Experimental Features Emily Parkany, Ian Anderson VTrans – Policy, Planning, and Intermodal Development Division Policy, Planning, and Research Bureau - Research Section Composite Arch Bridge Composite Arch Bridge (CAB) is an experimental feature constructed with fiber reinforced polymer ribbings to form an arch. This design creates a lightweight, easy to install bridge system with good waterway characteristics and reduced labor time. After four years of study, the arches have shown very minor expansion and contraction that is well within the ability of the arches to redistribute their loads. Minor bowing has occurred on the headwalls due to the settling of materials. Overall, the CAB system is performing well. Randolph Park and Ride Pervious Asphalt Study Impervious areas increase stormwater runoff and decreased water quality. The Randolph Park and Ride has been converted from porous concrete to pervious asphalt, a material that is expected to survive Vermont’s harsh climate. Constructed in 2018, the park and ride will be tested for infiltration rates, using a constant head test, over the course of its service life. The average infiltration rate at completion, and gain at 2 months, were found to be significantly higher than any potential rainfall event in Vermont, at 383 and 314 in/hr (current min 110 and max 950 in/hr) Pavement Markings Pavement markings are a critical safety feature for local roads and interstates. The VTrans Research Section is currently studying the durability, constructability and retroreflective capabilities of pavement marking tapes on US-302 in Berlin and liquid paints on I-89 between Brookfield and Montpelier. The studies incorporates different tape and liquid pavement markings and will report on the durability and retroreflectivity of tapes and liquids over their service life. Data from these projects has been shared with the Pavement Marking Committee and is being used to inform pavement markings moving forward. Ongoing Experimental Feature Projects Projects in the process of being finished, with draft reports and ongoing efforts to close projects (some reports posted: VTrans.Vermont.gov/docs/completed ) Pavement Marking Tape Study Randolph Park & Ride Porous Asphalt Study Liquid Pavement Marking Study Assessment of GPR to Verify Concrete Elements and Backfill Void Conditions Fiber Reinforced Polymer (FRP) Strips HAWK Traffic System Jahn Permeable Mortar System Composite Arch Bridge (Bridge in a Backpack) SuperSlab Sterling Lloyd Eliminator Waterproofing Bridge Membrane System Poly-Carb Flexogrid Bridge Deck Overlay System Bridge Preservation BDM Waterproofing Membrane System

Upload: others

Post on 20-Aug-2020

6 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: No Slide Title · Composite. Arch Bridge. Composite Arch Bridge (CAB) is an experimental feature constructed with fiber reinforced polymer ribbings to form an arch. This design creates

Experimental FeaturesEmily Parkany, Ian Anderson

VTrans – Policy, Planning, and Intermodal Development Division Policy, Planning, and Research Bureau - Research Section

Composite Arch BridgeComposite Arch Bridge (CAB) is an experimental feature constructed with fiberreinforced polymer ribbings to form an arch. This design creates a lightweight,easy to install bridge system with good waterway characteristics and reducedlabor time.

After four years of study, the arches have shown very minor expansion andcontraction that is well within the ability of the arches to redistribute theirloads. Minor bowing has occurred on the headwalls due to the settling ofmaterials. Overall, the CAB system is performing well.

Randolph Park and Ride Pervious Asphalt StudyImpervious areas increase stormwater runoff and decreased water quality. TheRandolph Park and Ride has been converted from porous concrete to perviousasphalt, a material that is expected to survive Vermont’s harsh climate.

Constructed in 2018, the park and ride will be tested for infiltration rates, usinga constant head test, over the course of its service life. The average infiltrationrate at completion, and gain at 2 months, were found to be significantly higherthan any potential rainfall event in Vermont, at 383 and 314 in/hr (current min110 and max 950 in/hr)

Pavement MarkingsPavement markings are a critical safety feature for local roads and interstates.The VTrans Research Section is currently studying the durability,constructability and retroreflective capabilities of pavement marking tapes onUS-302 in Berlin and liquid paints on I-89 between Brookfield and Montpelier.

The studies incorporates different tape and liquid pavement markings and willreport on the durability and retroreflectivity of tapes and liquids over theirservice life. Data from these projects has been shared with the PavementMarking Committee and is being used to inform pavement markings movingforward.

Ongoing Experimental Feature ProjectsProjects in the process of being finished, with draft reports and ongoing efforts to close projects (some reports posted: VTrans.Vermont.gov/docs/completed)• Pavement Marking Tape Study• Randolph Park & Ride Porous Asphalt Study• Liquid Pavement Marking Study• Assessment of GPR to Verify Concrete Elements and Backfill Void Conditions• Fiber Reinforced Polymer (FRP) Strips• HAWK Traffic System • Jahn Permeable Mortar System• Composite Arch Bridge (Bridge in a Backpack)• SuperSlab• Sterling Lloyd Eliminator Waterproofing Bridge Membrane System• Poly-Carb Flexogrid Bridge Deck Overlay System• Bridge Preservation BDM Waterproofing Membrane System