new lock at the soo - united states army
TRANSCRIPT
“The views, opinions and findings contained in this report are those of the authors(s) and should not be construed as an official Department of the Army position, policy or decision, unless so designated by other official documentation.”
Mollie Mahoney, Project ManagerU.S. Army Corps of Engineers, Detroit District22 March 2021
NEW LOCK AT THE SOO CONGRESSIONAL MEMBER AND STAKEHOLDER UPDATE
2
SOO LOCKS LOCATION & IMPORTANCE
Soo Locks
**Tonnage in 2020 lower than typical year due to Covid 19. Five year average tonnage is 71M tons.
3
MAINTAINING EXISTING SOO LOCKS FACILITY (O&M FUNDED)
05
101520253035
FY08 FY10 FY12 FY14 FY16 FY18 FY20Asset Renewal Routine O&M
Fund
ing,
$M
Upcoming Asset Renewal Priorities
• Poe Gate 1 Replacement• Poe Filling & Emptying Valve Repairs• MacArthur Miter Gate Anchorage Components
Projects Funded in FY21 Work Plan
• Poe Gate 1 Repairs - Blasting & Coating - $6.5M• Construction of Raceway for Lock Power Feeders - $6.5M• Replacement Tugboat – St. Marys River Strike Removal - $14.25M• Aquadigger Outfitting – St. Marys River Strike Removal - $1.25M• Design of Facility Sanitary Sewer Rehabilitation - $1M• Repair & Replace Poe Miter Gate Anchorage Components - $2.5M
4
MAINTAINING EXISTING SOO LOCKS FACILITY (O&M FUNDED)
Poe Gate 2 Sill Concrete RepairPoe Gate 1 Repairs
• Barge Huron Repairs• Dewatering System Cleanout• Poe Fill/Empty Valve Maintenance
FY21 Key Winter Work Maintenance• Poe Gate 1 Structural Repairs• Poe Gate 1 Flushing Valves• Poe Gate 2 Sill Repair
Repairs to Barge Huron
5
Dav
is L
ock
(Inac
tive)
Sabi
n Lo
ck (I
nact
ive)
Poe Bulkhead
Mac Tainter Valve Machinery
Davis & Poe Pump Wells
Poe Ship Arrestors
Davis and Poe Pumpwells ($37.3M FY21 Capability)• The pumpwell system will serve all locks (including new lock); system >100 yrs old• Delayed funding for repair increases O&M every year with additional interim risk
reduction measures required and increasing probability of failure; greatly increases operational risk to navigation. Locks must be dewatered in 10 hours due to extreme cold temps in January.
• Original 1914 manifold is most critical component; has lost half its wall thickness • New Pump Well will be contracted with the New Lock to reduce risk associated with 2
contractors working in close proximity at the same time.
FY2019
Poe BulkheadFabrication
MacArthur Tainter Valve Machinery
Davis and Poe Pump Wells
FY2021 FY2022FY2020
Design/ Advertise,
Offer, Award
Construction
FY2023
Poe Lock Ship Arrestors
FY2024 FY2025
Awarded Aug 2020
Completed Jan 2020
MAINTAINING EXISTING SOO LOCKS FACILITY (CG FUNDED) WE ARE HERE
7
NEW LOCK STATUS
* Early completion could be realized with approval of continuing contracts clause, efficient funding, and favorable weather conditions
Design
Contract Procurement
Construction
Phase 1: Upstream Channel Deepening (UCD)
WE ARE HERE
UCD 2020 Work AreaUCD 2021 Work Area
UAW 2021 Work Area
NLC 2022 Forward Work AreaN
UAW 2022 & 2023 Work Area
Phase 2: Upstream Approach Walls (UAW)
Phase 3: New Lock Chamber (NLC)
FY19 FY20 FY21 FY22 FY23 FY24 FY25 FY26 FY27 FY28 FY29 FY30
8CAPABILITIES AND ALLOCATIONS
FY22 & FY23 Activities FY22 Capability FY23 CapabilityNew Lock Chamber Design $841k $0Upstream Approach Wall Construction Management $2.4M $0New Lock Chamber Construction & Construction Management $476.7M $170M
TOTAL $480M $170M
$480M $170M $313M
FY21 Funded Work:• Upstream Channel Deepening Construction Management• Upstream Approach Walls Construction & Construction Management• New Lock Chamber Design & Construction (contract advertisement in FY21 with award in FY22)
9PHASE 1: UPSTREAM CHANNEL DEEPENING
Scope: Remove 300,000 CY of Jacobsville sandstone and overburden (loose sediment) to deepen the Upstream Approach Channel to depth of 30 feetConstruction Status: • $52.6M Contract awarded in January 2020 to Trade West Construction Co. of Nevada. • Contractor has completed roughly 50% of the required contract work. The contractor is on track to complete
work by Fall 2021Estimated Performance Period: 20 Months
Channel Deepening LimitsBedrock & Overburden Removal LimitsOverburden Removal LimitsMaterial Placement Area
10
Prior Condition(Apr 2020)
After Condition (Dec 2020)
PHASE 1: UPSTREAM CHANNEL DEEPENING
Major features of contract work • Mobilization• Instrumentation Installation• Northwest Pier Access Road Construction• Channel Deepening
→ 100% Complete→ 100% Complete
→ 95% Complete→ 33% Complete
11
Prior Condition (Apr 2020)
After Condition(Dec 2020)
PHASE 1: UPSTREAM CHANNEL DEEPENINGNORTHWEST PIER MATERIAL PLACEMENT SITE
13
Bedrock from Upstream Approach Channel Overburden from Upstream Approach Channel
PHASE 1: UPSTREAM CHANNEL DEEPENING
14
Site Work on Northwest Pier Material Placement Site Contractor worked 24-6 during periods of 2020 construction season
PHASE 1: UPSTREAM CHANNEL DEEPENING
15PHASE 2: UPSTREAM APPROACH WALLSN
34 ft diameter Circular SSP Cells - 1,900’SSP Transition Walls - 1,000’SSP Walls - 1,100’H-Pile (Soldier) Wall - 1,100’*Rubble Mound (non-mooring area) - 555’*Breakwater - 350’*West Center Pier Rehab
Work east of station 14+00 is to be completed by 15 Oct 2021
Scope: Rehabilitate approach walls upstream of New Soo Lock including reconstruction of walls, concrete caps, mooring bollards, electrical, and lighting.Project Status: • $111.3M Contract awarded to Kokosing Alberici in September 2020• Contractor expected to arrive on site in Spring 2021 and complete work in Fall 2023Estimated Performance Period: 36 Months
*Options that have not been exercised to date
16
PHASE 2: UPSTREAM APPROACH WALLS
• Contractor will begin on East end and work Westward
• Filling the sluiceway between the Upstream Approach Channel and the Unit 10 Power Plant headrace will be one of the first activities
SSP Cells
Stone Dam
17
PHASE 3: NEW LOCK CHAMBER
Scope: Construct new 1,200’ long by 110’ wide by 32’ deep chamber and rehabilitate downstream approach walls.Project Status: • 70% Design review completed in July 2020• 100% Design to be complete in July 2021• Construction contract award expected in February 2022 with contractor mobilization in Spring 2022Estimated Performance Period: 5-8 Years
N
18
NEW LOCK CHAMBER KEY FEATURES
Miter GatesFilling and Emptying SystemUpstream Ship ArrestorsDownstream Ship ArrestorsHands Free MooringNew Pump Well Miter Gates Ship Arrestor Hands Free Mooring Unit
19
NEW LOCK CHAMBER- TOOLS USED FOR DESIGN
REVIT model of existing lock structure
REVIT model of new lock structure
Virtual reality used for 70% design review by Soo Locks Operations and Maintenance Personnel
Changes Made Based on Virtual Reality Review• Operating shelter sightlines• Additional lock floor catch basins• Addition of miter gate tie back recesses
20
• Structural (LRN w/ support from LRL, LRP & LRE)• Civil Design (LRL)• Geology (LRL)• Geotechnical (LRL)• Electrical (LRP)• Mechanical (LRP & MVP)• Cost (LRH)• Hydraulics (MVS)• HTRW (LRB)• Security (NWO)• Materials (LRP with support from LRL & LRN)• Stantec/Cavotec – Hands Free Mooring Design
NEW LOCK CHAMBER DESIGN – INDC LEAD Inland Navigation Design Center (INDC) is Designer of Record and leading the design team that has members from 8 Districts and one A/E Firm
Design Review meeting, Nashville Jan 2020
Design Review meeting, Louisville Feb 2021
22
RESIDENT OFFICE – SCOPEUtilities:
• Water: City, • Sewer: City • Electrical: SAO• Fiber: SAO• Storm: City
• Tree Removal
Purpose: Provide office space for 26-30 person USACE Construction Management Team
Scope:6,000 SF modular structure- Conference Room - Bathrooms - Breakroom- Secure Storage
Schedule:- Design-Build Contract
scheduled to be awarded this Spring
- Occupancy slated for Nov. 2021
23
RESIDENT OFFICE – STATUSLocation Decision Criteria: - Size- Proximity to Construction Site- Cost- Timeliness- Minimize Impact to Community
and Park
Actions to Minimize Effect- Town Hall Meeting- Low Roof Line- Minimize Tree Removal- Restoration of Site Post New
Lock Construction
Artistic Rendering of the Resident Office in the Soo Locks Upper Canal Park
24
PROJECT’S ECONOMIC IMPACT
• $1.375B Total Project Cost
• Estimated 7-10 years of construction
• 1,240 jobs created on an annual basis• 600 direct jobs• 210 indirect jobs• 430 induced jobs
• 950,000 tons of limestone or granite
• 55,000 tons of American-made cement
• 25,000 tons of American-made steel
Menominee Unloading Aggregate on Northwest Pier in support of Upstream Channel Deepening Contract
25
Recent Engagements:• LTG Scott Spellmon, 55th Chief of Engineers and Commanding General of the U.S.
Army Corps of Engineers, visit to Soo Locks: Oct 2020• Mr. Vance Stewart, III, Senior Official Performing The Duties Of ASA(CW) and MG
William Graham, Deputy Commanding General for Civil and Emergency Operations, visit to Soo Locks: Feb 2021
Upcoming Engagement and Dates of Importance:• Detroit District Annual Congressional Meetings: Mar 2021• UAW Contractor Mobilizing to Site: Apr 2021• New Lock Chamber Stagger 1 Solicitation Start: Early Jun 2021• New Lock Chamber Pre-Proposal On-Site Meeting for Contractors: Mid-Late Jun 2021• New Lock Chamber Stagger 2 Solicitation Start: Late Aug 2021• Upstream Channel Deepening Completion: Nov 2021• New Lock Chamber Award: Feb 2022
RECENT ENGAGEMENTS AND UPCOMING DATES
26
QUESTIONS
Contact Info:Mollie Mahoney, New Lock at the Soo Project Manager (313) 226-2033
Email: [email protected] Website: https://www.lre.usace.army.mil/