newinfrastructure mmmmmmmmmmmmm

Upload: medo-saeedi

Post on 07-Apr-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/6/2019 newinfrastructure mmmmmmmmmmmmm

    1/12

    Connecting

    communitiesto the network

  • 8/6/2019 newinfrastructure mmmmmmmmmmmmm

    2/12

    Our approach

    How Western Power transports electricity

    As your network manager, Western Power

    is committed to creative solutions that will

    ensure safe and reliable power supplies to your

    community today into the future.

  • 8/6/2019 newinfrastructure mmmmmmmmmmmmm

    3/12

    How does the WesternPower grid work?

    There are many interconnecting pieces of infrastructure that make up the

    South West Interconnected System (SWIS). These pieces of infrastructure

    are used to take power from generators, such as coal, wind or hydro

    power stations, and deliver it through the poles and wires to your homes

    and businesses. Three of the most common types of infrastructure that

    Western Power uses to deliver power to your community include; substations,transmission lines and distribution lines.

    Energy created by power generators is delivered to your community by

    a network of high voltage transmission lines that connect through to a

    local substation.

    The power leaving a generator site may be 330,000 volts whilst the power

    being delivered into your home is either 240 volts or 415 volts, depending on

    your location. Western Powers substations transform power down for local

    communities. They are built near to the community that they are providing

    for - and the more our communities continue to develop and grow, the more

    substations will be required.

  • 8/6/2019 newinfrastructure mmmmmmmmmmmmm

    4/12

    Planning new infrastructure

    Our sustainability policy lies at the heart of all new infrastructure

    planning at Western Power. There are four main sustainability criteria

    that we take into consideration when choosing a transmission line route

    or substation site. Some examples of the criteria are:

    Social & community

    What are the predicted future energy usage requirements for

    the community?

    What is the visual impact upon the natural and social environment?

    We consider the predominant land use type; for example, is it used

    for urban, mining, agricultural or tourism purposes?

    We consider the number of houses and the size of the properties that

    are directly affected by the proposed route.

    Does the route pass near airstrips, military reserves or rifle ranges?

    Are there any Aboriginal heritage or cultural heritage considerations?

  • 8/6/2019 newinfrastructure mmmmmmmmmmmmm

    5/12

    Environmental

    Is the location close to environmentally sensitive areas or areas with high

    conservation value; for example, national parks or nature reserves?

    Is the location close to protected or threatened vegetation?

    How much clearing of native vegetation would be required?

    Are there any threatened fauna species in the area (including migratory

    birds) and what would be the effects on their habitats?

    What would be the effects on watercourses, ground water and wetlands?

    Could the line or substation contribute to the potential spread of dieback or

    noxious weeds?

  • 8/6/2019 newinfrastructure mmmmmmmmmmmmm

    6/12

    Planning new infrastructure

    Western Power considers many issues when investigating suitable

    routes for new transmission lines and sites for substations, including the

    environmental impact. So by the time Western Power finalises the route, allof the relevant issues and stakeholder interests will have been taken into

    account and we will aim to deliver an optimal solution for the community.

    Technical

    We consider physical elements such as terrain, access, soils,

    hydrology, lakes, dams, river crossings and other infrastructure.

    Is there restricted access to the land due to weather, disease or

    other environmental issues?

    Economic

    Is the project economically viable?

    What alternatives are available?

  • 8/6/2019 newinfrastructure mmmmmmmmmmmmm

    7/12

    Substations transform

    power down for local

    communities near to the

    homes and businesses that

    they are providing for.

  • 8/6/2019 newinfrastructure mmmmmmmmmmmmm

    8/12

    Vegetation management

    Vegetation management: During the construction of a transmission line, it may

    be necessary to clear or disturb vegetation. Depending on circumstances of the

    new infrastructure, vegetation may be able to regenerate under transmission

    lines depending on species.

    Permanent vegetation clearing: Permanent clearing of vegetation may be

    undertaken in areas close to the transmission line in order to enable construction

    and to provide access.

    Access tracks: In an area where there is no existing access to a structure, an

    initial four-metre-wide access track will typically be created to enable large

    vehicles to access the site. Where an access track already exists but is less than

    four metres in width, the existing track may be widened.

    To ensure transmission

    lines operate in a safe and

    secure manner clearances

    between vegetation and

    live electrical conductors

    must be maintained.

  • 8/6/2019 newinfrastructure mmmmmmmmmmmmm

    9/12

    Temporary vegetation disturbance: Temporary disturbance or clearing of

    vegetation along the transmission line route is required in order to carry

    out construction activities. After construction, vegetation will be allowed

    to regenerate in areas not occupied by equipment and not requiring

    permanent access.

    Vegetation clearing for safety: To ensure that transmission lines

    operate in a safe and secure manner, and to assist in preventing bush

    fires, sufficient clearances must be maintained between vegetation and

    live electrical conductors (wires). This is achieved through both the

    initial clearing of taller vegetation and ongoing vegetation management.

    Generally species that grow no higher than three metres are retained

    within the corridor. The width of the corridor is determined by the type

    of powerline. Vegetation removed is often mulched and spread within the

    corridor but other methods of disposal or utilisation of the product may

    also be undertaken in agreement with the landowners.

  • 8/6/2019 newinfrastructure mmmmmmmmmmmmm

    10/12

    Assessing the profile

    When Western Power builds new substations and transmission lines, one

    of the social factors considered is the way the infrastructure will look

    in the area. Western Power considers the possible effects the profile of

    infrastructure will have on landowners, communities, tourism and other

    significant viewpoints and where necessary engages professional landscapearchitects to determine how the profile of the proposed project will affect

    the surrounding environments.

    Reducing the visual impact

    Whenever possible, Western Power takes measures to reduce the

    visual impact of substations and transmission lines. As each piece of

    infrastructure is different, not all approaches are suitable to all sites.

    Landscape architects also advise Western Power on strategies that may be

    employed to reduce the visual profile of the infrastructure that are sensitive

    to the local conditions and usage of the surrounding land and space.

    Substations:

    Western Power has a number of options available to reduce visual profile

    when constructing a substation.

    Landscaping:

    substation to help the substation blend with the area.

    Walls:

    reduce the visual impact of a substation.

    Earth mounds:

    earth mound around the perimeter of the site to reduce the visual impact.

    Reducing the visual & noiseprofile of infrastructure

  • 8/6/2019 newinfrastructure mmmmmmmmmmmmm

    11/12

    Transmission lines:

    Reducing the visual profile of transmission lines may involve the selection

    of a route that avoids residential areas as well as areas of environmental

    or cultural significance.

    Wherever possible, Western Power takes into consideration natural

    vegetation and geography to reduce the visual impact of itstransmission lines.

    Reducing the noise profile

    In some situations it is necessary to build a solid wall around a substation

    or alternatively install a noise enclosure around a particular transformer

    to reduce the noise from that substation.

    Government regulations

    When a new project is seen to have significant environmental impact,

    Western Power will refer the project to the Environmental Protection

    Authority (EPA) for assessment.

  • 8/6/2019 newinfrastructure mmmmmmmmmmmmm

    12/12

    Important numbers

    Below is a list of important contact details should you require assistance

    or information regarding powerlines in your area.

    Faults and emergencies, power interruptions,

    estimated restoration times (24 hrs) 13 13 51

    Streetlights out (24 hrs) 1800 622 008

    Report vandalism (24 hrs) 13 13 51

    General enquiries 13 10 87

    Trees that are close to powerlines 13 10 87

    TTY users (speech or hearing impaired only) 1800 13 13 51

    Telephone Interpreter Services 13 14 50

    Report graffiti (24 hrs) 1800 442 255

    Dial 1100 Before You Dig 1100

    dialbeforeyoudig.com.au

    Western Power vegetation management team

    [email protected]

    Media enquiries 1300 139 240

    363 Wellington Street Perth WA 6000

    GPO Box L921 Perth WA 6842

    T: 13 10 87F: 9326 4594

    www.westernpower.com.au

    ProductCode:87262999.

    Printedon100

    %recycledpapercontaining40%

    post-consumerand60%pre-co

    nsumerAustralianwaste;ISO14001certifiedandprocesschlorinefree.MFWEP007510/09