nfx schedule delay analysis 21dec11.ppt [read-only] · critical remaining work mlestone pt230000234...

5
2 © M+W Group M+W U.S., Inc. NFX Delay Analysis Report Critical Status: >25D Delay Overall duration affected Caution Status: >5D Delay <25D Delay Controlled Status: On Schedule LE Controll LE On Sc

Upload: others

Post on 26-Mar-2020

5 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: NFX Schedule Delay Analysis 21DEC11.ppt [Read-Only] · Critical Remaining Work Mlestone PT230000234 PT230000238 PT230000242 PT23000024$ PT230000250 PT230000252 NFX Install Pipe Supports

2 © M+W GroupM+W U.S., Inc.

NFX Delay Analysis Report

Critical Status:• >25D Delay

• Overall duration affected

Caution Status:• >5D Delay

• <25D Delay

Controlled Status:• On ScheduleSAMPLESAMPLESAMPLEControlled Status:SAMPLEControlled Status:SAMPLE•SAMPLE• On ScheduleSAMPLEOn Schedule

Page 2: NFX Schedule Delay Analysis 21DEC11.ppt [Read-Only] · Critical Remaining Work Mlestone PT230000234 PT230000238 PT230000242 PT23000024$ PT230000250 PT230000252 NFX Install Pipe Supports

3 © M+W GroupM+W U.S., Inc.

Mechanical Trestle Piping

SAMPLESAMPLE

Page 3: NFX Schedule Delay Analysis 21DEC11.ppt [Read-Only] · Critical Remaining Work Mlestone PT230000234 PT230000238 PT230000242 PT23000024$ PT230000250 PT230000252 NFX Install Pipe Supports

4 © M+W GroupM+W U.S., Inc.

P6 Summary – Pipe Trestle Delay Impact

SAMPLE

Page 4: NFX Schedule Delay Analysis 21DEC11.ppt [Read-Only] · Critical Remaining Work Mlestone PT230000234 PT230000238 PT230000242 PT23000024$ PT230000250 PT230000252 NFX Install Pipe Supports

5 © M+W GroupM+W U.S., Inc.

P6 Summary – Pipe Trestle Delay Impact

SAMPLESAMPLE

Page 5: NFX Schedule Delay Analysis 21DEC11.ppt [Read-Only] · Critical Remaining Work Mlestone PT230000234 PT230000238 PT230000242 PT23000024$ PT230000250 PT230000252 NFX Install Pipe Supports

6 © M+W GroupM+W U.S., Inc.

Waffle Slab Schedule

SAMPLE