new nstx-u supported by · 2013. 9. 24. · nstx-u office of science review (10/ 2 & 3 /2013)...

14
NSTX-U Office of Science Review (10/ 2 & 3 /2013) L. Dudek, N. Atnafu, R. Hatcher, R. Kaita, R. Ramakrishnan, P. Sichta and the NSTX Upgrade Team Office of Science Review Princeton, NJ October 2 & 3, 2013 NSTX-U Supported by Culham Sci Ctr York U Chubu U Fukui U Hiroshima U Hyogo U Kyoto U Kyushu U Kyushu Tokai U NIFS Niigata U U Tokyo JAEA Inst for Nucl Res, Kiev Ioffe Inst TRINITI Chonbuk Natl U NFRI KAIST POSTECH Seoul Natl U ASIPP CIEMAT FOM Inst DIFFER ENEA, Frascati CEA, Cadarache IPP, Jülich IPP, Garching ASCR, Czech Rep Coll of Wm & Mary Columbia U CompX General Atomics FIU INL Johns Hopkins U LANL LLNL Lodestar MIT Lehigh U Nova Photonics Old Dominion ORNL PPPL Princeton U Purdue U SNL Think Tank, Inc. UC Davis UC Irvine UCLA UCSD U Colorado U Illinois U Maryland U Rochester U Tennessee U Tulsa U Washington U Wisconsin X Science LLC Ancillary Systems 1

Upload: others

Post on 22-Sep-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: New NSTX-U Supported by · 2013. 9. 24. · NSTX-U Office of Science Review (10/ 2 & 3 /2013) L. Dudek, N. Atnafu, R. Hatcher, R. Kaita, R. Ramakrishnan, P. Sichta and the NSTX Upgrade

NSTX-U Office of Science Review (10/ 2 & 3 /2013)

L. Dudek, N. Atnafu, R. Hatcher, R. Kaita, R. Ramakrishnan, P. Sichta

and the NSTX Upgrade Team

Office of Science ReviewPrinceton, NJ

October 2 & 3, 2013

NSTX-U Supported by

Culham Sci CtrYork U

Chubu UFukui U

Hiroshima UHyogo UKyoto U

Kyushu UKyushu Tokai U

NIFSNiigata UU Tokyo

JAEAInst for Nucl Res, Kiev

Ioffe InstTRINITI

Chonbuk Natl UNFRI

KAISTPOSTECH

Seoul Natl UASIPP

CIEMATFOM Inst DIFFER

ENEA, FrascatiCEA, Cadarache

IPP, JülichIPP, Garching

ASCR, Czech Rep

Coll of Wm & MaryColumbia UCompXGeneral AtomicsFIUINLJohns Hopkins ULANLLLNLLodestarMITLehigh UNova PhotonicsOld DominionORNLPPPLPrinceton UPurdue USNLThink Tank, Inc.UC DavisUC IrvineUCLAUCSDU ColoradoU IllinoisU MarylandU RochesterU TennesseeU TulsaU WashingtonU WisconsinX Science LLC

Ancillary Systems

1

Page 2: New NSTX-U Supported by · 2013. 9. 24. · NSTX-U Office of Science Review (10/ 2 & 3 /2013) L. Dudek, N. Atnafu, R. Hatcher, R. Kaita, R. Ramakrishnan, P. Sichta and the NSTX Upgrade

NSTX-U NSTX Upgrade Project – Office of Science Review – October 2-3,, 2013

Ancillary Systems

• Coil and Vacuum Vessel Support Structures• Power• Diagnostics• I&C• Passive Plate Mods• DCPS- will be presented this afternoon at a breakout

session by Hatcher / Erickson

2

Page 3: New NSTX-U Supported by · 2013. 9. 24. · NSTX-U Office of Science Review (10/ 2 & 3 /2013) L. Dudek, N. Atnafu, R. Hatcher, R. Kaita, R. Ramakrishnan, P. Sichta and the NSTX Upgrade

NSTX-U NSTX Upgrade Project – Office of Science Review – October 2-3,, 2013

Vacuum Vessel and Coil Support Structures (Smith)

3

New Clevis Supports

New Links and Rod Ends

OTF Weldments

OTF Outer Ring / Links

Page 4: New NSTX-U Supported by · 2013. 9. 24. · NSTX-U Office of Science Review (10/ 2 & 3 /2013) L. Dudek, N. Atnafu, R. Hatcher, R. Kaita, R. Ramakrishnan, P. Sichta and the NSTX Upgrade

NSTX-U NSTX Upgrade Project – Office of Science Review – October 2-3,, 2013

Umbrella External Reinforcements

4

New Aluminum block reinforcements

New Umbrella Legs

New Umbrella Reinforcement

New Stronger Sliding Foot

Reinforcement of dome rib welds with gusseting

Page 5: New NSTX-U Supported by · 2013. 9. 24. · NSTX-U Office of Science Review (10/ 2 & 3 /2013) L. Dudek, N. Atnafu, R. Hatcher, R. Kaita, R. Ramakrishnan, P. Sichta and the NSTX Upgrade

NSTX-U NSTX Upgrade Project – Office of Science Review – October 2-3,, 2013

Internal Umbrella Reinforcements

5

New Internal Umbrella Reinforcement

Page 6: New NSTX-U Supported by · 2013. 9. 24. · NSTX-U Office of Science Review (10/ 2 & 3 /2013) L. Dudek, N. Atnafu, R. Hatcher, R. Kaita, R. Ramakrishnan, P. Sichta and the NSTX Upgrade

NSTX-U Office of Science Review (10/ 2 & 3 /2013)

Electrical Power System (Ramakrishnan)

• Upgrade Requirements– TF : 129.8 kA, 1kV, ESW 7.08 sec @ 2400 sec (7.05kA rms) ; – OH : 24kA, ESW 1.474 sec @ 2400 sec ; 6kV – PF1a: Eliminate Ripple reduction reactors

• Design is complete, Installation spec. has been written and work is in progress. – About 80% of work completed in FCPC Building– Power Cabling changes from Transition Area to NSTX Test Cell completed and tested

• One fiber-optic DCCT (+/-0 to 150kA) has been procured and installed to measure the TF current. Another one procured and installation procedure has been prepared

Fiber Optic DCCT for TF Current

6

Page 7: New NSTX-U Supported by · 2013. 9. 24. · NSTX-U Office of Science Review (10/ 2 & 3 /2013) L. Dudek, N. Atnafu, R. Hatcher, R. Kaita, R. Ramakrishnan, P. Sichta and the NSTX Upgrade

NSTX-U Office of Science Review (10/ 2 & 3 /2013)

Electrical Power Systems (Contd)

• For OH system, the old PLT TF coils have been installed in the OH circuit as the DC Current Limiting Reactors. – About 400k$ saved by using these.– PTP is yet to be conducted

• Hardwired Controls– FDR completed to change part of the system to PLC.

Surplus PLT TF Coils installed for use as DC CLR for upgrade

7

Page 8: New NSTX-U Supported by · 2013. 9. 24. · NSTX-U Office of Science Review (10/ 2 & 3 /2013) L. Dudek, N. Atnafu, R. Hatcher, R. Kaita, R. Ramakrishnan, P. Sichta and the NSTX Upgrade

NSTX-U Office of Science Review (10/ 2 & 3 /2013)

Electrical Power Systems (Contd)

• TF Turn to Turn Fault Detection– New TF Turn to turn fault detection designed & order placed for sensor.

8

Page 9: New NSTX-U Supported by · 2013. 9. 24. · NSTX-U Office of Science Review (10/ 2 & 3 /2013) L. Dudek, N. Atnafu, R. Hatcher, R. Kaita, R. Ramakrishnan, P. Sichta and the NSTX Upgrade

NSTX-U NSTX Upgrade Project – Office of Science Review – October 2-3,, 2013 1NSTX-U NSTX Upgrade Project – Office of Science Review – May 2nd – 3rd 2012

Most Center Stack Diagnostics Fabricated (Kaita)

• Manufacture of Mirnov coils and Rogowski coils complete– Includes extra Mirnov coils and “segmented”

Rogowski coils for halo current measurements

• All copper and thermocouple wires procured– Satisfy specialized material and insulation

requirements for installation under plasma-facing components

• Fabrication drawings for Langmuir probes complete– Awaiting delivery of center stack tiles to begin

machining for probes

• Future plans include preparation of installation procedure and execution when center stack is ready

9

Mirnov Coil

Thermocouple

Page 10: New NSTX-U Supported by · 2013. 9. 24. · NSTX-U Office of Science Review (10/ 2 & 3 /2013) L. Dudek, N. Atnafu, R. Hatcher, R. Kaita, R. Ramakrishnan, P. Sichta and the NSTX Upgrade

NSTX-U NSTX Upgrade Project – Office of Science Review – October 2-3,, 2013 2NSTX-U NSTX Upgrade Project – Office of Science Review – May 2nd – 3rd 2012

Plasma and Halo Current Rogowski coil requirements met

• Limited space on air side of center stack and underneath plasma-facing components constrained thickness

• Turns needed to be non-overlapping and of correct number per unit length to insure proper gain (“nA”)

Plasma CurrentRogowski Coil

Halo CurrentRogowski Coil

10

Page 11: New NSTX-U Supported by · 2013. 9. 24. · NSTX-U Office of Science Review (10/ 2 & 3 /2013) L. Dudek, N. Atnafu, R. Hatcher, R. Kaita, R. Ramakrishnan, P. Sichta and the NSTX Upgrade

NSTX-U NSTX Upgrade Project – Office of Science Review – October 2-3,, 2013

Central I&C (6100, Sichta)

l The ~4x longer pulse length drives upgrades for data acquisition, networking, and real-time controls.

l Job is 36% complete. Remaining scope: $250k M&S, 1000 hrs programming, 900 hrs installation, 600 hrs testing. Ready to support ISTP Aug 21, 2014.

l Majority of procurements have been deferred into FY14; low-risk off the shelf data acquisition equipment.

l Network upgrades have been deferred to FY14. $80k external to NSTX-U project scope needed.

l Real-time Plasma Control algorithms for NSTX-U are in good shape. Software requirements document up to revision 6.

l Postponement of (Transrex rectifier) Fault Detector project will add minor scope change to 6100; additional CAMAC will (now) remain in service so more CAMAC memory upgrades are needed to accommodate longer pulse.

11

Page 12: New NSTX-U Supported by · 2013. 9. 24. · NSTX-U Office of Science Review (10/ 2 & 3 /2013) L. Dudek, N. Atnafu, R. Hatcher, R. Kaita, R. Ramakrishnan, P. Sichta and the NSTX Upgrade

NSTX-U NSTX Upgrade Project – Office of Science Review – October 2-3,, 2013

Secondary Passive Plates Upgrade

Brazed Joint

• Challenge: The existing secondary plates in the Bay A/L were weakened by the thermal cycle during brazing.

• Hardness and tensile test results confirmed that these plates are significantly weaker than the standard plates.– Standard (unbrazed) plates = 57 ksi

(tensile strength)– PCHERS Passive Plate braze joint = 7 ksi– Electron beam weld joint = 40 ksi– E-beam Heat affected area = 57 ksi

• A new design will use E-Beam welding to join the passive plates to the jumper plates.

12

Page 13: New NSTX-U Supported by · 2013. 9. 24. · NSTX-U Office of Science Review (10/ 2 & 3 /2013) L. Dudek, N. Atnafu, R. Hatcher, R. Kaita, R. Ramakrishnan, P. Sichta and the NSTX Upgrade

NSTX-U NSTX Upgrade Project – Office of Science Review – October 2-3,, 2013

Development of Secondary Passive Plates

E-Beam Welded Joint

• First, the passive plates and jumper plates will be fabricated.• Second, the two plates will be joined using E-Beam welding.• Last, the “throat” of the CHERS viewing channel will be

machined open• Key Milestones:

– Peer Review in 10/14/2013– Final Design Review in 02/04/2014– Fabricated Parts Delivered to PPPL by 06/23/2014– Installation complete by 07/22/2014, Total budget: – Total Budget: $333.5K

13

Page 14: New NSTX-U Supported by · 2013. 9. 24. · NSTX-U Office of Science Review (10/ 2 & 3 /2013) L. Dudek, N. Atnafu, R. Hatcher, R. Kaita, R. Ramakrishnan, P. Sichta and the NSTX Upgrade

NSTX-U NSTX Upgrade Project – Office of Science Review – October 2-3,, 2013

Conclusions

• Significant progress has been made in the ancillary system work over the last six months.

• Installation work is well underway• Work is on track to support the scheduled startup of the

upgrade

14