11-
2015/04:42:00
11-11-
2015/17:58:00
TRIPPED DUE
TO OVER
FLUX
PGCIL (SR-II)/
TANTRANSCO
TANTRANSCO:
Due to raise in 400 KV grid
voltage, Over fluxing relay
operated. Carried out the
maintenance work and the
overfluxing relay was tested and
healthiness was ensured.
PGCIL (SR-II):
Annexure-IV
Page 3 of 8
16 400 kV KAIGA - GUTTUR 213-11-
2015/18:21:00
TRIPPED ON R-
PH FAULTKAPS/ KPTCL
PGCIL-SR2:
Portion of the line in which fault
occured owned and maintained by
M/s KPTCL. May be clarified
from M/s KPTCL
KPTCL:
KAPS:
17 400 kV KAIGA - GUTTUR 215-11-
2015/22:04:00
DISTANCE
PROTECTIONKAPS/ KPTCL To-be-discussed
18 400 Kv NCTPS - SVCTM-I16-11-
2015/17:24:00
16-11-
2015/18:28:00Y -N FAULT
TANGEDCO/
TANTRANSCO
TANTRANSCO: Temporary
fault. Feeder normalised at 18:28
hrs. on 16.11.2015.
TANGEDCO:
19 220 kV CHITTOR - THIRUVALEM18-11-
2015/11:20:00
18-11-
2015/16:18:00
BUSBAR
PROTECTION
OPERATED @
CTR END
APTRANSCO/ TNEB
TANTRANSCO:
There was no tripping of 230kV
Thiruvalam – Chitoor feeder on
18.11.2015 at Thiruvalam end.
APTRANSCO:
20400 Kv KRISHNAPATNAM -
CHITTOOR
21-11-
2015/07:18:00CB PROBLEM
APGENCO/
APTRANSCOTo-be-discussed
21 400 kV KAIGA - GUTTUR 223-11-
2015/13:15:00
23-11-
2015/19:39:00
DISTANCE
PROTECTIONKAPS/ KPTCL To-be-discussed
Annexure-IV
Page 4 of 8
22 400 Kv HASSAN - UPCL 223-11-
2015/12:53:00
23-11-
2015/13:14:00
B-PH ZONE-1
DISTANCE
PROTECTION
OPERATED
PGCIL-SR2/ KPTCL/
UPCLTo-be-discussed
23 400 kV KAIGA - GUTTUR 227-11-
2015/15:07:00
27-11-
2015/16:11:00R-G FAULT KAPS / KPTCL To-be-discussed
24 400/220 kV ICT-2 AT BANGALORE27-11-
2015/18:47:00
27-11-
2015/19:26:00
BUS BAR
PROTECTION
ACTED
PGCIL (SR-II) To-be-discussed
25 400/230 kV ICT-3 AT UDUMALPET27-11-
2015/11:25:00
27-11-
2015/11:34:00
TRIPPED ON
MAL
OPERATION
PGCIL (SR-II) To-be-discussed
26 400/230 kV ICT-3 AT UDUMALPET27-11-
2015/17:25:00
27-11-
2015/18:38:00
RELAY
MALOPERATI
ON
PGCIL (SR-II) To-be-discussed
27 400 Kv ALM - SVCTM-II27-11-
2015/15:40:00
27-11-
2015/16:37:00C -G FAULT TANTRANSCO
TANTRANSCO: 400kV
S.V.Chatram - Alamathy -1 feeder
'C' phase jumper got cut at
Loc.No.178 from Alamathy end
and created temporary fault with
400kV S.V.Chatram - Alamathy -
2 feeder 'A' phase jumper. Both
feeders runs on the same tower.
PUTT Trip and AR successful at
S.V.Chatram end. AR lockout at
Alamathy end.
28 220 kV KANIAMPET - KADAKOLA27-11-
2015/09:55:00
TRIPPED ON
DISTANCE
PROTN
KSEB / KPTCL To-be-discussed
Annexure-IV
Page 5 of 8
29 400 Kv ALM - SVCTM-I27-11-
2015/15:40:00
SWITCH ON
TRANSIENT
FAULT
TANTRANSCO
TANTRANSCO: AR lockout at
both ends. C-Phase jumper cut at
LOC.NO.178 from Alamathy SS
end was attended. Feeder
normalised on 10.12.2015 at
12:45hrs.
30 400/220 kV ICT-1 AT BANGALORE27-11-
2015/18:47:00
27-11-
2015/19:15:00
BUS BAR
PROTECTION
ACTED
PGCIL (SR-II) To-be-discussed
31 400 kV KAIGA - GUTTUR 128-11-
2015/14:09:00
28-11-
2015/16:20:00B-N FAULT KAPS / KPTCL To-be-discussed
32 400 kV KAIGA - GUTTUR 129-11-
2015/01:04:00
TRIPPED ON R-
N FAULTKAPS / KPTCL To-be-discussed
33 400 kV KAIGA - GUTTUR 229-11-
2015/01:04:00
TRIPPED ON R-
N FAULTKAPS / KPTCL To-be-discussed
34400 kV DICHIPALLY -
RAMAGUNDAM
02-12-
2015/02:46:00
02-12-
2015/04:13:00B-N FAULT TSTRANSCO / NTPC To-be-discussed
35400 kV DICHIPALLY -
RAMAGUNDAM
02-12-
2015/12:40:00
TRIPPED ON B-
Y FAULTTSTRANSCO / NTPC To-be-discussed
36400 kV TALAGUPPA -
NEELAMANGALA
03-12-
2015/16:20:00
TRIPPED ON
LINE FAULTKPTCL To-be-discussed
37 400 Kv NCTPS - SVCTM-I04-12-
2015/03:54:00
04-12-
2015/04:58:00
TRIPPED ON B-
PH FAULT
TANGEDCO /
TANTRANSCO
TANTRANSCO/TANGEDCO:
Temporary fault. AR lockout at
both ends. No visible fault and
feeder normalised on 04.12.2015
at 04:58 hrs.
TANGEDCO:
Annexure-IV
Page 6 of 8
38 400 Kv HASSAN - UPCL 106-12-
2015/10:40:00
06-12-
2015/10:56:00
TRIPPED ON R-
N FAULTPGCIL (SR-II) / UPCL To-be-discussed
39400 kV NEYVELI TS 2 - NEYVELI
TS2 EXP
06-12-
2015/20:35:00
06-12-
2015/23:03:00DT RECEIVED NLC To-be-discussed
40400 kV NEYVELI TS2- NEYVELI TS-
I
06-12-
2015/23:12:00
07-12-
2015/00:46:00
MALOPERATI
ONNLC To-be-discussed
41 400/220 kV ICT-3 AT TRICHUR06-12-
2015/13:50:00
06-12-
2015/21:38:00
REF
OPERATEDKSEB To-be-discussed
42 400 Kv NPS - TPCIL 210-12-
2015/03:48:00
10-12-
2015/04:56:00
RELAY
MALOPERATI
ON AT TPCIL
END
To-be-discussed
43400 Kv VIJAYAWADA - NELLORE -
AP -
10-12-
2015/10:51:00
10-12-
2015/11:46:00
TRIPPED DUE
TOBACKIP
IMPEDANCE
RELAY ACTED
To-be-discussed
44 400 kV KALPAKKA - VEMAGIRI 210-12-
2015/15:20:00
10-12-
2015/16:20:00
BUS BAR
PROTECTION
OPERATED @
KLPAKA
To-be-discussed
45 400 kV SIMHADRI - KALPAKKA 410-12-
2015/15:20:00
10-12-
2015/16:30:00
BUS BAR
PROTECTION
OPERATED @
KLPAKA
To-be-discussed
46 400/220 kV ICT-2 AT CHITTOOR11-12-
2015/07:12:00
11-12-
2015/16:23:00
BUCHOLZ
RELAY
OPERATION
To-be-discussed
Annexure-IV
Page 7 of 8
47400 kV TRIVENDRUM -
TIRUNELVELI 1
11-12-
2015/04:56:00B-N FAULT To-be-discussed
48400 KV ALAMATHI -
THIRUVALLAM-1
13-12-
2015/22:42:00
Y-PH LA
BLAST @
THVLM END
To-be-discussed
49 400 kV ALAMATHI - VALLUR 213-12-
2015/22:42:00
Y-PH LA
BLAST @
THVLM END
To-be-discussed
Annexure-IV
Page 8 of 8
F. _SRPC /0. 3 (, 15 dated 2.& .11.2015.
TANTRANSCO
ToThe Member Secretary,
I SRPC,Bangalore.
From'I ErJ.Rexline Terese M.EChief Engineer,Protection and Commu nication5B Block, IfIoor,144 Anna salai, TNEB comple ,Chennai -2Lr.No.CE/ P&C/ SEt 01 Chi EPC4j AEE3
Sir,Sub: Elecy - Operation Circle / Tirunelveli - Tripping of 230KV TIPS
Koodankulam feeder - Action taken report - furnished -Reg
230KV TIPS-Koodankulam feeder tripping for the period from October 2013
to November 2015 is listed in the Agenda for 49 h PCSC meeting. In this regard the
following details are furn ished.
1. 7 Nos. tr ipping were due to flashed over disc insulators - (Breakdowns).
2. During rainy season, most of the trippings occurred (28 Nos.) which were dueto heavy rain, thunder and lightning for the period from October to December .
3. 6 Nos. tripping were due to earth wire cut.
4. I I Nos tripping were passing fault (Bird fault).
Earlier the 230kV TIPS- SR Pudur line made LILO at Koodankulam. The
frequent tr ipping of feeder may be due to the deposit ion of fly ash on the insulatorscoming out from TIPS and NTPL for a radial distance of 5 Km. Replacement of the old
insulators and corroded earth wire in and around TIPS area have already beensanctioned and work is in progress. 70% of disc insulators have already been replacedby Composite Polymer insulators . So deposit ion of fly ash problem will be eliminated in
due course.
In order to avoid frequent tr ippings and breakdowns, it is programmed to
replace the corrod ed earth wi re after the monsoon is over.
Chief Engineer/P&C
Annexure-V
Report of the Task Force on Power System Analysis Under Contingencies
Page 113
Appendix-9.1 (Page 5/7 of Appendix)
Various types of directional elements may be employed to control operation of ground over current (zero sequence over current) protection response. The most common approach is to employ Phase angle difference between Zero sequence voltage and current, since the relaying signals can easily be derived by summing phase current signals and by summing phase voltage signals from a suitable voltage transformer.
However, this method is not suitable for some applications where transmission lines terminated at different substations, run partially in parallel. In such cases following type of directional control is recommended to be used for the directional earth fault relay.
Relative phase of negative sequence voltage and current
To ensure proper coordination, operating time must be set according to following criteria:
The DEF protection should not operate when the circuit local backup protection of remote end clears a fault in an adjacent circuit i.e DEF should be coordinated with the remote end LBB.
12. POWER SWING BLOCKING FUNCTION While the power-swing protection philosophy is simple, it is often difficult to implement it in a large power system because of the complexity of the system and the different operating conditions that must be studied. There are a number of options one can select in implementing power-swing protection in their system. Designing the power system protection to avoid or preclude cascade tripping is a requirement of modern day power system. Below we list two possible options:
12.1. Block all Zones except Zone-I This application applies a blocking signal to the higher impedance zones of distance relay and allows Zone 1 to trip if the swing enters its operating characteristic. Breaker application is also a consideration when tripping during a power swing. A subset of this application is to block the Zone 2 and higher impedance zones for a preset time (Unblock time delay) and allow a trip if the detection relays do not reset. In this application, if the swing enters Zone 1, a trip is issued, assuming that the swing impedance entering the Zone-1 characteristic is indicative of loss of synchronism. However, a major disadvantage associated with this philosophy is that indiscriminate line tripping can take place, even for recoverable power swings and risk of damage to breaker.
Annexure-VI
Page 1 of 2
Report of the Task Force on Power System Analysis Under Contingencies
Page 114
Appendix-9.1 (Page 6/7 of Appendix)
12.2. Block All Zones and Trip with Out of Step (OOS) Function This application applies a blocking signal to all distance relay zones and order tripping if the power swing is unstable using the OOS function (function built in modern distance relays or as a standalone relay). This application is the recommended approach since a controlled separation of the power system can be achieved at preselected network locations. Tripping after the swing is well past the 180 degree position is the recommended option from CB operation point of view. Normally all relay are having Power swing Un-block timer which unblocks on very slow power swing condition (when impedance locus stays within a zone for a long duration). Typically the Power swing un-blocking time setting is 2sec. However, on detection of a line fault, the relay has to be de-blocked.
12.3. Placement of OOS trip Systems Out of step tripping protection (Standalone relay or built-in function of Main relay) shall be provided on all the selected lines. The locations where it is desired to split the system on out of step condition shall be decided based on system studies. The selection of network locations for placement of OOS systems can best be obtained through transient stability studies covering many possible operating conditions.
Till such studies are carried out and Out-of-Step protection is enabled on all identified lines, it is recommended to continue with the existing practice of Non-Blocking of Zone-I on Power Swing as mentioned under Option-12.1 above. However, it should be remembered that with this practice the line might trip for a recoverable swing and it is not good to breakers.
Committee strongly recommends that required studies must be carried out at the earliest possible time (within a timeframe of one year) to exercise the option-12.2 & 12.3 above.
13. LINE OVERVOLTAGE PROTECTION FOR 400kV LINES: Low set stage (Stage-I) may be set in the range of 110% - 112% (typically 110%) with a time delay of 5 seconds. High set stage (Stage-II) may be set in the range 140% - 150% with a time delay of 100milliseconds.
FOR 765kV LINES: Low set stage (Stage-I) may be set in the range of 106% - 109% (typically 108%) with a time delay of 5 seconds. High set stage (Stage-II) may be set in the range 140% - 150% with a time delay of 100milliseconds.
However, for over voltage Stage-I protection, a time grading of 1 to 3 seconds may be provided between overvoltage relays of double circuit lines. Grading on overvoltage tripping for various lines emanating from a station may be considered and same can be achieved using voltage as well as time grading. Longest timed delay should be checked with expected operating time of Over-fluxing relay of the transformer to ensure disconnection of line before tripping of transformer.
It is desirable to have Drop-off to pick-up ratio of overvoltage relay better than 97% (Considering limitation of various manufacturers relay on this aspect).
Annexure-VI
Page 2 of 2
PRACTICAL INTERLOCK LOGICS TO PREVENT UNDESIRED CIRCUIT BREAKER CLOSING, ISOLATOR OPENING & CHARGING OF BAY
IN SUB STATION USING IEDS
Sanjay U Bhatt, Protection, Automation and Metering Department
Adani Power Ltd, Ahmedabad E-mail: [email protected]
ABSTRACT Un desired charging of a bay / equipment when is ready to charge or immediately after getting isolated, due to accidental closing of circuit breaker or breaker flash over may result in severe undefined damage / loss to equipment / system stability / human loss, as well financial burden due to huge repairing cost and outage period till normalcy.
This paper describes practical interlock logics using IEDs for (1) controlling DC negative source to circuit breaker closing circuit and (2) Auto opening of Isolators after opening of circuit breaker.
KEYWORDS Circuit Breaker closing circuit logic, DC negative source breaking for CB closing, Isolator Auto opening logic, safety interlock for CB and isolator.
1. INTRODUCTION The essential element of a protection & control circuit design is to have inclusion of all engineering aspects for control, protection, monitoring & measurement having considerations for technical & operational limitations and capabilities of equipments, system and switchgear, operation possibilities & flexibilities with safety interlocking.
Fig. 1 is a typical such circuit conventionally used for a Circuit Breaker closing purpose.
Fig 1- Typical Closing circuit of a circuit
Accidental shorting of DC+ve to close CB
Reference- I
Page 1 of 11
The safety interlocking involves design of circuit in a controlled manner, by which ultimately actuates the operating mechanism of relevant circuit breaker / isolators / contactors / solenoids etc. for bridging primary connections to charge or operate the equipment. CASE-I In case of a circuit breaker for closing circuit interlock, the auxiliary supply (DC +ve or Phase) is extended from source to actuating point connection of closing coil of a circuit breaker through various permissive contacts ensuring healthy operating conditions, CB readiness, and absence of any abnormalities. The cables are routed through all relevant location of interlock contacts. DC –ve or Neutral is directly connected to other end of closing coil. A typical circuit is shown at Fig. 1.
The opening of isolator on load is also such kind of operation due to similar reasons indicated above.
CASE-II
In addition to the undue closing of circuit breaker, the undesired energizing of equipment (Transformer, Generator, Line etc.) may also happen in case of breaker flash over (internal or external) , particularly in case of Generator or two charged line from different sources, when going to synchronize or after isolated from grid. This is due to external insulation failure or arcing within breaker chamber, causing out of phase connection of two vector (peak to peak twice magnitude) causing severe oscillation and damage to equipment. The detection of breaker flash over reliably and isolation is still a serious concern especially in case of one and half breaker arrangement. Fig.2 shows a typical bay arrangement for a Generator with possible peak to peak voltage vector from Grid and Generator causing flash over. .
An automatic and comprehensive logic which can detect successful opening of breaker and initiate command to open the outgoing circuit isolator with flexibility of closing operation will be very useful to be secure against such wrong energisation of equipments
Fig 2- Typical One and Half CB arrangement possible breaker flash over due to peak to peak voltage across CB open contacts Breaker
Reference- I
Page 2 of 11
2 A CASE STUDY FOR GENERATOR BREAKER RECLOSING AFTER TRIPPING.
Recently at one of the large power plant the Generator Transformer Bushing of a phase failed which led to tripping of unit on operation of overall differential protection with tripping of both Main & Tie breaker. Due to heavy flash over and burning of insulation & oil, there was heavy fire and hot oil spread in nearby MK box & cable trench. This led to damage of all cables as shown in the pictures. After @10 Minutes the Main breaker got closed due to shorting of cable carrying DC+ve and return for closing. However the tripping command was persisting on operation of lockout relay hence tripping of breaker was taking place immediately on closing this sequence repeated multiple times and then stopped on blowing of main DC fuse.
Due to very short time closing, opening of B phase HV bushing of GT and residual rolling of turbine, nothing further damaged occurred.
Fig-3, indicates the control cables route for CB closing from switchyard kiosk to Generator Relay Panel and Synchronizer panel located at Main C/R. The cable trench route is passing near GT area where fire took place.
The detailed closing control circuit is shown at Fig-4.
It is therefore must to review the conventional closing circuit scheme for breaker & Isolator and cabling practices.
Fig 3- Showing location of Bay Kiosk, CB, GT and Main C/R with route of control cable.
Reference- I
Page 3 of 11
Due to fire cable damaged and shorted core to complete the closing circuit path for DC Positive return to Circuit Breaker Closing circuit.
Generator Relay Panel interlock for closing circuit
Synchronizing interlock for closing circuit and closing command from Main Control Room
CB cubicle at Switchyard
Control cables in cable trench from Switchyard to Main C/R
Interlocks
Figure-4- A Generator Breaker Closing circuit, event of closing control cable shorted resulting in undesired closing of circuit breaker Reference- I
Page 4 of 11
3. ISSUES WITH CONVENTIONAL CIRCUIT BREAKER CLOSING & ISOLATOR OPEN CIRCUIT.
Please refer case study mentioned earlier, where the breaker closing circuit philosophy used is conventional as described previously. The scheme is simple and being used everywhere.
Pl. refer Fig.1, and case study occurrence, it is seen that extension of DC +ve supply to closing coil terminal is the only deciding factor for closing operation of breaker and also opening sequence of isolator . Any undue extension of DC+ve to operating coil may lead to undesired operation of equipment. The undue extension of DC+ve to closing circuit/isolator opening circuit may happen due to (1) shorting of control cable carrying DC+ve and return path after permissive and command towards CB/Isolator, and (2) Simultaneous grounding of DC+ve system and terminal connected to CB closing / Isolator Open circuit. The sample case for CB are mentioned in following sections which will also apply to Isolator open circuit with due modifications.
4. SOLUTION TO BREAKER CLOSING DUE TO UNDESIRED SHORTING OF DC+VE.
The mishap due to above indicated DC+ve shorting can be avoided by breaking DC-ve immediately after closing CB and the same can be made through just before closing CB, command through SCADA/IED.
The simple solution is to switch OFF the closing supply immediately after closing CB and make ON when required to close. The same can be made by breaking DC +ve as well with the method described here. However this may involve addition of circuits and contacts for +ve at DC source also, with simultaneous operation of contacts on both sides, adding more complexity and online monitoring of closing circuit also is not possible. So for our purpose DC-ve breaking scheme is sufficient.
.
Existing Closing Circuit
Close Guard I/P
Fig. 5a- Closing circuit DC Negative breaking with CMR operated from Logical operation of IED / circuit. CMR placed at Breaker MK box.
Fig. 5b- Closing circuit DC Negative breaking with Output of IED / Logical circuit scheme placed at Control panel
Digital / Analogue Interlock I/O
Digital / Analogue Interlock I/O
Reference- I
Page 5 of 11
Fig. 5a and 5b above indicate the methods of breaking DC-ve using logical operation performed from numerical IEDs or such circuit from conventional relay, contactor, timers etc.
A simple way of breaking DC-ve is to route it from Master trip relay contacts where DC+ve for closing permissive is also routed.
However in case of manual opening or isolation Master Trip relay may not operate or can be reset after tripping for further interlocks and operations in a Generating Station. So it is also not covering complete risk.
In method 5a the CMR (Contact Multiplier Relay) placed in CB MK box is used to isolate the DC –ve. The CMR is operated by a separate DC/AC source from IED/ Logical device. As shown the CMR energizing supply is also wired from two separate contacts from IED at C&R panel. This will ensure complete secured operation of CMR even in case of the cable damage for CMR.
In method 5b the DC-ve is routed through contacts of IEDs/Device placed at Kiosk in Switchyard interfaced with SCADA.
Method 5a is the most appropriate one for all cases due to secured operation of CMR placed very near to CB closing circuit in MK box.
The CMR method should be used where there is no S/Y Kiosk near to CB and C&R panels are located at Main C/R directly connected with CB for control.
All above method should ensure secure operation with flexibility to operator and monitoring feedback. It should also supervise the shorting of cable or undue extension of DC+ve in closing circuit by guarding method.
5. LOGIC FOR BREAKING DC-VE USING IEDs & SCADA.
A practical logic using IEDs and SCADA interface implemented at the power station where the undesired closing of Generator Breaker happened as referred in case study is shown here at Fig. 6a and 6b.
Explanation of the logic:
Please refer Fig 6a, where a concept circuit is shown for placing of IED /CMR contact in the Negative terminal of closing coil (CC). The Guard input from DC+ve circuit is connected before CB auxiliary switch contact which is closed when breaker is OPEN or immediately after closing contact circuit. The guard input turns in high state when Close command is extended or any undue positive is extended in close circuit.
Please refer Fig 6b, the main logic part which can be built in IED (Relay/Bay Control Unit BCU / RTU having required logical blocks with IEC61850 accepting GOOSE signal and hard wired Binary I/O signal from scheme wiring and interfacing with local SCADA. This is generally available now with all IEDs installed in a switchyard.
The logic uses RS Flip Flop block having reset priority for latching output OPEN / CLOSE. The Flip Flop get reset and breaking DC-ve when
Circuit Breaker is closed successfully.
Lock out / Master trip relay operated.
Circuit Breaker Pole Discrepancy Relay (PDR) operated.
Circuit Breaker closeing permissive interlock NOT OK.
Negative Bypass command from Switchyard SCADA is given for Manual Bypass purpose.
All above condition will cause Flip Flop to reset and opening of contact to break DC-ve.
Reference- I
Page 6 of 11
52b
CC
Various external interlocks / commands
Breaker MK / Control Box
IED/ CMR Contact
DC ‐ve
DC +ve
CB CLOSE (Except Line Bay)
CB-PDR Operated
Lock out relay Operated
RESET
SET
OUT
+ve Guard input High
‘CLOSE circuit through command’ (Pulse) from OWS
RS Flip-flop
IED Contacts to
operate CMR or to
DC‐ve circuit of CB
as per scheme
adopted.
Guard BI of BCU / IED
200 ms
NOTE: The logic can be built in IED (Relay/Bay Control Unit BCU / RTU having required logical blocks with
IEC61850 accepting GOOSE signal and hard wired Binary I/O signal from scheme wiring and interfacing with local SCADA. This is generally available now with all IEDs installed in a switchyard.
Necessary wiring / GOOSE configuration should be worked out for I/O as per logic. ‘The Close circuit through command’ from OWS (Operator Work Station of SCADA) to extend DC-ve for
manual close should be initiated before closing of breaker so that –ve circuit to closing coil will be extended. In case of any unwanted DC +ve extension in closing circuit will be monitored by Guard circuit and will not
allow the flip flop to set to extend DC –ve to closing coil. Which is monitored in SCADA also. The Guard timing is considered as 200 mS allowing closing of breaker normally. The above circuit can also be used for isolator control circuit with modification in input logic and other
interlocks.
Manual Reset (Pulse) from OWS
CB closing permissive OK
Interlock status feedback to SCADA / OWS
Fig 6b - Logic for DC-ve breaking for Circuit Breaker Closing circuit
Fig-6a- Concept Circuit for Breaker Closing circuit
Breaker Aux. contact
Reference- I
Page 7 of 11
The Flip Flop will be set to drive BO to extend DC-ve under following condition.
Though manual command from OWS (SCADA) when it is really required to close breaker, if the DC Guard input is NOT High more than 200 mSec.
Immediately after closing of CB the Flip Flop will get reset breaking DC-ve till a manual intervention is made which should be done just before closing the breaker. In case of line after closing of breaker to allow Auto Reclosure operation DC-ve is not being broken, however except in case of three phase tripping.
Further it is also important to have wire cores for DC +ve source of closing circuit going to external wiring and return from CB MK should be in different cable and not in same cable.
Above logic has been implemented and proven well working taking care for all possible abnormalities. The same can also be used to take care for undue opening of Isolator with some modification of logic such as the phase and neutral (OR DC +ve and –ve) will be extended simultaneous when any open command generated from valid open sequence and other interlocks.
Snap of logic and control built in SCADA database is mentioned as under for a Generator Circuit Breaker.
Reference- I
Page 8 of 11
6. LOGIC FOR AUTOMATIC OPENING
OF ISOLATOR AFTER TRIPPING OF CIRCUIT BREAKER.
It is well known that an Isolator is OFF Load and Circuit Breaker is ON Load circuit breaking equipments. Opening of an Isolator on load will lead to a severe damage to equipment and human also. Due to this reason to avoid accidental opening of isolator a routine practice is being adopted for an isolator, to switch OFF isolator Driving Motor supply after closing electrically or manually. However in case of ABCB earlier, due to risk of getting closing of circuit Breaker on low air pressure automatic opening of isolators on immediate opening of CB was used using hard wired CB status based logic. Now days all isolators are remotely operated from SCADA and also with concept of unmanned S/S the Isolators are kept ready to operate with all auxiliary sources in service. With this arrangement it is must for isolator to have DC-ve and also automatic opening of isolator breaking logic schemes.
Please refer Section 2 Case-II and case study of occurrence, the reclosing of Circuit Breaker due to any reason or flash over subsequent to opening of breaker or before synchronizing will defiantly damage the equipment connected. In the referred case, the immediate opening of circuit (Line) isolator on opening of CB would have saved the impact on Transformer and Generator, if so designed in the scheme. The manual opening of isolator immediately after tripping of CB is also not expected due to human action.
The logic implemented at Sub station referred earlier is mentioned at Fig 7 & 8 using Bay Control Unit, GOOSE signal for status / Analogue signal over IEC 61850.
The output of Auto OPEN Logic is configured with same output of the existing logic for OOPEN sequence of isolator taking status and feedback as per logic.
Explanation of the logic:
Please refer Fig. 8, the Auto Open sequence will be initiated after proposed time delay of 5 sec, when (i) Under current relay picks up AND (ii) Main Breaker is not CLOSED AND (iii) TIE Breaker is not CLOSED AND (iv) Isolator closed status is high. For secure operation the interlock of load current and breaker status has been incorporated. The Auto open sequence will be automatically latched for next operation when (1) Under current relay resets OR (ii) Main Breaker CLOSED OR (iii) Tie Breaker CLOSED, after a proposed time delay of 5 sec. The next closing sequence will be initiated by Manual command from SCADA OWS for SET command to the RS Flip-Flop, and when it is set will allow manual CLOSE sequence to operate making the operation more secure and enhancing the CLOSE logic also.
Again after opening of breaker and sensing of under-current will allow Auto opening of isolator as per logic.
The implemented logic screen snap is also indicated at Fig-9.
Existing CLOSE sequence
Existing OPEN sequence
AUTO OPEN Logic
BCU Output for Isolator OPEN & CLOSE
SCADA interface
Reference- I
Page 9 of 11
Fig 8 - Logic for Auto open of Isolator after opening of Circuit Breaker
&
I<1 Under Current
Main Breaker CLOSE
TIE Breaker CLOSE
Isolator CLOSE status
Manual SET
(Pulse) from OWS
Timer OPEN
Command
to Isolator
RESET
OUT
O
R
SET
To Isolator CLOSE logic interlock
to ensure SET condition of Auto
Open sequence
& Existing LOGIC for
Isolator CLOSE command
CLOSEE
Command to
Isolator
T
5 S
NOTE: Manual SET command from OWS SCADA should be SET before Closing of Isolator. The Logic is built in BCU and connected with existing OPEN command of isolator. Manual Set command latch O/P from flip flop is interlocked with Existing Logic for Isolator Closing Required modification & configuration of relevant relay for under current setting and Logic should be worked out. Timing for Auto Open Isolator may be set at 5 second after opening of CB.
Fig 9 – Implemented Logic for Auto open of Isolator after opening of Circuit Breaker
Reference- I
Page 10 of 11
7. CONCLUSION
The described engineering practice should be implemented as a standard scheme for operation of Circuit Breaker and Isolators looking to secure operation of primary switching.
Because numbers of incidences are being occurred on account of damaged cables or DC- grounding or mal-operation even during fault finding or testing of control wiring. The use of latest technology or equipment without reliable operating mechanism is waiting for a disaster always.
Availability of Numerical technological IEDs and GOOSE signals over IEC61850 protocol with SCADA has made the task very easy and secure.
(1) Circuit Breaker Closing circuit should be equipped with DC-ve breaking as near as possible to Closing Coil with Contact Multiplying relay / IED (Relay) contact with secured logic, control and monitoring facility in SCADA.
(2) Isolator OPEN circuit should also be equipped with similar above scheme logic indicated at (1).
(3) Circuit (Line) Isolator should be automatically opened immediately after tripping /Opening of CB/s. The logic should be secured enough to ensure complete OFF Loading of circuit and also with no confliction with CLOSE sequence operation.
(4) The control cables carrying DC-ve from CB / Isolator and to IED/Relay at C&R panel should be in different cable, preferably separate route to avoid any possibility of malfunction of the above discussed circuit itself.
(5) All the input / output and logical status should be configured in event of IED and SCADA for future analysis on event of occurrence.
(6) The new specification for C&R panel and scheme should be included with above said requirements.
REFERENCES:
(1) Various schemes drawing for different substations.
(2) AREVA make application manuals on BCU MICOM C264 /EN/AP/ C30, PACIS Operation Interface for Automation and other IEDs
(3) ABB make application manuals on 670 series IEDs.
AUTHOR:
.
.
.
Sanjay U. Bhatt, working as DGM (Protection) at Adani Power Ltd, Ahmedabad, (Protection Automation & Metering Department), from January 2012.
B.E. (Electrical) -1993 from L.E. College Morvi , Gujarat (India). Worked: In G.S.F.C.-Jamnagar, as Ele. Maintenance Engr. In Govt. Polytechnic, as a lecturer on clearing GPSC. In GSECL as Junior Engineer at Sikka Power station as Electrical Testing & Maintenance engineer and at SLDC during commissioning of SCADA and related system. As Deputy Engineer at GSECL corporate office as Testing engineer.
Reference- I
Page 11 of 11
Application Notes P34x/EN AP/G44
MiCOM P342, P343, P344
Page 129 of 176
For generator applications the undercurrent elements should be measuring current from CTs on the terminal side of the generator. This is because for an internal fault on the generator after the CB has tripped the generator will still be supplying some fault current which will be seen by undercurrent elements measuring current from CTs on the neutral side of the generator. This could thus give false indication of a breaker fail condition.
The voltage dependent overcurrent protection and underimpedance protection used for back-up protection of system faults are usually connected to the neutral side CTs so that the generator is in the zone of protection. These protection functions use the IA, IB, IC current inputs in the P343/4. Therefore, if the IA, IB, IC inputs are connected to neutral side CTs then the IA-2, IB-2, IC-2 inputs should be selected for the undercurrent elements using the setting ‘I< Current Input - IA-1, IB-1, IC-1/IA-2, IB-2, IC-2’.
P2181ENa
DDB #162 : Any Trip (RL3)
DDB #493 : Bfail1 Trip 3ph
DDB #294 : CB Fail Alarm
tbf2
0s
DDB #494 : Bfail2 Trip 3ph
DDB #380 : Ext. Trip 3ph
OR
AND
DDB #631 : IA< Start
DDB #632 : IB< Start
DDB #633 : IC< Start
DDB #635 : IN< Start
DDB #447 : ISEF>1 Trip OR
S
Q
R
G37-0 : Disabled
G37-1 : Enabled
SETTING [4504] :
CB Fail 2 Status
G37-0 : Disabled
G37-1 : Enabled
SETTING [4502] :
CB Fail 1 Status
AND
AND
tbf1
0s
OR
SETTING [4503] :
CB Fail 1 Timer
SETTING [4505] :
CB Fail 2 Timer
AND
S
R
OR
Q
DDB #453, 457 : V< Trip
DDB #469 - 472 : F< Trip
DDB #757 : All Poles Dead
OR
DDB #380 : Ext. Trip 3ph
AND
DDB #634 : ISEF< Start
G68-0 : I< Only
G68-1 : CB Open & I<
G68-2 : Prot Reset & I<
SETTING [4506] :
Volt Prot Reset
G68-0 : I< Only
G68-1 : CB Open & I<
G68-2 : Prot Reset & I<
SETTING [4507] :
Ext Prot Reset
AND
AND
OR
AND
AND
OR
S
R
Q
S
R
Q
DDB #162 : Any Trip (RL3)
DDB #461, 465 : V> Trip
DDB #451, 457 : VN> Trip
DDB #416 : 100% ST EF Trip
DDB #497, 498 : PSlipz Trip
DDB #475, 476 : Power Trip
DDB #495, 496 : SPower Trip
DDB #422, 423 : Field Fail Trip
DDB #429 : V/Hz Trip
DDB #430 - 439 : RTD Trip
DDB #473, 474 : F > Trip
x 2 Stages
x 2 Stages
x 2 Stages
x 4 Stages
x 2 Stages
x 2 Stages
x 2 Stages
x10 Stages
x 2 Stages
x 2 Stages
Figure 52: CB fail logic
2.29 Breaker flashover protection
Prior to generator synchronization, or just following generator tripping, where the protected generator could be slipping with respect to a power system, it is possible to establish at least twice rated phase-neutral voltage across the generator circuit breaker. An even higher voltage might briefly be established just after generator tripping for prime mover failure, where the pre-failure level of excitation might be maintained until AVR action takes place. Whilst generator circuit breakers must be designed to handle such situations, the probability of breaker interrupter breakdown or breakdown of open terminal switch gear insulators is increased and such failures have occurred.
Reference-II
Page 1 of 2
P34x/EN AP/G44 Application Notes
Page 130 of 176
MiCOM P342, P343, P344
This mode of breaker failure is most likely to occur on one phase initially and can be detected by a neutral current measuring element. If the generator is directly connected to
the power system, the second stage of stator earth fault protection (“ΙN>2...”) could be
applied as an instantaneous element by setting the time delay “ΙN>2 TimeDelay” to 0s, to quickly detect the flashover. To prevent loss of co-ordination this stage must be blocked when the circuit breaker is closed. This can be programmed by correct configuration of the programmable scheme logic and can be integrated into the circuit breaker fail logic, as shown in Figure 53.
Where the machine is connected to the system via a step-up transformer a similar scheme can be arranged. The P34x relay standby earth fault protection element can be connected to measure the transformer HV earth fault current to provide the breaker flashover protection, via suitable scheme logic. The machine earth fault protection can be provided by the P34x sensitive earth fault protection element, as shown in Figure 54.
P2182ENa
MiCOMP343
IN
ISEF
DDB 39
L8 52-B
DDB 205
IN>2 Trip
& DDB 168
Extern Trip 3ph
DDB 310
Bfail1 Trip 3ph
R5 CD fail trip DW 100
Scheme logic in PSL
Figure 53: Breaker flashover protection for directly connected machine
P2183ENa
MiCOMP343
IN
ISEF
DDB 39
L8 52-B
DDB 205
IN>2 Trip
& DDB 168
Extern Trip 3ph
DDB 310
Bfail1 Trip 3ph
R5 CD fail trip DW 100
Scheme logic in PSL
Figure 54: Breaker flashover protection for indirectly connected machine
This CT shall
be provided
additionally. This CT is connected to P141realy (GRP-C). This CT signal shall be
extended to P344relay by connectingboth relay terminals in series.
Reference-II
Page 2 of 2
Adaptive Logic for Breaker Flashover Protection of Generator. Sanjay Bhatt
Protection Automation and Metering Group Adani Power Training and Research Institute
Adani Power Limited, Ahmedabad [email protected]
1. ABSTRACT:
Flashover can occur on any breaker in the network where an overvoltage condition is present, but the probability is higher for breakers being used to synchronize two isolated power systems; e.g. on generator breakers, line breaker connecting two separate sources or grids. For Generator/line breaker, the Period is considered as critical in view of withstanding rise in voltage vector appearing across poles of Circuit Breaker and the arc quenching process before generator/line synchronization, or just following generator/line tripping respectively. The circuit breaker for above said applications for must be designed capable of maintaining the sufficient insulation level to withstand the same. The detection of flashover reliably and operating protection to isolate the affected breaker and generator in possible minimum time calls for a logic based on immediate sensing of arc current supported by breaker status to reliably declare a flash. This paper describes the logic adapting the numerical relaying logic blocks with current status different from conventionally used and also described in IEEE guideline for Generator Protection C37.102.
2. KEYWORDS: Breaker Flashover, Generator Protection for GT Breaker flashover, unintended arc across Generator breaker
3. INTRODUCTION:
(I) It is because the vectors of the protected generator and grid vector across circuit breaker poles are slipping with respect to a power system. This will lead to a condition to establish at least twice rated phase-neutral voltage across the generator circuit breaker. Due to the system and machine operation condition it is quite often possible that even higher voltage may be established. This will lead to establishment of arc between two poles of circuit breaker, which may be internal or external, leading to failure of breaker damaging self and also nearby equipments and persons. Further the establishment of arc will also lead to the asynchronous energisation of Generator with grid and create oscillation damaging Generator Transformer / Generator. Detecting the flashover The abnormal rise in voltage just after generator tripping is most likely due to following reasons,
Prime mover failure: which is associated by the excitation level not matching instantly with the lowering of active power, where the pre-failure level of excitation might be maintained until AVR action takes place.
AVR malfunction: this is associated with failure of AVR to discharge energy through discharging resistor at the time of tripping boosted by residual flux.
Reference- III
Page 1 of 7
2 Adaptive Logic for Breaker Flash over protection of Generator.
The peak to peak voltage appearing across circuit breaker is indicated at Fig.1 below.
During the synchronization process, the out-of-phase angle between breaker contacts changes from 0 to 360 degrees continuously. Voltage between breaker contacts reaches its maximum instantaneous value when the angle difference between the voltages is 180 degrees, with a magnitude equal to double the nominal phase-to-ground peak voltage; posing severe stress to the insulation. May also result in out of step and swing.
The flash over thus occurred in most of the cases are of single phase in nature as because of probability of maximum peak to peak voltage at a time is for one phase and very rare may be of two phases depending up on deterioration of insulation and repeated peak across each phase.
(II) Detection of Flash over The detection of arc as a fault is very tricky due to lower magnitude and also resembling the breaker status with selectivity among various normal and abnormal grid behavior and remote fault. The arc current will always reflect as a Zero sequence or Negative sequence current which can be detected typically as under.
Fig 1- Typical One and Half CB arrangement possible breaker flash over due to peak to peak voltage across CB open contacts Breaker
Fig 2a- Typical CT connection to detect breaker arc current as residual current for Generator directly connected to Grid
Fig 2b- Typical CT connection to detect breaker arc current as residual current for Generator connected to Grid through Transformer.
Reference- III
Page 2 of 7
3 Adaptive Logic for Breaker Flash over protection of Generator.
Typically the detection of Neutral over current from Generator or Generator transformer as referred in fig (2a & 2b) with Breaker OPEN status is interpreted as breaker flash over condition, and after certain small time delay tripping is declared out. Alternatively detection of Negative sequence current at Generator Neutral and phase side with Breaker status is also used for detection of breaker flash over condition.
(III) Action: Tripping of associated bus is essential here, because, merely tripping of Generator or excitation will also initiate tripping of Generator breaker and still the breaker is shunted by flash arc current, with the breaker is already in OPEN status, will subsequently cause initiation of LBB and after certain time delay of LBB timer will trip Bus breakers, which is delayed tripping as per LBB setting and initializing scheme.
(IV) Reliability & Selectivity.
(a) Limitation of above logic remains always within the reliability of the breaker status, because defective status of breaker obtained through breaker auxiliary switch many times falsify due to switch and related gearing alignment and contact issues. During the defective status of breaker associated with remote fault or short duration unbalance due to auto reclosing will cause to operate the
logic undesirably causing tripping of Generator and bus also. However use of GT neutral current with interlocking of GTCB may lead to mal-operation when the Breaker contact is defective, which enables the function during normal operation of unit. Further the setting of IN for Flash over detection is kept low enough for effective detection of flash current therefore any earth fault or unbalance in the grid / line may lead to operation of the function. Use of Generator Neutral CT will avoid the possibilities of above mal-operation during grid disturbances. However pure single phase flash may not be reflected at Generator Neutral side because of the zero sequence isolation at generator side for faults on GT side.
(b) In case of Generator connected with one and a half breaker bus arrangement detection of breaker flash over if actual, will not identify the breaker (Main or Tie) which has undergone flash over. Pl. refer fig 1, where it has been indicated that the Generator / Line can be connected either from Main or Tie breaker and therefore the flash over condition may be for either of two breaker. Thus the automatic and reliable detection of the breaker which has undergone the mishap must be identified and output action should be relevant to the identification. It is now obvious that action to isolate the Generator from Grid should be separate for each condition with unique identification. Merely detecting breaker flash over condition from the breaker status (composite may be of Main and Tie) and neutral current from Generator Transformer or Generator, with action for Tripping of Bus bar and Class A tripping for Generator is not sufficient as well not truly as per requirement defeating the aim for Breaker flash over protection intended so.
Above limitation for reliability and selectivity will place a threat to undesired tripping, delayed tripping or stability aspects too.
& Breaker OPEN Status
IN>
I2p>
I2n>
TRIP Excitation& BUS
& Breaker OPEN Status
TRIP Excitation& BUS
Fig 3- conventional logic to detect breaker flash over
Time
Time
Reference- III
Page 3 of 7
4 Adaptive Logic for Breaker Flash over protection of Generator.
(V) Solution: Addressing above limitations with feasible solution is possible with following considerations. As earlier discussed Broadly two criteria are required to detect breaker flash over (i) Breaker OPEN status (ii) sensing of Neutral current at GT or Negative sequence current at Generator terminal and (iii) third one essential for One and Half breaker Bus arrangement is, identifying the affected breaker. The output actions are then decided and forwarded with suitable circuit schemes. (a) Detection of Breaker Status.
Indirect assessment of breaker pole status can only be done by detecting flow of current through all three phases simultaneously registering a status in logic block and removing also the register status as low, i.e. using flipflop block triggered by current threshold. Also as per IEEE GUIDE FOR AC GENERATOR PROTECTION: Std C37.102-1006, 4.7.1 Open generator breaker flashover protection: ‘Generator breaker flashover may also be detected by breaker pole disagreement relaying. This relay monitors the three-phase currents flowing through the breaker and senses whether any phase is below a certain low threshold level (indicating an open breaker pole) at the same time that any other phase is above a substantially higher threshold level (indicating a closed or flashed-over pole).’ Logic using FlipFlop :
Above logic criteria are indicated at Fig 4. The flow of current through circuit breaker at HV side of Generator Transformer is considered as Phase current (Iph) and IN as GT neutral current. The OPEN status is detected when all three phases detect current below 2% (or practically as low possible setting available in relay which can be detected reliably. The OPEN status implies isolated
condition of Generator from grid and SET the FlipFlop. The output of FlipFlop makes input of AND gate high arming for Breaker flashover protection active. On detection of neutral current in GT or Negative sequence current at Generator will operate breaker flash over protection trip output. The normal operation of Generator can be considered as (i) Before & During synchronizing (ii) After Synchronizing and (iii) Grid fault when Generator is normal in service (iv) After isolating from grid. (i) Before & during synchronizing there
is no current flow and hence FlipFlop O/P is High. There will not be Iph and IN hence keeping the logic O/P as low.
(ii) Immediate after synchronizing there will be Iph >5% (or to be set as possible initial loading normally) resetting the FlipFlop after 200 mS.
(iii) Machine running normally will also prevail condition (ii) above.
(iv) After tripping of machine there will be Iph<2% as set above will immediately put function in service.
Fig 4- Breaker open status Detection logic based on current threshold using SR FlipFlop
SR Flip Flop
S
R
O
IPh <2% 3 Phase
IPh > 5% 3 Phase
T = 200 mS
& IN> 10 to 20%
T = 100 mS
TRIP ALL / BUS TRIP
Iph= Phase current, IN = GT Neutral current
For 1-1/2 Breaker bus, separate logic for Main and Tie breaker path current.
Reference- III
Page 4 of 7
5 Adaptive Logic for Breaker Flash over protection of Generator.
Logic using AND –OR blocks : Some of the basic versions of IEDs do not have the Flip Flop logical blocks, for which following logic using basic AND – OR and Timer blocks can be used as indicated at Fig-5 here under.
The lower current threshold for any one phase is monitored for OPEN status, this implies for resetting only when all three phases have current more than 2% i.e. all poles closed. The drop out timer is intended for keeping function armed for 200 mS. after synchronizing during which practically picking up of load by Generator more than 5%.
All four conditions mentioned in earlier paragraph for Generator are addressed here
also detecting reliably the breaker flash over condition.
The IN setting for 10 to 20% is intended for detecting lower arc current as low as 10% keeping in consideration normal maximum unbalance current.
The delay in output is chosen as 100 mS for stability and reliability purpose considering normal breaker closing time and inherent difference in closing of individual pole and also initial unbalance current owing to measurement and magnetizing effect for lower magnitude.
OUTPUT Action:-
The output action of the protection must isolate the Generator from grid and also removal of excitation to Generator. The conventionally action for a LBB protection is similar to the required one for Breaker Flashover condition.
The difference here is the detection at a lower magnitude of current without any trip initiation and also operating time is much less than typical LBB time of 200 to 250 mS.
Fig 5- Breaker open status Detection logic based on current threshold using AND-OR blocks.
Iph= Phase current, IN = GT Neutral current
For 1-1/2 Breaker bus, separate logic for Main and Tie breaker path current
&
IN> 10 to 20%
PU Timer = 100 mS
TRIP ALL (Class A & BUS TRIP
IPh-B <2%
IPh-c <2%
OR
IPh-A >5%
IPh-B >5%
IPh-C >5%
OR
DO Timer 200 mS
Annunciation & SOE in SCADA / DCS
IPh-A <2%
LBB Initiation
OR
TRIP ALL (Class A & BUS TRIP
Breaker Flash over O/P
I>20% Timer 250 mS
&
Fig 6: Output action for LBB and Breaker flash over protection
Reference- III
Page 5 of 7
6 Adaptive Logic for Breaker Flash over protection of Generator.
(V) Solution
(b) Selectivity of Breaker Flash over for One and Half Breaker system arrangement of Bus.
The One and half breaker arrangement is mainly having advantage of redundant connectivity for feeders. As shown in fig-7, the Phase current used for Breaker flash over can be referred from Main or Tie breaker CTs. The breaker flash over may occur for Main or Tie breaker during synchronizing or after isolation from Grid. So both the paths must be
separately detected for flash arc current i.e. Main and Tie breaker. The action required after detection of flashover are different as detailed below.
(1) MAIN Breaker flash over Tripping of Generator in Class-A
to trip excitation immediately and stop prime mover for any rise in voltage due to residual magnetism.
Open all bus breaker to isolate the affected breaker from grid.
(2) TIE Breaker flash over. Tripping of Generator in Class-A
to trip excitation immediately and stop prime mover for any rise in voltage due to residual magnetism.
Trip Main breaker of Line side. Send Direct Trip Transfer signal to
isolate source from remote end.
The logic described for Current detection as Iph-A-B-C in earlier paragraphs equally used separately for Main and Tie breaker. The CT input for Main and Tie paths are indicated in fig-7.
Two separate logics should be built as conveniently in bay IEDs like, BCU or back up relay with separate set of actions as described above.
Please note that the neutral current here and elsewhere in document is indicated from GT neutral, whereas can also be used as Negative sequence current of Generator Phase connection also.
The setting values shown here are from experienced values for a 660 MW Generator, however can be considered on typical machine behavior and normal operation.
TIE
Fig 7: Current detection for selectivity for One and Half Breaker arrangement for breaker flash over protection.
Line Feeder
Y
D
Main-Line
Main-Gen
G
Iph-TIE
Iph-MAIN G
IN
Reference- III
Page 6 of 7
7 Adaptive Logic for Breaker Flash over protection of Generator.
(VI) CONCLUSION;
The breaker flash over phenomena is a very typical one to detect reliably and opt for action like isolation of bus and feeder at minimum possible time. Typical logic are offered by various manufacturer as indicated earlier, however use of reliable detection and output action is a part of scheme designing and adaption of philosophy.
Reliable detection and comprehensive logic is now very easy to be built in IEDs having numerous logical blocks, I/O configuration and even use of GOOSE signals for interlocking.
Breaker flash over protection must be used as a critical protection function particularly the locations like sea shore based or saline atmosphere surrounded installations, where chances of external flash over is higher. The lower flash arc current may also cause severe oscillation and asynchronous energisation may lead to damage to TG set or transformer.
Careful design should be carried out to handle flash over detection and isolation for one and Half breaker arrangement.
(VII) REFERENCES a. IEEE Guide for AC Generator
Protection: Std C37.102-1006, 4.7.1
b. Guide for Ac Generator Protection, ANSI/IEEEC 37.102-1995.
c. Application manual AREVA Micom P34x relay.
(VIII) Acknowledgement:
Author takes opportunity to express gratitude and special thanks to HOD of P&M Group of Adani Power Ltd., his guideline & knowledge, Adani Power Training & Research Institute, APL management for granting permission and inspiration to think and present this paper.
(IX) Author:
Sanjay U. Bhatt, working as DGM (Protection) at Adani Power Ltd, Ahmedabad, (Protection Automation & Metering Department), from January 2012.
B.E. (Electrical) -1993 from L.E. College Morvi , Gujarat (India).
Worked: o In G.S.F.C.-Jamnagar, as Ele.
Maintenance Engr. o In Govt. Polytechnic, as a lecturer on
clearing GPSC. o In GSECL, Gujarat as Junior Engineer
at Sikka Power station as Electrical Testing & Maintenance engineer and at SLDC during commissioning of SCADA and related system.
o As Deputy Engineer at GSECL corporate office as Testing engineer.
Reference- III
Page 7 of 7