MOCK DRILL ORGANISED AT NOKIA PLOT 25, GURGAON.
DATE:- 21/11/2016.
Prepared By :- ARITRO MUKHERJEE
AGENDA
1. Building Infrastructure Details.
2. ERT Members Details.
3. Building Evacuation Details.
4. Evacuation Highlights.
5. Fire Safety Training By Trainer.
BUILDING INFRASTRUTURE DETAILS
No. of Blocks: 4
Block A&B Ground Floor – 12906 sq. feet
Block A&B First Floor – 11948 sq. feet
Block C – 33878 sq. feet
Nokia University (Part of Block – C)
Block D – 18698 sq. feet
Canteen – 6064 sq. feet
Utility Blocks – 50106 sq. feet
No. of Washrooms: 15 Nos.
ERT MEMBERS DETAILS
S.NO Name Emp. ID Mobile No. 1 S.K. MISHRA FG0000025 98913032002 V.K. MALIK FG0001199 99118715153 SUNIL CHAWLA PGT000250 99991786414 RAVI SHARMA PGT000070 80108701095 RITA ARORA FG1000476 9711411628
6 JYOTI KUKREJA FG0001226 99588904507 ASHISH GHILDIYAL R-3207 99903332768 ARITRO MUKERJEE R-3379 98990767069 YUVRAJ SINGH C-135649 9911581326
10 SHILPI SG -330 7827831449
BUILDING EVACUATION DETAILS
5 – Title of the document or activity name – Month XX, 2016 – Insert tab > Header/Footer
Evacuation started at 1530 Hrs after siren got activated.
ERT Members was instructing the employees to follow the emergency routes.
All employees gathered at the Emergency Assembly Area at 1537 Hrs.
Total numbers of employees was 288 ( NOKIA(247), Sodexo(29), Terrier(12).
Total headcount at Assembly area was 241
47 Employee had not participated in Drill.
EVACUATION HIGHLIGHTS..
EVACUATION HIGHLIGHTS..
EVACUATION HIGHLIGHTS..
EVACUATION HIGHLIGHTS..
EVACUATION HIGHLIGHTS..
ERT MEMBERS TRAINING IN PROGRESS
11 – Title of the document or activity name – Month XX, 2012 – Insert tab > Header/Footer
THANK YOU