New xTCA Developments at SLAC. CERN xTCA for Physics Interest Grou p Sept 26, 2011 Ray Larsen SLAC National Accelerator Laboratory. Topics. Standards developments Applications Demonstration Program Future Plans. Standards. Hardware, Software working groups meet weekly/ needed - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: New xTCA Developments at SLAC](https://reader035.vdocuments.site/reader035/viewer/2022081502/56816599550346895dd874dd/html5/thumbnails/1.jpg)
26-Sep-11 1
New xTCA Developments at SLAC
CERN xTCA for Physics Interest Group Sept 26, 2011
Ray LarsenSLAC National Accelerator Laboratory
New xTCA Developments at SLAC - R. Larsen
![Page 2: New xTCA Developments at SLAC](https://reader035.vdocuments.site/reader035/viewer/2022081502/56816599550346895dd874dd/html5/thumbnails/2.jpg)
26-Sep-11 2
Topics
• Standards developments• Applications Demonstration Program• Future Plans
New xTCA Developments at SLAC - R. Larsen
![Page 3: New xTCA Developments at SLAC](https://reader035.vdocuments.site/reader035/viewer/2022081502/56816599550346895dd874dd/html5/thumbnails/3.jpg)
26-Sep-11 3
Standards
• Hardware, Software working groups meet weekly/ needed
• 2 new HW standards approved– ATCA
• PICMG3.8 Standard IO interface to Rear Transition Module (RTM), IPMI extension & power connector
– MTCA• MTCA.4 Crate, 2-wide AMC & RTM, IO interface,
IPMI extension and power pins designated
New xTCA Developments at SLAC - R. Larsen
![Page 4: New xTCA Developments at SLAC](https://reader035.vdocuments.site/reader035/viewer/2022081502/56816599550346895dd874dd/html5/thumbnails/4.jpg)
26-Sep-11 4
Standard Extensions for Physics
New xTCA Developments at SLAC - R. Larsen
![Page 5: New xTCA Developments at SLAC](https://reader035.vdocuments.site/reader035/viewer/2022081502/56816599550346895dd874dd/html5/thumbnails/5.jpg)
26-Sep-11 5
Standards Details– ATCA PICMG3.8
• 120 5GHz BW IO channels on 3- 4x10 ZD connectors• New connector (Positronix) for IPM, power• Mechanical, E-keying functions• Implemented on SLAC MPP Processor (M. Huffer)
– MTCA.4• Extends double-wide shelf (crate) to include RTM• 60 Ch IO, IPMI on 2- 3x10 ZD connectors• Extended backplane timing, trigger, interlocks layer• Compatible with all existing 1-wide AMC products• Implemented by Schroff, ELMA, PT, others in dev’mt
New xTCA Developments at SLAC - R. Larsen
![Page 6: New xTCA Developments at SLAC](https://reader035.vdocuments.site/reader035/viewer/2022081502/56816599550346895dd874dd/html5/thumbnails/6.jpg)
26-Sep-11 66New xTCA Developments at SLAC - R. Larsen
PICMG3.8 RTM Interface StandardRear View
120 - IO Channels (3x40)IPMI, Power Connector (blue)2 Mechanical Keys Courtesy M. Huffer, SLAC
![Page 7: New xTCA Developments at SLAC](https://reader035.vdocuments.site/reader035/viewer/2022081502/56816599550346895dd874dd/html5/thumbnails/7.jpg)
26-Sep-11 7
MTCA.4 AMC-RTM-Shelf Concept
New xTCA Developments at SLAC - R. Larsen
text
FAN TRAY-HOTSWAP
FRONT END MODULE
ADVANCED MEZZANINE CARD (AMC)
INPUT/OUTPUT SIGNAL CONDITIONING
REAR TRANSITION MODULE (RTM)
I/O
I/O
BP CONN
BACKPLANE
AIR IN
AIR OUT
FAN TRAY-HOT SWAP
USE
R D
EFIN
ED I/
O C
ON
NEC
TOR
S
![Page 8: New xTCA Developments at SLAC](https://reader035.vdocuments.site/reader035/viewer/2022081502/56816599550346895dd874dd/html5/thumbnails/8.jpg)
26-Sep-11 8New xTCA Developments at SLAC - R. Larsen
MTCA.4 12-AMC Backplane
Intlk, Vector Sums
Parallel Triggers
![Page 9: New xTCA Developments at SLAC](https://reader035.vdocuments.site/reader035/viewer/2022081502/56816599550346895dd874dd/html5/thumbnails/9.jpg)
26-Sep-11 9New xTCA Developments at SLAC - R. Larsen
MTCA.4 Backplane Timing Distribution
Backplane
Enc.ClockTrigger
MCH
Enc.ClockTrigger
Cross-
Point-Switc
h
Interlock Interlock
AMCADC
AMCADC
AMCTiming
Central Timing
2 radial clocks per AMC,low jitter
8 bussed lines,M-LVDS for
Clocks, triggers, interlocks
Courtesy K. Rehlich, DESY
![Page 10: New xTCA Developments at SLAC](https://reader035.vdocuments.site/reader035/viewer/2022081502/56816599550346895dd874dd/html5/thumbnails/10.jpg)
26-Sep-11 10New xTCA Developments at SLAC - R. Larsen
µRTM Extended IPMI Circuit
![Page 11: New xTCA Developments at SLAC](https://reader035.vdocuments.site/reader035/viewer/2022081502/56816599550346895dd874dd/html5/thumbnails/11.jpg)
26-Sep-11 11Emerging New Electronics Standards - R. Larsen
MTCA.4 Prototype Shelves & Modules
![Page 12: New xTCA Developments at SLAC](https://reader035.vdocuments.site/reader035/viewer/2022081502/56816599550346895dd874dd/html5/thumbnails/12.jpg)
26-Sep-11 12
MTCA.4 - 12 Slot Shelf Dual Star
New xTCA Developments at SLAC - R. Larsen
12 Payload AMC-RTMs Dual Star Redundant Front View
Back-Plane
Dual PU slot
Dual MCH Slot
![Page 13: New xTCA Developments at SLAC](https://reader035.vdocuments.site/reader035/viewer/2022081502/56816599550346895dd874dd/html5/thumbnails/13.jpg)
26-Sep-11 13
MTCA.4 - 6-Slot Shelf Non-Redundant
New xTCA Developments at SLAC - R. Larsen
6 Slot Development Shelf1-Star Non- Redundant
Front View
6-Slot Rear View
Courtesy Schroff, Struck
![Page 14: New xTCA Developments at SLAC](https://reader035.vdocuments.site/reader035/viewer/2022081502/56816599550346895dd874dd/html5/thumbnails/14.jpg)
26-Sep-11 14
SLAC Applications Demonstrations
1. LLRF for Main Linac S-Band 50MW station
2. Klystron interlocks for 10MW L-Band station
3. Beam Position Monitors for LCLSII Injector
New xTCA Developments at SLAC - R. Larsen
![Page 15: New xTCA Developments at SLAC](https://reader035.vdocuments.site/reader035/viewer/2022081502/56816599550346895dd874dd/html5/thumbnails/15.jpg)
26-Sep-11 15
1. S-Band LLRF
• Demonstrate intra-pulse feedback to achieve ~30fs phase control– Lower noise RF front end chassis– New solid state sub-booster– Feedback loop implemented in MTCA.4 using
Struck 10 Ch ADC 2 Ch DAC developed w/DESY– New LCLSI waveguide water-stabilized rack– Test on Standby triggering, switch to Accelerate
• Tests on accelerator to complete Oct 2011
New xTCA Developments at SLAC - R. Larsen
![Page 16: New xTCA Developments at SLAC](https://reader035.vdocuments.site/reader035/viewer/2022081502/56816599550346895dd874dd/html5/thumbnails/16.jpg)
26-Sep-11 16
LLRF MTCA & RF Chassis Testing
New xTCA Developments at SLAC - R. Larsen
![Page 17: New xTCA Developments at SLAC](https://reader035.vdocuments.site/reader035/viewer/2022081502/56816599550346895dd874dd/html5/thumbnails/17.jpg)
26-Sep-11 17
Rear View
New xTCA Developments at SLAC - R. Larsen
![Page 18: New xTCA Developments at SLAC](https://reader035.vdocuments.site/reader035/viewer/2022081502/56816599550346895dd874dd/html5/thumbnails/18.jpg)
26-Sep-11 18
RTM Inputs
New xTCA Developments at SLAC - R. Larsen
Note – Preliminary RTM shownFinal RTMwith full IPMI complete, In test.
![Page 19: New xTCA Developments at SLAC](https://reader035.vdocuments.site/reader035/viewer/2022081502/56816599550346895dd874dd/html5/thumbnails/19.jpg)
26-Sep-11 19
RF Chassis – Reference, LO, Sources, Downmixers
New xTCA Developments at SLAC - R. Larsen
Note – Next stageplan is to test L-Band down-mixers, other RF modules inMTCA card format
![Page 20: New xTCA Developments at SLAC](https://reader035.vdocuments.site/reader035/viewer/2022081502/56816599550346895dd874dd/html5/thumbnails/20.jpg)
26-Sep-11 20
AMC - 10/2Ch ADC/DAC 16bit 125 MSPS
Emerging New Electronics Standards - R. Larsen
Photo courtesy M. Kirsch,(Struck )
Initial Applications: LLRF DESY XFELLLRF SLAC Upgrade Proto
![Page 21: New xTCA Developments at SLAC](https://reader035.vdocuments.site/reader035/viewer/2022081502/56816599550346895dd874dd/html5/thumbnails/21.jpg)
26-Sep-11 21
RTM 10 Ch ADC-DAC, IPMI Interface
Emerging New Electronics Standards - R. Larsen
Rear Panel
• Mini-Coax IF Signals In
• RF Ref In• Trigger in• Dual I&Q
DAC Out• IPMI
Extension to RF Chassis
Courtesy A. Young, SLAC
![Page 22: New xTCA Developments at SLAC](https://reader035.vdocuments.site/reader035/viewer/2022081502/56816599550346895dd874dd/html5/thumbnails/22.jpg)
26-Sep-11 22
2. MTCA Klystron Interlocks S&L Band
• FPGA based interlocks in MTCA.4– S-Band interlocks currently in separate FPGA
non-modular chassis– L-Band interlocks currently FPGA based in VME– MTCA solution will serve both in future– SLAC designed RTM mates to new TEWS
Spartan 6 FPGA module (just received in US)– RTM testing starting– 1 board pair serves 8 Ch-60MSps, 16 Ch-2KSps– 2 board pairs serve 1 S- or L-band station
New xTCA Developments at SLAC - R. Larsen
![Page 23: New xTCA Developments at SLAC](https://reader035.vdocuments.site/reader035/viewer/2022081502/56816599550346895dd874dd/html5/thumbnails/23.jpg)
26-Sep-11 23
RTM FPGA Interlocks
Emerging New Electronics Standards - R. Larsen
Rear Panel
• Inputs- 8-60 MSps Ch- 16-2 KSps Ch- 12 bits Diff +/- 1V- Diode protection All channels• Outputs- Interlock Sums• RF Interlocks for L-Band 1 msec, S-band 1.5 µsec
Courtesy D.G. Brown, SLAC
![Page 24: New xTCA Developments at SLAC](https://reader035.vdocuments.site/reader035/viewer/2022081502/56816599550346895dd874dd/html5/thumbnails/24.jpg)
26-Sep-11 24
AMC TAMC651 FPGA w/RTM
New xTCA Developments at SLAC - R. Larsen
Courtesy TEWS
Note – Completion date for ESB installation Dec. 2011.
![Page 25: New xTCA Developments at SLAC](https://reader035.vdocuments.site/reader035/viewer/2022081502/56816599550346895dd874dd/html5/thumbnails/25.jpg)
26-Sep-11 25
3. BPMs for LCSLII Injector
• Goal: Demonstration of 8 BPMs in 12-slot– RTM has 4 Ch analog plus calibration w/ strip-
line coupling between 120 Hz pulses– AMCs will be 4 Ch 125 or 250 MSps (125
available now; 250 may be developed by commercial supplier(s)
– 250 MSps needed if multibunch (2 bunches 8 nsec apart)
– Requirements being finalized (16 bit ADCs)– Preliminary RTM layout indicates feasible
New xTCA Developments at SLAC - R. Larsen
![Page 26: New xTCA Developments at SLAC](https://reader035.vdocuments.site/reader035/viewer/2022081502/56816599550346895dd874dd/html5/thumbnails/26.jpg)
26-Sep-11 26
BPM System Block Diagram
New xTCA Developments at SLAC - R. Larsen
AFE
AFE
AFE
AFE
AFE
AFE
AFE
MCH
CPU
EVR
ADC
ADC
ADC
ADC
ADC
ADC
- Front -
12-slot MicroTCA crateInjector BPM Crate 1; 8 BPMs
- Back -
1 ADC per BPM
1 AFE per BPM
Signal cables to tunnel4 per BPM
Timing data
EPICSChannel Access Network
ADC
ADC
EVR
AFE
TrigFanout
TrigFanout
Calibrator trigger1 per BPM
ADC trigger1 per BPM
EVR provides clock to ADCs along the backplane
Courtesy S. Hoobler et al, private communication
![Page 27: New xTCA Developments at SLAC](https://reader035.vdocuments.site/reader035/viewer/2022081502/56816599550346895dd874dd/html5/thumbnails/27.jpg)
26-Sep-11 27
Conclusions 1
• Standards for hardware have passed 2 major milestones– Committees will disband when SOWs complete– Software committee continues developing
guidelines for architecture and protocols– Member labs remain involved in PICMG through
Coordinating Committee for oversight, servicing tweaks
– Start new initiatives, SOWs, form committees as needed
New xTCA Developments at SLAC - R. Larsen
![Page 28: New xTCA Developments at SLAC](https://reader035.vdocuments.site/reader035/viewer/2022081502/56816599550346895dd874dd/html5/thumbnails/28.jpg)
26-Sep-11 28
Conclusions 2• SLAC new initiatives open future opportunities
– Main Linac RF upgrades for LCLSII, I.– BPM upgrades for LCLSII Injector, Main Linac– Interlock systems wholly contained in MTCA.4
combined RF-Controls package– Long range: Complete replacement CAMAC
controls in 2-mile accelerator, $20M program• Timeline:
– RF and interlock demos complete in Q1-2 FY12– BPM AIP completes Q2 FY13
New xTCA Developments at SLAC - R. Larsen