newtown creek upgrade phase 1 improvements

2
Newtown Creek Upgrade Phase 1 Improvements P: 516.239.1600 718.634.1900 F: 516.239.1757 31 Garden Lane PO Box 9013 Lawrence, NY 11559 www.johnpicone.com — Committed to quality, backed by hard work.

Upload: others

Post on 12-Sep-2021

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Newtown Creek Upgrade Phase 1 Improvements

Newtown Creek Upgrade Phase 1 Improvements

P: 516.239.1600 718.634.1900F: 516.239.1757

31 Garden LanePO Box 9013

Lawrence, NY 11559www.johnpicone.com

— Committed to quality, backed by hard work.

Page 2: Newtown Creek Upgrade Phase 1 Improvements

Newtown Creek Upgrade Phase 1 Improvements

John P. Picone, Inc., is a member of the joint venture that is the general

contractor for the NYCDEP’s Contract NC-35G, Newtown Creek WPCP Plant

Upgrade – North and North-Central Batteries. Under a federal decree to be

completed by the end of 2007, a new battery of treatment tanks over 300,000

square feet in size, a new 81,400 square feet control building, and a new

influent distribution system have been constructed.

Nine new 2,000 HP process blowers have been installed along with a

96-inch-diameter, 1,500 foot long distribution header, located over the

existing treatment tanks. Finally, half of one of the two existing batteries

is being reconstructed to match the new tanks. The NYCDEP has recently

issued a change order to the joint venture to reconstruct the second half of

this battery. The project started in September 2003 with an original contract

value of $493 million and a contract completion of February 2008. To date,

the contract value is now over $655 million with an anticipated completion

date of December 2009.

When completed, over 165,000 cubic yards of concrete, 14,000 tons of steel

reinforcing, 110,000 linear feet of pipe and 180,000 lf of foundation piles will

be installed and 225,000 cy of hazardous and contaminated soil will be

removed from the site.

Challenges:

Due to the Federal decree, there was immense pressure to ensure that the

project was completed on time. All parties, the contractors, construction

manager, design engineers, and NYCDEP worked closely together to resolve

all issues quickly. As a result, there were twelve milestone dates that were

required to be met and all twelve were achieved ahead of schedule or on time.

The physical work presented many challenges. One in particular was to tie

the existing feed from Manhattan to the new distribution system constructed

in this contract, an 8-foot diameter opening had to be cored through a 3-foot

thick concrete reinforced slab that was located at the bottom of a 25-foot deep

shaft. Coring into an active force main required that the core driller had to be

set up at the top of the shaft and that the core had to be retrieved. Slattery,

Picone/McCullagh JV, Perini developed the custom drilling rig and Picone/

McCullagh workers fabricated the majority of the rig.

Project Manager: David Brackett

Contract Number: NC-35G

General Contractor: SPMP JV

Agency: NYC DEP

Contract Amount: $685,000,000.00