newinfrastructure mmmmmmmmmmmmm
TRANSCRIPT
-
8/6/2019 newinfrastructure mmmmmmmmmmmmm
1/12
Connecting
communitiesto the network
-
8/6/2019 newinfrastructure mmmmmmmmmmmmm
2/12
Our approach
How Western Power transports electricity
As your network manager, Western Power
is committed to creative solutions that will
ensure safe and reliable power supplies to your
community today into the future.
-
8/6/2019 newinfrastructure mmmmmmmmmmmmm
3/12
How does the WesternPower grid work?
There are many interconnecting pieces of infrastructure that make up the
South West Interconnected System (SWIS). These pieces of infrastructure
are used to take power from generators, such as coal, wind or hydro
power stations, and deliver it through the poles and wires to your homes
and businesses. Three of the most common types of infrastructure that
Western Power uses to deliver power to your community include; substations,transmission lines and distribution lines.
Energy created by power generators is delivered to your community by
a network of high voltage transmission lines that connect through to a
local substation.
The power leaving a generator site may be 330,000 volts whilst the power
being delivered into your home is either 240 volts or 415 volts, depending on
your location. Western Powers substations transform power down for local
communities. They are built near to the community that they are providing
for - and the more our communities continue to develop and grow, the more
substations will be required.
-
8/6/2019 newinfrastructure mmmmmmmmmmmmm
4/12
Planning new infrastructure
Our sustainability policy lies at the heart of all new infrastructure
planning at Western Power. There are four main sustainability criteria
that we take into consideration when choosing a transmission line route
or substation site. Some examples of the criteria are:
Social & community
What are the predicted future energy usage requirements for
the community?
What is the visual impact upon the natural and social environment?
We consider the predominant land use type; for example, is it used
for urban, mining, agricultural or tourism purposes?
We consider the number of houses and the size of the properties that
are directly affected by the proposed route.
Does the route pass near airstrips, military reserves or rifle ranges?
Are there any Aboriginal heritage or cultural heritage considerations?
-
8/6/2019 newinfrastructure mmmmmmmmmmmmm
5/12
Environmental
Is the location close to environmentally sensitive areas or areas with high
conservation value; for example, national parks or nature reserves?
Is the location close to protected or threatened vegetation?
How much clearing of native vegetation would be required?
Are there any threatened fauna species in the area (including migratory
birds) and what would be the effects on their habitats?
What would be the effects on watercourses, ground water and wetlands?
Could the line or substation contribute to the potential spread of dieback or
noxious weeds?
-
8/6/2019 newinfrastructure mmmmmmmmmmmmm
6/12
Planning new infrastructure
Western Power considers many issues when investigating suitable
routes for new transmission lines and sites for substations, including the
environmental impact. So by the time Western Power finalises the route, allof the relevant issues and stakeholder interests will have been taken into
account and we will aim to deliver an optimal solution for the community.
Technical
We consider physical elements such as terrain, access, soils,
hydrology, lakes, dams, river crossings and other infrastructure.
Is there restricted access to the land due to weather, disease or
other environmental issues?
Economic
Is the project economically viable?
What alternatives are available?
-
8/6/2019 newinfrastructure mmmmmmmmmmmmm
7/12
Substations transform
power down for local
communities near to the
homes and businesses that
they are providing for.
-
8/6/2019 newinfrastructure mmmmmmmmmmmmm
8/12
Vegetation management
Vegetation management: During the construction of a transmission line, it may
be necessary to clear or disturb vegetation. Depending on circumstances of the
new infrastructure, vegetation may be able to regenerate under transmission
lines depending on species.
Permanent vegetation clearing: Permanent clearing of vegetation may be
undertaken in areas close to the transmission line in order to enable construction
and to provide access.
Access tracks: In an area where there is no existing access to a structure, an
initial four-metre-wide access track will typically be created to enable large
vehicles to access the site. Where an access track already exists but is less than
four metres in width, the existing track may be widened.
To ensure transmission
lines operate in a safe and
secure manner clearances
between vegetation and
live electrical conductors
must be maintained.
-
8/6/2019 newinfrastructure mmmmmmmmmmmmm
9/12
Temporary vegetation disturbance: Temporary disturbance or clearing of
vegetation along the transmission line route is required in order to carry
out construction activities. After construction, vegetation will be allowed
to regenerate in areas not occupied by equipment and not requiring
permanent access.
Vegetation clearing for safety: To ensure that transmission lines
operate in a safe and secure manner, and to assist in preventing bush
fires, sufficient clearances must be maintained between vegetation and
live electrical conductors (wires). This is achieved through both the
initial clearing of taller vegetation and ongoing vegetation management.
Generally species that grow no higher than three metres are retained
within the corridor. The width of the corridor is determined by the type
of powerline. Vegetation removed is often mulched and spread within the
corridor but other methods of disposal or utilisation of the product may
also be undertaken in agreement with the landowners.
-
8/6/2019 newinfrastructure mmmmmmmmmmmmm
10/12
Assessing the profile
When Western Power builds new substations and transmission lines, one
of the social factors considered is the way the infrastructure will look
in the area. Western Power considers the possible effects the profile of
infrastructure will have on landowners, communities, tourism and other
significant viewpoints and where necessary engages professional landscapearchitects to determine how the profile of the proposed project will affect
the surrounding environments.
Reducing the visual impact
Whenever possible, Western Power takes measures to reduce the
visual impact of substations and transmission lines. As each piece of
infrastructure is different, not all approaches are suitable to all sites.
Landscape architects also advise Western Power on strategies that may be
employed to reduce the visual profile of the infrastructure that are sensitive
to the local conditions and usage of the surrounding land and space.
Substations:
Western Power has a number of options available to reduce visual profile
when constructing a substation.
Landscaping:
substation to help the substation blend with the area.
Walls:
reduce the visual impact of a substation.
Earth mounds:
earth mound around the perimeter of the site to reduce the visual impact.
Reducing the visual & noiseprofile of infrastructure
-
8/6/2019 newinfrastructure mmmmmmmmmmmmm
11/12
Transmission lines:
Reducing the visual profile of transmission lines may involve the selection
of a route that avoids residential areas as well as areas of environmental
or cultural significance.
Wherever possible, Western Power takes into consideration natural
vegetation and geography to reduce the visual impact of itstransmission lines.
Reducing the noise profile
In some situations it is necessary to build a solid wall around a substation
or alternatively install a noise enclosure around a particular transformer
to reduce the noise from that substation.
Government regulations
When a new project is seen to have significant environmental impact,
Western Power will refer the project to the Environmental Protection
Authority (EPA) for assessment.
-
8/6/2019 newinfrastructure mmmmmmmmmmmmm
12/12
Important numbers
Below is a list of important contact details should you require assistance
or information regarding powerlines in your area.
Faults and emergencies, power interruptions,
estimated restoration times (24 hrs) 13 13 51
Streetlights out (24 hrs) 1800 622 008
Report vandalism (24 hrs) 13 13 51
General enquiries 13 10 87
Trees that are close to powerlines 13 10 87
TTY users (speech or hearing impaired only) 1800 13 13 51
Telephone Interpreter Services 13 14 50
Report graffiti (24 hrs) 1800 442 255
Dial 1100 Before You Dig 1100
dialbeforeyoudig.com.au
Western Power vegetation management team
Media enquiries 1300 139 240
363 Wellington Street Perth WA 6000
GPO Box L921 Perth WA 6842
T: 13 10 87F: 9326 4594
www.westernpower.com.au
ProductCode:87262999.
Printedon100
%recycledpapercontaining40%
post-consumerand60%pre-co
nsumerAustralianwaste;ISO14001certifiedandprocesschlorinefree.MFWEP007510/09