1 News Letter August 2019 Issue 113 Bangalore Metro Rail Corporation Limited, 3rd Floor, BMTC Complex, K H Road, Shantinagar, Bengaluru—560 027. Phone: +91-080-22969300 / 301 Fax: +91 80-22969222 Toll free No 1800 425 12345 Email: [email protected] or [email protected] BANGALORE METRO RAIL CORPORATION LIMITED Driving Bangalore Ahead Durga Shanker Mishra, IAS Secretary, MoHUA, GoI & Chairman BMRCL Ajay Seth, IAS Managing Director BMRCL Sri Durga Shanker Mishra, Secretary, Ministry of Housing and Urban Affairs, Government of India, Chaired a meeting of all Metro Companies Managing Director’s Conclave on 10.08.2019 at Bengaluru High Lights of the month :

Upload: others

Post on 24-Jun-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: News Letter August 2019 Issue 113 BANGALORE METRO …News Letter August 2019 Issue 113 & Chairman BMRCL Bangalore Metro Rail Corporation Limited, 3rd Floor, BMTC Complex, K H Road,

1

News Letter August 2019 Issue 113

Bangalore Metro Rail Corporation Limited,

3rd Floor, BMTC Complex,

K H Road, Shantinagar,

Bengaluru—560 027.

Phone: +91-080-22969300 / 301

Fax: +91 80-22969222

Toll free No 1800 425 12345

Email: [email protected]

or [email protected]

BANGALORE METRO RAIL CORPORAT ION LIMITED Driving Bangalore Ahead

Durga Shanker Mishra, IAS

Secretary, MoHUA, GoI

& Chairman BMRCL

Ajay Seth, IAS

Managing Director

BMRCL

Sri Durga Shanker Mishra, Secretary, Ministry of Housing and Urban Affairs,

Government of India, Chaired a meeting of all Metro Companies

Managing Director’s Conclave on 10.08.2019 at Bengaluru

High Lights of the month :

Page 2: News Letter August 2019 Issue 113 BANGALORE METRO …News Letter August 2019 Issue 113 & Chairman BMRCL Bangalore Metro Rail Corporation Limited, 3rd Floor, BMTC Complex, K H Road,

2

News Letter August 2019. Issue 113

Phase– 2 Progress at a glance:

Phase-2 Expected Completion Schedule

Page 3: News Letter August 2019 Issue 113 BANGALORE METRO …News Letter August 2019 Issue 113 & Chairman BMRCL Bangalore Metro Rail Corporation Limited, 3rd Floor, BMTC Complex, K H Road,

3

News Letter August 2019 Issue 113

NICE Land

Hon’ble High Court of Karnataka has stayed proceedings of acquisition of NICE Lands in

respect of Reach-5. In respect of lands required for Reach-2, 3 and 4, SLAO, KIADB has to

determine the compensation to be paid.

Forest Land

Land at Kadugodi is required for Whitefield Depot. Stage-I clearance has been given by the

Regional Office, Ministry of Forest and Environment, Government of India. The Regional

Office has informed BMRCL to get the compensatory afforestation lands declared as Reserve

Forest/ Protected Forest (RF/PF) before Stage-II clearance. Forest Department has been

requested to expedite the issue of notifications declaring compensatory afforestation lands

as Reserve Forest/ Protected Forest (RF/PF) lands.

Land at U.M. Kaval is required for Anjanapura Depot. Stage-I approval for diversion of 0.71

ha of Forest land in Sy. No. 38 of U.M. Kaval has been communicated. Forest department has

been requested to process for Stage-II clearance.

Reach-6 Underground section

Langford Town Station:-The Board of Officers (BOO) has been constituted by Local

Military Authority (LMA) for the land required for Langford Station is 2137.334 sq mtrs on

permanent basis and 5866.569 sq mtrs on temporary basis. Final Board of Officers (BOO)

proceedings are yet to be signed.

Church land for Vellara Junction Station: The acquisition process for balance land

measuring 3797.271 sq mtrs on permanent basis is in progress (originally it was proposed

for temporary acquisition) through KIADB. Local Military Authority (LMA) have raised

objection for the compensation paid to Church for the land earlier acquired.

Critical issues faced regarding Land Acquisition for Phase-2 of the project

Page 4: News Letter August 2019 Issue 113 BANGALORE METRO …News Letter August 2019 Issue 113 & Chairman BMRCL Bangalore Metro Rail Corporation Limited, 3rd Floor, BMTC Complex, K H Road,

4

Reach-1A : KR Puram Station LHS Exit Entry Roof Slab

work is in progress

Reach-1A: K R Puram Concourse level central

slab casting work is in progress

News Letter August 2019 Issue 113

Eidgah-e-Jaded land for launching Shaft:- Wakf Board has been requested to hand

over the land to BMRCL after vacating the school building by providing them alternative

accommodation and vacating the shops. Payment will be made of R & R benefits as per BMRCL

norms.

BBMP land for Cantonment Station:- A Industrial Training Institute for differently abled

children is constructed on BBMP land. The building was constructed to run the I.T.I. There is

a dispute regarding payment of compensation for the building between Church Authority and

an NGO which was running the institute. Compensation will be paid after ascertaining the

rightful owner.

Lakkasandra Village Sy. No. 14 and 15:- Encroachments are obstructing access to

Casting Yard area identified for UG Works. The Deputy Commissioner, Bangalore has been

requested to take necessary action for removal of encroachment.

Phase– 2 Progress Photos at a glance :

Page 5: News Letter August 2019 Issue 113 BANGALORE METRO …News Letter August 2019 Issue 113 & Chairman BMRCL Bangalore Metro Rail Corporation Limited, 3rd Floor, BMTC Complex, K H Road,

5

News Letter August 2019. Issue 113

Reach-1B: Segment Erection Upto BP451-452 is completed,

preparation for Dismantling is in progress

Reach-1B: Kadugodi Station C6(TRK) Staging for Pier-Arm

Erection work is in progress

Reach-2A: Windows Installation in Jnanabharathi Station

Reach-2B: View of Kengeri Station work is in progress

Phase– 2 Progress Photos at a glance :

Reach-2A: View of Jnanabharathi Station work is in progress

Reach-2B: View of Launching work is in progress

Page 6: News Letter August 2019 Issue 113 BANGALORE METRO …News Letter August 2019 Issue 113 & Chairman BMRCL Bangalore Metro Rail Corporation Limited, 3rd Floor, BMTC Complex, K H Road,

6

News Letter August 2019. Issue 113

Reach-3C: Work is in progress at Manjunathnagar Station Reach-3C: Segmental Span Launching work at Jindal Station

Phase– 2 Progress Photos at a glance :

R-4B: Vajarahalli Station Roof Sheeting work is in progress Reach-4B: Parapet Erection work at EP300-EP304

R-5-P1: Segment launching work in progress at RP564-561 R-5-P1: Pier Form work is in progress at RP505

Page 7: News Letter August 2019 Issue 113 BANGALORE METRO …News Letter August 2019 Issue 113 & Chairman BMRCL Bangalore Metro Rail Corporation Limited, 3rd Floor, BMTC Complex, K H Road,

7

News Letter August 2019 Issue 113

R-5-P2: Casting Yard -I Girder Casting, curing & stacking R-5-P2: Chikkabegur Station- Pier Arm Erection at

Grid-C at Platform / Track Level

Phase– 2 Progress Photos at a glance :

R-5-P3: Grid Pier Concrete completed at Ragigudda Station R-5-P-3: RP 75 Rail Pier & Pier Cap concrete work completed

R-6: Work is in progress at Gottigere Station R-6: Post Tension I Girder work is in progress

Page 8: News Letter August 2019 Issue 113 BANGALORE METRO …News Letter August 2019 Issue 113 & Chairman BMRCL Bangalore Metro Rail Corporation Limited, 3rd Floor, BMTC Complex, K H Road,

8

News Letter August 2019 Issue 113

R-6-UG: Retaining Wall Raft at Cantonment Station R-6-UG: Piling in progress at Shivajinagar Station

Phase– 2 Progress Photos at a glance :

Operational High Lights August 2019

Operational efficiency achieved in the month : 99.98%

Ridership for the month : 1,26,28,651

Revenue earned during the month : ₹ 33,44,90,574/-

% Contribution of Smart Cards, Tokens and Group Ticket for the month for Phase-1:

Smart Cards : 68.31%

Smart Tokens: 37.67% Group Ticket: 0.04%

Instructions for permitting Additional & Over Sized Baggage / Luggage in Metro

1. Free Allowance of Luggage:

One Baggage per person of dimension less than or equal to 60 cms X 45 cms X 25 cms (LXBH) is allowed.

2. Additional & Over-Sized Baggage / Luggage:

Extra baggage is allowed at a payment of ₹ 30/- for each baggage / luggage.

3. Items not considered as Baggage / Luggage:

Back-Pack, Handbag, Brief Case, Laptop Bags, School Bags, Lunch Bags, Carry bags within the dimension

specified in free allowance & Shopping bags etc. within the dimension specified in free allowance.

Page 9: News Letter August 2019 Issue 113 BANGALORE METRO …News Letter August 2019 Issue 113 & Chairman BMRCL Bangalore Metro Rail Corporation Limited, 3rd Floor, BMTC Complex, K H Road,

9

News Letter August 2019 Issue 113

4. Items considered as Baggage / Luggage:

Suitcases, Trolley Bags, Duffle Bags, Backpacks—Big (Rucksacks), Roller Cases & Carton Boxes.

5. Scanning of Baggage's:

All the luggage / baggage have to pass through the baggage scanner / physical check. If any luggage /

baggage cannot be scanned due to over sizing then such baggage / luggage shall be allowed after manual

checking into Metro premises subject to payment of additional charges as mentioned above.

6. Any other luggage which is not defined in the above category shall be charged at ₹ 30/- per baggage and

permitted at the discretion of Station Controller on Duty.

Art in Transit is a collaboration between Srishti Institute of Art, Design and Technology and BMRCL

Art by: Fragrance by Anpu Varkey,

In this monsoon season, the Aakash Mallige trees are laden with their white fragrant blossoms.

Any rain or slight breeze, brings forth a shower of Aakash Mallige on to streets, cars and passers

by. We are blessed to have these trees in our city. Artist, Anpu Varkey worked with Art in Transit

to paint “Fragrance" at the entrance of the Chickpet Metro Station. This mural is a tribute to the

flower market in the Chickpet area, a treasure of our city.

Page 10: News Letter August 2019 Issue 113 BANGALORE METRO …News Letter August 2019 Issue 113 & Chairman BMRCL Bangalore Metro Rail Corporation Limited, 3rd Floor, BMTC Complex, K H Road,

10

News Letter August 2019. Issue 113