nfl final report

106
INTRODUCTION The rise in fertilizers consumption in India has been quite phenomenal during past two and half decades. To meet the rise in consumption of fertilizers creation of additional capacity was also planned. The change in the world wide energy concept and rise in the oil prices in 1973 forced India to increase its nitrogenous production by adopting new and sophisticated technology which could use cheaper sources of raw material. The NFL (public undertaking) was conceived to plan and implement two modern large capacity single steam nitrogenous fertilizers plant in the predominant fertilizer consuming oil to coup with the increasing demands of fertilizers. The industry was formed and registered on 23rd August 1974 to setup two nitrogenous fertilizers plants each with capacity 5-11 lakh tones per annum of idea at Panipat and Bathinda. Bathinda was basically selected as one of the site of fuel oil based plant from the consumption point of view since Punjab is mainly agriculture based state and Bathinda was the best choice for it. “Feed in” at Bathinda was achieved on 7 th Dec. 1978. Bathinda project produced ammonia successfully on May 28,1979 and urea on June 2, 1979. NFL was incorporated on Aug 23, 1974 in order to implement this project contract were entered into with M/s Page No. 1 of 106

Upload: aman11750

Post on 03-Apr-2015

2.179 views

Category:

Documents


6 download

TRANSCRIPT

Page 1: NFL FINAL REPORT

INTRODUCTION

The rise in fertilizers consumption in India has been quite phenomenal

during past two and half decades. To meet the rise in consumption of fertilizers

creation of additional capacity was also planned. The change in the world wide

energy concept and rise in the oil prices in 1973 forced India to increase its

nitrogenous production by adopting new and sophisticated technology which

could use cheaper sources of raw material.

The NFL (public undertaking) was conceived to plan and implement two

modern large capacity single steam nitrogenous fertilizers plant in the

predominant fertilizer consuming oil to coup with the increasing demands of

fertilizers.

The industry was formed and registered on 23rd August 1974 to setup two

nitrogenous fertilizers plants each with capacity 5-11 lakh tones per annum of

idea at Panipat and Bathinda.

Bathinda was basically selected as one of the site of fuel oil based plant

from the consumption point of view since Punjab is mainly agriculture based

state and Bathinda was the best choice for it.

“Feed in” at Bathinda was achieved on 7th Dec. 1978. Bathinda project

produced ammonia successfully on May 28,1979 and urea on June 2, 1979.

NFL was incorporated on Aug 23, 1974 in order to implement this project

contract were entered into with M/s “TOYO ENGINEERING CORPORATION” a

well-known Japanese Engg. Company and Engg. India Ltd. (EIL), a public sector

and Engg. Organization. This contract becomes effective on Sept. 26, 1974 with

a guaranteed “feed in” on the Bathinda fertilizers project to implement with in 36

months from the zero date. Later on with the need of electric power NFL estd. Its

own powerhouse known as CPP (Captive power plant) with two turbines of 15

MW each.

Page No. 1 of 75

Page 2: NFL FINAL REPORT

SALIENT FEATURES OF PLANT

PLANT RATED CAPACITY

UNIT UREA(Tonnes/annum)

NITROGEN(Tonnes/annum)

Nangal (PB) 318160 231340

Panipat (HR) 511500 235290

Bathinda (PB) 511500 235290

Vijaypur (MP) 1452000 667920

Total 2793160 1369840

PRODUCTS OF

National Fertilizers is producing “Kisan Khad, Kisan Urea & Ankur” on

commercial scale. NFL is marketing a number of industrial products produced as

by-products in its plants.

Fertilizer Products

1. Kisan Khad

Moisture by wt. 1.0% (max)

Total ammonical nitrogen by wt. 25% (min)

Ammonia nitrogen by wt. 12.5% (min)

Calcium nitrate by wt. 0.5% (max)

Particle size passes through 4mm 1.s sieve by wt. 80% (min)

Retained on 1mm 1.5 sieves below 1mm 1.s sieve 10% (max)

2. Kisan Urea

Moisture by wt. 1.0% (max)

Total nitrogen on dry basis 46% (min)

biuret by wt. 1.5% (min)

Page No. 2 of 75

Page 3: NFL FINAL REPORT

Particle size pass 2.8mm by wt. 1.s sieve 80% (min)

Retained on 1mm sieves 80% (min)

Industrial Products

1. Anhydrous ammonia (NH3)

Ammonia by wt. 99.5% (min)

Water by wt. 0.5% (max)

Air content by wt. 0.02% (max)

2. Methanol (CH3OH)

Methanol by wt. 99.85% (min)

Density at 200C 0.793 Kg

3. Sulphur (S)

sulphur purity 99.5% (min)

4. Nitric Acid (HNO3)

Nitric acid by wt. 53%

5. Ammonium Nitrate (NH4NO3)

Purity by vol. 99% (min)

6. Nitrogen (N2)

Purity by vol. 99.99% (min)

7. Oxygen (O2)

Purity by vol. 98.0% (max)

Inert by vol. 2.0% (max)

Page No. 3 of 75

Page 4: NFL FINAL REPORT

Moisture nil

Carbon nil

8. Carbon Dioxide (CO2)

Carbon dioxide by vol. On dry basis 98.0% (min)

Inert gases by vol. 2% (max)

Methanol by wt. As H2S 1ppm 500ppm (max)

9. Carbon (c) from slurry

Carbon on dry basis by wt. 98%

10. Sodium Nitrate

Ash etc. 2%

Purity by wt. 98% (min)

NaNO3 by wt. 0.50% (max)

FeNO3 by wt. 0.003% (max)

Water by wt. 1.0% (max)

Page No. 4 of 75

Page 5: NFL FINAL REPORT

IMPLEMENTATION OF BATHINDA UNIT

To take up this challenging job for completion of this unit within a limited

period of 36 months from zero date 26 sep,1974 contracts were signed with

Toyo Engineering Corporation Limited well known Japanese and Indian

Consultancy Companies respectively.

Project cost

The approval project cost of Bathinda Unit is Rs 240.47 Crores with a

foreign exchange component which was mainly met from Japanese Yen

Credit; however, certain special equipment requirement from others was met

out of the free foreign exchange and Dutch credit.

REQUIREMENT OF RAW MATERIAL AND INPUTS

Fuel Oil/LHLS 850 MTonne/day

Coal 1680 MTonne/day

Water 13 MGD

Power 28 MW

BENEFITS

This project has not only helped in increasing the country’s food output but

has also given direct employment to 6000 persons. Till March 99 this unit has

produced more than 8 million tons of food grains. The farmers of Punjab,

Haryana and Rajasthan have been the largest beneficiaries of this project. Both

central and state governments have been benefited by way of exercise duties

and other local taxes on various raw material and end products. Apart from plant

level staff, there is employment potential for entrepreneurs to set up ancillary

industries based on requirement of this plant such as polythene-lined jute bags,

alum, stitching thread etc. while by-product sulphur produced is already being

sold to outside parties. There is scope for marketing other by-products like

carbon and industrial gases e.g. Oxygen, Nitrogen, Carbon dioxide etc.

Page No. 5 of 75

Page 6: NFL FINAL REPORT

PRODUCTION PROCESS:

Ammonia is produced by the partial oxidation of heavy oil. Raw synthesis

gas is produced in the Gasification section by the partial oxidation of the

heavy oil. The raw synthesis gas produced in the Gasification section is

further purified in Desulphurised, CO-Shift Conversion and Decabonation

sections. After final purification in the nitrogen wash unit, it is compressed

to about 220 ATM pressure and is converted to ammonia using a special

synthesis catalyst. In order to manufacture Urea, the following procedure is

used. In Titanium Lined reactor, ammonia and carbon dioxide are mixed at

about 240 atmospheric pressure. The carbon dioxide used in the process

is obtained from ammonia plant. After decomposition and recovery steps,

to ensure maximum product yield, the urea solution obtained is

Concentrated, Crystallized, Centrifuged, dried and conveyed to the top of

the prilling tower where it is melted in the melter and sprayed through the

acoustic granulators to produce urea prills. By decomposition, uncoverted

carbonate solution is decomposition to recover ammonia, which along with

the carbonate solution is recycled back to the urea reactor.

Page No. 6 of 75

Page 7: NFL FINAL REPORT

MAJOR AWARDS AND RECOGNITION

National Safety Award from the ministry of Labour, Government of India

for meritorious performance in industrial safety during 1989.

Merit certificate from National Productivity Council (NPC) for performance

improvement during 1991-92.

Received during year 1994-95 “Prime Minister’s Shram Award and

Vishwakarma Rashtriya Puruskar” under various suggestion schemes. It

also received “Punjab Safety Krit Shiromany Award and Krit Veer Awards”

from the state Government. It also received “Udyog Excellence Gold

Medal & Citation” from Industrial Economic Forum, New Delhi.

It also won “Jawaharlal Nehru Memorial National Award” constituted by

the International Greenland Society, Hyderabad for Pollution Control &

Energy Conservation.

Page No. 7 of 75

Page 8: NFL FINAL REPORT

Three prizes were awarded by “Punjab Industrial Safety Council” it won

prizes in lower Accident Frequency Rate.

Maximum Reduction in accident Frequently Frequency Rate.

Longest Accident Free period.

An ISO-9002 & ISO-14001certified unit.

An OHSAS-18001 certified unit.

BRIEF WORKING OF PLANTS

BATHINDA FERTILIZER PLANT PROCESS

Bathinda Fertilizer Plant may be divided in four groups.

Offsite and Utilities Plants

Steam Generation And Material Handling Plant

Ammonia Plant

Urea and Bagging Plant

OFFSITES AND UTILITIES GROUP OF PLANTS comprised of “Raw

Water Filtration Plant, DM Water Plant”, “Instrument Air Compressor House”,

Cooling Tower”, “Sulphur Recovery Plant” & “Effluent Treatment Plant”.

Raw water plant is designed to treat 2400 M3/hr. of raw water into potable

water and thus its effective distribution to Township and NFL Plant. Thus to

avoid surface corrosion due to different minerals water is further

demineralised and finally polished in DM Plant before finally feeding it to

boilers. It consists of Cation Units Degasser Towers Anion Units and Mixed

Page No. 8 of 75

Page 9: NFL FINAL REPORT

bed units no. H2 Instrument Air Compressor House supplies instrument air

and service air compressors and two service air compressor one in each as

standby. The cooling towers systems provided in NFL, Bathinda are closed

recirculating system supplying cooled water to various consumption points in

plants. Sulphur Recovery Plant has helps in production of additional by

product, sulphur in the plant. It is based on the process of recovery of

elemental sulphur from Hydrogen Sulphide gas. Effluent treatment plant

serves a major role in decreasing the extent of pollutants in the waste outlets

and also in the recovery of fuel oil from the oily effluents.

STEAM GENERATION PLANT

Steam generation plant produces and supplies steam at 100kg/cm2pressure and

4800C temperature to ammonia plant

Introduction

Steam has many qualities. It is easily distributed. It is used for power process

and heating. It is taste less and odorless steam for use in industry is

generated in boilers. Modern all welded packaged and water tube boiler is

very economical and popular as such units are compact mounted on a

common base fitted with mounting and fittings. Machine fuel fire devices and

equipments and auxiliaries accessories, automatic control for fuel burning

pressure and feed variations and thus have immersed as modern industrial

steam generators for the new order of over industrialization in our country and

world over.

The boilers are generally to fire conventional fuels such as coal, oil, natural or

waste gas at NFL Bathinda the steam is generated for dual purposes.

1. For running prime mover.

2. To exchange heat in the processes.

Page No. 9 of 75

Page 10: NFL FINAL REPORT

There are 3 boilers supplied and erected by BHEL. Each boiler is designed to

produce steam at the rate of 150Tonne/Hr. Normally operation of two boilers

should be sufficient to meet the above mentioned objectives, but the third

boiler has to run simultaneously due to increase in steam load consumption

by main consumers.

The boilers are type of BU40. Coal is major source of heat, but oil spot is also

given to produce the steam of desired temperature and pressure. The plant is

designed for heat efficiency of 86.44% as per British standard of 1974. Coal is

used as fuel. Coal comes from coal handling plant through conveyor belt. In

the coal handling plant crushers are provided for crushing the coal into small

pieces. After the crushers a heavy electromagnet is also installed for

preventing the iron particles. Coal comes into bunkers and from the bunkers,

coal is sent to the grinding mill in a limited quantity.

Grinding mill coal is grind and converted into powder form. This powder form

of coal is sent into the boiler corners through a pump. This pump sucks the

coal from grinding mill and outlet of the pump is connected to a pipe and this

pipe is further branched into four pipes. These four pipes are connected to

four corners of the boiler. Initially coal cannot burn separately; therefore, oil

fuel LSHS/LDO is mixed with coal and sent into furnace and coal starts

burning. Initially burning temperature is necessary to maintain 1000C. After

burning this fuel and coal, the flue gases flow surrounding the water tubes

that are filled with water, due to these flue gases, steam is produced

WHY STEAM IS REQUIRED

Major consumption of steam is in ammonia plant and roughly 6.5 to 7 Te of

steam is required for producing one Te of ammonia, this steam is used:

a) for driving the turbo compressors

b) as process steam for various reactions

c) for heating purpose

Page No. 10 of 75

Page 11: NFL FINAL REPORT

The designing and introduction of high pressure turbines and compressors

has revolutionized the industry especially the fertilizer industry. Single stream

high capacity plants of 2200Te/day urea and 1350Te /day. Ammonia have come

up which was not feasible a few decades back. The turbines used to run these

compressors are driven by high pressure and high temperature steam. If we add

the output power of various turbines run by steam, it comes around 50MW in

other words we are saving 50 MW of electricity.

In our factory where heavy fuel oil is used as feed stock, requirement of

steam is very high i.e. 7 Ton per tonne of ammonia as compared to plants using

natural gas or naphtha as feed where steam requirement is 3Te per ton of

ammonia. It shows the importance of steam and steam generation plant.

Moreover steady pressure and temperature is very essential for the life and

efficiency of these turbines. Hence role of SGP is very important

Steam in SGP is generated by three number VU-40 type boilers

supplied .by M/S BHARAT HEAVY ELECTRICALS LTD. These are in operation

from 1977 and each boiler can generate up to 150Te of steam per hour. These

are water tube boilers which mean the water used for steam formation is inside

the tubes and the heating material that is coal or oil is burnt in the outer furnace.

Roughly speaking about 750KCal of heat required to generate one ton of steam

at the present efficiency of these boilers. This heat is mainly supplied by

pulverized coal. Heavy fuel oil is used for initial start –up and continuous support

to coal burners and light diesel oil is also used for initial start-up.

FIRING SYSTEM:-

Pulverized coal is the coal grinded to easily combustible and economically

viable level so that it burns completely with in the available time inside the

furnace .BOWL MILLS are used for grinding the coal. Coal received from

material handling plant is stored in coal bunker and is fed to the bowl mill through

a coal feeder. Hot air is also supplied in the mill for heating the coal and

conveying it to the furnace through a fan called EXHAUSTER FAN which takes

suction from the mill and maintains it under negative pressure. Oversize and

Page No. 11 of 75

Page 12: NFL FINAL REPORT

ungrindable material like stones are thrown out by the mill. Coal and air mixture

called pulverized fuel from the exhauster is supplied to COAL BURNER. Coal

burners are arranged tangentially on all the four corners of the rectangular

furnace at three elevation levels. Thus there are 12 coal burners. In between

these three elevations OIL BURNERS AND START UP BURNERS or IGNITERS

are arranged at two elevations. Thus there are 8 oil burners and 8 igniters. As

coal requires some minimum temperature for ignition, igniters use LIGHT

DIESEL OIL (LDO) and can be lighted by remote control. Oil burners use heavy

fuel oil (LSHS).

The FURNACE is a cubical suspended enclosure with water tubes forming

its four walls. The furnace is designed with sufficient volume to provide for

complete and efficient combustion at all loads without flame impingent by the

reaction of carbon present in coal and oxygen present in air to form carbon-

dioxide.

C + O2 → CO2 + Heat

These gases called FLUE GASES heat up the water in tubes to form steam.

As the FLUE GASES rise up, their heat is utilized in various ways as shall be

discussed later. The furnace is maintained at a negative pressure of 5 mm water.

WATER AND STEAM SYSTEM

The steam generated should be free from all impurities like minerals,

silica, oxygen, iron etc, for the safety of and efficiency of steam turbines and

boilers. For this purpose RAW WATER is physically and chemically treated and

finally supplied to SGP from ammonia plant. This water is called BOILER FEED

WATER. Feed water is further heated to around 2400C by the flue gases and

taken to STEAM DRUM. Steam drum acts as storage tank and also separates

water from the steam at 3150C and 106kg/cm2 pressure water then enters MUD

DRUM through BANK TUBES heated by flue gases. This drum helps to maintain

Page No. 12 of 75

Page 13: NFL FINAL REPORT

circulation of water. Water from mud drum enters the RING HEADER formed at

the bottom of outside the furnace and rises by gravity through water wall tubes

on all the four sides, takes heat from furnace and enters steam drum as a

mixture of steam and water. Water is separated here and steam at about 3150C

is taken through two SUPER HEATERS called PLATEN SUPER HEATER AND

FINAL SUPER HEATER heated by flue gases to attain final temperature of

steam around 4900C. The outlet temperature from these super heaters is

controlled by adding boiler feed water.

FLUE GAS SYSTEM

The products of combustion in the furnace consist of carbon-di-oxide,

nitrogen, ash, oxygen and sulphur-di-oxide. After leaving the furnace the heat

Of these gases called FLUE GASES, is utilized at various levels.

First the steam from steam drum is heated in two super heaters to get the

required temperatures of 4950C and then feed water in BANK TUBES is also

heated and the gases leave bank tubes at around 4970C next the heat is utilized

to heat feed water in the ECONOMIZER and gases are cooled down to 3200C.

These gases are further cooled down to 1500C in ROTARY AIR HEATER where

the air is required for combustion and conveying the coal is heated up.

Temperature is not reduced further because at lower temperature oxides of

sulphur present in flue gases are converted to ACID which damages the down

stream equipments. These gases then pass through ELECTRO STATIC

PRECIPITATOR (ESP) where ash is removed. From ESP these gases pass on

to INDUCED DRAFT FAN which maintains draft in the furnace and finally the

gases are let off to the atmosphere through a chimney about 80mtr high.

POLLUTION AND THEIR DISPOSAL

Along with optimum utilization of company’s resources to achieve

maximum profitability, our unit has always performed its duty to keep the

Page No. 13 of 75

Page 14: NFL FINAL REPORT

environment clean. We have installed latest available pollution control

instruments and equipments. The chief pollutants generated in SGP are ASH

and SULPHUR –DI-OXIDE. Their separation and disposal are discussed in brief.

ASH:

Ash is the incombustible material contained in raw coal which has about 40%

ash. It also consists of heavy metals like vanadium and nickel. If inhaled it can be

harmful to human beings.

After combustion of coal, ash remains as such. About 20% ash of total ash

generated consist of higher wt. particles which fall down to BOTTOM ASH

HOPPER provided at the bottom of the furnace. Ash slurry is formed here due to

water level maintained in the bottom ash hopper. This is taken out by water

ejector once in eight hours and sent for disposal in lagoons.

FLY ASH:

Fly ash is the ash containing light particles. It forms the major portion that

is 80% of the ash generated. It is carried away from the furnace along with the

flue gases. The ash particles are removed from the gases in electro-static

precipitators as shown in block diagram after air-pre heaters.

ELECTRO-STATIC PRECIPITATORS:

The electro-static precipitators’ forces to separate out dust particles from

the flue gas. High voltage is applied between electrodes arranged in rows

alternately. Due to high voltage gas particles are ionized. Most of the ions are

negatively charged. They stick to dust particles and carry them to positively

charged electrodes which are in the form of a rectangular plate. Thus dust

particles stick to those plates. These plates are rapped periodically to dislodge

the deposited dust which is collected in the hopper below.

Ash is ejected from these hoppers by water jet and it forms ash slurry. Fly

ash slurry and bottom ash slurry are mixed together and sent to ash slurry

Page No. 14 of 75

Page 15: NFL FINAL REPORT

disposal ponds outside the factory where the slurry settles down and overflowing

clear water is recycled back to the system.

SULPHUR-DI-OXIDE:

Sulphur-di-oxide is formed due the presence of sulphur in coal which

varies from 0.1% to 0.5%. For safe disposal of SO2 minimum chimney height has

been recommended by pollution boards, depending upon the quantity of sulphur-

di-oxide generated per hour. In our case it comes out to be around 75 mts. taking

maximum amount of SO2 generated. Chimney height of SGP boiler is 80mtrs.

Suitable instrumentation has been provided for monitoring all the

parameters and important analyzers and cutouts of a part or even complete

boiler has been provided in case of emergency.

MAIN EQUIPMENT

Economizer

The main function of Economizer is to preheat the boiler water before it is

introduced into the steam drum. It recovers some of the heat from the flue

gases leaking out of the boiler. The economizer is located in the second pass

of the boiler above the air heater. Each section is composed of number of

parallel tubes circuit which is arranged in the horizontal rows. All tubes circuit

originated from inlet header and discharge at outlet header.

Feed water is supplied to inlet water header via free of stop and check valves.

The feed water flow is upward through the economizer that is in counter flow

to the hot flue gases. Any chance of steam generation within the economizer

is eliminated by the upward water flow that is led to the drum via the

economizer outlet link.

Super-heater

The main function of the super-heater is to superheat the steam. Super

heater is located at the outlet of the furnace.

Page No. 15 of 75

Page 16: NFL FINAL REPORT

Operation

Before lighting off the unit, open wide inlet and outlet header drains, vents

links drains and main steam line drains. Close all the drains prior to lighting

off when the headers and links appear free of water drain that senses as a

starting drain header drain and is kept open after the unit is on line.

Desuper-heater

Mainly the function of desuper heater is to reduce the temperature of the

steam. Desuper heater are provided in super heater connecting links to

permit reduction of steam temp. When necessary and to maintain the

temperature at design values within the limits of the nozzle capacity.

Reduction in the steam temperature is accomplished by injecting spray water

into the path of the steam; the spray water source is the boiler feed water

system. It is essential that the spray water should be chemically pure and free

of suspended and dissolved solids. Containing only approved volatile organic

treatment materials in order to prevent the chemical deposition in the super

heater.

Drum

It is necessary to separate the saturated steam from the steam water

mixture for circulation type boiler. This performance is achieved by steam

separators arranged in the drum.

Page No. 16 of 75

Page 17: NFL FINAL REPORT

CAPTIVE POWER PLANT

Since inception, Bathinda unit was drawing power from PSEB. Electricity is the

main driving force after steam, being used for moving auxiliary equipments. The

unit requires about 27MW’s of power per hour when running at full load.

NEED FOR CPP

It was thought to install a captive power plant in which electric power for

our requirement shall be generated in a COAL FIRED BOILER. The benefits

envisaged were:

1. Any disturbance in the PSEB grid used to trip the whole plant. Lot of

money was lost due to this as each re-startup costs around 40 to 50 lakhs

rupees. Moreover, frequent trippings had an ill effect on machines and

equipments extending the re-startup period.

2. Three boilers of 150Te/hr steam capacity were initially installed in SGP

to keep 25 boilers running and one stand by as designed steam requirement was

less than 300Te/hr. but in actual operation steam requirement was more and all

Page No. 17 of 75

Page 18: NFL FINAL REPORT

three boilers had to be run and there was no breathing time for their

maintenance. As new boiler was to be installed for CPP, its capacity was so

designed that it could export around 60Te of steam for process requirement so

that only 2 boilers of SGP would be run keeping the 3rd as stand by.

With these points in mind CPP was installed. The functioning of CPP can

be sub-divided into parts:

1. BOILER AND ITS AUXILIARIES: for generation of high pressure

superheated steam.

2. TURBO-GENERATOR AND ITS AUXILIARIES: to generate power, using

steam from the boiler.

Operation of CPP is based upon microprocessor based computerized

instrumentation which allows automatic operation, start up, shut down of the

whole or the part of the plant.

BOILER

Boiler has been supplied by M/S MITSUI ENGINEERING AND SHIP

BUILDING CO. OF JAPAN. It has a capacity to produce maximum 230Te/he of

steam at 105KG/cm2 pressure and 4950C temp. 150Te/hr steam is used for

power generation if both generators are running at 15MWH each. Around 60Te

steam per hr is drawn for process use and joins with the SGP steam header.

The basic principle of this boiler is the same as discussed earlier for SGP

boiler that is formation of steam by heating boiler feed water inside furnace fired

by coal and heavy oil, utilization of heat of the gases and venting these gases at

a safe height. Main differences between the two boilers are:

1. SGP boiler is tangentially fired where as CPP boiler is front fired with 6

coal burners and 6 oil gun fixed inside the coal housing.

2. SGP boiler can be loaded upto 30% load with oil firing only whereas CPP

boiler can be fully loaded with oil alone.

3. Height of combustible zone in CPP boiler is more and it has residence

time of 1.5 sec where SGP boiler has 1.0 sec.

Page No. 18 of 75

Page 19: NFL FINAL REPORT

4. Mills used for pulverizations of coal in SGP are negative pressure bowl

mills whereas in CPP ball tube mill are used which are positive pressure

mills.

5. Due to more residence time and better pulverization the efficiency of CPP

boiler is about 4% higher.

6. Boiler feed water required for steam generation can be fully generated in

CPP itself.

A part of the steam generated is exported for process use in ammonia plant and

rest is utilized for power generation in turbo generators as described below:

Description

MITSUI RILEY TYPE BOILER

Maximum evaporation 2,30,000kg/hr

Design process for boiler 124kg/cm2G

Steam temp at outlet 4950C

Heating surface 1250M2

FUEL COAL SYSTEM

The purpose of fuel coal system is to pulverize coal to dry coal and to

convey the pulverized coal from ball tube mill to burners by primary air for coal

firing.

Fuel coal system consists of three systems:

1. coal supply system.

2. primary air system.

3. seal air system.

Coal supply system

Primary air system

Page No. 19 of 75

Coal bunkers

Coal feeders

Crushers dryers

Ball tube mill

Page 20: NFL FINAL REPORT

The primary air system performs two functions. It provides the proper

amount of air required to convey the pulverized coal to the burners and the heat

necessary to dry coal so it can be pulverized and burned efficiently. The details

of primary air fan are:-

Make MEIDEN

Degree of protection IP 55

No of poles 4

Frequency 50Hz

RPM 1475

Power factor 0.89

Insulation class F

Rated power 195kW

Type of construction IEC-34

Normal temp rise limit 700C

Seal air system

The seal air is distributed to the components by the sealing of the mill

system by the sealing air fan. The sealing air fan takes suction from silencer and

discharges it to a common header. The controller for each mill system provides a

constant differential pressure to protect against coal leaking into the bearings and

seals. This system should be in service before being placed in operation.

Crusher dryer system

Crusher-dryer performs the CRUSHING function. Metered coal from the

feeders blends with a properly heated amount of air from the primary air fan and

enter the crusher dryer. The non clogging pre crushing flash dryer operates

continuously at constant speed. Rotating hammers drive the incoming coal

against a breaker plate and adjustable crusher block, increasing the surface area

of the coal and mixing it with the incoming preheated air.

BALL TUBE MILL

Page No. 20 of 75

Page 21: NFL FINAL REPORT

Grinding the coal to the proper fineness is done by ball tube mill. The

crushed coal and air mixture from the crusher dryers enter the mill through the

mill inlet boxes on both ends of the mill. The mill barrel rotating at constant

speed,contains thousands of kilograms of various sizes of hardened steel balls

which cascade down upon the entering coal and pulverize it to talcum powder

consistency. The heated primary air, entering with coal,not only completes the

drying process, but now conveys the coal dust from the mill through the mill

output boxes to the classifiers on both ends of the mill. The specifications of the

balll tube mill are as:-

Make MEIDEN

Degree of protection IP 55

Insulation class F

No of poles 4

Voltage 3300V

Frequency 50Hz

Current 98A

Power factor 0.89

Type of construction IEC-34

Power rating 445kW

Connection Y

Temp. risk limit normal 700C

RPM 1430

The pulverized coal from the BTM is fed to the boilers with the help of

primary air fans. The coal is burnt in the boiler to generate steam to move the

turbines. The forced and induced draft fans are used to assist in the combustion

of fuel and steam production. These two major types of fans supporting the units

operation.

FORCED DRAFT FAN

Page No. 21 of 75

Page 22: NFL FINAL REPORT

The forced draft fans supply the proper amount of secondary air required

to support the combustion of the fuel delivered to the boiler. The details of the FD

fan are:

Make MEIDEN

Rating continuous

Insulation class F

Rated power 320kW

Voltage 3300V

Power factor 0.85

Current 71A

RPM 980

Poles 6

Connection Y

Page No. 22 of 75

Page 23: NFL FINAL REPORT

INDUCED DRAFT FAN

The induced draft fans control the furnace draft by drawing the gases of

combustion through the boiler, regenerative air heaters, delivering them to the

stack. Thus the FD fan provides combustion air for the furnace while the ID fan

removes flue gases from furnace through chimney. The details of the ID fan are:

Make MEIDEN

Rating continuous

Insulation class F

Rated power 295kW

Voltage 3300V

Power factor 0.83

Current 67.5A

RPM 735

Poles 8

Connection Y

POWER GENERATION

There are two 15MW turbine generator sets to generate power at 11kV

which is fed into 132kV bus of PSEB and again distribution network.

TURBINE

The turbine used is supplied by M/S SGP of AUSTRIA. It is condensing cum

extraction turbine designed as single casing reaction turbine with single control

stage and high pressure (HP), mild pressure (MP) and low pressure (LP) reaction

parts.

The turbine is fed with high pressure steam at 100kg from boiler and flows

through various control valves for normal and emergency operation. It gets high

velocity through the nozzle group and then passes over the impellers fixed on to

the rotor and fixed diffusers thus rotating the turbine. The enthalpy of steam is

utilized in steps. Steam is also extrated from various stages. HP1 at 10.4kg/cm2,

HP2 at 8.1kg/cm2, feed water bleed at 4.3kg/cm2 and LP bleed at 0.9kg/cm2.

Page No. 23 of 75

Page 24: NFL FINAL REPORT

The exhaust steam from the turbine is condensed in a condenser

maintained under vaccum to extract maximum steam enthalpy. The output of the

turbine depends on flow of steam and heat difference that is on condition of

steam at the main steam valve and the pressure at the turbine outlet or

condenser pressure. The turbine is connected to the generator through speed

reducing gears.

The exhaust steam is condensed in a condenser using cooling water. The

resulting condensate can be fed back to LP heater but is normally sent to the

polishing water plant.

As shall be clear from the attached block diagram various bleeds from the

turbine are utilized for heating purpose. HP1 and HP2 are used for heating boiler

feed water in HP1 and HP2 heaters. Feed water bleeds is used for heating the

feed water tank and LP bleed is used for heating the polish water make up to the

feed water tank.

A lubrication system is also there to lubricate the various bearings of the

turbine, gears and generator. Normally the oil pump driven by the turbine shaft

supplies oil but auxiliary motor driven pumps are used for start up and during

shutdown. A turning gear has been provided for slow cooling of turbine rotor.

Latest instrumentation has been used in this plant. Bailey’s net work-90

microprocessor based instrumentation system is being used. The NETWORK 90

SYSTEM is a distributed process control system. Using a series of integrated

control nodes. The network 90 system allows controlling process variables like

flow, pressure and temperature according to a control configuration. There is

operator interface unit (OIU) like a TV screen on which various parameters can

be displayed and controlled. It allows fully automatic start-up/shut-down of boiler,

turbine and other auxiliaries.

Description:-

Make Simmering Graz Panker, Austria

Type Multifunction (28 stages)

Capacity 65 T/H at 15 MW

Page No. 24 of 75

Page 25: NFL FINAL REPORT

RPM 6789 at 50 Hz

Critical speed 3200-3600 RPM

GENERATORS

CPP is having two number turbo generators of capacity 15MW each. The

generators are type SAT three phase, 50Hz, 11kV, 984amps, at 0.8 power factor

rating supplied by M/S JEUMONT SCHNEIDER OF FRANCE. These are totally

enclosed self ventilated type with two lateral airs to water coolers for cooling. The

alternators are able to bear 10% overload for one hr with an increase in temp. of

100C while maintaining the voltage as near as possible to the rated one. The

excitation is compound and brushless with exciter rotor and Rectifier Bridge

mounted on the extended main shaft on non driving end. The excitation is

controlled automatically with automatic voltage regulator and a PLC controller. All

protection relays installed for protection of generator are solid state having high

accuracy, quick response and low power consumption.

Under normal running conditions of the plant and healthiness of the PSEB

grid, we generally run in synchronism with the grid merely drawing the power

corresponding to minimum charges to be paid to state electricity board. In case

of any disturbance in the grid measured by higher low frequency, high rate of

change of frequency, low voltage etc. our system gets isolated from the grid

automatically. With both generators running, we are able to feed power to the

whole plant, thus production is not affected. In case only one TG is in line and

grid cuts off, urea plant is cut off automatically to balance the load with one

generator. As soon as the grid becomes stable, the generators are again

synchronized with it.

Page No. 25 of 75

Page 26: NFL FINAL REPORT

SYNCHRONOUS GENERATOR [3 Phase] [T.G’s]

Description:-

Make- SAT,(JEUMONT SCHNEIDER)-FRANCE

Degree of protection IP (54)

Type of excitation Brush less

Insulation class Rotor-FStator-F

Temperature rise Rotor-800C B CLASSStator-700C

Output Voltage 11,000V ± 5%

Frequency 50Hz

Current 984 A

Speed 3000 RPM, Permissible-3500 RPM

Excitation Voltage 163V

Excitation current 580 A

Power factor 0.8

Duty Continuous

Noise level at 186mt. 85dB ± 3dB

Total weight 45Tonnes

Capacity 15 MW, 12.75 MVA at 0.8p.f (Lag)

Page No. 26 of 75

Page 27: NFL FINAL REPORT

Connection Star-Delta

Max. Inlet temperature Air 500CWater 360C

EXCITATION CHARACTERISTICS At no load I = 276A V = 55V At MRC I = 580A V =163VAt 125% of MRC I = 672A V = 189V

REACTANCES Synchronous Xd 133% Transient Xd’ 18.2% Subtransient Xd” 12.1%

TIME CONSTANT 4.5 secs

EFFICIENCY AT 0.8 PF At 100% load 97.53%At 75% load 97.25%At 50% load 96.49%

EFFICIENCY AT UNIT PF At 100% load 98.03% At 75% load 97.06%At 50% load 96.82%

Page No. 27 of 75

Page 28: NFL FINAL REPORT

AMMONIA PLANT

TECHNICAL DATA

1. Liquid Boiler Feed Water

2. Pumping Temp. 131°C

3. No. of Stages 6

4. Impeller Type Closed

5. Dia 420mm

6. Wearing dia 224mm

7. Clearance 0.38mm

8. Brg. Radial Journal

9. Thrust Bearing Kingsbury Type

10. Lube oil Turbine Oil 90 forced

11. Coupling Gear type

12. Rotation CW (when viewed from coupling

end)

13. Capacity (Nor.) 382m3/hr

Page No. 28 of 75

Page 29: NFL FINAL REPORT

14. Capacity (Des.) 473m3/hr

15. Suction Pr. 3 Kg /Cm2

16. Discharge Pr. 138.0 Kg /Cm2

17. Total Head 1477.5m

18. RPM 3230

19. Power 2310 kW

20. Des. Eff. 76.8%

21. Min. Cont. Flow 100m3/hr.

22. Cooling Water 33°C

TURBINE DATA

1. Rated Output 2541

2. RPM 5366

3. Inlet Steam Pr. 39.6 Kg/cm²

4. Inlet Steam Temp. 370˚C

5. Exhaust Pr. 0.126 Kg/cm²

Page No. 29 of 75

Page 30: NFL FINAL REPORT

The ammonia plant of NFL Bathinda is based on the partial oxidation of

fuel oil. The plant went into commercial production in august, 1979 and has been

built by M/S TOYO ENGINEERING CORPORATION as the main engineering

contractor.

The ammonia plant has the following processing units:-

Sl no. Unit/section Supplier Features

1. Air separation unit M/S HITACHI

JAPAN

Mol. Sieve and

activated

alumina gel bed

for CO2&

moisture

removal, cold

recovery from

the products in

plate and fin type

heaty

exchangers and

conventional

double column

for distillation.

2. Gasification M/S TEC under

process licence

from M/S SHELL

INTERNATIONAL

3 refractory

gasifiers of

series 700.

3. Rectisol (de-

sulfurisation)

M/S TEC under

process licence

from M/S LURGI

Selective

absorption of H2S

and CO2by low

temperature

methanol

4. Rectisol(decarbonation M/S TEC under Total regenration

Page No. 30 of 75

Page 31: NFL FINAL REPORT

) process licence

from M/S LURGI

of partial steam

only.

5. CO shift M/S TEC Double bed high

temperature CO

shift converter.

6. Absorption refrigeration M/S BORSIG Part of heat duty

is supplied by the

converted gas

from shift

convertor.

7. Nitrogen wash unit M/S HITACHI Mol.sieve

adsorbers for

removal of

methanol and

CO2

8. Ammonia synthesis M/S TEC under

process licence

from M/S

HALDOR

TOPSOE

Topsoe S-100

radial flow

basket, waste

haet recovery of

the converter exit

gases in BFW

economizers.

The compressor house of ammonia plant has the follwing major equipments:-

Sl no. Section Supplier Features

1. Air compressor M/S MITSUI,

JAPAN

1,40,000NM3/hr

capacity 15.45

MW turbine

2. Nitrogen

compressor

-do- 30,000 NM3/hr

capacity 6.9 MW

Page No. 31 of 75

Page 32: NFL FINAL REPORT

turbine

3. Oxygen

compressor

Compr.-DEMAG

Turbine-AEG

24,970 NM3/hr

capacity 6.59MW

turbine

4. Synthesis

compressor

BHEL Hyderabad 1,10,000 NM3/hr

for 1st ,2nd and 3rd

stages recycle

stage 15.983MW

turbine

5. Refrigeration

compressor

-do- 41,330 NM3/hr

capacity 2.8MW

turbine

Against the rated capacity of 900Te/day, plant has produced a record

production of 1011Te and has been constantly running above 105% for the past

few years.

The basic chemistry for production of ammonia is based on the

HABERS’S BOSCH PROCESS for ammonia synthesis. The reactants in the

ammonia plant are nitrogen and hydrogen. Nitrogen is obtained from its

abundant source i.e. atmosphere and hydrogen is obtained from fuel oil which is

hydrocarbon with C/H ratio of approximately 8.

As will be evident from above, the constituents in the synthesis gas other

than nitrogen and hydrogen does not play any part in the ammonia synthesis

reaction, rather they exercise undesirable effects like exerting their own partial

pressure, poisoning the catalysts etc.as such, the ammonia plant process is laid

down such that the undesirable constituents in the raw gas are removed in the

process of purification before the synthesis gas mixture, containing hydrogen and

nitrogen in the ratio of 3:1 at the required pressure is sent to ammonia synthesis

converter for synthesis reaction.

Page No. 32 of 75

Page 33: NFL FINAL REPORT

The plant has been provided with a fail safety system to take care of all

eventualities. The periodical review of the safety system is also done and

incorporations whenever necessary are done.

The plant is also equipped with a flare system with 80M height flare stack

provide with pilot and main burners capable of burning around 90,000 NM3/hr

of process gas at a time and also mol. Seal to prevent flow of gas into the flare

gas system. The pilot burner is of automatic ignition system.

The harmless gases like CO2 and nitrogen are vented through a cold flare

outlet also at 80M height. The flare system has been designed so that the toxic

gases are burnt so that their combustion products are not harmful to the

environment.

Adequate measures have been taken to contain the air and water

pollutants with in the MINAS standard. As in this process of ammonia

manufacturing, the gases,CO and H2S are extremely toxic. Monitors have been

provided in the control room with sensors installed at sensitive locations of plant

for continuous monitoring of the environment.

BRIEF DESCRIPTION OF VARIOUS PROCESS UNITS IS GIVEN

HEREUNDER:-

The plant has been supplied as a package unit by M/S HITACHI and was

plagued with constraints during the initial years of operation. These constraints

have now been overcome by:

1. Interconnecting the screw refrigeration compressor with the main

refrigeration compressor of the synthesis section.

2. Changing the material of construction of the air precooolers at the

upstream of the chilling unit from C.S. tubes to S.S. tubes.

3. Increasing the packed volume of mol. Sieve in the ASU dryers.

4. Modifying the air drier post filtration system of air before entering

the cold box.

Air separation unit provides nitrogen while section nos. 2 to 7 is for generation

and purification of hydrogen. Eighth one is for synthesis of ammonia.

Page No. 33 of 75

Page 34: NFL FINAL REPORT

Page No. 34 of 75

Page 35: NFL FINAL REPORT

1. AIR SEPARATION UNIT

Supplier of air to ASU is air compressor. It draws 1, 40,000 NM3/hr of air

from atmosphere, compress it around 7.0kgf/cm2 pressure and sends the

compressed air to ASU air compressor is a multi-stage axial flow compressor

supplied by M/S MITSUI,JAPAN coupled with a steam turbine of 15,455KW

rated output supplied by M/S MITSUI BROWN BOVERI, JAPAN. It consumes a

maximum of 60Te/hr of steam. Capacity of the air compressor can be varied with

the movement of blades fitted into the stators of LPC and HPC casings. For

running plant at higher loads extra quantity of air is required. To augment this

shortfall, a small centrifugal compressor has been installed. It supplies around

4500 NM3/hr of air and is fitted with an electrical motor of 650KW rated output.

Air separation unit is having the capacity to supply maximum 25,920 NM3/hr

oxygen (minimum 98% purity) and 30,000 NM3/hr of nitrogen (minimum 99.99%

pure oxygen content less than 8ppm).

Feed air is first cooled in an ammonia chiller equipped with a screw

compressor (GB-5: with a refrigeration capacity of 825 refrigeration ton) and then

atmospheric moisture and carbon dioxide are removed from the air in air dryers,

filled with alumina gel and molecular sieves. This purified air is further cooled up

to its liquification temperature with cold outgoing product streams in the multi

path main air heat exchanger.

The cooled air gets partially liquefied. This liquid air is distilled in specially

designed two columns, lower column and upper column and a main condenser

which acts as condenser for lower column and reboiler for upper column.

In the distillation column liquid air is separated into pure oxygen and

nitrogen streams. The cold streams (along with impure and high pr. N2 streams)

are used to cool and liquefy the incoming air and subsequently oxygen is sent to

gasification section and nitrogen wash unit and for stripping in rectisol section.

To avoid cold loss from the equipments or pipings, operating at very low

temperatures, these equipments have been installed in a box known as cold box

and this box has been filled with PERLITE insulation.

Page No. 35 of 75

Page 36: NFL FINAL REPORT

Since all the cold loss can be recovered from the outgoing streams, some

cold loss occurs which is compensated by expansion turbines provided inside the

cold box. The expansion turbines generate cold by expanding air from 7kg/cm2 to

0.7kg/cm2.

Liquid oxygen and liquid nitrogen are also drawn for selling as by product.

Refrigeration capacity of the screw compressor GB-5 provided for chilling air

prior to adsorption of CO2 and moisture is 825 refrigeration ton.

2. GASIFICATION SECTION

The hydrogen generation takes place in gasification section. This section

is provided with three nos 700 series gasifiers supplied by M/S SHELL

GASIFICATION. 700 series signifies the generation capacity of a gasifier i.e.

700×1000 NM3 of gas per day.

Fuel oil at a pressure of 130kg/cm2 and a temp of 2300C is partially

oxidized in the gasifiers with oxygen and 64kg/cm2 steam. As the reactions

involved are highly exothermic the inside temp of the gasifiers are maintained at

13600C with the help of steam and endothermic reaction. The gaseous mixture

formed by the partial oxidation of fuel oil leaves the gasifier at 13600C. The

operating pressure for gasifier is 55kg/cm2.

The waste heat of the gas is recovered in a boiler where 100kg/cm2 steam

is generated and in turn gas is cooled to 3180C from 13600C. Further the temp

of these gases is brought down to 2000C in the economizer by preheating the

boiler feed water. Residual carbon is formed during the gasification of oil is

separated in the form of carbon slurry in quench pipes and carbon separator,

with help of quench water. Gases leaving the carbon separators of all the three

streams are mixed together and further cooled in BFW preheater and scrubbed

with water or removal of the remaining content of carbon in the carbon scrubber.

It is necessary to remove the carbon completely from the gas otherwise it will

choke the down stream equipments in rectisol desulphurization section. The raw

gas contains mainly CO and H2 while other constituents like H2S, methane are

also present.

Page No. 36 of 75

Page 37: NFL FINAL REPORT

Oxygen is fed to the gasifier in a controlled quantity which is lower than that

required for total oxidation, with the intention of partially oxidizing the

hydrocarbon content of the fuel oil, and this result in the formation of 48% of

carbon mono-oxide in raw gas. This CO content is then reacted with steam in CO

shift section to form further quantity of hydrogen and hence the name of the

process i.e. “PARTIAL OXIDATION OF FUEL OIL”.

100kg/cm2 saturated steam is superheated to 4800C from 3140C in the

steam super heater with the help of tail gas combustion (obtained from nitrogen

wash unit) and is then mixed with main steam header coming from auxiliary

reboilers. In order to have flame stability in the super heater, oil support is also

provided.

3. RECTISOL-1(DESULPHURIZATION)

The feed stock contains around 2.5%sulphur and this leads to the

formation of hydrogen sulphide in the gasifiers. This impurity of H2S has to be

removed from the gaseous mixture as sulphur is a serious poison for the

catalysts used in CO shift and synthesis section. Rectisol desulphurization

section is employed for the purpose of removal of H2S by absorption in low

temperature methanol.

The gaseous mixture coming from gasification section is first cooled to

220C in ammonia chiller and with cold desulphurized gas in exchangers. It is then

fed to a tall tower called H2S absorber, equipped with valve type trays. Cold

methanol at a temperature of -310C is fed at the top of the tower. As the gas

moves up and cold methanol flows downward, these have intimate contact with

Each other on the trays. Here the H2 in the gas is absorbed by methanol and

desulphurized gas leaves at the top of the tower. The operating pressure of the

tower is 46.1kg/cm2.

H2S loaded methanol withdrawn from the bottom of H2S absorber is

flashed to 12 kg/cm2.,0.5 kg/cm2.and then heated to 880C. Regenerated methanol

is subsequently cooled and recycled back to H2S absorber, one of the gases

generated during regeneration process of methanol in hot regenerator is known

Page No. 37 of 75

Page 38: NFL FINAL REPORT

as clause gas and is rich in H2S content. It is sent to sulphur recovery plant,

where sulphur is produced from this gas as a by product.

4. CO SHIFT CONVERSION SECTION

Desulphurised gas coming from rectisol-1 is led to this section. In this

section CO in the gases reacts with steam as per following CO SHIFT reaction

CO + H2S CO2 + H2 + Heat

34.7TE/hr of 64 kg/cm2. steam is added form outside sources. Though the

actual steam consumed in CO shift reaction is only 37Te/hr but due to kinetics of

the reaction involved steam to gas ratio has to be maintained at 1.5 and for this,

large amount of steam will be required. But this demand of excess steam is met

by humidification of the gas. For this purpose gas is contacted with hot process

condensate, saturating the gas with water vapours and after the CO shift reaction

excess water is removed from the gas by dehumidification process.

Heat of the gas shifted is utilsed in the reboiler of absorption refrigeration

unit and subsequently 3 kg/cm2. Steam is generated. Gas is sent to

rectisol(decarbonation) after cooling to 450C. Gas leaving CO shift section

contain 3.5% CO.

5. RECTISOL-2(DECARBONATION)

This section is employed for the removal of CO2 content of the gas. Here

again methanol is used for absorption of CO2 though at a relatively colder

temperature than those in rectisol(desulphurization).

Similar to desulphurization process, CO shifted gas is first cooled with cold

CO2, synthesis gas from nitrogen wash unit washing column outlet and ammonia

chiller, then fed at the bottom of CO2 absorber, which is a tall tower equipped

with valve type trays. Methanol at temperature of -580C and -700C is charged at

the top and middle of the tower respectively. With the intimate contact of gas and

Page No. 38 of 75

Page 39: NFL FINAL REPORT

liquid methanol on trays, CO2 is absorbed by methanol and operating pressure of

this tower is 39.5 kg/cm2.

CO2 loaded with methanol is withdrawn from the bottom of the tower and is

flashed to 0.8 kg/cm2 and (-) 0.4 kg/cm2 pressure and then stripped with nitrogen

for regeneration. A blower is used for generating vaccum for the 2nd stage

regeneration of the methanol. Generated CO2 from the flash and vaccum

sections of the tower is sent to the urea plant.

6. ABSORPTION REFRIGERATION UNIT

For cooling rectisol(desulphurization) and rectisol(decarbonation)

incoming gas streams and circulating methanol streams, ammonia chillers are

employed in which cooling is done by evaporating liquid ammonia. These chillers

are linked with absorption refrigeration unit (ARU).

In this section ammonia vapours are absorbed in lean ammonia solution.

Rich ammonia solution thus formed is raised to a pressure of around 15.5 kg/cm2

and pure ammonia vapours and lean ammonia solution are separated in a

distillation tower. High pressure ammonia vapours are condensed with cooling

water and liquid ammonia thus formed is sent to ammonia chillers. Lean

ammonia solution formed is reused for absorbing low pressure ammonia vapours

coming chillers. Refrigeration capacity of ARU IS 1600 refrigeration ton.

7. NITROGEN WASH UNIT

Decarbonated gas coming to rectisol-2 at 39.5 kg/cm2 and 550C contains

5.21%CO ,0.50% CH4 , in addition to 93.62% of hydrogen and 0.67% of

N2+Ar.CO and CH4 are undesirable constituents in synthesis section,wher these

will act as catalyst poison and inert respectively. Hence these are removed from

the gaseous mixture in NWU. Hydrogen boils at a considerably lower

temperature than all other impurities i.e. CO and CH4 present in the

decarbonated gas. This difference in boiling points allows removing these

impurities by fractional condensation. Boiling points of hydrogen, nitrogen,

carbon-mono-oxide and methane at atmospheric pressure are -249.40C,

Page No. 39 of 75

Page 40: NFL FINAL REPORT

-195.80C, -191.50C and -161.50C respectively. Nitrogen wash unit has been

supplied by M/S HITACHI ,JAPAN as a package unit.

Decarbonated gas coming form rectisol-2 unit at -550C contains a

maximum of 10ppm of methanol. These constituents are removed completely by

passing the gas through molecular sieve adsorber beds. There are three

adsorber beds filled with 5A type 7.0Te (for each adsorber) molecular sieves.

These adsorbers operate on a ten hour cycle. One adsorber remains in line and

other two undergo regeneration with 6 kg/cm2, N2 obtained from ASU. Nitrogen

wash unit operation takes place at very low temperatures, of the order of -1950C.

Hence the equipments,down stream of adsorbers, are installed in cold box filled

with perlite.

After CO2 and methanol removal, in adsorbers, the gases enter the cold

box. Here the gas is first cooled to -1900C by outgoing washed gas in raw gas

exchangers. It is then fed to the bottom of washing column in which liquid

nitrogen at a temperature of -1950C is charged from the top of the tower. This

tower consists of sieve trays and on these undesired components i.e. CO and

CH4 are carried along by the downward flow of liquid nitrogen.

Purified gas, slightly rich in nitrogen, leaves at the top of the tower. After

frigony recovery of the gases in exchangers of rectisol section, where the

incoming gases to CO2 absorber are cooled, and this gas goes to synthesis

compressor suction as make up gas for synthesis section. Tail liquid formed at

the bottom of the column is flashed to 0.6-0.8 kg/cm2 pressure and the tail gas is

burned in steam superheater,as it has high calorific value.

Cold requirement of NWU is fulfilled by sending a partially cooled nitrogen

stream to ASU for liquification and super cooling. In the course of operation of

adsorbers, due to attrition, fine dust of molecular sieve is formed. During the

earlier operation of the plant up to 1983-84, thus dust used to get deposited on

the heat transfer area of the heat exchangers causing higher cold loss which

used to result in stoppage of plant for back blowing of the equipment for dust

removal leading to production losses. To overcome this problem 2MOTT filters

Page No. 40 of 75

Page 41: NFL FINAL REPORT

consisting of sintered iron candles with pore size of 5 microns were installed.

With this modification, problems sue to dust has been overcome.

Nitrogen to NWU is supplied by nitrogen compressor. It takes suction

nitrogen from air separation unit; it compresses it to 45 kg/cm2 and feeds to

NWU. It is a centrifugal type compressor having two casings i.e. high pressure

casing and low pressure casing. Each casing is having two compression stages.

Compressor is coupled with a steam turbine, supplied by M/S MITSUI,JAPAN.

The turbine is single cylinder, impulse reaction type extraction condensing type

turbine with rated output as 6890KW and requires a maximum of 83Te/hr of 100

kg/cm2 superheated steam. For normal operation it supplies 5659KW of power

with a steam draw of 75Te/hr. out of this 54Te/hr of steam at pressure of 64

kg/cm2 is drawn as extraction steam which is used in gasification and CO shift

sections.

8. SYNTHESIS SECTION

Make up gas coming from NWU is compressed to around 220 kg/cm2

pressure by synthesis compressor. Up to three stages of the compressor make

up gas is compressed; while at the suction of fourth stage know as recycle stage.

It is mixed with recycle gas coming from synthesis section. The compressor of

BHEL make and the turbine is of SIEMENS. The compressor is of multistage

vertically split casing type and consists of three barrels. Steam turbine of

synthesis compressor is an extraction condensing type with rated output of

15983KW. It requires 181Te/he of 100 kg/cm2 superheated steam at 4800C out of

this 145Te/hr at 40 kg/cm2 is drawn as extraction.

The compressed make up gas along with recycle gas is fed to the

ammonia converter after preheating with outgoing gases. Ammonia converter is

S-100 type radial flow converter supplied by M/S HALDOR TOPSOE. It consists

of two beds charged with reduced iron oxide catalyst. The operating temperature

for the converter is in the range of 3750C to 5000C. Nitrogen and hydrogen react

with each other in the presence of the catalyst as per following reaction.

Page No. 41 of 75

Page 42: NFL FINAL REPORT

N2 + 3H2 2NH3 + Heat (26000Kcal)

Ammonia produced from the above reaction along with unreacted gasses

leave the converter at around 3170C. It is cooled in BFW economizer to 1690C,

then synthesis hot gas-gas exchanger up to 710C, in synthesis water cooler up to

400C ,synthesis cold gas-gas exchanger up to 330C and then finally to 100C in an

ammonia chiller. At this temperature product ammonia gets liquefied and is

separated in a separator. Separator gases are sent to the synthesis compressor

at recycle stage suction. The cooling system of NH3 chiller is equipped with

refrigeration compressor and capacity of this system is 2676 refrigeration ton.

The product ammonia thus formed at a rate of 37.5Te/hr is either sent to urea

plant or for storage.

9. BFW/STEAM SYSTEMS

a.) STEAM SYSTEMS

Fuel oil partial oxidation based ammonia plant is major consumer of

steam. It requires around 7Te of steam per ton ammonia. Around 310-320Te/hr

of 100 kg/cm2 superheated steam at 4800C is supplied by auxiliary boilers and

another 82Te of 100 kg/cm2 saturated steam is generated in waste heat boilers in

gasification section. This steam after super heating to 4800C in steam

superheater is mixed with the main steam coming from boilers. There are total

six steam headers.

b.) BFW SYSTEMS

Polish water at a rate of around 425Te/hr is supplied from

demineralising plant. After thermal dearation with steam, hydrazine is added as

oxygen scavenger. Further ammonia is dosed to raise its pH to 9.0. then this

boiler feed water is pumped to auxiliary boilers and waste heat boilers by BFW

PUMPS, which raises its production to around 131 kg/cm2. There are two steam

driven pumps and one electric driven available for this purpose, all supplied by

M/S EBARA,JAPAN.

Page No. 42 of 75

Page 43: NFL FINAL REPORT

POWER DISTRIBUTION IN AMMONIA PLANT

Two feeders from MRS incomer A and incomer B feed the 11kV bus at

ammonia control panels for 11kV are provided by L&T. each panel is provided

with circuit breaker of 630A, 300MVA which are activated by the relay in case of

fault. Panels 1-5 and 12-17 are fed to 415V panel through 11kV/415V, 2MVA

transformer and panels 6 and 11 feed the 3.3kV panel through transformer of

rating 11/3.3kV, 10MVA. Bus coupling is provided between buses A&B from

ammonia there are two feeders to coal handling (1.6MVA), boilers (2MVA), and

D.M plant (2MVA). If one of the feeders fails or there is any abnormality then the

total load is transferred on the other feeder by using bus coupler. The 11kV

supply is then further stepped down to 3.3kV and 415V using step down

transformers, 3.3kV is used for H.T. motors and 415V is used for L.T. motors.

This plant also has the facility of battery room.

Page No. 43 of 75

Page 44: NFL FINAL REPORT

Page No. 44 of 75

Page 45: NFL FINAL REPORT

UREA PLANT

Urea plant has a rated capacity of 1550Te/day of prilled urea produced in

a single stream plant employing MITSUI TOATSU TOTAL RECYCLE C

IMPROVED PROCESS.

Features of the plant are as under:-

Sl no. Features MTC-C-IMPROVED

1. Type of process Conventional

2. Molecular ratio

NH3 : CO2

H2O : CO2

4:1

0.544:1

3. Conversion percentage 70%

4. Reactor conditions

Pressure kg/cm2

Temperature 0C

250

200

5. Reactor lining Titanium

6. Reactor features Hollow

7. Excess NH3 recycle As liquid NH3

8. Decomposition stages 1st: 17.5kg/cm2

2nd : 2.5 kg/cm2 ( 5% CO2

fed to 2nd decomposer)

3rd: 0.3 kg/cm2

9. Heat recovery in

carbonate condenser

For supplying heat to

crystallization to urea

slurry and heating hot

water.

10. Sp. Cons.

Te NH3/Te urea

Te CO2/Te urea

Power /Te urea KWH

Steam /Te urea

0.58

0.76

86.4

1.24

Page No. 45 of 75

Page 46: NFL FINAL REPORT

11. No. of conc. Stages One

12. Type of prilling tower Induced draft

13. Approx. prilling height 40M

14. Salient features a.) power saving as

5% CO2 is fed to

LD

b.) P.T. height is less

cause of cooler at

bottom.

c.) Low biuret

d.) Because of Ti

lining in reactor

corrosion rate is

less and thinner

liner.

e.) Water recycle is

less due to

counter current

flow of liquid and

vapour in

decomposers.

The plant is divided into four sections:

1. Synthesis section.

2. Decomposition section.

3. Crystallization and prilling.

4. Recovery.

The brief description of various sections is given as under:

Page No. 46 of 75

Page 47: NFL FINAL REPORT

SYNTHESIS SECTION

In MITSUI TOATSU TOTAL RECYCLE C IMPROVED PROCESS liquid

ammonia is recycled since it is easier to handle but require equipments like

rectification column storage tanks etc. and higher capacity liquid ammonia

pumps.

Recycling of carbamate requires higher capacity carbamate pumps.

CO2 is received from ammonia plant at a pressure of 0.2 kg/cm2 and 200C and is

compressed in a centrifugal booster compresser,UGB-101 to 32 kg/cm2 in 3

stage unit. The compressor supplied by M/S BHEL has a normal capacity of

25256NM3/hr and has 2 barrels 2 M.C.L. 805 and MCL 455. The drive of the

compressor is an extraction and condensing type by steam turbine supplied by

M/S BHEL. The turbine is driven by 40K super heated steam and has a rated

output of 5792KW.

UREA SYNTHESIS

2NH3 + CO2 NH2CONH4, H = -37.64Kcals 1

NH2CONH4 NH2CONH2+ H2O, H = 6.32Kcals 2

Where as reaction 1 is an exothermic and rapidly goes to completion of 2

and is endothermic and is always incomplete. The overall reaction is exothermic

and hence heat has to be removed continuously for the equilibrium reaction to

proceed. The conversion of ammonium carbamate to urea depends upon:

1. Reaction temperature.

2. Mol. Ration of NH3/CO2, H2O/CO2 of the feed reactants.

3. Residence time.

The conversion increases with the increase in temperature, NH3/CO2 ratio and

residence time and decreases with H2O/CO2 ratio since the presence of water

tends to shift reaction 2 in the backward direction. The pressure employed

depends on the reaction temperature and has to be kept higher than the

dissociation pressure of ammonium carbamate at that temperature. Further since

Page No. 47 of 75

Page 48: NFL FINAL REPORT

the dehydration of ammonium carbamate to urea takes place in liquid phase

only. The pressure employed must also be higher than the vapour pressure of

ammonium carbamate which is rather high.

High ratio of NH3/CO2 increases conversion and helps to minimize

corrosion. As this ratio increases the load on recovery section increases since

excess NH3 over stoichiometric requirement has to be recovered and recycled

back to reactor. This excess ammonia can either be recycled as liquid NH3 or

carbamate. In each case it becomes necessary to inject CO2 into carbamate

condensers.

The compressed CO2 is washed with water in a packed bed tower called

methanol absorber for removal of entrained methanol in CO2 which is normally

100ppm. The washed CO2 is further compressed to a pressure of 260kg/cm2 in a

two stage compressor, UGB-102 supplied by M/S KOBE STEEL, JAPAN. This

reciprocating compressor has a normal capacity of 26260NM3/hr and is driven by

a 2.2MW synchronous motor. Anti corrosion air at the rate of 120NM3/hr is fed to

CO2 at the suction of centrifugal CO2 booster compressor.

Liquid ammonia at 110C and 18kg/cm2 pressure is received in the

ammonia reservoir, UFA-401 from the Horton sphere. Ammonia booster pump

UGA-404A&B boost the pressure of the feed ammonia to 24kg/cm2 and feeds at

the suction of plunger type ammonia feed pumps UGA-101A-D. the ammonia

feed pumps are of URACA MAKE driven by 3.3kV/450KW and have capacity of

53.2M3/hr, 178RPM and 89% efficiency. The ammonia preheater UEA-101 and

102. The preheated ammonia at 85.30C is fed to the urea reactor at bottom.

The recycled carbamate solution of CO2 concentration, 7.5 lit per 25ml, at

1050C and 260kg/cm2 pressure is delivered to the urea reactor at bottom by

recycle carbamate solution pumps UGA-102A&B. these pumps are centrifugal

type and are driven by back pressure steam turbine, supplied by M/S

EBARA,JAPAN and have a capacity of 81M3/hr.

The three feeds i.e. CO2 liquid ammonia and recycled pump solution are

fed to a Ti lining multi layer urea reactor. The reactor is a 12 layered C.S vessel

with Ti liner thickness of 5mm, 4mm and 3mm for the 1/6th, 1/6th and 2/3rd of total

Page No. 48 of 75

Page 49: NFL FINAL REPORT

height of the reactor from bottom. The reactor top temperature is maintained at

2000C maximum. The effluents from urea reactor from top are let down to

17.5kg/cm2 pressure through a pressure control valve PCV-101 and fed to the

high pressure decomposer at 1240C.

DECOMPOSITION SECTION

MITSUI TOATSU TOTAL RECYCLE C IMPROVED PROCESS is a

conventional process.

The decomposition reaction

NH4COONH2 2NH3 + CO2

Is favored by lower pressure of system or by low partial pressure of one of the

reaction products i.e. NH3 and CO2. Conventional process means the process

where the decomposition is affected by lowering in pressure in successive stages

followed by indirect heating whereas the processes where decomposition takes

place by lowering the partial pressure of either NH3 or CO2 followed by indirect

heating are called STRIPPING PROCESSES.

The reactor effluents at 17.5kg/cm2 and 1240C enters the part of high

pressure decomposer U-DA-201 having sieve trays at upper and falling film

heater at lower section. The flashed gases go up and liquid flows down through

sieve trays. On trays the high temperature gas from reboiler,U-EA-201 and falling

film heater contacts with the liquid flowing down. The sensible heat of gas and

heat of condensation of water vapour are used to evaporate the excess ammonia

and to decompose the carbamate.

This helps in minimizing water evaporation and thus reducing water

recycle to reactor. The reboiler further heats the liquid by 12kg/cm2 steam to

release excess ammonia and carbamate gases. The temperature at middle is

maintained at 1510C by a temperature control valve TCV-201. The temperature

at bottom is maintained at 1650C through TCV-202. The falling film heater is used

to minimize residence time in order to reduce biuret formation and hydrolysis of

urea.

Page No. 49 of 75

Page 50: NFL FINAL REPORT

Anti corrosive air is fed to high pressure decomposer and reboiler through

air compressor UGB-201@ 2500ppm as air. Overhead gases from HD are

absorbed in HAC(high pressure absorber cooler). The bottom liquid flows to L.D.

(low pressure decomposer) at 2.5K, 1450C,upper part, having 4 sieve trays. A

similar phenomenon occurs in the low pressure decomposer. The reboiler U-EA-

202 provides heat using 7kg/cm2 steam for decomposition and hot stream from

H.D heats up the solution from L.D in an exchanger before entering the upper

part. The temperature is maintained at 1300C at middle by TCV-203. Small

amount of CO2 is fed below packed bed for improved stripping of decomposed

gases. The overhead gases from low pressure decomposer are absorbed in low

pressure absorber U-EA-402. Bottom liquid flows to 3rd stage of decomposer

called gas separator U-DA-203. The upper part of gas separator operates at

1060C, 0.3K and lower part with packed bed operates at 1000C and atmospheric

pressure. The sensible heat of solution from low pressure decomposer is enough

for evaporating the overhead gases. In the lower part, air containing trace

amounts of NH3 and CO2, is blown under the packed bed, by off gas recycle

blower UGB-401. The urea solution is concentrated to 70-75% and sent to

crystallization section.

CRYSTALLIZATION AND PRILLING SECTION

The urea solution obtained from the last decomposition stage i.e. gas

separator contains 25% H2O since every mole of urea one mole of H2O is

formed. Urea has to be concentrated to 99.5% before prilling.

MTC-C-IMPROVED PROCESS employs crystallization-remelt prilling

route and uses spray nozzles for prilling. The prilling tower is of induced raft type.

The solution from gas separator enters lower part of crystallizer, U-FA-

201. The upper part is vaccum concentrator with two stage ejectors and

barometric condenser.

In vaccum concentrator. Operating at 75mm of Hg and 600C, water is

evaporated and supersaturated urea solution comes down through barometric

Page No. 50 of 75

Page 51: NFL FINAL REPORT

low into the crystallizer, where urea crystals grow. The heat required for water

evaporation comes from:

1. Sensible held of feed urea solution.

2. The heat of urea crystallization.

3. Heat recovered by urea slurry circulated through high pressure absorber.

The crystallizer is operated at 600C and atmospheric pressure, so the slurry

leaving the bottom contains 30-35% urea crystal by weight.

Hot water from hot water pump is used in jackets of crystallizer and pipe to

avoid crystal build up on vessels walls which may cause choking otherwise.

The urea slurry is pumped from crystallizer bottom to centrifuges U-CF-

201A-E (1000RPM, 43Te/hr of slurry) maintaining minimum recirculation to

crystallizer to prevent choking of lines.

Biuret remains with mother liquor, which after separation from urea

crystals in the centrifuges is recycled back to the system. Because of excess

ammonia in reactor biuret, thus recycled is converted back to urea.

NH2CONHCONH2 +NH3 2NH2CONH2

Urea crystals separated from slurry with 2-4% moisture are discharged to

fluididsing dryer UFF-301 at 1100C. The mother liquor flows down to mother

liquor tank, provided with steam coils. Mother liquor is pumped back to

crystallizer via LCV-207. a part of mother liquor going to low pressure absorber

has been cutoff and instead dust chamber overflow solution has been lined up.

Air is blown from blower U-GB-301(82360NM3/hr) and heated to 1000C in

air heater. This hot air droes the crystals to 0.1% to 0.3% moisture content. Dried

crystals are conveyed by a pneumatic duct to cyclones at the prilling tower top.

The collected crystals are melted in melter (1370C) and urea melt is sprayed

through 12 nos. acoustic granulators. Prills are cooled in fluidizing bed called

CFD,installed at the prilling tower bottom. Air/cyclone scrubbed for urea dust

separators. Air containing urea dust from P.T column is scrubbed with water and

Page No. 51 of 75

Page 52: NFL FINAL REPORT

passed through 144 sets of poly urethane filters before exhaust to atmosphere to

reduce air pollution.

RECOVERY SECTION

The gases from gas separator are condensed in off gas condenser UEA-

406 to 620C and enter the bottom of off gas absorber DA-402(OGA). Condensed

liquid flows down to off gas absorber tank UFA-203. After cooling to 360C, liquid

is sent to top portion of OGA as absorbent. OGA bottom fluid is recycled as

absorbent at OGA middle position (2nd bed).

Air from top of OGA is blown to gas separator by GB-401 blower. The

gases from low pressure decomposer are absorbed in low pressure absorber

(EA-402) bubbling a sparger. Dust chamber over flow solution (10-15% urea) is

used as absorbent. Low pressure absorber temperature is controlled at 450C and

CO2 concentration 2.2 lit/2.5ml.

Solution from LA is pumped by GA-402A/B to high pressure absorber (DA-

401) middle through mixing cooler where liquid ammonia is mixed and serves as

medium in the absorber.

The gases from HD top are bubbled through a sparger in high pressure

absorber cooler EA-401, where 65% of CO2 is absorbed. Remaining gases from

HAC go to HA and are cooled down to 800C max. in middle cooler at the bottom

of HA 35% of CO2 is absorbed in packed bed by a mixture of lean carbamate

from low pressure absorber through FCV-401 and liquid ammonia from GA-

404A/B( temp. max 600C) through FCV-402. the scrubbed gas then passes

through five nos. of condensers(EA-404A-E) and purge condenser EA-403.

Liquid ammonia flows down to ammonia reservoir FA-401. Non-condensable

gases flow to ammonia recovery absorber. Recovery loop pressure is controlled

by PCV-405 at top of EA-405 lV. Cold steam condensate is fed for absorption.

Aqueous ammonia is with drawn from recovery absorber bottom by GA-405A/B.

Page No. 52 of 75

Page 53: NFL FINAL REPORT

WATER AND AIR POLLUTION

AIR POLLUTION

The sources of air pollution in urea plant is the air from prilling tower which

in the process of cooling of molten urea being sprayed from the top of the prilling

tower gets entrained with urea dust. In order to contain the urea dust emissions

in the exit air, the air is scrubbed with water and subsequently passes through

144 poly urethane filters before being discharged to atmosphere. The normal

emission level in the exit air is 30-40mg/NM3 against the prescribed norms of

50mg/NM3.

LIQUID POLLUTANTS

The sources of liquid pollutants in urea plant are:-

1. dust chamber over-flow solution

The over-flow from dust chamber is being completely utilized after

introduction of innovative operational practice mentioned above.

2. Dilute urea solution during start-up and shut-down of plant

To take care of the dilute urea solution during start-up and shut-down of

the plant 3 SS tanks of 100M3 and 200M3 capacity have been provided.

Three tanks are equipped with steam coils for concentration of the urea

solution. The solution, thus stored, is reprocessed after the plant condition

is normalized.

3. C.F.D washing

The frequency of CFD washing is 11/2 months during summer months

and three months during winter months. The washed water from CFD

containing urea is stored in a pacca pit of 250M3 capacity. This pit has

been provided with a pump and the stored solution is reprocessed during

normal operation of the plant.

4. leaks from pumps and effluents generated during flushing of strainers

The pollutants generated are diverted to a effluent pit.

Page No. 53 of 75

Page 54: NFL FINAL REPORT

The effluent is subsequently sent to the bio urea hydrolyser in the effluent

treatment plant for hydrolysis of the urea.

HYDROLYSIS OF UREA

In aqueous solution urea is sufficiently stable up to 800C. Above that

temperature , it changes into ammonium isocyonote and subsequently into

ammonium carbonate.

CO (NH2)2 = NH4NCO

NH4NCO + 2H2O = (NH4)2CO3

Which changes into ammonium hydro-carbonate and this ultimately dissociates

into ammonia and carbon-di-oxide.

(NH4)2CO3 = NH4HCO3 + NH3

NH4HCO2 = CO2 + H2O + NH3

The overall hydrolysis reaction is shown by equation:

(NH4)2CO3 + H2O 2NH3 + CO2

Page No. 54 of 75

Page 55: NFL FINAL REPORT

POWER SOURCES AND FEEDERS

It was the final stage of the whole plant where urea is actually produced.

The single line diagram is quite similar to that of ammonia plant. There are three

feeders to DM plant of 2MVA and 10MVA. Two 11kV feeders are coming from

MRS to this plant namely incomer-A and incomer-B. These feeders comprises of

bus of 11kV at urea plant. Further there are transformer which steps down the

voltage i.e. 10MVA and 1.6MVA. There are two 10MVA and four 1.6MVA

transformers. One feeder at 11kV from urea directly feeds the 11kV synchronous

motor. The stepped down voltage i.e. 3.3kV and 415V is further fed to HT and LT

motors. Further new buses are made at 415V and is fed to motor control

center(MCC). Bus coupling is also provided in between the two feeders at the

bus so that in case there is nay fault on one feeder the total load will

automatically shifts to other feeder.

EQUIPMENT DETAILS

There are about 150 small and big motors in urea plant and about 40

motors in bagging plant. Some important motors are:

11kV-2200kW synchronous motor for UGB102

3.3kV-600kW induction motor for UGB302

3.3kV-450kW motor for UGA101

415V-110kW induction motor for UGB301

415V-60kW induction motor for UGD304

415V induction motor for PJD107

Total connected motor load for urea plant is about 8MW and normal

running load is about 5.5MW for bagging plant, connected motor load is about

200KW and running load is 140KW.

Power supply system

We receive two 132kV feeders from PSEB and two 132kV feeders from CPP in

MRS where after stepping down to 11kV through transformer, this supply is

distributed to various plants.

Page No. 55 of 75

Page 56: NFL FINAL REPORT

In urea plant, two feeders of 11kV supply are received from MRS in urea

substation at 11kV panel designated and UNB205. This is further stepped down

to 3.3kV & 415V through transformer. There are two nos. 11kV/3.3kV 10MVA

transformer and four nos. 11kV/415V 1.6MVA transformers. Power supply to

O&U plant is fed from 11kV bus. Supply to UGB102 motor is also given from this

bus.

For 3.3kV supply system, output of 10MVA transformer is terminated at

3.3kV panel designated as UNB301. It also has two sections A&B. normally;

similar feeders are divided into two groups and fed from alternative sections. It is

being done to have availability of partial equipments in case of limitation to some

sections.3.3kV motors connected to both the sections are as under:

3.3kV SECTION ‘A’ 3.3Kv SECTION ‘B’

UGA302 UGB303

UGA101A& B UGA101C& D

CGA302A CGA302B

IGB101A MGA101A

CGA101D CGA101F& G

CGA201A& B CGA201C& D

CGA301A CGA301B

Similarly, for 415V system, there are 4nos. transformers feeding 2 nos.

415V panels designated as UNB401 &UNB402. Both these panels are also

having two sections A& B. there is one more panel namely UNB403. This panel

has two power supply source, one from UNB402B and other from emergency

diesel generating set installed near instrument air compressor house. In case of

normal power failure to this panel, emergency power panel is made available to

this panel within 40 secs and all the sequence of power to this panel is

automatic. One more panel namely UNB404 has recently has been introduced in

the system. Power to this panel is coming from MRS through an old construction

power sub-station. All the welding outlets, cranes etc are connected to the panel.

An additional source is also connected to this panel from UNB401 a section for

reliable power availability during shutdown.

Page No. 56 of 75

Page 57: NFL FINAL REPORT

Besides above power supply system, we are also having one 110V DC

supply system backed by battery bank. This power is used for protection system

of electrical equipments and instrumentation.

SYNCHRONOUS MOTOR

Description

Output 2200kW

Speed 333.3RPM

Poles 18, excited field voltage- 55V

Voltage 11kV, excited field voltage-13A

Power factor 0.8

Current 153A

Motor field volts 220V, motor field current-152A

Armature insulation class motor-B,exciter-B

Field insulation class motor-B, exciter-B

Space heater 2.5kW, 240V

Make TOKYO SHIBAURA ELECTRICAL CO LTD

Purpose For CO2 compressor

Synchronous motor is not self starting. The current in a synchronous

motor is approximately in phase opposition in phase to the EMF generated

current, remains high for longer period to avoid the tripping of motor circuit. The

effect of armature reaction is to increase the flux in leading half of each pole. The

flux is distorted in the direction of rotation and the lines of flux in the gap are

skewed in such a direction as to exert a clockwise torque on the rotor. Since the

resultant magnetic flux due to stator current rotates at synchronous speed, the

rotor must also rotate at the same speed. As in case of induction motor if load is

increased, speed slows down but in case of synchronous motor if there is

increased in load then there is no change in speed. But in case of synchronous

motor if there is increase in load the there is no change in speed. But in case the

RPM decreases, the motor will stop running even a point difference in RPM

Page No. 57 of 75

Page 58: NFL FINAL REPORT

causes the motor to stop running. Varying the field current can control power

factor of synchronous motor.

STARTING OF SYNCHRONOUS MOTOR

When the rotor of three phase synchronous motor is stationary, the

rotating magnetic field due to stator currents produces an alternating torque on

the rotor i.e at once instant the rotor is moved clockwise and other counter

clockwise. Since a net torque is zero, a synchronous motor is not self starting.

The method to bring the motor up to synchronism is as follows:-

By damping grid in pole shoes:- these grid consist of copper bars short

circuited at each end. The rotating magnetic flux induces current in these grids

and the machine accelerates. During the starting period the rotor field winding is

usually closed through the armature of exciter, normally a DC shunt generator

carried on the extension of the shaft and current in the stator is limited to

permissible value. When the machine has reached nearly full speed, the rated

voltage is applied to stator winding and the exciter voltage will have built up

sufficiently to magnetize the rotor poles. The resultant magnetic flux due to stator

current is then moving past the rotor poles at a slow speed and produces a slow

frequency alternating torque superimposed upon that exerted by the damping

grids. Consequently the rotor is accelerated at one instant and retarded at other

and the fluctuation of speed is sufficient to bring the rotor up to synchronous

speed. Once this speed has been attained the rotor can run in synchronism.

Page No. 58 of 75

Page 59: NFL FINAL REPORT

SYNCHRONOUS MOTOR SELECTION CRITERIA

We are having 2200kW, 11kV synchronous motor for running CO2

compressor UNB102. Why this motor was selected? Why we have not gone for

an induction motor or steam turbine? Some of the reasons are:-

1. Low speed reciprocating compressor

CO2 compressor popularly known as KOBE compressor is a low

speed reciprocating compressor. We need very constant speed for this

compressor. Normal induction motor has effect of voltage, frequency &

mechanical loading on its speed due to said reasons, so this synchronous

motor is selected.

2. Power factor improvement

In electrical AC system, voltage and current are concurrent. They

always deviate with each other by some angle when drawn vertically.

Cosine of this angle is known as power factor. Low power factor has some

disadvantages; it affects the efficiency of generating station. Large

electrical equipment such as transformers, motors are inductive in nature

and they result in low pf of the system. Resistive loads have limiting pf.

Capacitive loads are used to improve pf, which takes care of the motor of

the loads. If we would have used an induction motor of 200kW, then

capacitor requirement to improve the pf must have increased

considerably. To overcome that problem, synchronous motor has been

used, which maintains its own pf along with improving the pf of the

system.

3. Protection of motors

All the equipments are provided with sufficient & efficient protection

system. For HV motors, sophisticated relays such as CIM relays,CAU

relays etc are provided which monitor the current drawn by the motors

while running and isolate the individual feeder in case the current exceeds

Page No. 59 of 75

Page 60: NFL FINAL REPORT

the present values. There is one more relay called 86-P, which must be pf

of your interest. Normally when any HV motor is started, 86-P relay is to

be got reset. This relay monitors various parameters that are to be fulfilled

before the main equipment is started. These parameters are lube oil

pressure, seal oil pressure, value positions, dampers position etc. in case

the requisite parameters are not fulfilled , the 86-P relay will get reset

hence the equipment cannot be started. For LV motors, protection is fuses

and thermal overload relay fuses & relay are selected in accordance with

size of motor, starting and running conditions for monitoring of process

parameters, one interlock contact is given in the starting circuit of the

motor, which restricts the starting of the equipment if the parameter is not

met. There are some other interlock also depending upon the service of

equipment such as conveyors etc thermal overload relay is bimetallic

conductor exceeds the limits bimetallic conductor expands in uneven

fashion and actuate the trip system, tripping the motor. Fuses are provided

as back up protection and for severe faults.

Advantages of synchronous motor

1. The ease with which the pf can be controlled. An overexcited synchronous

motor having a leading pf can be operated in parallel with induction motors

having lagging pf thereby improving the power factor of the supply.

2. The speed is constant and independent of the load this is mainly used

when the motor is required to derive another alternator to generate a

supply of different frequency.

Disadvantage of synchronous motor

1. Cost per kW is higher then induction.

2. DC supply is necessary for rotor excitation. Small DC shunt generator

carried on the extension of the shaft usually provides this.

Page No. 60 of 75

Page 61: NFL FINAL REPORT

Page No. 61 of 75

Page 62: NFL FINAL REPORT

BAGGING PLANT

The bagging plant can be divided into two main sections:

1. Storage system

2. Reclamation system

Under storage system, 3 conveyors come namely; PJD-101, PJD-102, PJD-

103 is the overhead conveyor inside silo. One tripper is provided over PJD-103

which can be placed at any convenient position depending upon the requirement.

By means of the tripper, the material can be poured over any vibrofeeder

desired. Tripper is designated as PJD-104.

The reclaimation system comprises of six electromagnet vibrofeeders,seven

no. of belts conveyors namely PJD’S 106,107,109,109A,110,111,111A,one

electromagnet (PJD-108),six no. of weighing machines,stiching machines

&loading platform namely;A-1,A-2,B-1,B-2,C-1 and C-2. In addition to these,

there are 3 bunkers/platform, one empty bag storage and one filled bags storage.

By operating flap gate no.102, the material can be directly fed to PJD-107 without

taking it to silo.

The plant has a capacity to load 2250Te/Day of packed material either in road

wagons or road trucks or in both. The loading platforms can accommodate six

trucks at a time or three BCN type wagons or 6CRT type wagons.

The weighing machines are microprocessor based and have speed of 12 to

14 bags per minute. The machines run with an accuracy of ± 50 grams. The

system of counter checking of weight of filled bags is rigorously followed to

ensure correct weightment.

The plant is provided with a central control room from where the system is

started or stopped. The two systems of storage and reclaimation are separately

provided with safety interlocks to trip the belts in case one belt in the link trips.

The urea silo is designed to accommodate 30 days production. For reclaiming

urea from silo, front end pay loaders are used.

Page No. 62 of 75

Page 63: NFL FINAL REPORT

The plant is also provided with empty bags storage and overhead E.O.T

crane for shifting the bags from the storage to the loading platform.

The filled bags storage is provided for stacking the filled urea bags.

Both jute and HDPE bags are used for filling of product urea. The stitching

thread used is normally of cotton unbleached and at times poly. Thread is also

used.

The consumption of bags is approximately 104 lacks per annum and pf

thread 41600KMs.

Normally four operators, one heavy equipment operator, 6 stichers, 6 fillers

and 24 loaders besides sealman and weight checking staff are deployed every

shift. The shift engineer coordinates with the operational activities of the plant

and also coordinates with the transportation section for the movement of finished

goals.

The spitted urea or the urea from the ruptured bags is recycled back to the

system by 2 buckets elevators, which transport the material from the loading

platform to the conveyor PJD-109.

Normally locomotive is used for shunting of rail wagons. However, a winch is

also provided to take care of exigencies when the locomotive is not available.

Page No. 63 of 75

Page 64: NFL FINAL REPORT

OFFSITES AND UTILITIES PLANTS

The 0&U group of plants consist of the following sections : -

i) Raw Water Plant.

ii) D.M. Water Plant.

iii) Instrument .Air Compressor House.

iv) Cooling Tower.

v) Sulphur Recovery Plant.

vi) Effluent Treatment Plant & Steam Generation Plant.

(i) RAW WATER FILTERATION PLANT

This water treatment plant has a design capacity to treat 2400 NM3/hr of raw

water into portable occasional over lead of 20%. The plant consists essentially of

flash Mixers Clarifloculators, rapid gravity filters and a chemical House

comprising of Alum tanks, lime tanks and a chlorine room etc.

The raw water from the pumping main is received by the inlet of the RCC Ventury

flume. In the ventury flume the calculated amount of alum solution is closed for

mixing with the raw water. The chemically treated water then flows to

clarifloculators. The pludge thus formed after chemical treatment settles down in

the clarifloculator where from it is expelled out while the clear water overflows to

the launder leading to filter beds. The filter water is disinfected with the addition

of chlorine and then collected in filter eater sump.

(ii). D.M. WATER PLANT

D.M. water plant was supplied by M/s Ion Exchange (India) Ltd. It consists of

cation units, Degasser Towers, An-ion units. Mixed bed units No.l&2. Filtered

water coming from raw water filtration plant is received in filter water reservoir.

From reservoir filter water passes through a strongly acidic cat-ion exchange

resin where cat-ions like Ca, Ng & Na are removed, the water passes through

degasser tower where dissolved, Ce2 is removed. Then water passes through

Anion exchange resin and Anion like CI, S, Se4 and silica, are removed in this

Page No. 64 of 75

Page 65: NFL FINAL REPORT

unit. Free from cations and anions water passes through mixed bed unit No.l,

where further removal of cations and anions takes place. Then treated water

coming out from MB, unit goes to DM water tank.

Return condensate from Ammonia and Urea Plants is collected in D.M. water

tank after treatment in cat-ion unit No.2. Then D.M. water is pumped from DM

water tank to mixed bed No.2(MB) for further polishing and collected in polish

water tank, which is supplied to boilers through Ammonia Plant.

(iii) INSTRUMENT AIR COMPRESSORS HOUSE

The purpose of this section is to supply instrument air and service air to all the

plants. The instrument air compressor house consists of three instrument air

compressors and one service air compressor. One is kept in line generally.

The compressed air from instrument air compressors at 9.3 kg/cm2 absolute

pressure passes through two sets of dryer, which is filled with silica-gel for

removal of moisture. Air coming out from dryer is sent to instrument air feeder

for supplying to different plants through instrument air receiver in order to

drive various valves and instruments.

(iv) COOLING TOWERS

The cooling water system provided in NFL, Bathinda is closed re-circulating

system supplying cooling water to various consumers in the plant. The system

mainly consists of cooling towers, cooling water re-circulation pumps, supply &

return headers and cooling water treatment facility.

There are three cooling water systems : -

1) C.W. system supplies cooling water to Ammonia Plant.

2) Urea Plant and Boilers, Instrument -Air Compressor, Caustic dissolving

facilities & Sulphur Recover Plant.

3) C.W. system supplies cooling water to Crystallization section of Urea Plant.

Page No. 65 of 75

Page 66: NFL FINAL REPORT

(v) SULPHUR RECOVERY PLANT

The separation of sulphur by catalytic reactions is as follows:-

H2S + 3/2 O2 SO2 + H2O

H2S + 1/2 O2 S+ H2O

2H2S+ SO2 2H2O + 3S

The capacity of the plant:

Generation steam : 26.5 T/day

Export steam : 6.4 T/Hr.

Plant performance : 85%

PROCESS OF SULPHUR RECOVERY:

The Acid gas from Rectisol Section of Ammonia Plant is composed of 47.5%

H2S, 50.3% C02 and a little COS & CO and flows to this unit, 70% of feed gas is

introduced into Acid gas exchanger where 1/3 of total H2S is burnt to S02 with air

supplied through furnace air blower. The S02 reacts with H2S and forms

elemental sulphur. I he sulfur is thus condensed at 191 deg.C and separated in

sulphur storage tank. The gas stripped off the above sulphur is mixed with the

remaining 30% of feed acid gas and bypass from acid gas exchanger in such a

way that the temp. of mixed gas is controlled at 215 deg.C and proportion of H2S,

S02 in this gas is over 2:1 ratio. This gas reacts over the first catalyst bed of

reactor to form elemental sulphur. This gas is cooled to 177 deg.C in acid gas

exchanger and stripped off and so condenses sulphur in the sulphur storage

tank. The remaining H2S & S02 react again to form elemental sulphur.

D.M. WATER PLANT

Water in its natural form contains no. of dissolved salts such as sulphates,

chlorides and nitrates of calcium magnesium and sodium. If water is used as

such in the boilers for raising steam, these salts will form scale on the tubes,

Page No. 66 of 75

Page 67: NFL FINAL REPORT

which in addition to heat losses lead to many other many problems. Hence,

removal of these salts from the water becomes quite essential. Ion exchange

resign are used for this purpose of salt removal.

The de mineralizing water plant of NFL Bathinda was supplied by M/s ION

exchange (India) ltd Delhi.

It consisted of three units each of cation, anion, mixed bed, four secondary mixed

bed and three units of condensate cation. At the time of setting up of a captive

power plant, another stream to augment the existing capacity of polish water

generation was by M\s BPMEL. It consisted of one unit each of cation, anion,

primary mixed bed, two secondary mixed bed and two condensate cations.

Filtered water is received from raw water filtration plant into two filtered water

reservoir feed water pumps discharge water from these reservoir tom cation units.

These are total five feed pumps each having a capacity 0f 130m3/hr and four cation

units. Three of these are charged with 13125L of cation resin and fourth unit is

having 11900 0f resins. Cation like Na+, Ca++, and Mg++ present in the water are

removed in the cation unit once exhausted, these units are regenerated with the

counter current flow of dilute sulphuric acid.

The present day resins are made of cross linked polystyrene and cross linking is

done by di vinyl benzene.Cation resins are made of sulphonated polystyrene

SO3H can be represented by as RH.anionic resin is similarly made but is

chloromethylated and then is animated. The final product is quaternary

ammonium compound a strong base and is represented by ROH.

CATION UNIT:

In the cation unit’s free H+ ion of the resin is replaced by Ca and Mg or Na ions

as per the following reactions.

Page No. 67 of 75

Page 68: NFL FINAL REPORT

RH + NaCl---------------RNa+ HCl

2RH + MgSO4--------------------- R2Mg + H2SO4

2RH + Ca (HCO3)2---------------------------R2Ca +2CO2 + 2H20

Natural salts are converted into respective mineral acid and alkaline salt

split into carbon dioxide. The outlet water has low pH.

DEGASSER:

From the cation units water move to the degasser. Here the free CO2 content of

the water is splitted off with the help of air by passing the water over by the

rasching ring packed bed. Water from the degasser is received into three Nos.

degasser water sump each of having a capacity 40m3 from these sump

degassed water pumps discharge water into the anion units. There are total five

Nos of pumps each having a capacity of 150M3/ hr.

ANION UNITS:

Anionic impurities of water beside CO2 and silica are removed in the anionic unit.

There are total four No of anionic units. Two anionic units having a capacity

7920L of resin while the two are 5965 and 8400L of resin. Anion present in the

water gets removed as per the following reactions.

2ROH + H2SO4---------------- R2SO4 + 2 H2O

ROH + HCl------------------------ RCl + H2O

MIXED BED UNITS (PRIMARY):

Certain amount of sodium and silica ions gets slipped from cation and anion

units. Very large volume of resin is required to check these leakages. Hence

these ions are removed in mixed bed units. It consists of bed of mixed cation and

Page No. 68 of 75

Page 69: NFL FINAL REPORT

anion resins. This water is stored in DM water tank there are two DM water tanks

each having a capacity 1400L. Each of cation and anion resin is charged in three

mixed bed units while in fourth unit the quantity is 1880L.

CONDENSATE CATION UNITS:

Steam condensate is received from ammonia plant. It contains ionic and colloidal

iron. Colloidal iron is removed in colloidal filters while ionic iron is removed in

condensate cation units. Condensate coming from ammonia plant is first cooled

to 45 C in a condensate cooler. There are total five condensate units. Three units

are charged with 1810L of resin while two are charged with 4200L of resin. After

polishing the condensate it is stored in DM water tanks.

SECONDARY MIXED BED UNITS:

DM water from DM water tank is pumped to secondary mixed bed units with the

help of DM water pumps. Final traces of impurities are removed again with the

help of mixed bed cation and anion resins. After passing through the bed polish

water of the following specifications is obtained.

pH 7+0.2

Conductivity 0.2 micro mhos/cm

Total iron as Fe 0.015 mg/l

Silica 0.015 mg/l

Hardness NIL

Polish water thus obtained is stored in polish water tanks. There are two polish

water tanks each having a capacity of 1500M3. it is pumped to ammonia pant and

captive power plant with the help of five nos. of polish water pumps each having

a capacity of 220M3/hr.

Page No. 69 of 75

Page 70: NFL FINAL REPORT

FINAL DISPOSAL AREA

This area is used for receiving, storing and finally disposing off the treated

water from ETP and storm water. This area is having five ponds. Their capacities

and services for which these are used are given below.

Sl no. Name Capacity Service

Page No. 70 of 75

Page 71: NFL FINAL REPORT

1. Pond no 1 25,000 Ash pond

overflow & off

grade effluent

2. Pond no 2 25,000 -do-

3. Pond no 3 26,000 Treated water

4. Pond no 4 48,000 Storm water

5. Pond no 5 60,000

Treated water meeting the MINAS standard is received in pond no 3 and 5 from

final effluent pump discharge located in EFFLUENT TREATMENT PLANT.

If this water is not conforming to MINAS standard, then provision is to

receive it in pond no no. 1& 2. Storm water from the factory is received in pond

no.4 and stagnant water area. It is then pumped from this place to pond no. 1&2

with the help of four vertical pumps. Effluent from ponds no 1&2 is pumped to

factory for deashing in SGP and CPP. Three pumps each with a capacity of

500m3/hr, have been provided for this purpose.

Treated water received in pond no. 3 and 5 is supplied for irrigation in fields and

township. Provision is also being made to use this water as fire water and for

kitchen garden in township. Two pumps each with a capacity of 275M3/hr has

been provided for this purpose.

WATER BALANCE ACROSS FINAL DISPOSAL AREA

WATER IN WATER OUT

Sl no Source Qty M3 Sl no Supplied to Qty M3

1 From ETP 230 1. For

deashing in

350

Page No. 71 of 75

Page 72: NFL FINAL REPORT

SGP

2. Ash ponds 388 2. For

deashing in

CPP

139

3. For

irrigation in

township

73

4. For fire

header

changing

and for use

in

township.

56

Total 618 618

SAFETY

Safety & fire Department manned by qualified personnel in various disciplines

has been provided in the Factory. High quality safety equipments are made

available to the employees free of cost. In order to make workers safety

conscious, regular publicity and frequent training programmes are arranged.

Page No. 72 of 75

Page 73: NFL FINAL REPORT

As this plant containing chemicals therefore it is dangerous while working in

factory.

As protecting from these gasses these are prepares and kept in spheres, still

there is chance of leakage of gasses; gasses like Ammonia, CO are very

dangerous to the human life. As some gases smell less they can be detected.

For this reason windsocks have been installed at several places on Plant/building

tops to see the direction of wind. In case of any toxic gas / vapours in to

atmosphere, it is preferable to run in a direction at right angle of wind. They have

a separate department known as 'Safety Department' that gave the knowledge

about these things. Fire station also comes under this section. They placed fire

detectors at different places. Some secret automatic systems are also there for

security purposes.

“Safety Comes In Cans”

I CAN, YOU CAN, WE CAN

Page No. 73 of 75

Page 74: NFL FINAL REPORT

HOW WINTER PROJECT IS USEFUL

Industrial training is very useful for an engineer. It gives an overall idea

about the company’s production problems one has to face in realizing companies

goals, when he is in the field. Winter Project done under IFFCO fetched me much

of the practical knowledge. I was at least aware of many factors that play crucial

role in an Manager’s life while working with in an industry. Training made me

understand the rudiments of an manager.

At IFFCO I came in contact with workers and officers of various cadres. I

found both of them to be well versed in their fields.

Exposure to industry makes an MANAGER grasp the subject in a better

way since confidence plays an important role in it and it is some thing which can

be gained only by practical training.

Having came in contact of IFFCO AONLA, its glories, its triumphs, its

success due to its toiled, zeal and zest employees. I am fully inspired to work

hard with dedication and my uttermost sincerity.

Page No. 74 of 75

Page 75: NFL FINAL REPORT

Page No. 75 of 75