Operational Plan 2010
Nguti Council
Organizer: Nguti Council
Co-Sponsor: Programme for the Sustainable Management of NaturalResources (PSMNR) South West Region.
Facilitated by: Municipal Development Counselling (MUDEC) Group,Buea
Nguti Operational Plan 2010 ii
TABLE OF CONTENT
LIST OF ABBREVIATIONS ................................................................................................. iii
EXECUTIVE SUMMARY .......................................................................................................1
PART 1 : Prioritized activities which could be executed in 2010 based on the availableresources - grouped in 5 programs.............................................................................................3
PROGRAMME OBJECTIVE 1: BASIC INFRASTRUCTURE..........................................4PROGRAMME OBJECTIVE 2: ACCESS TO SOCIAL BASIC SERVICES ....................9PROGRAMME OBJECTIVE 3: LOCAL ECONOMIC DEVELOPMENT......................14PROGRAMME OBJECTIVE 4: NATURAL RESOURCE MANAGEMENT .................18PROGRAMME OBJECTIVE 5: FUNCTIONAL CAPACITY OF THE COUNCIL........21
PART 2 : The Budget .............................................................................................................26BUDGET SUMMARY .......................................................................................................27
CONCLUSION .......................................................................................................................28
RECOMMENDATIONS: .......................................................................................................28
ANNEXES:..............................................................................................................................29Technical Follow-Up Committee ........................................................................................30Picture Gallery.....................................................................................................................31Attendance list participants Operational Workshop 2010...................................................32Strategies to communicate Nguti Council 2010 operational Plan .......................................34Monitoring and Evaluation Plan..........................................................................................35Reporting Format (Sample) .................................................................................................36Suggested project profile .....................................................................................................37
Nguti Operational Plan 2010 iii
LIST OF ABBREVIATIONS
Abbreviation Meaning
ANC Antennal Clinic
CAFECO Cameroon Agricultural and Forestry Exploitation Company
CAMTEL Cameroon Telecommunications
CEAC Center for Economic Skills Transfer
CIG Common Initiative Group
CEFAM Local Government Training Center
CFMC Council Forest Management Committee
DED German Development Service
DMO District Medical Officer
EISERVI Education Information Service International
ERUDEF Environment and Rural Development Foundation
FEICOM Council Support Fund
FAO Food and Agricultural Organization
FGF Forest Governance Facility
GTZ German Technical Assistance
HC Health Center
HIV/AIDS Human Immune Virus/ Acquired Immune Deficiency Syndrome
HPI Heifer Project International
IPT Intermittent Preventive Treatment
IRAD Institute for Rural Agriculture Development
MUDEC Municipal Development Counseling Group
MINADER Ministry of Agriculture and Rural Development
MINFI Ministry of Finance
MINEDUB Ministry of Basic Education
MINESEC Ministry of Secondary Education
MINPLADAT Ministry of Plan and Regional Development
MINEPAT Ministry of Planning and Regional Development
MINEPIA Ministry of Livestock and Animal Husbandry
MINFOF Ministry of Forestry and Wildlife
MINSANTE Ministry of Public Health
Nguti Operational Plan 2010 iv
MP Member of Parliament
MTN Mobile Telephone Network
MVFMC Main Village Forest Management Committee
NGO Non-Governmental Organization
NBDC National Book Development Council
NTFP Non Timber Forest Products
OSRI Organization for Sustainable Rural Infrastructure
PIAISI Project to Support Actors in the Informal Sector
PSMNR-SWR Programme for the Sustainable Management of Natural Resources-
South West Region
PTA Parent Teacher Association
RDARD Regional Delegation of Agriculture and Rural Development
RMC Road Maintenance Committee
RUMPI RUMPI Area Participatory Development Project
SOWEFCU South West Farmers Cooperative
SOWEDA South West Development Authority
SSV Sales Standing Volume
SWSFH South West Special Fund for Health
TFC Technical Follow-up Committee
TOR Terms of Reference
VCDA Village Council Development Association
VFMC Village Forest Management Committee
VPT Village Planning Team
VTC Village Traditional Council
WMC Water Maintenance Committee
WWF World Wildlife Fund
Nguti Operational Plan 2010 1
EXECUTIVE SUMMARY
The Elaboration of the Operational Plan 2010 for Nguti Council was done within the
framework of the participatory planning process of the municipality. The activity took place
from the 25th to 27th of August 2009 in the Council chambers. 30 participants (10 women)
were invited but 43 persons (16 women) took active part during the deliberations.
Participants represented all 9 clans in the municipality and had diverse socio economic and
cultural backgrounds. The activity was executed after the elaboration of the 5 year (2010 to
2014) Strategic Plan for the municipality. The main focus was to:
Harmonize the Strategic Development Plan for Nguti Council
Identify prioritized strategies for intervention
Develop the Operational Plan (2010) for Nguti Council
Define the Monitoring and Reporting processes for the operational plan.
In order to elaborate the operational plan, the Strategic Plan was first of all harmonized. This
entailed the following:
Prioritizing the various programme and project objectives;
Ensuring that the details in the Project Planning Matrix are coherent, exhaustive,
realistic and not contradictory to each other.
Thus the operational plan was centered on five main programme objectives:
1) Basic Infrastructure in the municipality improved (P1)
2) Access to basic social services in the municipality improved (P2)
3) Local economy of the municipality improved (P3)
4) Natural resource management in the municipality improved (P4)
5) Functional capacity of the council strengthened (P5)
The operational plan is presented in two main parts. The first part contains the prioritized
activities which could be executed in 2010 based on the available resources. It also highlights
a monitoring plan, a reporting format, a communication plan as well as a basic format for
project profiling which can facilitate the smooth functioning of the technical follow up
committee. These documents are found in the annex of this plan.
Nguti Operational Plan 2010 2
The second part (the budget) contains estimates of the activities that were prioritized in the
first part. From analysis on the potential sources of revenue, the Council can raise about
eighty six million four hundred and thirty seven thousand four hundred and forty francs
(86,437,440) FCFA for the fiscal year 2010 as follows: seventy million one hundred
thousand (70,100,000 FCFA) from the Council Support Fund (FEICOM), three million
(3,000,000 FCFA) from the MP Micro Project Grants, ten million (10,000,000 FCFA) from
potential sales of standing volume and three million three hundred thousand (3,300,000
FCFA) from the DED. The 2010 operational plan expenditures can be sub divided into five
programme objectives as follows: P1 (3,935,000 FCFA), P2 (6,265,000 FCFA), P3
(5,315,000 FCFA), P4 (12,287,440 FCFA) and P5 (58,635,000 FCFA).
In order to ensure a high degree of success in the execution of the activities identified in the
2010 operational plan, the Council must engage in a concerted effort at fundraising
(13,000,000 FCFA is needed beside the current main support from FEICOM and DED). The
council also has to streamline certain allocations that are found in the current (2009) budget.
This will require that the Technical Follow-up Committee receive maximum support from
the Council and the communities. The committee has been coached and members are aware
of their terms of reference. It is recommended for them to produce quarterly action plans in
order to keep track, monitor as well as produce reports of ongoing activities.
This plan has been developed in the most participatory manner involving a cross section of
the population of the municipality and should be given its widest publicity. Management
should use it as the base document during the elaboration of the 2010 Municipal Budget
which will become the finance law of Nguti after adoption by the deliberative organ of the
Council.
Nguti Operational Plan 2010 3
PART 1 : Prioritized activities which couldbe executed in 2010 based on the available
resources - grouped in 5 programs
Nguti Operational Plan 2010 4
PROGRAMME OBJECTIVE 1: BASIC INFRASTRUCTUREObjectives Activities Indicators With whom Deadline Resources Budget
CFAPotential Funding
Sources1. ProgrammeObjective:InfrastructureImproved1.1. SpecificObjective:ElectricityImproved1.1.1 Mobilization ofResources Improved
1.1.1.1 IdentifySources of Funding
At least 03 sourcesof funding identifiedand contacted
InfrastructureCommittee, NatureCameroon
March2010
Transport,Communication,Stationeries
85,000 MP Funds,
1.1.1.2 Mobilize Fundsfor electrification
At least 01 fundingsource forelectrificationsecured
FinanceCommittee, NatureCameroon
Sept 2010 Transport,Communication,Stationery
100,000 MP Funds, Elites
1.2. SpecificObjective:Road NetworkImproved1.2.1 RoadRehabilitation andMaintenanceImproved
1.2.1.1 Lobby forfunds for roadmaintenance
At least 02 fundingsources secured
InfrastructureCommittee,SOWEDA, PublicWorks
Dec 2010 Transport,Stationery,Communication
100,000 FEICOM,MP Funds
1.3. SpecificObjective:Access to Pipeborne waterImproved
Nguti Operational Plan 2010 5
Objectives Activities Indicators With whom Deadline Resources BudgetCFA
Potential FundingSources
1.3.1 Maintenance ofPipe Borne WaterImproved
1.3.1.1 Carry outStudies onrehabilitation on pipeborne water in twoclans (Bebun andNgemengoe)
02 studies carriedout in two clans,reports producedand circulated
InfrastructureCommittee, OSRI,SOWEDA
September2010
Engineer,Transport,Stationery,Communication
800,000 FEICOM, WIJMA
1.3.2 Contaminationof nearby StreamsReduced
1.3.2.1 Sensitizepopulation in themunicipality on thehealthy use of nearbystreams
One sensitizationmeeting organizedin all 9 clans
Health Committee April2010
Transport,Stationery,Communication,Resourcepersons
150,000 SSV, WIJMA,MP Funds
1.3.2.2 PlaceTraditional Bans onrivers in the hinterlands
Traditional bans thatare respected placedon four drinkablestreams
Health Committee April2010
Resourcepersons,Transport
80,000 MP Funds
1.4. SpecificObjective:CommunicationSignals Improved1.4.1 Access toCommunicationEquipment increased
1.4.1.1 Carry out studyand Lobby for theinstallation of Fixedtelephone lines in Ngutiand Manyemen towns
One study con-ducted and at least02 contacts securedfor the installation offixed telephone lines
InfrastructureCommittee,CAMTEL
Oct 2010 Engineer,Transport,Stationery,Communication
455,000 FEICOM
1.4.2 PrivateCommunicationStations Increased
1.4.2.1 Meet with MTNand Orange and discussthe possibility ofincreasing networkcoverage in themunicipality
At least twomeetings held andaction planselaborated
InfrastructureCommittee,MTN& OrangeNet Work
July 2010 Lodging,Transport,Stationery,Communication
100,000 FEICOM
Nguti Operational Plan 2010 6
Objectives Activities Indicators With whom Deadline Resources BudgetCFA
Potential FundingSources
1.5. SpecificObjective:RecreationalFacilities Increased1.5.1 RecreationalFacilities Developed
1.5.1.1 Rehabilitateexisting RecreationalFacilities (recreationalgardens)
At least 02recreational facilitiesrehabilitated andmade functional
InfrastructureCommittee,Ministry ofTourism
Oct 2010 Labour,Transport, Treeand flowerSeedlings,Materials andCommunication
220,000 SSV, St John ofGod Nguti,ManyemenHospital
1.5.1.2 MaintainRecreational Facilities
One staff employedand regularly main-tained recreationalfacilities
InfrastructureCommittee
Oct 2010 Labour,transport
120,000 FEICOM
1.5.2 FundsIncreased
1.5.2.1 Lobbying forFunds to increasenumber ofRecreational facilitiesand to rehabilitateexisting ones
At least 01 fundingorganizationidentified and fundsdisbursed
InfrastructureCommittee
Nov.2010
Transport,Stationery,Communicationand Resourcepersons
195,000 FEICOM
1.5.2.2 Sensitize theinhabitants of Ngutiand Manyemen on theuse of recreationalfacilities
At least 02sensitizationmeetings conducted
InfrastructureCommittee, NatureCameroon
Aug 2010 Transport,Stationery,Communicationand Resourcepersons
220,000 FEICOM
1.6. SpecificObjective:Town and HousingPlanning Improved
Nguti Operational Plan 2010 7
Objectives Activities Indicators With whom Deadline Resources BudgetCFA
Potential FundingSources
1.6.1 Implementationof Government LawsImproved
1.6.1.1 SensitizePopulation in Nguti andManyemen on townand housing planninglaws
At least 02sensitizationmeetings organized
InfrastructureCommittee, NatureCameroon, Min. ofUrbanDevelopment andHousing,
March2010
Transport,Stationery,Communication
125,000 SSV, WIJMA,MP Funds
1.6.1.2 Verify the status(building plan) of allbuildings in Nguti andManyemen towns
At least 50% ofpermanent buildingsstatus verified
InfrastructureCommittee, Min.of UrbanDevelopment andHousing,
Dec 2010 Transport,Stationery,Communication
60,000 SSV, WIJMA
1.6.1.3 ReinforceGovernment Laws onTown and HousingPlanning in Nguti andManyemen anddefaulters punished
Copies of the Lawdistributed to allquarter heads
InfrastructureCommittee, Min.of UrbanDevelopment andHousing,
Sept 2010 Transport,Stationery,Communication
60,000 SSV, WIJMA
1.6.2 Buildingswithout permitsReduced
1.6.2.1 ImplementMunicipal Master Planin Nguti andManyemen towns
At least 95 % of newstructures havebuilding permits
InfrastructureCommittee ,Min.of UrbanDevelopment andHousing,MINEPAT, StateProperty and LandTenure
Dec 2010 Transport,Stationery,Communication
60,000 SSV, WIJMA
1.6.2.2 ControlBuilding in Nguti andManyemen towns
Conduct monthlycontrol visits
InfrastructureCommittee, Min.of UrbanDevelopment andHousing,MINEPAT,
End ofeachmonth(Jan- Dec2010)
Transport,Stationery,Communication
60,000 SSV, WIJMA
Nguti Operational Plan 2010 8
Objectives Activities Indicators With whom Deadline Resources BudgetCFA
Potential FundingSources
1.6.3 Master PlanRegularly updated
1.6.3.1 Train TownPlanning Personnel
01 training organizedfor CouncilPersonnel on NgutiMaster Plan
InfrastructureCommittee,CEFAM,Min. of UrbanDevelopment andHousing
Sept2010
Transport,Stationery,Communicationand Resourcepersons
170,000 FEICOM
1.6.3.2 Update MasterPlan
Nguti Master Planupdated and put touse
InfrastructureCommittee, Min.of UrbanDevelopment andHousing,
Oct 2010 Resourcepersons andStationery
60,000 FEICOM
1.7. SpecificObjective:MarketInfrastructureImproved andrevenue increased1.7.1 Study onMarkets carried out
1.7.1.1 Carry out studyon existing markets inElumba and Babubock
01 study conducted,report produced andcirculated
InfrastructureCommittee
September2010
Engineer,Transport,Stationery,Communication
500,000 FEICOM,SOWEDA
1.7.2 Mobilizationof ResourcesImproved
1.7.2.1 Train RevenueCollectors
At least 01 trainingorganized for allCouncil RevenueCollectors
FinanceCommittee,CEFAM,MUDEC Group
June2010
Resourcepersons,TrainingMaterials
165,000 FEICOM
1.7.2.2 Review thecollection of MarketTolls
Revenue fromexisting marketsincreased by at least80%
FinanceCommittee,MUDEC Group,CEFAM
July 2010 Stationary,transport
50,000 FEICOM
Nguti Operational Plan 2010 9
PROGRAMME OBJECTIVE 2: ACCESS TO SOCIAL BASIC SERVICESObjectives Activities Indicators With whom Deadline Resource Budget
(CFA)Potential
Funding Sources2. ProgrammeObjective: Socialservices improved2.1 Specificobjective: Healthstatus improved2.1.1 Access to
health servicesimproved
2.1.1.1 Lobby forrecruitment of nursesin Mbetta HealthCenter
At least 01 nurserecruited and takenservice
Social committee,MINSANTE
Aug2010
Transport,Public Relations
95,000 MP Funds
2.1.1.2 Lobby forSupply ofConsultation andLaboratoryequipment inMbetta Health Center
Basic equipmentsecured
Social committee,MINSANTE
Dec2010
Transport,Public Relations
95,000 MP Funds
2.1.2 Prevalence ofHIV/AIDSreduced
2.1.2.1 Sensitizecommunities onHIV/AIDs
Sensitizationworkshops onHIV/AIDS in 18communities (2 perclan) organized
Social committee,MINSANTE,REACHOUT
Nov2010
Stationery ,Transport,Allowances &Technicians
1,540,000 FEICOM, GTZ,SWSFH,WIJMA,
2.1.3 Diseaseoutbreaks in thecommunitiesreduced
2.1.3.1 Identify andTrain SanitaryCommittees
At least 09SanitaryCommittees (oneper clan)identified, trainedand functional
Social committee,MINSANTE
June2010
Resourcepersons, &Allowances
300,000 SSV, WIJMA,MP Funds
2.1.3.2 Sensitize thepopulation onhygiene andsanitation
At least 9Sensitizationmeetings organized(01 per clan)
Social committee,Nature Cameroon
Oct2010
Transport,Allowances,Materials
450,000 SSV, St John ofGod, ManyemenHospital,WIJMA
Nguti Operational Plan 2010 10
Objectives Activities Indicators With whom Deadline Resource Budget(CFA)
PotentialFunding Sources
2.1.3.3 Enforce cleanup campaigns inNguti and Manyementowns
Clean upcampaignsorganized monthly
Social committee,St John of GodNguti, ManyemenHospital,
At theend ofeachmonth
Transport, 120,000 FEICOM
2.1.3.4 Control strayanimals in themunicipality
Number ofcomplaints relatedto stray animals inthe municipalityreduced by at least80%
Social committee,St John of GodNguti, ManyemenHospital,Nature Cameroon
Dec2010
Transport, 150,000 FEICOM
2.1.4 Endemicdiseases reduced
2.1.4.1 Distributemectizan
At least 44 CDDsare supported todistribute mectizanin all clans
Social committeeMINSANTE,
Oct 2010 Payment ofCDD
100,000 FEICOM, GTZ
2.1.4.2 Sensitizewomen on the use ofIPT & ferroussupplement in ANC
At least 500pregnant womencome for IPTduring ANC in allhealth centers
Social committeeMINSANTE,
Dec2010
Drugs 200,000 FEICOM, GTZ
2.1.4.3 Sensitizewomen onvaccination &vitamin A (EPI) forChildren below 5 y
At least 1,200childrenvaccinated in EPIin all 9 clans
Social committee,MINSANTE,
Dec2010
Vaccines andinjectionmaterials, gas
250,000 FEICOM, GTZ
2.1.4.4 Sensitizeyouth on use offamily planningservices inHC/Hospitals
At least 9 planninghealth servicesfunctional in themunicipality (oneper clan)
Social committee,MINSANTE
Dec2010
Contraceptives(Pills, IUD,DEPO)
100,000 FEICOM, SouthWest SpecialFund for Health
Nguti Operational Plan 2010 11
Objectives Activities Indicators With whom Deadline Resource Budget(CFA)
PotentialFunding Sources
2.1.4.5 Lobby for thecreation of MutualHealth Organizations
At least 01 studyconducted for thecreation of oneMutual HealthOrganization in themunicipality
Social committee Dec2010
Resourcepersons
100,000 FEICOM, GTZ,South WestSpecial Fund forHealth
2.1.4.6 Assistcommunities toidentify diseasesunder surveillance
At least onedisease case undersurveillanceinvestigated inNguti district
Social committee,MINSANTE,
Dec2010
Stationery,Transport,TechnicalAssistance
85,000 FEICOM, GTZ,South WestSpecial Fund forHealth
2.2 Specificobjective: Level ofeducation increased2.2.1 Number of
didacticmaterialsincreased
2.2.1.1 Supplydidactic materials
01 primary schoolper clan in themunicipalityreceive didacticmaterials
Educationalcommittee,MINESEC,MINEBASE
August2010
Chalk, desks,books, benches,
1,000,000 MP, GuinnessCameroon,NBDC, EISERVI
2.2.2 Scholarizationrate of the girlchild increased
2.2.2.1 Awardscholarship for theeducation of girlchild
At least 50 primary/ 25 secondaryschool girls receivescholarships
Educationcommittee
August2010
Books, schoolfees, Uniforms
500,000 FEICOM
2.2.3 Number oftrained teachersincreased
2.2.3.1 Lobby for therecruitment of trainedpersonnel to thehinterland schools
New teacherstransferred toprimary andsecondary schoolsand take upservice
EducationCommittee,MINEBASE,MINESEC,PTA
September 2010
Transport,Public relations
100,000 MP Funds
Nguti Operational Plan 2010 12
Objectives Activities Indicators With whom Deadline Resource Budget(CFA)
PotentialFunding Sources
2.3 Specificobjective: Genderinequality andinequity reduced2.3.1 Women control
over resourcesincreased
2.3.1.1 Sensitizewomen on landownership
At least 10 morewomen own landin Nguti andManyemen towns
2nd Deputy Mayor,Min of WomenEmpowerment andthe Family, NatureCameroon
Dec2010
Resourcepersons,Communication,Transport
100,000 MP Funds
2.3.2 Women indecision makingpositionsincreased
2.3.2.1 Encourage /support womenparticipation inpolitics
At least 30 womentrained ontechniques onrunning for publicoffice
2nd Deputy Mayor,Min of WomenEmpowerment andthe Family,MUDEC Group
Dec2010
Resourcepersons,Communication,Transport
120,000 MP Funds
2.3.2.2 Appointwomen in CBO(VCDA,TC)
At least 3 womenappointed in CBOin each clan
2nd Deputy Mayor,Min of WomenEmpowerment andthe Family, NatureCameroon
Dec2010
Communication,Stationery
50,000 MP Funds
2.3.3 Women takingdecisionsincreased
2.3.3.1 Developstrategies to enablewomen takedecisions
At least 50% ofwomen trained ontechniques on run-ning for publicoffice takeappropriatedecisions regularly
2nd Deputy Mayor,Min of WomenEmpowerment andthe Family, NatureCameroon
Dec2010
Communication,Stationery
50,000 MP Funds
2.3.4 Number ofEducated girlsincreased
2.3.4.1 Sensitizecommunities on theimportance ofeducating the girlchild
02 sensitizationmeetings organizedin each clan
2nd Deputy Mayor,Min of WomenEmpowerment andthe Family, NatureCameroon
Dec2010
Communication,Stationery
100,000 MP Funds
Nguti Operational Plan 2010 13
Objectives Activities Indicators With whom Deadline Resource Budget(CFA)
PotentialFunding Sources
2.4 Specificobjective: Positivecultural practicesenhanced2.4.1 Organization of
cultural eventsincreased
2.4.1.1 Identifyrepresentatives ofcultural groups perclan
At least 02 culturalgroups identifiedper clan
MunicipalCouncilors, Min.of Culture, NatureCameroon
March2010
Communication 50,000 MP Funds
2.4.1.2 Organizemeetings withcultural associationsand traditionalcouncils to organizecultural events
At least 01meetings organizedper clan
MunicipalCouncilors, Min.of Culture,Min. of Tourism
March2010
Transport,Stationery
180,000 MP Funds
2.4.2 Education ofyouths ontraditionalvalues increased
2.4.2.1 Promote theuse of locallanguages in thecommunities
At least 01 culturalcontest involvingyouths of all 9clans organized
Social committee,Min. of Culture,
Dec2010
CulturalMaterials
100,000 MP Funds,WIJMA
2.4.2.2 Sensitizeyouth on culturalactivities
01 sensitizationcampaign per clan
Social Committee,Min. of Culture,
Dec2010
Transport,Materials
180,000 MP Funds,WIJMA
2.4.3 Cultural revivalstrategiesincreased
2.4.3.1 Sensitizepopulation againstnegative culturalvalues
At least 01sensitizationcampaign per clan
Social Committee,Min. of Culture,
Dec2010
Transport,Materials
180,000 MP Funds,WIJMA
Nguti Operational Plan 2010 14
PROGRAMME OBJECTIVE 3: LOCAL ECONOMIC DEVELOPMENTObjectives Activities Indicators With whom Deadline Resource Budget
FCFAPotential Funding
Sources3. Programmeobjective:Local EconomyImproved3.1 Specificobjective:Agriculturalproduction andproductivityincreased3.1.1 Crop
destruction byanimalsreduced
3.1.1.1 Mobilize andsensitize thepopulation on theneed to confinedomestic animals
One meetingorganized for 18persons (2 per clan)with at least 7women inattendance
2nd Deputy Mayor,MINADER,MINEPIA
Feb2010
Materials,Transport
180,000 FEICOM
3.1.1.2 Control ofstray domesticanimals
A functionalControl Team of 18persons is created(two per clan fromsanitationcommittee)
MunicipalCouncilors,MINADER,MINEPIA
July2010
Resourcepersons,Transport,Motivation
60,000 MP Funds
3.1.2 Soil fertilityimproved
3.1.2.1 Sensitizefarmers on improvedagricultural practices
01 Sensitizationmeeting held perclan
1st Deputy Mayor,MINADER
March2010
Transport,Sensitizationmaterials
100,000 SVV, RUMPIproject
3.1.3 Use of farminputsincreased
3.1.3.1 Supplyimproved plantingmaterials to farmers
At least 10,000cassava cuttings,100kg of maize,1,000 plantainsuckers supplied totrained farmers
1st Deputy Mayor,MINADER
Sept2010
Transport,Materials,Communication
500,000 SVV, RUMPIproject
Nguti Operational Plan 2010 15
Objectives Activities Indicators With whom Deadline Resource BudgetFCFA
Potential FundingSources
3.1.3.2 Conductfeasibility study onthe development of afarmer cooperative
01 studyconducted, reportproduced andcirculated
1st Deputy Mayor,MINADER
June2010
Communication,Resourcepersons
300,000 SVV, RUMPIProject
3.1.3.3 Support theorganization andmanagement ofAgriculturalCooperative
01 agriculturalcooperativeorganized forfarmers in themunicipality
1st Deputy Mayor,MINADER
Nov2010
Communication,Resourcepersons
550,000 SVV, RUMPIProject
3.1.3.4 Facilitate theorganization of agricshow exhibitions
01 show organizedin the municipality
1st Deputy Mayor,MINADER, NatureCameroon
Nov2010
Communication,Technicians
1,200,000 SSV, SOWEDA,RUMPI project
3.1.4 Storage,processingand marketingimproved
3.1.4.1 Train farmerson storage, processingand marketing ofmaize, cassava ,egusiand NTFPs
01 trainingorganized for atleast 36 farmers (4per clan)
1st Deputy Mayor,MINADER,MUDEC Group
June2010
Resourcepersons,Trainingmaterials,Transport
410,000 SSV, SOWEDA,RUMPI Project
3.1.4.2 Lobby forgrants to purchasemachines and ovensfor farmers in LowerMbo, Banyu, Lower& Upper Nkonghoclans
At least 03machines and ovenpurchased anddistributed
1st Deputy Mayor,MINADER
Dec2010
Materials,Transport,Resourcepersons
110,000 SSV, RUMPIProject, SOWEDA,
3.2 Specificobjective:Livestockproduction andproductivityincreased
Nguti Operational Plan 2010 16
Objectives Activities Indicators With whom Deadline Resource BudgetFCFA
Potential FundingSources
3.2.1 Knowledge inlivestockproductionincreased
3.2.1.1 Train farmerson improved animalhusbandry
01 three dayworkshoporganizedinvolving 54persons ( one pervillage) with atleast 20 women inattendance
1st Deputy Mayor ,MINEPIA
July2010
Resourcepersons,Trainingmaterials,Transport,Communication
360,000 FEICOM,SOWEDA,HPI
3.2.2 Access toanimal feedand drugsimproved
3.2.2.1 Facilitate theestablishment ofdealers in animal feedand drugs in themunicipality
At least 02 dealersin animal feed anddrugs operate in themunicipality
1st Deputy Mayor,MINEPIA
Nov2010
Communication,Transport,Resourcepersons
55,000 FEICOM,HPI
3.2.3 Sources ofimprovedbreedsincreased
3.2.3.1 Facilitatecontacts with Partners
At least 50livestock breederssecure improvedbreeds
1st Deputy Mayor,MINEPIA
Sept2010
Communication,Transport,Resourcepersons
55,000 FEICOM,HPI, SOWEDA
3.2.3.2 Organizevaccinationcampaigns
02 vaccinationcampaignsinvolving allbeneficiary farmers
1st Deputy Mayor,MINEPIA
Oct2010
Drugs,Technicians,
550,000 FEICOM,HPI,SOWEDA
3.3 Specificobjective:Business venturesincreased3.3.1 Business
managementtechniquesimproved
3.3.1.1 Identifyvarious types ofbusiness ventures
At least 20business venturesidentified
S.G., MUDEC,PIAISI
March2010
Resourcepersons,Transport
30,000 MP Funds
3.3.1.2 Facilitatetraining on businessmanagementtechniques
01 workshop orga-nized for 40 parti-cipants of which 20are women
S.G. , MUDECGroup, PIAISI
July2010
Resourcepersons,Transport,Materials
375,000 FEICOM
Nguti Operational Plan 2010 17
Objectives Activities Indicators With whom Deadline Resource BudgetFCFA
Potential FundingSources
3.3.2 Investment byeconomicoperatorsincreased
3.3.2.1 Facilitate theestablishment offinancial institutionsin the municipality
At least 01financial institutionestablished andgive loans to 30economic operators(10 women )
S.G. , MUDECGroup
Oct2010
Resourcepersons,Transport,Materials
110,000 SSV,Ntale VillageBank, Nguti CreditUnion
3.4 Specificobjective: Tourismsector improved3.4.1 Undeveloped
tourist sitesimproved
3.4.1.1 Carry out astudy on the existingand potential touristattractions in themunicipality andelaborate aparticipatorydevelopment plan
01 study carriedout and adevelopment planelaborated
InfrastructureCommittee, NatureCameroon, Min ofTourism
April2010
Transport,Resourcepersons,Materials
110,000 FEICOM
3.4.2 Local tourismstrategiesincreased
3.4.2.1 Publicizeexisting tourist sites
Organize 01meeting withvillages concernedand produce/distributesensitizationmaterials on sites
InfrastructureCommittee,Ministry ofTourism, NatureCameroon
April2010
Resourcepersons,Materials,Transport
260,000 FEICOM
Nguti Operational Plan 2010 18
PROGRAMME OBJECTIVE 4: NATURAL RESOURCE MANAGEMENTObjectives Activities Indicators With whom Deadline Resource Budget Potential
Funding Sources4. Programmeobjective:Natural ResourceManagementImproved4.1 Specificobjective:Management offorest resourcesimproved4.1.1 Forestmanagementcapacity improved
4.1.1.1 Provideremuneration forCFO
Remunerationprovided monthly
MunicipalTreasurer
Monthly Stipend,Training,Transport
3,337,440 DED
4.1.1.2 Provideinstitutional supportfor council forestactivities
Support madeavailable onquarterly basis
MunicipalTreasurer
Quarterly Materials,Transport,Feeding,Equipment
3,000,000 FEICOM,PSMNR-SWR
4.1.2 Decline inNTFPsreduced
4.1.2.1 Sensitize ondomestication ofNTFPs all villages(excluded councilforest villages)
01 sensitizationcampaignorganized per clanand 9 NTFPsdomestication unitsput in place in themunicipality
Council Forester,MINFOF,ERUDEF, NatureCameroon
Sept2010
Resourcepersons,Communication,Materials
330,000 FEICOM,FAO, GTZ,PSMNR-SWR
4.1.2.2 Produceseedlings of selectedNTFPs
09 nurseries (oneper clan) each withat least 1,000seedlingsestablished
Council Forester,MINFOF,ERUDEF, NatureCameroon
Sept2010
Resourcepersons,Communication,Materials
625,000 FEICOM,FAO, GTZ ,PSMNR-SWR
Nguti Operational Plan 2010 19
Objectives Activities Indicators With whom Deadline Resource Budget PotentialFunding Sources
4.1.3 Illegalhuntingreduced
4.1.3.1 Sensitize localpopulation on articlesof the law related tohunting
At least 01 meetingorganized per clan
Council Forester ,ERUDEF, NatureCameroon,MINFOF
Oct 2010 Communication,Materials,Transport
400,000 FEICOM,FAO, GTZ ,PSMNR-SWR
4.1.4 Illegalexploitationof timberreduced
4.1.4.1 Sensitize onsustainable harvestingof timber
At least 01 meetingorganized in eachclan with 30participants each
Council Forester ,ERUDEF, NatureCameroon,MINFOF
Dec.2010
Equipment,Technicians,Communication,Materials,
905,000 FEICOM,GTZ,PSMNR-SWR
4.1.4.2 Promote re-forestation
At least 01 haforested per clan
Council ForesterERUDEF, NatureCameroon,MINFOF
Dec.2010
AccommodationEquipment,Technicians,Materials
850,000 SSV,PSMNR-SWR,GTZ, WIJMA
4.1.4.3 Sensitize localeconomic operators onlegal exploitation
03 meetings(grouping threeclans each)organized with 20participants each
Council Forester,ERUDEF, NatureCameroon,MINFOF
Dec.2010
Materials,Resourcepersons,Transport
900,000 SSV,PSMNR-SWR,GTZ, WIJMA
4.2 SpecificObjective:Unsustainablefishing practicesreduced4.2.1 Knowledge
on fishingtechniquesincreased
4.2.1.1 Inform onmodern fishingtechniques
At least 01workshoporganized for 30participants in thehinterlands
Council Forester,MINEPIA,ERUDEF, NatureCameroon,
Oct2010
Fishingequipment,Technicians,Communication
500,000 FEICOM,HPI
4.2.2 Riverpoisoningreduced
4.2.2.1 Sensitizationcommunities on theuse of poisons forfishing
At least 09sensitizationcampaigns held(one per clan)
Council ForesterMINEPIA, NatureCameroon
Oct2010
Transport,Communication,Technicians,materials andequipment
450,000 FEICOM,SOWEDA, HPI
Nguti Operational Plan 2010 20
Objectives Activities Indicators With whom Deadline Resource Budget PotentialFunding Sources
4.3 Specificobjective: Landuse practicesimproved4.3.1 Agricultural
practicesimproved
4.3.1.1 Train farmerson modernagricultural practices(mix farming alleycropping)
At least 01workshoporganized per clanfor 30 participants
Council Forester,ERUDEF,Nature Cameroon,MINADER
Nov2010
Resourcepersons,TrainingMaterials,Communication
790,000 SOWEDA
4.3.1.2 Liaise withMINDUH to sensitizecommunities on landlaws
At least 09sensitizationcampaigns carriedout (one per clan)
Council Forester,ERUDEF, NatureCameroon,
Nov2010
Resourcepersons,TrainingMaterials,Communication
200,000 FEICOM
Nguti Operational Plan 2010 21
PROGRAMME OBJECTIVE 5: FUNCTIONAL CAPACITY OF THE COUNCILObjectives Activities Indicators With whom. Deadline Resource Budget
CFAPotential
Funding Sources5. Programmeobjective :Functionalcapacity of theCouncilstrengthened5.1 Specificobjective:Management andLeadershipimproved5.1.1 Planning,
MonitoringandEvaluationimproved
5.1.1.1 Set up amonitoring andevaluation system
PME systemelaborated &functional
Secretary General,CEFAM,MUDEC
Jan 2010 Resourcepersons,Stationery
200,000 FEICOM
5.1.1.2 Train staff onplanning, monitoring& evaluation
01 workshoporganized on PMEfor senior staff
Secretary General,CEFAM,MUDEC
Jan 2010 Resourcepersons,Stationery
175,000 FEICOM
5.1.2 Managementof personnelimproved
5.1.2.1 Allocate staffto existingassignments/jobs
Organigramcompeted
Secretary General,CEFAM,MUDEC
Jan 2010 Stationery,Resourcepersons
20,000 FEICOM
5.1.2.2 Supportcapacity building forstaff
At least 03 undergospecific capacitybuilding training
Secretary General June2010
Stationery,Resourcepersons
270,000 FEICOM
5.1.2.3 Organize aworkshop on councilmanagement forCouncilors
01 workshoporganized
Secretary General,CEFAM,MUDEC
Feb 2010 Stationery,Resourcepersons
500,000 FEICOM
Nguti Operational Plan 2010 22
Objectives Activities Indicators With whom. Deadline Resource BudgetCFA
PotentialFunding Sources
5.1.2.4 Support publicfestivities (labour day,women day, youthday, national day)
At least 05 publicfestivitiessupported withinthe municipality
Secretary General,St JohnManyemenHospital
Dec2010
Materials ,Entertainment
4,000,000 FEICOM,WIJMA
5.1.3 Capacity toimplement2010OperationalPlan improved
5.1.3.1 Organizetraining and coachingsessions for councilexecutive, senior staffand technical follow-up committee
At least 01 trainingand coachingsession carried outmonthly
Secretary General,MUDEC
Monthly Materials,Stationery,Communication,Resource Person
1,200,000 SSV,PSMNR-SWR
5.1.3.2 Support actionplan of technicalfollow-up committee
Visits to ongoingprojects andmeetings heldmonthly
Technical Follow-up Committee
Monthly Stationery,transport,materials
1,000,000 SSV,PSMNR-SWR
5.1.4 Flow ofinformationimproved
5.1.4.1 Organizemonthly meetings
Monthly staffmeetings
SG, MUDEC End ofeverymonth
Stationery 50,000 FEICOM
5.1.4.2 Install officephone, fax & Internet
Office phone, faxand internet install
Council Forester /Secretary General
June2010
Technician &Phones
785,000 FEICOM
5.1.4.3 Employ acommunication officerand elaboratecommunication plan
Communicationplan elaborated andfunctional
Secretary General,MUDEC
Sept2010
Wages &Allowances
600,000 FEICOM
5.1.4.4 Use existingmass communicationmedia to valorizecouncil activities
At least 02 mediahouses contactedand Councilactivities regularlypublish
CommunicationOfficer, CRTV,Eden
Dec2010
Payment forpublications,Transport,Communication
300,000 FEICOM
5.1.4.5 Initiate processto create communitylibrary
Process elaboratedand fundingorganizationsofficially contacted
1st and 2nd DeputyMayors , EISERVI,NBDC ,British Council
Dec2010
Books,Stationary,Transport
350,000 FEICOM
Nguti Operational Plan 2010 23
Objectives Activities Indicators With whom. Deadline Resource BudgetCFA
PotentialFunding Sources
5.2 Specificobjective:
Funds increased5.2.1 Sources ofrevenue increased
5.2.1.1 Identifypotential internal andexternal sources ofrevenue
At least 05 internaland 03 externalsources of revenueidentified andexploited
MunicipalTreasurer, MUDEC
March2010
Technicians,Stationery,Transport
260,000 FEICOM
5.2.1.2 Developproject proposals
05 projectproposalsforwarded
Secretary General,MUDEC Group
June2010
Technicians,Stationery,Transport,Communication
300,000 FEICOM
5.2.1.3 Train staff onresource mobilization
02 workshopsorganized
Secretary General,CEFAM, MUDEC
Jan 2010 Resourcepersons,Stationery,Transport
120,000 FEICOM
5.2.2 Appropriateuse of council fundsincreased
5.2.2.1 Elaborate cashliquidation system
Cash liquidationsystem in place andfunctional
Finance committee,CEFAM, MUDEC,Nature Cameroon
March2010
ResourcePersons,Stationery,
130,000 FEICOM
5.3 Specificobjective:Financialmanagementimproved5.3.1 Knowledgeon financialmanagementimproved
5.3.1.1 CoachTreasurer andFinance Clerks onbook keeping
02 coachingsessions on bookkeeping organized
Secretary General,CEFAM, MUDEC
June2010
ResourcePersons,Stationeries
250,000 SSV,PSMNR-SWR
5.3.1.2 Remuneratecouncil staff
Staff salaries andallowances paidregularly
Secretary General Monthly Salaries,Allowances
41,260,000 FEICOM
Nguti Operational Plan 2010 24
Objectives Activities Indicators With whom. Deadline Resource BudgetCFA
PotentialFunding Sources
5.3.2 Budgetingimproved
5.3.2.1 Coach seniorstaff on budgeting
02 coaching ses-sions on budgetingorganized
Secretary General,CEFAM, MUDEC
June2010
ResourcePersons,Stationeries
200,000 SSV,PSMNR-SWR
5.3.2.2 Traincouncilors on councilfinancial procedures
01 workshop onfinancial proce-dures organized
Secretary General,CEFAM, MUDEC
July2010
ResourcePersons,Stationeries
550,000 SSV,PSMNR-SWR
5.4 Specificobjective: Workingenvironmentconducive5.4.1 Council
office spaceincreased
5.4.1.1 Provide moreoffice space
02 rooms madeavailable
Secretary General April2010
Technicians,rods, cement,sand, zinc,wood, nails,
1,450,000 FEICOM
5.4.1.2 Provide officesupplies
Office suppliespurchased andmade available
Secretary General Jan 2010 Stationary 500,000 FEICOM,WIJMA
5.4.1.3 Beautifycouncil premises
Flowers and treesplanted
Secretary General,MINFOF
March2010
Flower seedsand cuttings,labour,equipment
100,000 FEICOM
5.4.2 Buildingrenovationsincreased
5.4.2.1 Paint Counciloffices
Council buildingembellished
2nd Deputy Mayor March2010
Paint,Technicians
1,000,000 FEICOM
5.4.3 Officeequipmentincreased
5.4.3.1 Purchaseinformationprocessing equipment
01 computer, 01printer and 01photocopieracquired and used
S.G., BritishCouncil, Embassies
June2010
Generator, fuel,computers /accessories
1,000,000 FEICOM
5.4.3.2 Provideadditional chairs,tables, cupboards &shelves
06 chairs, 04 tables,03 cupboards and02 shelvesprovided
S.G. August2010
Wood, nails,locks, vanish,sand paper
500,000 FEICOM,WIJMA
Nguti Operational Plan 2010 25
Objectives Activities Indicators With whom. Deadline Resource BudgetCFA
PotentialFunding Sources
5.5 Specificobjective:Staff performanceimproved5.5.1 Staff
performanceimproved
5.5.1.1 Elaborate andadopt staffperformance criteria
Performanceappraisal formsavailable
Secretary General,MUDEC
Jan 2010 Stationary 25,000 FEICOM
5.5.1.2 Evaluate staffannually
Staff evaluatedannually
Secretary General,MUDEC
Sept2010
Stationery 60,000 FEICOM
5.5.2 Qualifiedstaffincreased
5.5.2.1 Train availablestaff on delivery ofquality services
02 trainingsorganized for staff
Secretary General,MUDEC
June2010
Trainingmaterials,Resourcepersons
200,000 FEICOM
5.5.2.2 Secureuniversity graduatevolunteers
At least 02volunteers secured
Secretary General,MUDEC
June2010
Stipend 480,000 FEICOM
Nguti Operational Plan 2010 27
BUDGET SUMMARY
A. Income:
I. Council Support Fund (FEICOM) = 70,100,000 frs
II. Member of Parliament Fund = 3,000,000 frs
III. Sales of standing volume = 10,000,000 frs
IV. Support from DED = 3,337,440frs
Total Projected Income = 86,437,440 FRS
B. Expenditure:
I. Infrastructure Development (P1) = 3,935,000 frs
II. Social Development (P2) = 6,265,000 frs
III. Local Economic Development (P3) = 5,315,000 frs
IV. Natural Resource Management (P4) = 12,287,440 frs
V. Functional Capacity of Nguti Council (P5) = 58,635,000 frs
Total projected Expenditure = 86,437,440 FRS
Nguti Operational Plan 2010 28
CONCLUSION
Nguti Council has successfully completed the planning cycle by elaborating an operational plan
for 2010. Several development actors from all nine clans have been consulted and their
aspirations have been heightened as a result. The council has identified several potential
partners who could be solicited for assistance. This document should be given its widest
circulation as per the communication plan attached in annex. A Technical Follow up
Committee comprising six (06) members has been identified and coached with clear terms of
reference. A few tools such as a basic format for proposal writing to assist the committee in
fundraising as well as basic formats for monitoring and reporting have been made available to
facilitate their smooth functioning. It is incumbent on the management of the Council to
immensely commit in fostering the work of this committee by making available the necessary
funds for monitoring of planned activities. In the spirit of the planning process, the Mayor and
Secretary General should use this document in developing the municipal budget for 2010
which will become the finance law of Nguti Council area upon approval by the deliberative
organ.
RECOMMENDATIONS:a. The Council should give this document its widest publicity by making copies
available to each councilor, presidents of each clan chiefs conference, MP,
VCDA and members of the Technical Follow up committee.
b. Enhanced efforts at internal as well as external fundraising should be elaborated
on a quarterly basis and closely monitored by management.
c. Elites from Nguti (especially those in the diasporas) should be contacted and
highly solicited to take active roles in the search to realize the contents of this
plan.
d. Regular consultative meetings between Council management, the technical
follow up committee, the service provider and the PSMNR-SWR should be held
in order to ensure the ultimate transfer of project implementation skills to the
council.
Nguti Operational Plan 2010 29
ANNEXES:
1. TOR for Technical Follow up Committee
2. Picture Gallery
3. Attendance Lists
4. Strategies to Communicate OP 2010
5. M & E Plan
6. Reporting Sample
7. Project Profile Sample
Nguti Operational Plan 2010 30
Technical Follow-Up Committee
Attributions: Annual review/ update of monographic study report beginning after the publication of
2005 population and housing census and executed once every 2 years Solicit Annual reports from all services (public / private) that operate within the
municipality Maintain a library / database for all activities taking place within the Municipality Identify potential internal and external sources of council income Assist in fundraising Extracting from the OP 2010 the activities to be carried out per responsible person /
structure and submit an overview with time frame of those specific activities to theconcerned person / structure (=sub operational plan per person / structure)
Inform the different persons /structures responsible of implementing the activities aboutthe council administrative procedures to obtain the necessary funds for the activity
Continuous review of 2010 Operational Plan and council budget implementation Ensure that projects implemented have municipal balance Monitor and Evaluate ongoing projects Work in close collaboration with the SG and the Municipal treasurer Prepare an annual working budget 2010 for discussion with the PSMNR-SWR Review / assess indicators in Strategic Plan and Operational Plan 2010
Members:
The Lord Mayor…………………... ChairpersonMr. Tabi Titus……………………... ReporterMr. Monge Julius………………….. ReporterMrs. Ngabe Florence………………. MemberMr. Epie Felix……………………… MemberMr. Asek Lordson………………….. Member
Nguti Operational Plan 2010 31
Picture Gallery
Group work: Committee on LED Group work: Committee on NRM
Group work: Committee on social facilities Group picture
Group work: Committee on Councilfunctioning
Group work: Committee on infrastructuredevelopment
Nguti Operational Plan 2010 34
Strategies to communicate Nguti Council 2010 operational Plan
ACTION TIMEFRAME PERSONS RESPONSIBLEOrganize Restitution Meetings at
clan level involving Councilors,
Clan Chiefs, Village
Development Associations,
Presidents of Common Initiate
Groups, Heads of Government
Technical Services
By 30th November 2009 Councilors and Elites who
attended the 2010 Operational
Planning workshop
Organize lobbying visits to
relevant Organizations and
Ministries : E.g. SOWEDA,
RUMPI, RDARD, MINEPIA and
Embassies
By 15th December 2009 Mayors and Committee
Chairpersons
Carryout Radio broadcast
Programs
30th November 2009 Mayor
Publish Newspaper articles (Eden
& the Post News papers)
30th November 2009 Mayor and
Secretary General
Produce leaflets with major
objectives , activities and
circulate in all 9 clans in the
Municipality
30th November 2009 Mayor and the Council Forest
Officer
Nguti Operational Plan 2010 35
Monitoring and Evaluation Plan
Micro Project
Strategic Action to be AccomplishedDate of Monitoring / EvaluationWhat was planned tobe done
PersonResponsible
What hasbeen done
What still has tobe done
WhenShould itbeCompleted
What will be there to
show that it has been
done
Comments and
reactions of the TFC
Activity 1
Activity 2
Activity 3
Activity 4
Activity 5
Activity 6
Activity 7
Activity 8
Activity 9
Activity 10
36
Technical Follow up Committee
Reporting Format (Sample)
PROGRAMME OBJECTIVE:
Period of Report ------------------------------- To ------------------------------
Specific objective(s) Results Activities realized Activities notrealized
Challenges Observations/Suggestions
37
Suggested project profile
Project title:
1- Project formTitle of the action .
Place of realization
Objectives of the action The project intends to:
Expected resultsPrincipal activities to be realisedTarget population
Duration of the action
Starting date of the projectCost of the projectCouncil contributionRequested assistanceOther sources of fundingPrincipal means (human and material)mobilised for the project (quantity)Multi actor dimension of the project(which are the stakeholders involved inthe Project and in what aspect?)How does the action proposed take intoaccounts the felt needs of the population