new lock at the soo - united states army

26
“The views, opinions and findings contained in this report are those of the authors(s) and should not be construed as an official Department of the Army position, policy or decision, unless so designated by other official documentation.” Mollie Mahoney, Project Manager U.S. Army Corps of Engineers, Detroit District 22 March 2021 NEW LOCK AT THE SOO CONGRESSIONAL MEMBER AND STAKEHOLDER UPDATE

Upload: others

Post on 24-Feb-2022

1 views

Category:

Documents


0 download

TRANSCRIPT

“The views, opinions and findings contained in this report are those of the authors(s) and should not be construed as an official Department of the Army position, policy or decision, unless so designated by other official documentation.”

Mollie Mahoney, Project ManagerU.S. Army Corps of Engineers, Detroit District22 March 2021

NEW LOCK AT THE SOO CONGRESSIONAL MEMBER AND STAKEHOLDER UPDATE

2

SOO LOCKS LOCATION & IMPORTANCE

Soo Locks

**Tonnage in 2020 lower than typical year due to Covid 19. Five year average tonnage is 71M tons.

3

MAINTAINING EXISTING SOO LOCKS FACILITY (O&M FUNDED)

05

101520253035

FY08 FY10 FY12 FY14 FY16 FY18 FY20Asset Renewal Routine O&M

Fund

ing,

$M

Upcoming Asset Renewal Priorities

• Poe Gate 1 Replacement• Poe Filling & Emptying Valve Repairs• MacArthur Miter Gate Anchorage Components

Projects Funded in FY21 Work Plan

• Poe Gate 1 Repairs - Blasting & Coating - $6.5M• Construction of Raceway for Lock Power Feeders - $6.5M• Replacement Tugboat – St. Marys River Strike Removal - $14.25M• Aquadigger Outfitting – St. Marys River Strike Removal - $1.25M• Design of Facility Sanitary Sewer Rehabilitation - $1M• Repair & Replace Poe Miter Gate Anchorage Components - $2.5M

4

MAINTAINING EXISTING SOO LOCKS FACILITY (O&M FUNDED)

Poe Gate 2 Sill Concrete RepairPoe Gate 1 Repairs

• Barge Huron Repairs• Dewatering System Cleanout• Poe Fill/Empty Valve Maintenance

FY21 Key Winter Work Maintenance• Poe Gate 1 Structural Repairs• Poe Gate 1 Flushing Valves• Poe Gate 2 Sill Repair

Repairs to Barge Huron

5

Dav

is L

ock

(Inac

tive)

Sabi

n Lo

ck (I

nact

ive)

Poe Bulkhead

Mac Tainter Valve Machinery

Davis & Poe Pump Wells

Poe Ship Arrestors

Davis and Poe Pumpwells ($37.3M FY21 Capability)• The pumpwell system will serve all locks (including new lock); system >100 yrs old• Delayed funding for repair increases O&M every year with additional interim risk

reduction measures required and increasing probability of failure; greatly increases operational risk to navigation. Locks must be dewatered in 10 hours due to extreme cold temps in January.

• Original 1914 manifold is most critical component; has lost half its wall thickness • New Pump Well will be contracted with the New Lock to reduce risk associated with 2

contractors working in close proximity at the same time.

FY2019

Poe BulkheadFabrication

MacArthur Tainter Valve Machinery

Davis and Poe Pump Wells

FY2021 FY2022FY2020

Design/ Advertise,

Offer, Award

Construction

FY2023

Poe Lock Ship Arrestors

FY2024 FY2025

Awarded Aug 2020

Completed Jan 2020

MAINTAINING EXISTING SOO LOCKS FACILITY (CG FUNDED) WE ARE HERE

6

NEW LOCK AT THE SOO

7

NEW LOCK STATUS

* Early completion could be realized with approval of continuing contracts clause, efficient funding, and favorable weather conditions

Design

Contract Procurement

Construction

Phase 1: Upstream Channel Deepening (UCD)

WE ARE HERE

UCD 2020 Work AreaUCD 2021 Work Area

UAW 2021 Work Area

NLC 2022 Forward Work AreaN

UAW 2022 & 2023 Work Area

Phase 2: Upstream Approach Walls (UAW)

Phase 3: New Lock Chamber (NLC)

FY19 FY20 FY21 FY22 FY23 FY24 FY25 FY26 FY27 FY28 FY29 FY30

8CAPABILITIES AND ALLOCATIONS

FY22 & FY23 Activities FY22 Capability FY23 CapabilityNew Lock Chamber Design $841k $0Upstream Approach Wall Construction Management $2.4M $0New Lock Chamber Construction & Construction Management $476.7M $170M

TOTAL $480M $170M

$480M $170M $313M

FY21 Funded Work:• Upstream Channel Deepening Construction Management• Upstream Approach Walls Construction & Construction Management• New Lock Chamber Design & Construction (contract advertisement in FY21 with award in FY22)

9PHASE 1: UPSTREAM CHANNEL DEEPENING

Scope: Remove 300,000 CY of Jacobsville sandstone and overburden (loose sediment) to deepen the Upstream Approach Channel to depth of 30 feetConstruction Status: • $52.6M Contract awarded in January 2020 to Trade West Construction Co. of Nevada. • Contractor has completed roughly 50% of the required contract work. The contractor is on track to complete

work by Fall 2021Estimated Performance Period: 20 Months

Channel Deepening LimitsBedrock & Overburden Removal LimitsOverburden Removal LimitsMaterial Placement Area

10

Prior Condition(Apr 2020)

After Condition (Dec 2020)

PHASE 1: UPSTREAM CHANNEL DEEPENING

Major features of contract work • Mobilization• Instrumentation Installation• Northwest Pier Access Road Construction• Channel Deepening

→ 100% Complete→ 100% Complete

→ 95% Complete→ 33% Complete

11

Prior Condition (Apr 2020)

After Condition(Dec 2020)

PHASE 1: UPSTREAM CHANNEL DEEPENINGNORTHWEST PIER MATERIAL PLACEMENT SITE

12

Xcentric RipperPC1250 with 6.5 CY Bucket

PHASE 1: UPSTREAM CHANNEL DEEPENING

13

Bedrock from Upstream Approach Channel Overburden from Upstream Approach Channel

PHASE 1: UPSTREAM CHANNEL DEEPENING

14

Site Work on Northwest Pier Material Placement Site Contractor worked 24-6 during periods of 2020 construction season

PHASE 1: UPSTREAM CHANNEL DEEPENING

15PHASE 2: UPSTREAM APPROACH WALLSN

34 ft diameter Circular SSP Cells - 1,900’SSP Transition Walls - 1,000’SSP Walls - 1,100’H-Pile (Soldier) Wall - 1,100’*Rubble Mound (non-mooring area) - 555’*Breakwater - 350’*West Center Pier Rehab

Work east of station 14+00 is to be completed by 15 Oct 2021

Scope: Rehabilitate approach walls upstream of New Soo Lock including reconstruction of walls, concrete caps, mooring bollards, electrical, and lighting.Project Status: • $111.3M Contract awarded to Kokosing Alberici in September 2020• Contractor expected to arrive on site in Spring 2021 and complete work in Fall 2023Estimated Performance Period: 36 Months

*Options that have not been exercised to date

16

PHASE 2: UPSTREAM APPROACH WALLS

• Contractor will begin on East end and work Westward

• Filling the sluiceway between the Upstream Approach Channel and the Unit 10 Power Plant headrace will be one of the first activities

SSP Cells

Stone Dam

17

PHASE 3: NEW LOCK CHAMBER

Scope: Construct new 1,200’ long by 110’ wide by 32’ deep chamber and rehabilitate downstream approach walls.Project Status: • 70% Design review completed in July 2020• 100% Design to be complete in July 2021• Construction contract award expected in February 2022 with contractor mobilization in Spring 2022Estimated Performance Period: 5-8 Years

N

18

NEW LOCK CHAMBER KEY FEATURES

Miter GatesFilling and Emptying SystemUpstream Ship ArrestorsDownstream Ship ArrestorsHands Free MooringNew Pump Well Miter Gates Ship Arrestor Hands Free Mooring Unit

19

NEW LOCK CHAMBER- TOOLS USED FOR DESIGN

REVIT model of existing lock structure

REVIT model of new lock structure

Virtual reality used for 70% design review by Soo Locks Operations and Maintenance Personnel

Changes Made Based on Virtual Reality Review• Operating shelter sightlines• Additional lock floor catch basins• Addition of miter gate tie back recesses

20

• Structural (LRN w/ support from LRL, LRP & LRE)• Civil Design (LRL)• Geology (LRL)• Geotechnical (LRL)• Electrical (LRP)• Mechanical (LRP & MVP)• Cost (LRH)• Hydraulics (MVS)• HTRW (LRB)• Security (NWO)• Materials (LRP with support from LRL & LRN)• Stantec/Cavotec – Hands Free Mooring Design

NEW LOCK CHAMBER DESIGN – INDC LEAD Inland Navigation Design Center (INDC) is Designer of Record and leading the design team that has members from 8 Districts and one A/E Firm

Design Review meeting, Nashville Jan 2020

Design Review meeting, Louisville Feb 2021

21

New Lock Chamber 3D Model video

NEW LOCK AT SOO VIRTUAL REALITY VIDEO

22

RESIDENT OFFICE – SCOPEUtilities:

• Water: City, • Sewer: City • Electrical: SAO• Fiber: SAO• Storm: City

• Tree Removal

Purpose: Provide office space for 26-30 person USACE Construction Management Team

Scope:6,000 SF modular structure- Conference Room - Bathrooms - Breakroom- Secure Storage

Schedule:- Design-Build Contract

scheduled to be awarded this Spring

- Occupancy slated for Nov. 2021

23

RESIDENT OFFICE – STATUSLocation Decision Criteria: - Size- Proximity to Construction Site- Cost- Timeliness- Minimize Impact to Community

and Park

Actions to Minimize Effect- Town Hall Meeting- Low Roof Line- Minimize Tree Removal- Restoration of Site Post New

Lock Construction

Artistic Rendering of the Resident Office in the Soo Locks Upper Canal Park

24

PROJECT’S ECONOMIC IMPACT

• $1.375B Total Project Cost

• Estimated 7-10 years of construction

• 1,240 jobs created on an annual basis• 600 direct jobs• 210 indirect jobs• 430 induced jobs

• 950,000 tons of limestone or granite

• 55,000 tons of American-made cement

• 25,000 tons of American-made steel

Menominee Unloading Aggregate on Northwest Pier in support of Upstream Channel Deepening Contract

25

Recent Engagements:• LTG Scott Spellmon, 55th Chief of Engineers and Commanding General of the U.S.

Army Corps of Engineers, visit to Soo Locks: Oct 2020• Mr. Vance Stewart, III, Senior Official Performing The Duties Of ASA(CW) and MG

William Graham, Deputy Commanding General for Civil and Emergency Operations, visit to Soo Locks: Feb 2021

Upcoming Engagement and Dates of Importance:• Detroit District Annual Congressional Meetings: Mar 2021• UAW Contractor Mobilizing to Site: Apr 2021• New Lock Chamber Stagger 1 Solicitation Start: Early Jun 2021• New Lock Chamber Pre-Proposal On-Site Meeting for Contractors: Mid-Late Jun 2021• New Lock Chamber Stagger 2 Solicitation Start: Late Aug 2021• Upstream Channel Deepening Completion: Nov 2021• New Lock Chamber Award: Feb 2022

RECENT ENGAGEMENTS AND UPCOMING DATES

26

QUESTIONS

Contact Info:Mollie Mahoney, New Lock at the Soo Project Manager (313) 226-2033

Email: [email protected] Website: https://www.lre.usace.army.mil/